Engineering & Projects 13.

6kV Switchgears at Power House # 3 at TSL,Jamshedpur


Project Planning
Master Document List
Submission Submission Approval Approval No. of
Sl Document Description Document No. Discipline Category
Plan Actual Plan Actual revisions

1 HV Drawing
1.1 Single Line Diagram (3) G71570 - K6730 - S001 Elect. App. 12.06.2018 12.06.2018 26.06.2018
1.2 Front View & Sectional View (3) G71570 - K6730 - F001 Mech. App. 12.06.2018 12.06.2018 26.06.2018
1.3 Plan View & Base Frame Drawing (3) G71570 - K6730 - P001 Civil App. 12.06.2018 12.06.2018 26.06.2018
1.4 Gas SLD (3) G71570 - K6730 - G001 Mech. App. 12.06.2018 12.06.2018 26.06.2018
1.5 Design Instruction Sheet (3) G71570-K6730-D001-01 Elect. App. 12.06.2018 12.06.2018 26.06.2018
2 Quality Assurance Plan EM-MS_GIS_GOI_QAP_8DAB Elect. App. 12.06.2018 30.06.2018 26.06.2018
3 Spare Material List Elect. App. 12.06.2018 12.06.2018 26.06.2018
4 LV Drawing
4.1 Master Single Line Diagram (3) G71570 - K6730 - M003 Elect. App.
4.2 Door Equipment Layout (3) G71570 - K6730 - L005 Elect. App.
4.3 Name Plate List (3) G71570 - K6730 - N006 Elect. App.
4.4 Wiring Diagram - IC 1 (3) G71570 - K6730 - W101 Elect. App. Within 2
4.5 Wiring Diagram - IC 2/3/4 (3) G71570 - K6730 - W102 Elect. App. weeks after
4.6 Wiring Diagram - Generator TG 4 (3) G71570 - K6730 - W103 Elect. App.
HV Approval
4.7 Wiring Diagram - Generator TG 5 (3) G71570 - K6730 - W104 Elect. App.
4.8 Wiring Diagram - Bus Coupler (3) G71570 - K6730 - W105 Elect. App.
4.9 Wiring Diagram - Outgoing Feeder (3) G71570 - K6730 - W106 Elect. App.
4.10 Wiring Diagram - Outgoing Feeder with BPT (3) G71570 - K6730 - W107 Elect. App.

GAS FILLING & GAS PRESSURE MONITORING SYSTEM DRG & OPEARTION MANUAL SHALL BE INCLUDED

EARTHING PLAN OF GIS SHALL BE SUBMITTED


INTEER CONNECTION & INTERPANEL WORING DETAILS SHALL BE INCLUDED
DC POWER REQUIREMENT DATA SHALL BE SUBMITTED

truth table for interlock shall be submitted

catalogue of motor control unit with internal


circuit diagram, & other equipment
scheme drg shall be submitted for each
feeder & as per board formation

Unrestricted