Vous êtes sur la page 1sur 5

Australian Construction Law Newsletter Issue #15 47

NPWC/NBCC "No Dispute" Paper 8 - Variations

1. Introduction
1.1. The terms of reference for the JWP in respect of 1.7. Contractual provisions should not assist the Principal
variations were as follows: avoid the consequences of its variation requirements. On
examine the BritishProperty Federation (BPF) the otherhand, a Principal should be given the opportunity
system and recommend which ofits concepts to mitigate the extent of its liability. Timely communica-
should be adopted in Australia; tion regarding variations is necessary to allow the effective
• propose guidelines for contractual arrange- cost management of projects. (See Paper 5 - "Cost Man-
ments for variations. agement".)

1.2. Most variations to the project directed by a Principal 1.8. The above observations indicate that variations, and
can be classified into two basic types, namely: particularly "urgent" variations, benefit neither party,
Type (i) variations, caused by inadequate, incomplete or despite the traditional belief that Contractors make their
ambiguous documentation; and profits from variations. Itis in the interests ofall parties for
Type (ii) variations, caused by changes or additions to the number and extent of variations to be kept to a mini-
project requirements. mum.

1.3. Variations may also bedirected to overcomedefective 1.9. This response to the JWP' s terms of reference is set
materials or work. This special category ofvariation may out under the following headings:
be appropriate in circumstances where it is not realistic to • Variations under the British Property Federa-
remove and reconstruct defective materials or work. tion (BPF) system;
Procedures for dealing with such variations are discussed • Guidelines for minimising the incidence of
in Section 8 of this paper. The term "variation" is usually variations;
thought of as applying to matters described as Type (i) or Procedural requirements for dealing with
Type (ii) variations. Accordingly, unless the context v"ariations;
indicates otherwise, the term "variation" in this paper • Guidelines for minimising the cost of vari-
refers only to Type (i) andlor Type (ii) variations and does ations;
not apply to variations to overcome defective materials or Valuation of variations;
work. Disputes regarding variations;
Variations in respect of defective materials
1.4. As well as the Type (i) and Type (ii) classifications and work;
described above, variations can also be classified as either • Summary of Findings.
"urgent" or "non-urgent". An "urgent" variation is a
variation instructed after the commencement of the lead 2. Variations Under The BritiSh Property Federation
time necessary to allow the variation to be planned, and to (BPF) System
allow the part of the Works affected by the variation to be 2.1. Under the BPF system, detail design development is
re-planned, so that the variation can be carried out in an normally the responsibility of the Contractor, Le. the
orderly manner and in proper trade sequence with the other Contract is based on the Principal's performance require-
project work. Generally, the price for an "urgent" vari- ments and specifications, except where the Principal has
ation cannot be established before the variation work is particular construction requirements. The Contractor
performed. usually employs specialist consultants to carry out the
detailed design on its behalf. In this respect, the BPF
1.5. Variations, and particularly urgentvariations, disrupt system mirrors certain aspects of detail design and con-
the orderly performance of the Works, demand a dispro- struction contract strategy (see Paper 11 - "Alternative
portionate amount ofmanagementtime andresources, and Contract Strategies").
thereby affect the effective managementofprojectquality,
cost and time. The proper valuation of variations is often 2.2. The procedures for raising and processing variation
a complex matter,. particularly if the . variation affects orders under the BPF system are set out in Section 5.5 of
critical activities or resources. The indirect cost of a the BPF Manual. As the Contractor is usually responsible
variation may not be apparent until the later stages of a for the detailed design! documentation, the procedures are
project. framed to cater predominately for Type (ii) variations.
Under the BPF system, one point control of variations is
1.6. The Risk Allocation Model described in Paper 1 - exercised through the Client's Representative, (the Princi-
"Risk Allocation", indicates that the Contractor is entitled pal), and the value of a variation should be agreed or
to full compensation for performing variations instructed determinedprior to authorising the work. The BPF system
by the Principal, or variations necessary as a result of provides for a bonus payment to the Contractor of50% of
problems with design andlor documentation for which the any saving resulting from a Contractor-originated vari-
,Principal is responsible. However, the subtle nature of ation.
certain of the factors that affect the performance of con-
struction works means that it is sometimes difficult for the 2.3. The procedures for raising a variation order under the
Contractorto identify and substantiate its proper entitle- BPF system ate described in Section 5.5 (pp 54 - 56) ofthe
ment. Manual of the BPF System. The general thrustoftheBPF
Australian Construction Law Newsletter Issue #15 48

variation procedures are appropriate for non-urgent Type sation of variations should be vested with the member of
(ii) variations, but are inappropriate for Type (i) variations the project team responsible for managing the interface
and urgent Type (ii) variations. between the design team and the construction team.

3. Guidelines For Minimising The Incidence Of 3.9. Any amended drawing, specification or other docu-
Variations ment issued during the construction period should have all
3.1. The incidence of variations can be reduced by: changes highlighted and the document given an amend-
preparation of a carefully considered, objec- ment revision number.
tive, performance-orientated Principal's
brief; 3.10. Ensure that an alleged variation is in fact a variation,
careful preparation and co-ordination ofdetail and is not work already covered by the Contract.
design and documentation;
one-point control of variations; 4. Procedural Requirements For Dealing With
elimination or minimum use of provisional Variations
sum items. 4.1. Clearly definedprocedures for dealing with variations
should be established, and all members of the project team
3.2. Ensure that all Principal requirements are fulfilled by made fully aware of their respective roles, in order to
the design and documentation, that the Principal is ac- ensure that the system operates smoothly. It is of prime
quainted with all planning solutions and in agreement with importance that variations receive prompt attention by all
same, and that the Principal is made fully aware of the parties, particularly variations which affect critical activi-
adverse cost and time implications ofvariations during the ties or resources.
construction stage.
4.2. Type (i) variations relate to the correction ofproblems
3.3. Aim for the highest standard of accuracy and ade- with the design andlor documentation. The Principal has
quacy in design and documentation. Ensure that sufficient no option but to instruct such variations. Type (i) vari-
time (and adequate fees) are allocated to the design/ docu- ations should be identified and instructed at the earliest
mentation process for anomalies to be resolved prior to possible time.
construction. The design and documentation process
should be the subject of a formal Quality Assurance 4.3. Procedures for dealing with Type (i) variations should
system. include the following steps:
(i) When an ambiguity, error, omission, discrep-
3.4. Ensure that the detail design and documentation is ancy, inconsistency or other fault is found in
described in objective terminology. Objective specifica- the documents, it should promptly be made
tions are an essential requirement for the implementation known to the member of the project team
of quality assurance systems. Subjective specifications responsible for the authorisation ofvariations
cause uncertainty and misunderstandings, which lead to (the authorised person).
inefficiency, delay, disruption and increased costs. (ii) Where necessary, the authorisedperson should
promptly discuss the most appropriate rem-
3.5. Ensure effective communication between the design edy for the fault with the relevant members of
and construction teams. Continuity of involvement of the the design team and the construction team.
design team throughout the construction stage of the (iii) As soon as practicable after notification of the
project can significantly reduce the incidence of unneces- fault, the authorised person should issue a
sary variations, delays and disruption. Variation Order to the Contractor correcting
the fault and directing that the work proceed in
3.6. In general, the designer should not be the Principal's accordance with the instruction.
Contract administrator, because of the tendency for the (iv) As soon as practicable after receipt of the
designer to amplify its requirements as the construction Variation Order, the Contractor should advise
proceeds. However, if the roles are combined for a the authorised person ifthe Variation Order is
particular project, the designer/contract administrator likely to result in an increase in price or time
should take care to avoid ordering variations in this man- andlor affect the interface with the work of
ner. The contract administrator should be aware that an other contractors.
instruction to "clarify" requirements may be a variation. (v) Where possible, the parties should agree a price
and, if relevant, an extension of time for such
3.7. When properly priced, "last minute" and "multiple" Variation Order before the variation is carried
variations are expensive, after taking account ofthe result- out.
ing delay and disruption to the orderly performance of the (vi) If pre-agreement of price andlor time for the
project. Type (ii) variations should not be ordered without variation is notpossible, the Contractorshould
careful consideration of their viability. Variations which submit the readily identifiable costs and de-
are not viable or essential should not be implemented. In lays resulting from the VariatioD. Order as
certain instances it may be more appropriate to defer a soon as practicable (say not later than 28 days)
proposed modification until after the project has reached after performance of the variation work.
Practical Completion. (vii)The valuation of most variations should be
capable of being finalised in step (vi) above.
3.8.0nepointofcontrolandresponsibilityfortheauthori- However, for certain variations there will be
Australian Construction Law Newsletter Issue #15 49

other less easily identifiable costs and delays 4.6. The general principles and procedures set out in Sec-
caused as result of, say, the ripple effect ofthe tion 5.5 of the BPF System Manual should be considered
Variation Order, or the cumulative effect of for "non-urgent" Type (ii) variations.
many such matters. Details of such costs and
delays should be submittedprogressively, and 4.7. Procedures for dealing with "non-urgent" Type (ii)
again as soon as practicable. Contract proce- variations should include the following steps:
dures should ensure that a Contractor does not (i) The originator of a proposed variation should
delay in submitting readily identifiable costs clearly define the proposed change and
and delays (step (vi) above) merely because arrange for a budget estimate to be prepared;
there may be an ongoing ripple effect. If the (ii) If the proposed variation appears viable and
Contractor considers that there will be indirect appropriate, the variation design is finalised;
costs and delays associated with the variation, (iii) A firm price for the proposed variation is
this should be advised to the Principal at the requested from Contractor within stated time
time of submitting the statement of readily period. Where possible, such price should
identifiable costs and delays. include all indirect costs related to the vari-
(viii)Payment and extension of time for the vari- ation and should state the impact (if any) on
ation work should be resolved promptly (and Contract time;
progressively, ifnecessary) and incorporated (iv) Price submitted by Contractor. Where appli-
into the contract payment and administration cable the quotation should state the latest date
systems. for acceptance of the variation quotation;
(v) Price and time scrutinised, negotiated and
4.4. The disruptive nature of "urgent" variations cause agreed or determined. Where necessary ob-
impact cost and delays that often cannot be ascertained at tain Principal's approval for expenditure;
the time of performing the variation. Attempts to pre- (vi) If variation is to proceed, a variation order is
agreed a price for an "urgent" Type (ii) variation would issued;
probably cause additional delays and disruption to the (vii) Variation undertaken and paid for.
project, because of the time that would necessarily be
required to pre-agreed a price for the proposed variation. 4.8. The procedural requirements for dealing with all vari-
In many instances it would not be practical to quote an all ations should include:
inclusive price for the ripple effects that may be caused be (i) A realistic budget allowance should be in-
the "urgent" variation. cluded in the project budget for variations, but
this allowance should not be stated in the
4.5. Procedures for dealing with "urgent" Type (ii) vari- Contract.
ations should include the following steps: (ii) For the purposes of facilitating effective com-
(i) The originatorofthe proposedvariation should munication between the parties, the Contrac-
clearly define the proposed variation. tor should promptly notify the Principal if it
(ii) The authorised person should discuss the considers that a Principal' s instructionconsti-
proposed variation with the relevantmem- tutes a variation, so as to give the Principal the
bers of the design team and the construction opportunity to amend its instruction, or to
team to establish what would be the most enable it to keep appropriate records. Whilst
appropriate manner of implementing the the Contractor should make every endeavour
proposed variation so as to minimise delay to comply with this requirement, failure to
and disruption to the project. The Contrac- comply should not constitute a bar to its enti-
tor should be asked to provide a non-binding tlement to payment or time for the perform-
budget estimate of cost and time of the pro- ance of the varied work. In this regard, the
posedvariation. This analysis ofthe proposed Principal is reasonably deemed to be aware of
variation should be carried out as quickly as the Contract design and documentation for
practicable so as not to exacerbate the likely which it is responsible, and whether or not an
delay and disruption to the project that would instruction to the Contractor varies such de-
be caused by the proposed variation. sign or documentation. It is not reasonable
(iii) If the proposed variation is to proceed, a that a construction Contractor be penalised by
variation order is issued. barring provisions if it reasonably overlooks
(iv) The Contractor should submit the readily or fails to recognise immediately the signifi-
identifiable costs and delays resulting from cance of such a Principal's instruction.
the variation order as soon as practicable (say, (iii) The Contract procedures for the valuation of
not later than 28 days) after the perform- Variations should recognise that, whilst the
ance of the work. readily identifiable direct costs of performing
(v) Other less easily identifiable costs and delays a variation should be established within a
should be submitted progressively and reasonable specified time after the perform-
again as soon as practicable. The comments in ance of a variation, the indirect delay and
step (vi) of Type (i) variations also apply to disruption ripple effect may not be capable of
urgent Type (ii) variations. being ascertained at that time.
(vi) Resolve payment and extensions of time (iv) If a CORtractor unreasonably delays in notify-
promptly. ing the Principal that it considersaPrincipal's
Australian Construction Law Newsletter Issue #15 50

instruction to be a variation or unreasonably 5. Guidelines For Minimising The Cost OfPerforming


delays in submitting a valuation of variation, Variations
the Principal should be entitled to are m - 5.1. The cost ofperforming variations, and hence the price
edy against the Contractor. (See Paper 9 - properly payable by the Principal, may be minimised
"Claims", and Paper 10 - "Dispute Resolu- through adherence to the following general guidelines:
tion,,). (i) Variation instructions should be explicit as to
(v) The Contract provisions should provide an technical requirements and extent.'
appropriate balance between the legitimate (ii) Contract procedures should be consistent and
requirements of the Principal for prompt no- clear and not open to uncertainty and ambigu-
tice and valuation ofvariations, and the legiti- 0us interpretation.
mate requirement ofthe Contractor for proper (iii) Restrict each Variation Order to one change
compensation for the performance of vari- only.
ations. (iv) A variation should be instructed in sufficient
(vi) A nominated member of the project team time to allow proper re-planning of the work
should have the responsibility for co-ordi- under the Contract, and to allow the work to be
nating all functions of the variation process carried out in an orderly manner in proper
and for ensuring that all procedures are com- trade sequence.
plied with, reports submitted and authorisa- (v) Keep the number of variations to a minimum
tions obtained. to avoid the additional costs incurred as a
(vii)Contract administration procedures should be result of the compounding effect of multiple
accompanied by an effective cost monitor- variations.
ing and reporting format to the Principal. The (vi) Whereverpossible, avoid "urgent"variations.
following data should be included with re- Urgent variations are expensive and have a
spect to variations: high potential for delay, disruption and later
• The budget allowance for Type (i) dispute.
variations and costs committed to (vii) Whenever possible, the parties should
date; agree the price for a variation prior to au-
The progressive value of Type (ii) thorising the varied work to proceed. How-
variations and the budget for ,them. ever, it may not be practical to pre-agreed
the valuation of "urgent" variations. A delay
(viii)The project budget and program should be in authorising a variation pending agreement
regularly monitored and if necessary updated on price may cause a "non- urgent" variation
to reflect the effect of variations and other to become an "urgent" variation.
delaying events on the performance of the (viii)Where a variation is instructed prior to agree-
Project. ment on price, "without prejudice" progress
(ix) The indirectdelay and disruption ripple effect payments should be certified and paid pend-
that maybe caused by a variation may not be ing resolution of the final price.
capable of being ascertained at the time of
performing the variation. In such circum- 6. Valuation Of Variations
stances it may only be possible to analyse the 6.1. The Risk Allocation Model indicates that variations
indirect effect of variations and other factors are a Principal's obligation/risk, and that the Contractor is
that haveaffected the peiformance ofthe proj- entitled to full and fair compensation for the performance
ect at a later stage in the project. However, ofvariations to the project instructed by the Principal, and
Contract procedures should ensure that the for variations necessary as aresult ofproblems with design
Contractor does not delay the submission of and/or documentation for which the Principal is respon-
readily identifiable costs merely because sible. Contractual provisions should not assist the Princi-
there may be ongoing indirect effects caused pal avoid the consequences of variations.
by variations and other delaying events. If the
Contractorconsiders that there will be indirect 6.2. Where practicable, the price for a proposed variation
costs and delays associated with a variation, should be agreed prior to the Principal authorising the
this should be advised to the Principal at the varied work. In general, this procedure is only practical for
time of submitting the statement of readily non-urgent variations where the pricing and agreement
identifiable costs and delays. process for the proposed variation can be completed prior
(x) Variation Orders shouldnot be issued after the to the start of the lead time necessary to allow the varied
Works have reached Practical Completion. work to be properly planned and to allow the varied work
Any modifications or additional workrequired to be carried out in an orderly manner and in proper trade
to be executed after Practical Completion sequence with the performance of the project.
should be the subject of a separate agreement
with the Contractoror otherpersons employed 6.3. Ifvariation work is ofa similarcharacter and executed
by the Principal. If other persons are em- under similar conditions to work described in the Bills of
ployed, the Principal s~ould take care not to Quantities, then it may be appropriate to apply the relevant
void warranties relating to the Works. prices or rates contained in the Bills of Quantities.
Australian Construction Law Newsletter Issue #15 51

6.4. However, urgent variations are not carried out under resolution of the dispute, whether by negotiation, arbitra-
the same orderly conditions as the original contract work tion or other means, as binding on both parties.
described in the Bills of Quantities. When itis reasonable
to do so it may be appropriate to establish a fair valuation 7.2. Such procedure overcomes the potential problems
of the direct cost component of an urgent variation based associated with parallel dispute resolution procedures under
on an extra - over increase in the prices and rates set out in the Head Contract and the Subcontract in respect of the
the Bills of Quantities. same matter.

6.5. Ifthe conditions under which a variation is performed 7.3. The Contractor should ensure that only those matters
are so different to the conditions under which the original that are relevant to the Principal's responsibilities are dealt
Contract work would have been carried out there may be with in this manner; it is inappropriate to forward to the
no reasonable alternative but to build up from first prin- Principal components of a Subcontractor's claim that are
ciples a reasonable price for the variation based on job matters properly limited to the Contractor and not matters
specific data and other relevant factors. for which the Principal could be held accountable.

6.6. The valuation of variations, particularly urgent vari- 8. Variations In Respect Of Defective Materials Or
ations, may include costs relating to the delay and disrup- Work
tion caused by the variation. It may be appropriate to state, 8.1. If the Contractor's materials or work is not in accor-
as separate valuations items, the direct costs and the dance with the Contract, it is normal practice for the
indirect costs incurred carrying out an urgent variation, so Contractor to remove and replace the defective materials
that the Principal is aware of the cost penalty to the project or work.
of urgent variations.
8.2. In certain circumstances, it may be more appropriate
6.7. The pricing and payment structure of most construc- for the defective work to be "varied", such that the defec-
tion contracts is based on the conceptofprogress payments tive work as varied satisfies the Principal's requirements
being made monthly in respect ofwork carried out during for the project.
the previous month. The Principal should make "without-
prejudice" progress payments in respect of variations, 8.3. If the Principal agrees to vary the defective work as
even if the final. prices of the variations have not been described, the Contractor should not be entitled to an
established. extension of time or payment for such variation unless the
. variation causes an increase in the value to the Principal of
6.8. If payment for a variation is not made until after the the Works, in which case a valuation of the variation
final price for a variation has been agreed or determined, should have regard to such increase.
the valuation may reasonably include for the financing
costs incurred by the Contractorduring theperiodfrom the 8.4. The Principal and the Contractor should agree on any
date of the next progress payment after the variation work increase or decrease in the Contract price or time for such
was performed to the date when payment is made. a variation prior to the variation being instructed.

6.9. The direct cost and immediate ripple effect of a vari- 8.5. The Principal should be under no obligation to order
ation should be established within a reasonable specified such a variation merely to assist the Contractor.
time after the performance of the variation. The indirect
delay and disruption ripple effect that may be caused by a 8.6. A Contract provision dealing with this class of vari-
variation may not be capable of being ascertained at the ation is set out in Clause 30 of AS2124-1986.
time ofperforming the variation. In such circumstances it - Reprinted with the permission of the National
may only be possible to analyse the indirect effect of Public Works Conference and the National
variations and other factors that have affected the perform- Building and Construction Council.
ance of the project at a later stage in the project. The
valuation of the indirect component of a variation should
be addressed progressively after identification and sub-
mitted as soon as practicable. The Contractprocedures for
valuing variations should recognise this two stage process
in the establishmentofthe proper valuation ofcertain vari-
ations' particularly urgent variations.

7. Disputes Regarding Variations


7.1. If a Subcontractor's claim relates to a variation, or an
alleged variation, to the Head Contract Works, (and as-
suming the technical documentation for the Subcontractis
the same as that included in the head contract), the
Subcontractor's entitlement in respect of the variation
should be resolved in a single forum pursuant to the terms
ofthe Head Contract. The Contractor and the Subcontrac-
tor should co-operate to prepare submissions to the Princi-
pal in respect of the disputed variation and accept the

Vous aimerez peut-être aussi