Académique Documents
Professionnel Documents
Culture Documents
GTR-1.0 GENERAL...........................................................................................................1
GTR-1.1 PROJECT LOCATION.............................................................................................2
GTR-1.2 PROJECT DURATION.............................................................................................2
GTR-2.0 SCOPE OF WORK............................................................................................2
GTR-2.1 GENERAL..............................................................................................................2
GTR-2.2 CIVIL WORKS........................................................................................................3
GTR-2.3 ARCHITECTURAL WORKS.....................................................................................4
GTR-2.4 MECHANICAL WORKS...........................................................................................4
GTR-2.5 ELECTRICAL WORKS............................................................................................7
GTR-2.6 OTHERS................................................................................................................9
GTR-3.0 CODES AND STANDARDS............................................................................9
GTR-4.0 DESIGN AND DUTY CONDITIONS.............................................................10
GTR-4.1 ACKNOWLEDGEMENT TO SITE CONDITIONS.....................................................10
GTR-4.2 SITE CONDITIONS...............................................................................................11
GTR-4.3 EARTHQUAKE AND WIND DESIGN REQUIREMENTS..........................................11
GTR-4.4 GENERATING UNIT DESIGN PARAMETERS........................................................11
GTR-4.4.1 General........................................................................................................12
GTR-4.4.2 Equipment and Operation Description....................................................12
GTR-4.5 WORKING STRESSES.........................................................................................12
GTR-4.6 WELD-FABRICATED PRESSURE CONTAINING PARTS.......................................13
GTR-4.7 NOISE..................................................................................................................13
GTR-5.0 MATERIALS AND EQUIPMENT...................................................................13
GTR-6.0 WORKMANSHIP.............................................................................................13
GTR-6.1 GENERAL............................................................................................................13
GTR-6.2 WELDING.............................................................................................................14
GTR-6.2.1 General........................................................................................................14
GTR-6.2.2 Minimum Weld Requirements..................................................................14
GTR-6.2.3 Preparation of Base Material....................................................................14
GTR-6.2.4 Technique of Welding................................................................................14
GTR-6.2.5 Welding Qualifications...............................................................................14
GTR-6.2.6 Weld Finish..................................................................................................15
GTR-6.2.7 Hydraulic Cylinders and Related Equipment.........................................15
GTR-6.3 STEEL CASTINGS................................................................................................15
GTR-6.3.1 General........................................................................................................15
GTR-6.3.2 Inspection....................................................................................................15
GTR-6.3.3 Repair Welding...........................................................................................16
GTR-6.3.4 Dimensions..................................................................................................16
GTR-6.4 NON-DESTRUCTIVE TESTING.............................................................................16
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-i
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-6.4.1 General........................................................................................................16
GTR-6.4.2 Examination of Welds................................................................................16
GTR-6.4.3 Examination of Castings...........................................................................17
GTR-6.4.4 Examination of Forgings...........................................................................17
GTR-6.5 MACHINE WORK.................................................................................................17
GTR-6.5.1 General........................................................................................................17
GTR-6.5.2 Finished Surfaces.......................................................................................17
GTR-6.5.3 Unfinished Surfaces...................................................................................17
GTR-6.5.4 Pins and Pin Holes.....................................................................................18
GTR-6.6 ASSEMBLY...........................................................................................................18
GTR-6.7 SURFACE FINISH.................................................................................................18
GTR-6.8 TOLERANCES......................................................................................................18
GTR-7.0 FOUNDATION MATERIALS AND ANCHOR BOLTS...............................19
GTR-8.0 LUBRICANTS AND HYDRAULIC FLUID...................................................19
GTR-9.0 EQUIPMENT MARKING & MISCELLANEOUS REQUIREMENTS.......19
GTR-9.1 ERECTION MARKS..............................................................................................19
GTR-9.2 NAMEPLATES AND LABELS.................................................................................19
GTR-9.3 LOCKS.................................................................................................................20
GTR-9.4 GUARDS..............................................................................................................20
GTR-9.5 LIFTING LUGS.....................................................................................................20
GTR-10.0 PACKING, SHIPMENT, AND STORAGE....................................................21
GTR-10.1GENERAL............................................................................................................21
GTR-10.2PACKING/CRATING.............................................................................................21
GTR-10.3SHIPMENT/TRANSPORT......................................................................................23
GTR-10.4STORAGE............................................................................................................24
GTR-11.0 INSTALLATION................................................................................................24
GTR-11.1GENERAL............................................................................................................24
GTR-11.2PREPARATORY WORK........................................................................................25
GTR-11.3INSTALLATION MEASUREMENT AND RECORDS..................................................25
GTR-11.4PAINTING.............................................................................................................26
GTR-11.5WELDING.............................................................................................................26
GTR-11.6EMBEDDED ITEMS AND ITEMS BEARING ON CONCRETE..................................26
GTR-11.6.1 General...................................................................................................26
GTR-11.6.2 Grouting of Bearing Plates & Machinery Bases...............................26
GTR-11.7OIL AND GREASE................................................................................................26
GTR-12.0 CORROSION PROTECTION AND PAINTING...........................................26
GTR-12.1GENERAL............................................................................................................26
GTR-12.2PAINTING SYSTEMS............................................................................................27
GTR-12.3SURFACE PREPARATION.....................................................................................28
GTR-12.4EXECUTION OF PAINTING...................................................................................28
GTR-12.5QUALITY CONTROL.............................................................................................29
GTR-12.6GALVANIZING.......................................................................................................30
GTR-12.7WARRANTY.........................................................................................................30
GTR-13.0 DRAWINGS AND TECHNICAL DOCUMENTS..........................................31
GTR-13.1GENERAL............................................................................................................31
GTR-13.2DRAWINGS/DOCUMENTS TO BE SUBMITTED WITH THE BID.............................31
GTR-13.3CONTRACTOR’S/MANUFACTURER’S DRAWINGS/DOCUMENTS.........................32
GTR-13.3.1 General...................................................................................................32
GTR-13.3.2 Submission & Processing of Drawings/Documents.........................33
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-ii
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-13.3.3 Drawings.................................................................................................33
GTR-13.3.4 Diagrams.................................................................................................35
GTR-13.3.5 Specifications.........................................................................................38
GTR-13.3.6 Lists and Schedules..............................................................................39
GTR-13.3.7 Calculations............................................................................................42
GTR-13.3.8 Operation and Maintenance Manuals................................................42
GTR-13.3.9 Documents for NPC’s Records...........................................................44
GTR-13.4AS-BUILT DRAWINGS..........................................................................................45
GTR-14.0 QUALITY ASSURANCE REQUIREMENTS...............................................45
GTR-14.1GENERAL............................................................................................................45
GTR-14.2QUALITY ASSURANCE PROGRAM......................................................................46
GTR-14.3QUALITY PLAN....................................................................................................46
GTR-14.4RECORDS............................................................................................................46
GTR-14.5PARTICULAR QUALITY ASSURANCE REQUIREMENTS.......................................47
GTR-14.5.1 General...................................................................................................47
GTR-14.5.2 At Shop...................................................................................................47
GTR-14.5.3 At Site......................................................................................................47
GTR-14.6REPORTING AND CORRECTIVE ACTION.............................................................47
GTR-15.0 INSPECTION AND TESTS............................................................................47
GTR-15.1GENERAL............................................................................................................47
GTR-15.2TESTS AT MANUFACTURER’S/CONTRACTOR’S PREMISES................................48
GTR-15.2.1 Inspection at Contractor’s Premises..................................................48
GTR-15.2.2 Factory Tests..........................................................................................48
GTR-15.2.3 Model Tests............................................................................................50
GTR-15.3PRE-COMMISSIONING/COMMISSIONING TEST...................................................50
GTR-15.3.1 Pre-Commissioning Test......................................................................50
GTR-15.3.2 Commissioning Test..............................................................................51
GTR-15.4START-UP AND INITIAL OPERATION....................................................................51
GTR-15.4.1 General...................................................................................................51
GTR-15.4.2 Preparation for Starting the Unit.........................................................52
GTR-15.4.3 Initial Operation......................................................................................52
GTR-15.5PERFORMANCE TEST.........................................................................................53
GTR-15.6RELIABILITY RUN................................................................................................54
GTR-15.7TESTS FAILURES................................................................................................54
GTR-15.8TEST REPORTS/CERTIFICATES..........................................................................55
GTR-15.9WAIVER OF FACTORY TESTS WITNESSING / INSPECTION BY NPC.................55
GTR-16.0 TRAINING OF NPC’S PERSONNEL...........................................................55
GTR-16.1GENERAL............................................................................................................55
GTR-16.2TRAINING AT MANUFACTURER’S/CONTRACTOR’S PREMISES...........................56
GTR-16.3OPERATION AND MAINTENANCE TRAINING AT SITE..........................................56
GTR-17.0 SPARE PARTS AND TOOLS........................................................................57
GTR-17.1SPARE PARTS.....................................................................................................57
GTR-17.2TOOLS AND APPLIANCES...................................................................................58
GTR-18.0 REMOVAL/DISMANTLING AND RELOCATION REQUIREMENTS.....59
GTR-19.0 CLEAN-UP........................................................................................................59
GTR-20.0 GUARANTEES................................................................................................59
ANNEXES
Annex No. 1 – Painting Schedule
Annex No. 2 - Technical Data of Existing Equipment
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-iii
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-1.0 GENERAL
This specification covers the general requirements for the uprating of Agus
6 (Units 1 & 2) HEP which shall generally consist of but not limited to
engineering investigation (equipment inspection and data
gathering/confirmation); design; detailing; manufacture; packing/crating;
supply; delivery; installation; painting; testing and commissioning of electro-
mechanical equipment, complete with state of the art control systems,
spare parts, tools and other materials and devices necessary to meet the
requirements of the specifications for the safe and reliable operation of the
plant. Works shall also include any modification/rectification and restoration
of affected civil/hydraulic structures and the removal/dismantling of all
equipment, components and devices which need to be replaced including
its hauling/transport to the yard area located inside the Agus 6/7 HEP
Complex.
The Contractor shall accept full responsibility for its work including design,
drawings, performance qualifications, specifications, documentation,
reports, fabrication, corrosion protection, cleaning, shop testing,
preparation for shipment, field testing and commissioning, warranty
provisions, and compliance with the applicable codes and standards and
the requirements of this Specification.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-1
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The project is located within the Agus 6 HEP in Sitio Fuentes, Bgy. Maria
Cristina, Iligan City in Mindanao. The plant is approximately eight (8)
kilometers away from the city proper and is accessible via concrete
national and NPC service roads.
The duration of the project is seven hundred eighty (780) calendar days
for the first unit and associated auxiliaries including the common
equipment/facilities for Units 1 & 2; and nine hundred (900) calendar
days for the second unit and associated auxiliaries both reckoned from
the date stated in the Notice to Proceed.
GTR-2.1 GENERAL
The scope of work covers the furnishing of all labor, materials, equipment,
tools and other necessary incidentals required for the Uprating of Agus 6
(Units 1 & 2) HEP wherein each unit shall be uprated to a minimum
capacity of 34.50 MW (measured at the generator terminal).
All equipment shall be designed and constructed to fit into the space
available and to pass through the finished opening/hatchway in the
concrete structure of the plant with proper regard to accessibility,
passageway, handling and existing equipment foundation limitations. It
shall also be constructed in such a manner that it can be removed and
maintained to suit the available crane lifting height and capacity. Any
necessary modification and restoration of affected civil/hydraulic
structures to erect, install, test and make the equipment ready for
operation shall be done by the Contractor at his own expense.
Any item or device not specifically called for in the Specifications but is
necessary to complete the uprating works shall be furnished and installed
including all accessories necessary to operate and meet the service
requirements of the Specifications.
3. Renovation of control room that will be used for the installation of the
new control systems for Units 1 & 2;
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-3
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
1. Restoration of floor system and its finishes at all rooms affected by the
transfer or installation of equipment;
6. Installation of 3mm thick vinyl floor finish at canteen area which will be
converted into Auxiliary Control Room;
The Contractor shall perform all the mechanical works specified below.
The detailed descriptions of the equipment are specified in subsequent
sections of the Technical Specifications.
2. Replacement of the existing two (2) units of governors for the vertical
Francis turbines with new and state of the art governing system
Works shall include the removal of the existing units and the
design, supply, installation, testing and commissioning of the new
electro-hydraulic governors. Each governing system shall consist of
but not limited to the following main components:
3. Replacement of the existing two (2) units of butterfly valve (main inlet
valve) with new and upgraded units
Works shall include the removal of the existing units and the
design, supply, installation, testing and commissioning of the new
units of butterfly valve (main inlet valve) complete with hydraulic
operator, bypass piping and valves, and appurtenant
instrumentation and controls, piping and interconnecting electrical
wiring/cables;
Works shall include the removal of the existing system and the
design, supply, installation, testing and commissioning of one (1)
complete set of cooling water system for each turbine-generator
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-5
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
unit. Each set of cooling water system shall consist of but not
limited to the following components:
The two (2) systems shall be interconnected and each system shall
be designed to supply sufficient capacity of cooling water to both
turbine-generator units in case of disturbance and/or failure of one
system.
Works shall include the removal of the existing system and the
design, supply, installation, testing and commissioning of the new
drainage and dewatering system which shall consist of but not
limited to the following components:
Works shall include the removal of the existing system and the
design, supply, installation, testing and commissioning of the new
compressed air system for station service air requirements, i.e.
generator brake system, air pressure-operated maintenance
sealing, use of pneumatic tools for maintenance & repair works and
other miscellaneous powerhouse services. The new compressed
air system shall consist of but not limited to the following
components:
Works shall include the removal of the existing system at the main
control room and the design, supply, installation, testing and
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-6
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Contractor shall perform all the works required in accordance with
this technical specification. The detailed descriptions of the equipment are
specified in every sections of the Technical Specifications. The work
required under this Contract shall include the engineering, design,
manufacture, supply, delivery, installation, testing and commissioning of
the equipment and materials enumerated below. It should be noted that
the Contract also includes all and every work and service although not
specifically mentioned but are required to fully complete the uprating and
rehabilitation works ready for operation as well as the dismantling and
hauling works of all equipment to be replaced to the designated location.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-7
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
a. Battery
b. Battery Charger
c. Power Inverter
GTR-2.6 OTHERS
All works to be performed shall be in accordance with, but not limited to, the
codes and standards issued by the authorities listed below. Other codes
and standards under which the works shall be performed and tested are
specified throughout the Specifications. Where such standards are
specified, the latest revision or edition at time of submission of bids shall
apply. Other equivalent standards may be substituted for those specified,
subject to approval of NPC. If it is desired to use substitute standards,
details of the proposed substitutions shall be submitted for approval.
Name Abbreviation
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-9
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
European Norms EN
In addition to the above codes and standards, the Contractor shall comply
with all applicable national and local laws, codes, regulations, statutes,
and ordinances.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-10
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
All parts of the plant shall be suitable in every respect for continuous
operation at maximum output under the climatic and operating conditions
prevailing at the site.
The plant required under this Contract shall meet the seismic design
requirement for earthquake conditions.
It is evident from the design response spectra that the degree of response
varies markedly with the period of vibration. It is essential, therefore, that
any equipment, or its supporting structure which has modes of vibration or
components with modes of vibration with a natural period longer than 0.1
second be identified.
The plant and equipment located outside the powerhouse under this
contract shall meet the requirements for a wind velocity of not less than
250 km/hr.
GTR-4.4.1 General
In the event that the main transformer circuit breaker automatically trips the
transmission line out of service, the generating unit shall operate
independently and carry the station service load. Under these conditions of
independent operation and very light loading, the frequency deviation of the
generating unit shall not vary more than 5%.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-12
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-4.7 NOISE
GTR-6.0 WORKMANSHIP
GTR-6.1 GENERAL
GTR-6.2 WELDING
GTR-6.2.1 General
All welds shall be made continuous and watertight. The minimum size of
fillet welds shall be 6 mm measured on the leg. All butt welds shall be full
penetration, welded from both sides.
The technique of welding, the appearance and quality of the welds, and the
methods used in correcting defective work shall conform to the AWS D1.1,
"Structural Welding Code." Special care shall be taken to avoid undercuts
along the seam or warping of the structure. If undercuts appear along the
welds, they shall be filled using a small diameter electrode of the same
composition as the original electrode.
for qualification testing of the welders who will perform the field welding on
the equipment. The procedure for qualification testing of the field welders
shall be prepared by the Contractor.
Welds shall in general be treated so that they will display good appearance
and a surface suitable for painting. Structural welds shall be ground and
blended to avoid stress raisers. All welds which require nondestructive
examinations shall be dressed by chipping and grinding as required for
good interpretation by the selected weld examination methods.
GTR-6.3.1 General
GTR-6.3.2 Inspection
Castings shall be inspected visually at the foundry after they are cleaned
and while defects are being removed. Castings shall also be inspected
after repairs and after heat treatment. Radiographic or other nondestructive
tests will be required as specified and as directed when permission is
granted to repair major defects. NPC reserves the right to require
nondestructive tests to determine:
Minor defects that will not impair the strength and serviceability of the
castings may be repaired by welding in accordance with accepted foundry
practice. Defects shall be considered when the depth of cavity properly
prepared for welding is not greater that 25% of the actual wall thickness but
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-15
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-6.3.4 Dimensions
GTR-6.4.1 General
All butt welds on skin plates and main beam flanges, and all welds on other
main components shall be subject to complete nondestructive examination
by ultrasonic, dye penetrant, magnetic particle methods, or by radiographic
examination.
Major forgings shall be given ultrasonic examination with liberal overlap and
other applicable nondestructive tests, to determine that they are sound.
Nondestructive examination of minor forgings shall be in accordance with
best and accepted practice to assure their soundness. The structure of
forgings shall be homogeneous and free from excessive nonmetallic
inclusions. An excessive concentration of impurities or separation of
alloying elements at critical points in a forging shall be cause for rejection.
GTR-6.5.1 General
All surfaces that require machining for their intended function, and those
surfaces that are normally machined in good shop practice, shall be
machined.
All work shall be laid out to secure proper matching of adjoining surfaces.
Where there is a large discrepancy between adjoining unfinished surfaces
they shall be chipped and ground smooth, or machined, to secure proper
alignment. Unfinished surfaces shall be true to the lines and dimensions
shown on the Drawings and shall be chipped or ground free of all
projections and rough spots. Depressions or holes not affecting the
strength or usefulness of the parts may be filled in an approved manner.
Corrosion resistant steel seal plate surfaces in contact with seals shall be
thoroughly cleaned to have a smooth and even surface.
Pin holes shall be drilled smooth and straight, and at right angles to the axis
of the member. The drilling shall be done after the member is securely
fastened in position.
GTR-6.6 ASSEMBLY
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-17
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Before assembly, all bearing surfaces, journals, and grease and oil
grooves, shall be carefully cleaned and lubricated with an approved oil or
grease. Solvents shall not be used on “Lubrite” bearings. After assembly,
each lubricating system shall be filled with an approved lubricant. “Lubrite”
bearings shall not be greased and shall be assembled dry, in accordance
with the manufacturer's instructions.
The qualities of all surface finishes shall be selected with due regard for the
nature and function of the surface, and in accordance with conservative
design practice.
GTR-6.8 TOLERANCES
Suitable pads, jacks, and anchor bolts shall be provided for supporting,
leveling, and fixing the equipment for proper installation. Suitable grout and
vent holes with plugs shall be provided. Anchor bolts shall be furnished
with flat washers, lock washers and nuts.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-18
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Grease, lubricating oil, and hydraulic fluid required for initial filling of all of
the equipment (plus 20% additional) including the necessary quantity for
flushing and first oil change shall be furnished, except as otherwise
specified hereinafter.
SPIN or Tag Numbers for instruments and other devices shall also be
provided. SPIN for piping and tanks shall distinctly be printed on its
external surfaces.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-19
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The labeling, size of label plates, and their location shall be subject to
approval by NPC. A sample label-plate (with indication of material used)
with lettering shall be submitted for this purpose. The inscription shall be
printed or stenciled but in any case, water-proof, oil-proof and wear-
resistant.
GTR-9.3 LOCKS
Where locks are called for in the Specification, they shall be of the barrel
type. Whenever possible, they shall be incorporated in the appropriate
door handle. Padlocks will be acceptable on valves and are preferred for
all outdoor equipment.
In general, all locks shall be supplied with three keys, and all locks and
keys are to be non-interchangeable. However, in the case of an electric
switchboard containing a number of lockable doors, all locks shall be
operated by one key. In all other cases where a set of locks is provided
under any section of the equipment, a group master key shall also be
supplied. Where a group of locks is supplied under any part of the
Contract, a key cabinet is to be supplied for the accommodation of all
padlocks and/or keys while not in use. Padlocks and keys are to be
engraved with a suitable identifying code or inscription and this is to be
repeated in the cabinet on engraved labels.
GTR-9.4 GUARDS
Coupling, drive shafts, fans, etc. shall be provided with guards. It shall
comply with ANSI Standard B15.1 Safety Code for Mechanical Power
Transmission Apparatus or equivalent IEC Standards.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-20
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-10.1 GENERAL
GTR-10.2 PACKING/CRATING
After the workshop assembly and prior to dismantling for shipment to the
site, all items of machinery and equipment shall be carefully marked to
facilitate site erection. Wherever applicable, these markings shall be
punched or painted so they are clearly visible.
All large and heavy shipping units shall have suitable skids for moving.
Crating shall also be adequate for lifting with slings. If location of slings is
critical, these locations shall be marked accordingly.
As the shipment may be left in open storage at the designated place, the
Contractor shall ensure that the delivered items have appropriate
protection from water and other elements. All delicate electrical and
mechanical parts susceptible to damage from moisture shall be packed in
hermetically sealed container or other approved containers within their
packing cases, with all machined surfaces coated with a rust preventive
compound. All sealed packages shall include bags of silica or equally
moisture absorbing chemical. When electric space heaters are provided
for that purpose, these should be wired to the outside of the equipment so
that energization immediately upon receipt is possible without
disassembly of crates, etc. This also requires that no combustible
material be left inside the equipment.
Valves, including its bolts, nuts, and washers, shall be segregately packed
and properly marked according to plant system, size, and number of
pieces.
All spare parts shall be packed in a sealed container including special and
standard tools in their separate sealed toolboxes.
All packages shall be forwarded with a copy of packing list placed inside
the package and another copy thereof contained in a waterproof envelope
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-22
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
placed outside the package. The packing list shall give all information on
the package such as package no., packing appearance, net weight, gross
weight, dimension, measurement, and description of the equipment
including storage and handling instructions with descriptions for periodic
inspection and/or storage maintenance to ascertain that no deterioration
will occur during storage.
GTR-10.3 SHIPMENT/TRANSPORT
Prior to shipment, the Contractor shall furnish NPC advance copies of all
non-negotiable shipping documents, invoices, packing list and other
pertinent documents.
The Contractor shall employ methods that will warrant safe delivery of
equipment to its ultimate destination, with careful consideration given to
the type of commodity, method of transportation, destination, storage time,
and storage facilities at point of destination.
The Contractor shall be responsible for the sea and land transportation of
the equipment, materials and supplies required under this Specification
and shall ensure that they are safely and timely delivered to the specified
site. Contractor shall be deemed to have visited the sites and other areas
on the route of delivery, including port facilities, inter-island shipping
facilities, island transport, access roads, bridges and to have acquainted
themselves with all factors that will affect the cost of shipping and freight
to Site. Any damages to the roads, bridges, railways, etc. arising out of
neglect of Contractor shall be the responsibility of the Contractor.
Likewise, any additional claim attributable to Contractor’s lack of
knowledge or understanding on existing conditions of the site shall not be
given due credence.
The Contractor shall ship the plant on clear commercial bill of lading and
the cost of all freight, insurance, shipping, handling and road transport
charges shall be included in the Bid Price.
Upon arrival of equipment and materials at site, NPC and the Contractor
or their authorized representatives, shall jointly verify the plant equipment
to be stored at site following the steps below:
b) Visual inspection of the condition of the packing and its surfaces; and
c) Partial opening of the crates and plastic sheet protection of the plant
auxiliary equipment and diesel generating sets to verify the content
and its physical condition and to check pilferage or damage during
shipment and storage.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-23
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-10.4 STORAGE
NPC shall designate areas where the Contractor may store the equipment
and materials. The Contractor shall, at his own expense, render such
areas suitable for the respective purposes.
If large parts are stored in the open air, they shall be provided with
weather-resistant and fire-resistant covers. Electrical parts which are not
packed in heavy duty polyethylene foil and those so packed but whose
packing has been damaged shall be kept in suitable places from the
moment of storage to the moment of installation.
GTR-11.0 INSTALLATION
GTR-11.1 GENERAL
All labor, tools, supplies, bracing, spiders, shims, supports, fixing bolts
and all other items or materials necessary to assemble, erect, install, test,
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-24
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
and make the equipment ready for operation shall be furnished. The
equipment and all its components shall be placed with great care and
accuracy and shall be correctly aligned to provide an installation
consistent with the close tolerances used in the manufacture of modern
hydroelectric equipment. The proper grades and centerline to which
equipment is to be set shall be established. Equipment shall be checked
for alignment, clearances and fit before grouting.
All transportation and handling of the equipment from the place of storage
to the place of installation shall be carried out by the Contractor. He shall
provide all hoisting equipment, staging and scaffolding, winches and wire
ropes, slings, tackles and all other appliances and temporary materials.
The erection staging and scaffolding shall be provided with coverings and
barriers and shall guarantee safe working conditions.
The Contractor shall comply with all applicable and approved safety
regulations while carrying out the works on site and with all reasonable
requirements of NPC. This stipulation shall in no way release the
Contractor from any obligation concerning his liability for accidents and
damages. He shall be responsible for adequate protection of persons,
equipment and materials against injuries and damages resulting from his
operations.
GTR-11.4 PAINTING
GTR-11.5 WELDING
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-25
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
All field welding required on the parts to join the shipping sections and to
attach anchorage, jackplates, baseplates, jacks, and piping and any
welding required for proper erection and installation of the equipment shall
be performed with special care. All field weld filler material shall be
provided to specifications established by manufacturers. Qualifications of
welding procedures, welding operators and welders shall be in
accordance with the applicable AWS Code. Final selection of welding
procedure, special requirements for operator qualification, sequence of
welding, requirements for weld backing, chipping, preheating, peening
and similar details shall be as determined by equipment manufacturers.
GTR-11.6.1 General
GTR-12.1 GENERAL
The Contractor shall submit for the approval of NPC, a full schedule of
coating systems containing the following information:
d) Surface preparation;
On request of NPC, painting samples for the different coats and colors
shall be provided by the Contractor. Rehabilitated or replaced
components shall be painted by nearly the same colors as the non-
rehabilitated items up to sharp borders, like edges, flanges, etc.
To be ready for painting, surfaces should be clean, dry and sound. The
surface to be coated shall be free from any deleterious material liable to
impair good paint adhesion or attack the coat.
For removing rust and mill scale on structural steel, piping and other steel
surfaces, those parts suitable for sandblasting shall be sandblasted to a
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-27
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Hand or power tool cleaned parts of minor importance and not exposed to
water or humidity may be coated with a quick-drying rust-proof primer
formulated on a combination of synthetic resins (ready-mixed paint).
The Contractor shall supply full details regarding the extent to which the
sandblasting and subsequent painting shall be performed in his workshop
or at the Site after installation. A properly equipped paint shop shall be
set up at the Site with a crew of specialists experienced and skilled in the
preparation and application of protective coatings, to deal with all site-
protective treatment.
Each coat shall be free from pores, runs, pinholes, and sags. Each coat
shall be allowed to dry or to harden before the succeeding coat is applied.
Where pore-free coats are specified, it shall be compulsory for the
Contractor to prove this quality with adequate instruments.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-28
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Care shall be taken to maintain full paint thickness at all corners and
edges and special attention shall be paid to the application of protective
coatings over welds, miter joints, etc.
The first coat shall be applied immediately after sandblasting and shall be
finished within six hours to avoid new corrosion.
Shop coats shall be checked for good quality and where necessary,
before proceeding with the painting or coating operations at the Site, the
Contractor shall clean and repair all shop coats which are defective or
damaged.
The first and each successive coat shall not be applied without inspection
and approval by NPC.
For coating films having a total film thickness of 500µm, low voltage wet
sponge test equipment may be used.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-29
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
A detailed inspection of all painting work shall likewise be made, and all
abraded, stained, or otherwise disfigured portions shall be touched-up
satisfactorily or refinished as required to produce a first-class job
throughout and to leave the entire work in a clean and acceptable
condition.
GTR-12.6 GALVANIZING
- for all other parts, except for hydraulic steel structures or parts
intermittently or permanently submerged in water, approx. 70
micrometer
GTR-12.7 WARRANTY
The guarantee period for all painting shall be five (5) years, starting from
the issue of “Provisional Acceptance Certificate”. This painting guarantee
period shall be effective regardless of any other guarantee periods for the
project or parts of the project, or any Final Acceptance Certificate, issued
prior to the lapse of the painting guarantee period.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-30
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-13.1 GENERAL
This Section specifies the general scope and gives a definition of the
drawings and document which shall be submitted by the Contractor to
NPC within the periods, and in a number and quality as specified. These
documents shall not only provide for the new components to be delivered
and installed, but also for the components to be replaced, rehabilitated,
upgraded or modified.
The Contractor shall submit with his Bid the required copies of drawings
and documents as specified in Section VI - Part II -Technical Data
Sheets, Item VI – List of Drawings and Documents to be Submitted
with the Bid.
Drawings and other technical documents shall show all the essential
items and details of the equipment being offered to enable NPC to
determine all essential details of the various items of equipment and
materials to be used. The drawings and documents shall be marked “FOR
BIDDING PURPOSES ONLY” to distinguish them from the Contract
Drawings/Documents to be submitted later for NPC’s review and
approval. The winning bidder shall not be released of his responsibility
and guarantee after the drawings and documents submitted with the bid
have been accepted by NPC.
The winning bidder shall supply, at the time of the award of the Contract,
two (2) additional copies of drawings and documents submitted with his
Bid as attachment to the Contract Documents.
GTR-13.3.1 General
Before submitting any drawing, the Contractor shall obtain approval of the
Schedule/List of Drawings/Documents he proposes to submit indicating
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-31
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Should any error be found in the Contractor’s drawings during the works,
the correction, including any field change considered necessary, shall be
noted on the drawings and shall be resubmitted for approval and recorded
as outlined above.
NPC reserves the right to reproduce any drawings or prints received from
the Contractor as may be required despite any notice prohibiting the same
appearing on the drawing or the print. All drawings are preferred in a
computer-aided format. However, if unable to comply with this
requirement, manual drafted drawings will be acceptable. All CAD
produced drawings are to be submitted in Autocad or PDF formats. All
other computer-generated documents are to conform to Microsoft Office
or shall be submitted in PDF formats.
Six (6) prints with dark lines on a white background shall be furnished to
NPC for each drawing submitted for approval or for information/reference.
NPC shall return one (1) print to the Contractor within twenty (20)
calendar days after receipt of the drawing. NPC shall mark the drawings
either “Approved, A”, “Approved with Corrections Indicated, AWCI” or
“Returned for Corrections, RFC”. If drawings are marked “Approved with
Corrections Indicated, AWCI” or “Returned for Corrections, RFC”, the
Contractor shall make all necessary corrections and re-submit same in six
(6) copies within fourteen (14) calendar days. Any comment given by
NPC on a “For Information”” type of drawing shall have the same effect as
if it were given on a “For Approval” type of drawing. Every revision shall
be shown by number, date and subject in a revision block.
GTR-13.3.3 Drawings
For all larger pieces of equipment which, due to their dimensions and/or
weight and transport limitations, will require special means for their
transportation, the Contractor shall submit binding loading drawings
indicating dimensions, weights, etc., of the respective pieces of equipment
and the necessary trailer for its transportation to the site.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-33
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Dimension or Outline Drawing shall show all elements and the main
dimensions of individual construction units where necessary with plan,
section, side and top views. If possible such dimension shall be shown on
Arrangement Drawings.
- location and sizes of auxiliary connections for oil, grease, water, air,
etc.
- instructions for heat treatment (if any), pressure tests (if any), surface
preparation and anti-corrosive protection
GTR-13.3.4 Diagrams
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-35
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The circuit diagrams shall show the power circuits in all phases with the
main apparatus as well as the pilot circuits (measuring and control
circuits). It shall show in full the functional part of all installations,
equipment or circuits with all required technical information.
The control part shall be subdivided into separately drawn “current paths”,
each showing all its components regardless of their actual physical
location. The individual circuits are to be drawn in a straight line
sequence, avoiding line crossings. The current paths (to be designated
by numbers or a sheet quadrant cross reference indicating system) shall
be drawn starting from two horizontal lines which represent the control
voltage source. All devices belonging to the equipment or forming part of
the equipment or control devices shall appear between these two lines.
The power circuit portion of the installation shall be drawn at the left side
of the drawing.
Circuit diagrams shall also contain all terminals and their correct
designations. Terminals, grouped together to terminal blocks of
switchboards, distribution boards, etc., shall be shown on the circuit
diagrams in one fictitious horizontal line surrounded by demarcation lines.
If, for any reason, the current paths of circuit diagrams must be separated,
the corresponding counter terminal has to be indicated by cross-
referencing symbol and designation of continuation diagram.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-36
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Process or P & I Diagrams shall show the piping including type,
dimensions, fittings, flanges, etc., and the flow directions, they shall also
show the process data, measuring points, instrumentation control
functions and locations of the equipment.
Such diagrams shall be prepared for any type of terminal box, marshalling
rack, control cubicle, switchboard, etc., and shall show the terminals
(properly numbered) and the internal and/or external conductors (wires or
cables) connected to them.
GTR-13.3.5 Specifications
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-38
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The motor starter lists shall include all starters and contactors used for
motors and shall contain the following technical information as a minimum
requirement:
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-39
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Cable Lists shall include for each individual cable the following as a
minimum requirement:
- cable number
- cable type
- rated voltage
- number and size of conductors
- overall diameter
- cable termination at each end
- connection point at each end with cubicle/equipment
identification and terminal numbers
- cable routing
This list shall indicate all measurements, local as well as remote, and
shall contain at least the following:
These lists shall indicate all alarms and shall contain at least the following:
This list shall indicate all control actuators and control valves and shall
contain at least the following:
- item/code number
- data of pipe and valve connections
- data of valve layout
- maximal required and rated power
- type of ends
- maximum operating pressure/temperature
- design temperature
- insulation type
The list of Tools and Spare Parts to be supplied shall at least contain the
following:
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-41
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-13.3.7 Calculations
13.3.8.1 Contents
a) Table of Contents
b) List of Illustrations
c) Introduction
d) Detailed Description
f) Operating Instructions
The entire testing and adjustment procedure required for the plant
after overhauls and during operation shall be described.
h) Maintenance Instructions
- daily
- weekly
- monthly
- quarterly
- yearly
(or other) cycles as applicable.
h3) Spare parts lists, containing all the necessary data for
ordering spare parts. These lists shall include all spare parts;
those to be supplied and those not be supplied under the
present Contract.
statements and data valid for sizes and types not delivered must be
crossed out (or used items to be marked by frames).
j) As-Built drawings
Deletions:
One sheet of errata, printed on pink paper, shall be issued indicating the
pages and date of issue of those pages which are to be deleted and are
no longer valid.
Insertion, Supplements:
The Contractor shall furnish six (6) copies of the following documents for
NPC’s records:
NDE Results
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-44
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
These drawings shall be kept in the Contractor’s field office and shall be
used only as record set. At the end of every month, all entries, changes
or revisions made in the drawings by the Contractor shall be checked and
approved by NPC.
Prior to Final Acceptance of the Works, the Contractor shall furnish NPC
the complete and duly checked and approved “As- Built” drawings in five
(5) prints, one (1) reproducible copy of approved quality and one (1)
electronic copy in a write-once recordable CD. Such CDs shall be
suitable for CD ROM/WRITE drive of computer system.
GTR-14.1 GENERAL
Within thirty (30) days of the Effective Date of Contract, the Contractor
shall submit six (6) copies of his complete quality control and assurance
procedures, and manuals for review and approval by NPC. The manual
shall include pro-forma checklists for all requirements of the Contractor’s
quality control and assurance program and those called for in this
Specification.
The Contractor shall ensure that all computer systems and software to be
utilized on the project is qualified for the application under consideration
and such qualification is documented.
The Contractor shall establish and implement quality plans detailing the
specific activities, design reviews, operations, control procedures,
inspections, testing, approvals and certification requirements applicable.
All procedures, which support the quality plan shall be referenced and
distributed to NPC together with the quality plan. Quality plans shall be
submitted to NPC for review and approval.
GTR-14.4 RECORDS
All records generated during the course of the Contract, including those
generated as evidence of effective implementation of the quality
assurance program of the Contractor and his subcontractors, shall be
retained by the Contractor for a minimum period of five (5) years from the
date of contract completion. These records shall be made available to
NPC on request during the retention period.
GTR-14.5.1 General
GTR-14.5.2 At Shop
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-46
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
GTR-14.5.3 At Site
The required tests at site shall be in accordance with the latest edition of
ANSI or applicable IEC Standard.
NPC or his duly authorized representative shall control said site tests, in
collaboration with the Contractor’s representatives.
GTR-15.1 GENERAL
The Contractor shall perform at his own expense all tests required to
ensure adequacy of material, workmanship and conformance of
equipment to the guaranteed data other requirements of the specifications
and standards.
The Contractor shall submit to NPC for approval a complete test program
for all equipment to be supplied under the Contract. Likewise, six (6)
copies of test procedures shall be submitted for approval at least sixty
(60) days prior to the conduct of actual test.
NPC shall be entitled to attend and witness all applicable tests specified
for the various items of equipment detailed in the relevant sections of the
Specifications. NPC shall be notified by the Contractor sixty (60) days in
advance about any tests requiring the presence of NPC. Mandatory
notification to NPC shall be observed for all testing to be done by the
Contractor. NPC’s acceptance of the work by waiving the inspection of
tests and receipt of the Contractor’s Certified Test Reports and Inspection
& Testing Certificates shall in no way relieve the Contractor of the
responsibility in accordance with the requirements of the Specifications.
Tests not requiring the presence of NPC shall be, in any case, notified in
advance. In such case, the Contractor shall then proceed with the tests
and shall submit test reports in six (6) copies to NPC.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-47
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
For inspected or tested goods that fail to conform with the Specifications,
the Contractor shall either replace or apply remedial measures necessary
to meet the requirements of the Specifications at no costs to NPC.
During the test and commissioning period, NPC shall provide operations
and maintenance personnel to assist the Contractor in the operation and
maintenance of the plant under the direction of the Contractor.
Unless otherwise specified, all costs for testing of the works and charges
associated with it shall be borne by the Contractor. This includes the
measuring devices, instruments, tools and any pertinent accessories
which shall be made available by the Contractor for the entire duration of
the tests. The Contractor shall delegate his experts to perform such tests.
NPC reserves the right to inspect all shop and assembly work associated
with the Works, verify quantities consigned to stores and inspect quality
control and assurance records as well as shop and purchase order
records. The Contractor shall provide all the necessary assistance to
these visits, inspections and checks and give all necessary information
requested.
In particular, the Contractor shall provide NPC with the list of the
workshops in which different parts of the supply are manufactured and/or
fabricated and shall furnish all the information that may be useful for the
checking of the manufacturing/fabrication and assembly of materials.
NPC reserves the right to witness factory tests specified for the various
types of equipment. No equipment or material shall be shipped from the
factory until it has been inspected or until inspection has been waived in
writing and certified copies of test and inspection reports have been
accepted by NPC.
The Contractor shall carry out tests, as may be required by the specified
Standards and the Quality Control and Assurance Program, as well as the
entire test program approved by NPC. Prior to the witnessing of Factory
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-48
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Tests, the Contractor shall remove all faults found and correct all failures
noted to the best of his knowledge such that no functional or procedural
errors will occur during the test.
The Contractor shall immediately advise NPC should failures occur, take
remedial action subject to NPC’s approval, and proceed with the test as
and when directed by NPC. It shall be the NPC’s prerogative to order a
repeat of all such tests that he deems may have been affected by the
failure.
The Contractor shall ensure that during the test, all hard copies from
output devices are retained and that no outside parties interfere in any
way with testing, equipment or test instruments, fixtures and jigs for the
entire duration of the Factory Test. Only Contractor’s personnel who are
needed on the testing of the equipment shall be allowed in the test area.
The Contractor shall appoint a chief-tester who shall be responsible for
conducting the test, ensuring at all times that the test instruments,
fixtures, jigs and extender cards, and those of the Contractor’s personnel
who in any way may contribute to the test, including testers, specialists
and maintenance personnel, are available prior to scheduled
commencement of each test or as maybe instructed by the Contractor.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-49
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Model tests, if required for certain parts of the work or equipment, shall be
carried out as specified in the subsequent sections of the Specifications.
The typical Pre-commissioning Test shall include but not limited to the
following:
GTR-15.4.1 General
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-51
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Contractor shall develop and submit the procedures for initial
operation of the generating unit for NPC’s review and approval.
The checks and tests specified herein are the minimum requirements. All
other checks and tests shall be performed as may be required. All checks
and tests shall be recorded. Such records shall be signed by applicable
manufacturer’s/contractor’s representative and copies shall be furnished
to NPC.
If any defects or irregularities affecting the safety and reliability of the plant
should arise during the initial operation, the initial operation shall be
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-52
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
interrupted and started again after such defects or irregularities have been
corrected by the Contractor.
Performance test shall include but not limited to unit capacity test and
efficiency test and shall be conducted in accordance with international
standards such as the latest edition of ASME Power Test Code and IEC
41.
a) Introduction;
b) Purpose of Test;
f) Step by step calculations indicating how the test data are used to
arrive at the final results;
After the Performance Test and after the Contractor has notified NPC that
the generating unit including its associated auxiliary equipment is ready
for commercial operation, provided that NPC is satisfied that such is ready
for commercial service, Reliability Run shall be carried out for a period of
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-53
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
seven days (168 hours) for each unit to confirm its reliability. The unit with
all its auxiliaries is required to operate under normal working conditions of
the plant within the limits of output specified and operating continuously
without major failure or interruption for the entire duration of the Reliability
Run.
The unit shall be operated by NPC personnel under the supervision of the
Contractor’s Engineers during the reliability test period, but the Contractor
shall be allowed to make any minor adjustments which may be necessary,
provided that such adjustments do not in any way interfere with or prevent
the commercial use of the plant by NPC or reducing the plant output.
Reliability Run would be considered a failure for any one of the following
causes:
In case of the above failure, the reliability test period of seven days (168
hours) shall recommence after the Contractor has remedied the cause of
defect.
If any equipment or component fails to pass any test, NPC reserves the
right to direct the Contractor to make any necessary corrections or
alterations for defects or order equipment/component replacement, as
maybe deemed appropriate. Any and all expenses due to additional tests
or retests made necessary by failure of Contractor’s supplied
equipment/component, i.e. failure to meet the guarantees and other
requirements of the specification, shall be borne by the Contractor. The
costs of witnessing the Factory Test by NPC as a result or re-test to be
conducted on the equipment shall also be borne by the Contractor. Any
penalty specified in the relevant sections of the Specifications shall be
applied.
NPC also reserves the right to reject any equipment or material that is
found to be defective or fails to meet the guarantees.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-54
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
Six (6) certified copies of the reports of all NPC’s specified tests and other
manufacturer’s standard tests shall be furnished to NPC within a
maximum of fifteen (15) days following the completion of the tests.
Test certificates shall include, in addition to the test results, the following
information:
The Contractor shall bear the cost of furnishing these records and reports.
If NPC opted not to witness the Factory Tests, NPC will issue a Certificate
of Waiver of Tests Witnessing/Inspection for the equipment and materials.
In such case, the Contractor shall proceed with the Factory Tests in
accordance with the requirement of the specification and the
manufacturer’s test specification as approved by NPC.
GTR-16.1 GENERAL
The cost of training shall be borne by the Contractor and shall be included
in the bid price.
At least four (4) NPC representatives shall attend the training program for
each item above.
The Contractor shall provide adequate training facilities for the entire
duration of the training program. The training program shall impart
necessary expertise and competence in the area of design, engineering,
erection, operation and maintenance of the specified equipment/system.
The components of the training modules shall include but not limited to
the training procedures/methodology, instruction materials and manuals
for each trainee.
The Contractor shall conduct training at Site of NPC personnel who will be
assigned to operate and maintain the plant. At least twenty (20) NPC
personnel from the plant shall participate in the training program. The
Contractor shall provide a comprehensive training program related to
design application, operation and maintenance, including trouble shooting
of the Contractor’s supplied system and equipment to such extent that
thereafter the duties can be assigned to the trained personnel.
The contents of the training program shall include but not limited to:
The timing of the training should be such that the participants will be
equipped with sufficient know-how to participate in the pre-commissioning
and commissioning tests of the Plant.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-56
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Contractor shall supply all the spare parts listed and specified in the
subsequent sections of the Specifications. However, items not specifically
mentioned but required for regular operation and maintenance shall be
supplied to ensure reliable operation for two (2) years. Spare parts shall
include all items that are expected to be consumed or replaced during the
commissioning stage and these shall be identified in the Spare Parts List.
During the Guarantee Period, if the quantity specified in the final list of
spare parts is found not sufficient for two (2) years reliable operation, the
Contractor shall supply the additional spare parts at his own cost.
Acceptance of any spare parts will not take place before the Contractor
has submitted the complete final detailed list of all spare parts and tools.
All spare parts shall be delivered in marked boxes of sufficient sturdy
construction and placed in storage areas nominated by NPC. The delivery
will be deemed to be complete when the packages have been opened by
the Contractor, their contents checked by NPC, and articles reprotected
and replaced by the Contractor to the satisfaction of such representatives
or assembled into units at NPC’s option and stored as directed by NPC.
Damaged or incorrect item shall be replaced by the Contractor at his own
cost.
All bidders are required to submit in their proposal the detailed list of
spare parts to be supplied with its corresponding costs. This list is
preliminary and subject to changes in order to conform with the final
design without any additional cost. The final list of spare parts shall be
submitted to NPC for approval not later than one (1) month prior to the
delivery of the equipment.
The Contractor shall indicate the expected life of the parts requiring
replacement and the minimum recommended inventory of the spare parts
for installation, start-up, continuous operation, and maintenance. The
Contractor shall state whether the recommended spare part is a stock
item or a special item, and shall furnish name and location of the nearest
supplier, and approximate lead time required for delivery.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-57
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The following tools and appliances shall be supplied under this Contract
including all items listed and specified in the subsequent sections of the
Specifications and the Contractor shall give a full list with complete detail
in the Schedule of Tools and Appliances:
a) One (1) set of special tools and instruments required for start-up,
test and commissioning, operation and normal maintenance of the
equipment supplied under these Specifications.
Special tools are defined as all tools required for installation, assembling,
dismantling and adjustment of all the works and usually not available in a
standard machine shop.
Each tool or appliance is to be clearly marked with its sign and purpose
identifying the function of each tool and the specific item(s) for which it is
used. Each set of tools and appliances listed above shall be fitted into a
custom built lockable box clearly marked with the name of the item or
equipment for which they are used and with a list of the tools contained,
stamped and attached on an attached metal tab.
If the weight of any box, or its size, is such that it cannot be conveniently
carried, it shall be supported on steerable rubber tired wheels. All large
tools and wrenches shall be mounted on a suitable shadow board
arranged for wall mounting.
All tools and appliances supplied shall be handed over to NPC in perfect
condition at the time of taking over.
All bidders are required to submit in their proposal the detailed list of
special tools to be supplied with its corresponding costs. This list is
preliminary and subject to changes in order to conform with the final
design without any additional cost. The final list shall be submitted to
NPC for approval not later than one (1) month prior to the delivery of the
equipment.
The Contractor shall remove, dismantle, haul, transport and unload to the
designated storage area all equipment that need to be replaced and other
devices identified to be no longer required for installation.
Procedure and work program covering the above works shall be prepared
and submitted by the Contractor for NPC’s review and approval.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-58
BID DOCUMENTS AGUS 6 (UNITS 1 & 2) UPRATING PROJECT
SECTION VI – TECHNICAL SPECIFICATIONS
PART I – TECHNICAL SPECIFICATIONS MinP12Z310Se
The Contractor shall identify the most convenient access and manner of
moving the equipment out of a fixed structure. Whenever possible, the
Contractor shall transport/haul the equipment area by skids or assembly
so as to reduce the dismantling works.
GTR-19.0 CLEAN-UP
When the works are completed, the Contractor shall remove from the
Site, without expense to NPC, all temporary structures, excess materials,
debris, and rubbish of every sort; shall fill and dress all holes and cavities
made for his convenience; and shall leave the whole area in good order
and condition, all as required and directed by NPC.
GTR-20.0 GUARANTEES
Should the works divert from the provisions of the Contract, NPC has the
right to reject any part or parts thereof. In case of rejection, the
Contractor shall be bound to effect at his own cost, modifications or
substitutions as may be considered necessary in order that the works
shall conform to the requirements of the Contract.
The Contractor shall guarantee that he will repair and/or replace, at his
own cost, equipment and machineries against defect in design,
workmanship and materials for a period of twelve (12) months after the
equipment have been installed, commissioned, and accepted by NPC.
____________________________________________________________________________________________________________
NATIONAL POWER CORPORATION VI-GTR-59