P + 4M + O
PERT PERT = Time Management
6
Give number of days that the activity can delay without delaying project.
Total Float LS – ES ( OR ) LF - EF Time Management
CPI > 1 , Efficiency in utilizing the resources allocated to the project is good.
BAC − EV
To Complete Performance Index TCPI = Cost Management
𝐵𝐴𝐶 −
The result is the amount of money you need to invest today (PV) for n years at r % interest
𝐹𝑉 in order to end up with the target sum (FV). The higher the PV the better.
Present Value ( PV ) 𝑃𝑉 = Cost Management
(1 + 𝑟)𝑛
𝑁 (𝑁 − 1) Total amount of channel among n people in group.
𝐶𝐶 =
Communication Channels (CC ) 2 Communication
k
P : Pessimistic O : Optimistic M : Most likely EV: Earned Value AC : Actual Cost BAC : Budget At Completion LS: Late Start ES: Early Start
LF: Late Finish EF: Early Finish FV: Future Value r : Annual Interest Rate. n : number of years N : is the number of project members