• QUALITY PLAN AUDIT CHECKLIST

• PROJECT QUALITY PLAN AUDIT REPORT FORM

Quality System Audit Checklist


Version 20140317

Project ID Project Name Auditor Date


[ProjectNumber] [ProjectName]
YES NO Project Quality Coordination and Communication

A project startup meeting was conducted to communicate project goals and


□ □ expectations.

Before each scheduled work task, a preparatory meeting was conducted to


□ □ communicate requirement details and coordinate work activities.

YES NO Employee Qualifications

• Employee qualifications were evaluated based on previously


□ □ identified requirements including licensing requirements, training
qualifications, responsibilities, and authority for each job position.

• Field employees were trained on quality standards and procedures


□ □ for their job position.
• Employee capabilities were validated before employees were
□ □ assigned to carry out quality job responsibilities.

• Employee qualifications, quality practices, and performance are


□ □ being reviewed on an ongoing basis as part of the employee
performance management process.

YES NO Qualification of Subcontractors and Suppliers

• Outside organizations’ qualifications were verified based on licensing


requirements, compliance with specific quality standards, quality
□ □ responsibilities, qualification of personnel and quality improvement
processes.

• Subcontractor and supplier quality performance is being evaluated


□ □ on an ongoing basis.

YES NO • Project-Specific Quality Standards

• All relevant regulations, codes, and industry standards are available


□ □ on jobsite.

• Specifications for materials that meet contract as well as regulatory


□ □ requirements are available on jobsite.

• Quality and certification requirements for materials and equipment


□ □ that affect quality are available on jobsite.

• Measuring devices that affect quality were calibrated to special


□ □ requirements when applicable.

• Contract and published standards were supplemented with


□ □ company quality standards as required to reduce quality risks and
assure quality results.

YES NO • Inspections and Test Plan

• Inspections and tests were performed to contract specifications and


□ □ industry standards.

• Inspection and test results were recorded for each quality inspection
□ □ and test.
• Inspection and test samples were sent to independent laboratories
□ □ that are certified by nationally recognized accreditation agencies.

YES NO • Work Task Quality Inspections

• Required quality work task inspections were performed at key


□ □ milestones during the project.

• All quality inspections and quality control activities were performed


□ □ for each work task as required by the contract, industry, and
company policies.

• The full series of quality inspections (including before work begins,


□ □ at first article completion, while work is in process, and at
completion) were performed for each construction task.

□ □ • All materials were inspected before use.

• The results of each work task inspection were recorded. A copy of


□ □ the inspection report is available for review.

YES NO • Quality Control of Corrections and Nonconformances

• Nonconformances and rework items were marked clearly to identify


□ □ them for correction.

• Corrections were made in a timely manner and validated for their


□ □ effectiveness.

• Customer approval was received before accepting any


□ □ nonconforming items.

□ □ • Nonconformance items were noted for future prevention.

• Standards and specifications were updated to address the causes of


□ □ nonconformances.

• A review was done of the effectiveness of actions that were taken to


□ □ prevent nonconformances.
YES NO • Project Completion Inspections

• Senior managers, independent of production, performed a rigorous


□ □ inspection at project completion.

• All deviations were corrected and reinspected prior to submittal to


□ □ the customer for final review.

• Management participated in the customer’s final inspection and


□ □ quickly addressed issues that were found.

• Notes:


Project Quality System Audit Form
Version 20140128
Project ID Project Name Auditor Date
[ProjectNumber] [ProjectName]
Review Topics:
(Place check mark next to each item audited)
• Customer satisfaction
• On-time task completion
• Contract administration
• Safety compliance
• Quality risk planning and mitigation
• Performance improvement results
• Action plan for improvements

Quality Plan Conformance:


• Project QC Personnel
• Project Quality Coordination and Communication
• Employee Qualifications
• Qualification of subcontractors and suppliers
• Project Quality Specifications
• Testing Plan
• Test Reports
• Work Task Quality Inspections
• Daily Quality Control Report
• Control of Punch Items and Nonconformances
• Project Records and Documents

Nonconformance Notes and observations

Action plan for improvement

Follow-up results and date