Vous êtes sur la page 1sur 60

Contents

1. Understanding the Engineering Documents ............................. 4


1.1 Anchor Bolt Setting Plan
1.2 Cross Section
1.3 Roof Framing Plan
1.4 Roof Sheeting Layout
1.5 Sidewall & Endwall Sheeting & Framing
1.6 Other Drawings
1.7 Bill of Materials (BOM)

2. Preparation for Erection ....................................................................... 11


2.1 Introduction
2.2 Pre-Erection Checks
2.3 Receiving Materials at Site
2.4 Unloading Containers (for Overseas Shipments)

3. Erection of the Framing ........................................................................ 14


3.1 Preparation of the First Bay
3.2 Main Frames
3.3 Mezzanine Floors
3.4 Crane Beams

4. Sheeting & Trimming .............................................................................. 19


4.1 Sheeting Preparation
4.2 Sheeting the Walls
4.3 Sheeting the Roof
4.4 Miscellaneous Trimming
4.5 Fascia

5. Care & Handling of Sheeting ............................................................. 25


5.1 Handling & Installation of Sheeting
5.1.1 Unloading
5.1.2 Storage
5.1.3 Handling
5.1.4 Cutting & Fixing
5.1.5 Completion & Inspection
5.1.6 Paint Repair
5.2 Water Test Procedures for Roofing
5.3 General Tips

6. Maintenance Procedure ....................................................................... 29


6.1 Maintenance for Longer Life
6.2 Safety Notes
6.3 Exterior Maintenance Procedure
6.4 Maintenance of Accessories
6.5 Record of Maintenance

7. Safety Precautions ................................................................................... 32

8. Quality Control .......................................................................................... 33

9. Basic Erection Equipment .................................................................... 34


Zamil Steel Pre-Engineered Buildings I Erection Manual
9.1 Main Erection Equipment ............................................................... 35
Mobile Crane Guy Wires
Forklift Clamps, Shackles & Clips
Telescopic Handler Ratchet Puller
Scissor Lift Light Duty Scaffolding
Lifting Beam Ladders
Slings

9.2 Electrical Equipment & Tools ......................................................... 37


Generator Aviation Snips (Left & Right Cut)
Screw Gun Vise Grips
Nibbler Torque Wrench (With Sockets)
Grinder Ratchet Spanne (With 19 mm Sockets)
Hammer Drill Staple Applicator
Hole Cutter Utility Knife
Impact Wrench Hacksaw
Electric Shear Mastic Gun
Heavy Duty Drill with Reamer Spud Wrench
Reciprocating Saw Drift Pin
Drill 10 mm Miscellaneous Tools
Powder Actuated Tool Tool Belt & Bolt Bag
Pop Rivet Puller Chalk Line

9.3 Measuring & Surveying Equipment ........................................... 42


Plumb Bo
Theodolite
Automatic Level
Spirit Level
Measuring Tape & Square

9.4 Safety Equipment .............................................................................. 43


Welding Hood
Goggles
Gloves
Safety Harness & Fall Arrest
Safety Boots
Hard Hat
First Aid Box
Cones & Ribbons
Portable Fire Extinguisher
Ear Protection

9.5 Other Equipment ............................................................................... 44


Welding Machine
Oxy - Acetylene Cutting Outfit

10. Attachments .................................................................................................45


Glossary ........................................................................................................... 55
Commonly Used Abbreviations ............................................................. 58
Introduction
The primary goal of Zamil Steel is the satisfaction of
our customers. We design, detail and fabricate our
buildings using sound principles of engineering,
and fabricate every component with the utmost
attention to quality and detail. When work at the
factory is finished, only one final operation remains,
erection. The importance of following a specific
method of erection cannot be underestimated,
and the purpose of this manual is to facilitate and
ensure Quality Erection, thereby creating the finest
possible steel structure.

For purpose discussed here, erection refers to the


assembling of the various component parts that
make up the pre-engineered steel building. The
erection process entails much more than merely
installing the fabricated steel for the building. It
actually begins with the foundation and building
anchorage and continues to cleaning the job site
upon completion.

The methods and procedures suggested by this


Erection Guide represent basic, safe erection
practices. They can, and should, be modified
when necessary to adapt to special conditions or
circumstances.

Before beginning erection work, familiarize


yourself with the building details and the sequence
of erection. This will enable you to plan your work
efficiently and avoid unnecessary delays during
construction.

Zamil Steel’s policy of continuous product


improvement may necessitate changes in
materials, design specifications, and procedures
without prior notice.

Important notice: Zamil Steel recommends that


the erection work, be caried out by a Zamil Steel
certified builder. However, Zamil Steel accepts no
responsibility for erection quality, leakage, defects
or collapse due to negligence or failure to follow
proper erection procedures.
Zamil Steel Pre-Engineered Buildings I Erection Manual
1
Understanding
the Engineering
Documents

1.1 Anchor Bolt Setting Plan


1.2 Cross-Section
1.3 Roof Framing Plan
1.4 Roof Sheeting Layout
4
1.5 Sidewall & End wall
Sheeting & Framing
1.6 Other Drawings
1.7 Bill of Materials (BOM)
1. Understanding the Engineering Documents
Prior to beginning the erection work, it is essential The Anchor Bolt layout also includes an anchor bolt
to have a clear understanding of the Engineering schedule, in table form, showing the, quantities
Documents, especially the Erection Drawings and and sizes of the anchor bolts required.
Bill of Materials.
The key plan specifies out-to-out the dimensions,
Erection Drawings to be used at site should be bay spacing dimensions, bolt setting details and
labeled “Issued for Construction” and represent critical dimensions for the span. Critical distances
the latest project revision. Approval Drawings on the drawing should be respected at all times.
should never be used at the erection site. The details specify whether grout is required under
the columns. The grout thickness will be shown on
1.1 Anchor Bolt Setting Plan the drawings, as well as the bolt projection.

This drawing shows the layout of all anchor bolts, it Adherence to anchor bolt setting tolerance is
is normally presented on one sheet, but for relatively important; deviation shall not exceed 6mm.
large buildings, this layout may be represented on
two or more sheets. Erection drawings are not
made to scale, so do not attempt to scale any
dimensions. All dimensions appear in millimeters
unless otherwise noted on the drawings.

5
Zamil Steel Pre-Engineered Buildings I Erection Manual
1.2 Cross-Section

The cross-section drawing indicates columns


and rafter references, connection details, bolt
schedules, flange brace schedules and other
information as applicable, such as strut tubes and
flange brace details.

When reviewed in conjunction with the Bill of


Materials it is possible to determine the weight
of individual members, or a combination of
assembled members. This data is essential during
the planning of erection, and needed in order
to determine the capacity of the erection crane to
be used.

The cross section drawing may be typical


throughout in standard buildings but for more
complex jobs, there may be several cross sections,
identified by grid numbers.

CROSS SECTION

CROSS SECTION
1. Understanding the Engineering Documents

1.3 Roof Framing Plan

The roof framing plan illustrates the purlins, bracing


and related miscellaneous details. Part numbers
are indicated on this drawing for purlins, bracing,
sag rods (where applicable), strut tubes etc.

The drawings should be studied very carefully,


otherwise it is possible to overlook critical details
such as nested purlins, strut purlins, strut clips,
and purlins/girts at expanstion joints.

ROOF FRAMING PLAN

ROOF FRAMING PLAN


Zamil Steel Pre-Engineered Buildings I Erection Manual
1.4 Roof Sheeting Layout

The roof sheeting plan displays all the panels


including their length and part numbers. It also
shows the sky light distribution and downspout
positions.

Standard details of panel lap, fasteners, trims and


insulation are also included. It is very important to
note the starting dimension of the sheeting from
the steel line.

ROOF SHEETING LAYOUT

ROOF SHEETING PLAN


1. Understanding the Engineering Documents

1.5 Sidewall & Endwall Sheeting & Framing

Depending upon the drawing and erection


requirements, sidewall framing and sheeting may
be represented on one drawing or more.

The framing elevation shows the position and


part numbers of girts, eave struts, bracing and
sag rods.

The sheeting elevations show the panel positions


with length and part numbers. Wall lights eave
trims, gutters and downspouts are also shown
along with part numbers. Related standard details
are included which indicate the number, size and
position of fasteners. Additional trimming details
are also included in the drawing. For side walls, it
is important to check the starting dimension of the
sheeting from the steel line.

End-walls are detailed in a similar manner.

SIDWALL SHEETING

SIDWALL FRAMING AND SHEETING ELEVATION


Zamil Steel Pre-Engineered Buildings I Erection Manual
1.6 Other Drawings

Other drawings may include crane beam layouts The sub total of weight and the total number
and details; Mezzanine layouts and details; of items is shown at the end of each sub-area.
and accessories such as Sliding Doors, Roll-up The last page indicates the total BOM quantity and
doors, Staircase Cage Ladders, Personnel doors, weight.
Windows, Louvers and Ventilators.
The BOM is a reference to the items shown on the
1.7 Bill of Materials (BOM) Erection Drawings and can be used to verify that all
items have been received at the site. It is also used
The BOM supplied with the Erection Drawings is to identify frame weights for crane capacities.
the Customer BOM.
The BOM has 9 columns indicating
The BOM begins with a cover sheet indicating the 1 - Line number
job number, building number and phase, customer 2 - Part number
name, location, and building size. The cover sheet 3 - Quantity
also shows the number of phases in the building, 4 - Revision number
any revisions, and special notes. 5 - Description of part
6 - Colour
The second page indicates the various sub-areas of 7 - Length of item
the phases. On the next page, the detailed BOM 8 - Weight of item
list of the items included in each phase begins. 9 - Total weight of line item

10
2
Preparation
for Erection

2.1 Introduction
2.2 Pre-Erection Checks
2.3 Receiving Materials at Site
2.4 Unloading Containers
(for Overseas Shipments)
11
Zamil Steel Pre-Engineered Buildings I Erection Manual
2.1 Introduction

Erection of Pre-Engineered steel buildings is a


straightforward operation, provided some basic
principles are followed and common sense used.

The light weight of built-up and cold formed


members used in pre-engineered steel buildings
require less crane capacity but will need more
temporary bracing during the erection stages. Due
to the synergic design, temporary bracing should
be left in place until the braced bay components
are completely erected, aligned and tightened.

A clear understanding of the sequence of erection Anchor bolts in concrete foundations


is necessary together with careful planning.
The erection drawings and bills of material
provided by Zamil Steel should be studied before
commencement. Familiarize yourself with the
various components and their weights, evaluate
the site conditions, and decide where to start,
bearing in mind the stability of the building
during erection thence a braced bay must be
erected first.

The major components comprise of, rigid frame


columns and rafters, eave struts, purlins, girts,
flange braces, end-wall columns and bracing
systems which may be cables, rods, angles
or portals. 12
2.2 Pre-Erection Checks

Make sure that the building foot print, in addition


to 10m wide strip around it, is clear of obstructions,
level and compacted. Check the anchor bolt
settings for compliance with the details provided
on the Anchor Bolt Setting Plan. The allowable
tolerances are given in the General Notes on
the drawing.
The following dimentions must
Check the foundation levels. In buildings that
require grout, shim packs are placed in the be controlled:
centre of the bolt pattern. Buildings without
crane systems generally do not require grout, but A - Steel Line to outer bolt row
B - Diagonal distance between bolt groups
variances inconcrete levels may necessitate the
C - Distance from axis center line to bolt row
use of shims if the concrete is outside the stated
C - Distance between bolts
tolerances. Due to design requirements on certain
D - Distance between frame axis
buildings, double nuts may be used.
E - Destance between Steel Lines Levels of
foundations Anchor Bolt protrusion
A comprehensive survey report should be made
and documented. A site take-over report from
the client will assure site accessibility and level for
cranes and trucks to maneuver freely.
2.3 Receiving Materials at Site

Receiving and unloading of materials should take


place as near as possible to the place of erection.
The lay-down area should be clean and leveled. A
suitable forklift or telescopic handler is ideal for
unloading, but a mobile crane is equally suitable. In
either case, care needs to be exercised in handling
the various components and bundles, to minimize
damage to paint. Protect cold-formed members
such as purlins, girts, and channels from weather,
by storing the bundles with an inclination to permit
water drainage in case of rain or condensation. It is Unloading from trailer
advisable to lightly cover with a tarpaulin. Bundles
of sheets should be stored in the same way,
keeping the bundles clear of the ground. Check
materials against the Packing List and immediately
report shortage or excess material to Zamil Steel
representative.

2.4 Unloading Containers


(for Overseas Shipments)

Good Preparation will make container unloading


a straight forward operation. If possible select a
firm, level, asphalt, concrete or compacted area.
Unloading will be considerably easier if a small step
is made so that the inside base of the container is Unloading to lay-down area
level with the external ground.
13
Unload the container from the trailer using a mobile
crane and four leg slings or chains of the correct
capacity. Set the container on the ground, and
level it, open the doors before final positioning.

Sliding tracks are provided in the container for


withdrawing the skid. Pull out the tracks, lay them
on the leveled ground, and align them with the
inside tracks. Secure the tracks by nails or steel pins,
the tracks must be continuous from the container
to end of the runway, (Length of Container).

Attach chains to the front of the skid in the Stacking on wooden planks
container, and then attach to the pulling vehicle.
Take up the strain on the chains, and steadily pull
the skid from the container. When the materials
are clear of the container, remove the skids from
the container floor.

Unloading containers
Zamil Steel Pre-Engineered Buildings I Erection Manual
3
Erection of
the Framing

3.1 Preparation of the First Bay


3.2 Main Frames
3.3 Mezzanine Floors
3.4 Crane Beams

14
3. Erection of the Framing

3.1 Preparation of the First Bay 3.2 Main Frames

Prepare all materials for the first bay erection with Erect the first four columns at the braced bay.
permanent bracing, (braced bay). Identify the rafter Verify the part number and orientation, and
sections required by part number, assemble the position over the anchor bolts. Adjust the columns
rafter sections as near as possible to their intened for plumb by tightening or loosening the anchor
positions. The splice connections are made with bolt nuts (Step 1).
high strength bolts; the sizes are shown on the
drawing cross section, identified as S1, S2, and S3 Fix the wall girts to the columns for additional
etc. Tighten the splice bolts and check for correct stability. Girts are attached to the columns by mild
torque value using a calibrated torque wrench, or steel (MS) bolts.
by turn of nut method. Attach eave strut clips using
high strength bolts. Fix flange braces to the rafter Position the crane for lifting the assembled rafter
using machine bolts, the flange brace positions sections. Make sure that the ridge connection
and part numbers are shown on the drawing cross is torque-tightened (Step 2). Check that slings,
section. Flange braces are fitted on one side of chain and shackles are in good condition and of
the rafter only. For uniformity it is preferable to adequate capacity for the weight to be lifted. The
maintain the same side throughout the building. chains or slings should be long enough to provide
sufficient spread, at an angle of not less than
Attach temporary guy wires to the rafter, manila or 45 degrees. The spread of the slings is normally
nylon ropes are not recommended for temporary calculated by dividing the member length by
guying, they can stretch and break. They are also four, which will give the distance of the lifting
unsuitable for aligning purpoes. point from each end. This formula may require
some minor adjustment depending on the weight
Prepare the mobile crane and Forklift for erection.

15
Step 1

Step 2

Step 3

3.1
3 1 First frame of braced bay 3.2
3 2 Second frame of braced bay 3.3 Roof purlins
Zamil Steel Pre-Engineered Buildings I Erection Manual
distribution and configuration of the rafter. Refer placed from the top, with the nut and washer on
to image 3.1. the underside. Hand-tighten the bolts. Ratchet
pullers are attached to the guy wires, which are
Flange clamps are a safe lifting device which also then connected to suitable stable objects, such as
minimizes damage to paint. When using clamps, anchor bolts. The rafter is now aligned by means
install temporary bolts in the purlins holes, or use of the guy wires and ratchet pullers. Once all guy
“G” clamps to prevent the clamps from sliding. If wires are in place it is safe to release the crane
clamps are not available, conventional slings may (Step 4).
be used, in which case timber or other protection
should be used on the flanges to prevent slipping Erect the second rafter and hold in place with the
and damage. crane, at the same time position the purlins and
bolt-up using mild steel bolts (Step 5). Connect
Commence lifting the rafter (Step 3). Previously the previously attached flange braces to the purlins
attached hand ropes will help to guide the rafter with mild steel bolts (Step 6). The eave strut should
to its position. Carefully lower the rafter to the also be installed at this stage, but unlike the purlins
column cap plates, and position it using spud the eave strut requires high strength bolts. Refer
wrenches. Spud wrenches are an invaluable tool to image 3.2.
for aligning members and holding in position
whilst bolting up.

Install the high strength bolts, nuts and washers


in the knee connection. The bolt is normally

16
Step 6

Step 5

Step 4

3.4 Roof bracing 3.5 Erect next bay 3.6 Erect remaining bays
3. Erection of the Framing

Complete the purlin installation and then install When the main frames are all completed, the
the diagonal bracing. Before tightening the end-wall framing is erected. Pre-assembly of
diagonal bracing, ensure that the lip of the hillside columns and girts on the ground saves time and
washer is correctly seated in the web slot. Adjust is more efficient. End-wall posts are connected
the tension of the bracing; at the same time adjust to the purlins by post spanners using high
the rafter alignment. The bracing shall be just strength bolts.
tight enough to eliminate visual sagging. In case
of portal bracing, it must also be erected before The complete frame should be checked for plumb
proueding in the other bay. For high endwalls use and alignment. Adjustments can be made by
temporary bracing during erection. Refer to image tightening or loosening bracing, or by ratchet
3.3 on the previous page. puller, to pull a misaligned frame into plumb.
After completion of all checking, bolt tightening
The completed braced bay should now be aligned. can commence. Air or electric impact wrenches
A theodolite should be used for plumbing, if may be used and checked with a torque wrench,
available, or for buildings of low eave height, a or they can be tightened manually using the
spirit level or plumb-bob may suffice (Step 7). “Turn of Nut Method” (preferred).
A tolerance of 1:300 is allowable in low rise
buildings. Refer to image 3.4. The Turn of Nut Method is achieved by bringing all
the bolts in the pattern to a snug tight position,
After completing the first bay alignment the high using a normal spud wrench. Match mark the
strength bolts at the knee connection shall be fully nuts against the connection plate, and then apply
tightened. Time spent on correct alignment of the a further one third turn to all the nuts.
first bay will reap benefits as work proceeds with
the remaining bays. Prior to sheeting, framed opening members for
sliding doors shall be installed; this includes door
The remaining bays are erected following the jambs, brackets and header.
same procedure (Step 8). All components shall
17 be installed as work progresses, including crane PLUMBING THE BRACED BAY
beams. Refer to image 3.5.

Multi-span frames provide a degree of flexibility in


erection in that partial spans may be erected if site
conditions dictate. Refer to image 3.6.

Step 7

Step 8
Zamil Steel Pre-Engineered Buildings I Erection Manual
3.3 Mezzanine Floors

When mezzanine floors are provided, they are


erected with the main frames, generally prior
to sheeting.

Alignment is achieved by setting each end of the


beam to the correct dimension as shown on the
drawing, and stretching a line from end to end,
alternately, a theodolite can be used if available.

The crane beam brackets have slotted holes to


The mezzanine beams are first installed by assist in ease of alignment, if the building has been
connecting to the columns with clips and high carefully plumbed, adjustment will be minimal.
strength bolts as indicated on the drawing details. During alignment install the “T” brackets and shim
plates, and install the angle braces from column
The joists are then placed between the beams and to beam. Once final alignment is confirmed, fully
connected as shown on erection drawings. An tighten all high strength bolts.
edge angle is then screwed at the perimeter of the
mezzanine area, prior to laying and screwing the 3.5 Important 18
decking panels.
No loads should be supported from the purlins
The decking panels are attached by self drilling unless the building has been designed for those
fasteners without washers. Openings for stairs additional loads. In such cases, the loads can be
and penetrations are framed before fixing the supported from the purlins after the roof sheets
concrete reinforcement. have been installed and fully screwed.

It is important to advise the concreting crew about The following sketches show correct and incorrect
placement of concrete, particularly if a pump is to methods of support from rafters and purlins.
be used. The concrete should be evenly spread;
concentrated piles of wet concrete could cause
deformation in joists or decking, which could
lead to collapse. It is, sometimes advisable to use Rafters
temporary shoring at mid spans inorder to assure
straightness of finished concrete.

3.4 Crane Beams

Special care should be taken in buildings with


crane runways, the column supporting runway
beams should be erected on shims provided, or
Purlins
double nuts in addition to grouting under the
base plates.

Alignment of crane beams i s very important, the


centerlines of the crane beam webs should matche
with the centerlines of the crane wheels, and the
maximum allowabletolerance is 10mm.
4
Sheeting &
Trimming

4.1 Sheeting Preparation


4.2 Sheeting the Walls
4.3 Sheeting the Roof
4.4 Miscellaneous Trimming
4.5 Fascia
19
Zamil Steel Pre-Engineered Buildings I Erection Manual
4.1 Sheeting Preparation

Touch-up any damaged paint on the main frame


prior to sheeting.

The base angle is fixed to the concrete slab by


means of masonry nails. Power actuated tools are
preferred for fixing. The fixings for the base angle
are provided by the erection contractor, to ensure
compatibility of nails and fixing tools.

The base angle should be set at the wall grit line


(steel line) which is 200mm from the column
flange in the case of by-pass girts.

There is a tendency for wall girts to sag under their


own dead load, especially in bays over 7.5 meters.
Girts are temporarily supported in a horizontal line
with vertical timber props from floor to girt, girt
to girt, and girt to eave strut. The props remain in
place until the wall panels are screwed. They can
then be removed and relocated to the next bay.
The girts will remain straight and horizontal once
the panels are installed. In bays over 8.5 meters
sag rods are provided and once adjusted there is
no requirement for temporary timber props.

Before commencing with sheeting check the


details on the drawings. A starting position will be
given in relation to the steel line. Mark the starting 20
position, and then mark out the gauge cover
width of the sheets along the concrete notch. This
will provide a check against “creep” or “bunching”
of the panels. An important point in order for the
corner trims to fit as detailed. Insulation is more
convenient to handle if unrolled on the ground
and pre-cut to the required lengths. A full length
piece is used from eave to floor, with an allowance
at top and bottom for folding over.

Tools Preparation on roof


4. Sheeting & Trimming

A chalk line is essential for marking the girt position


and thus maintaining a straight screw line. All
screws are self drilling and require an electric
screw-gun with a speed of 2000 to 2500 RPM.
Depth sensitive or torque regulated screw-guns
should be used to control the screw tightness. The
EPDM washer should be compressed 1 mm wider
than the steel washer when correctly tightened.

4.2 Sheeting the Walls

The first “drop” of insulation is fixed using double


face tape on the eave strut and the base angle;
Chalk Line
this is used to hold the insulation in place. The
insulation must be kept vertical, and pulled taught.
Remove the fibres from the allowance at top and
bottom and fold the white facing before placing
the wall panel. Place the panel in the pre-marked
position, plumb it and screw.

The second “drop” of insulation is fixed to the


double faced tape and then the side tabs are
stapled to the first “drop” at 300mm centres,
folded and stapled again in-between the previous
staples, thus providing a closed joint and vapour
barrier. Then, the second panel is installed in the
same manner and so on.
21 Wall Insulation
End-wall panels are pre-cut in the factory. The
panels are stepped, the steps being covered by
the gable trim. (Field cutting may be necessary on
steep slopes).

The preferred procedure is to complete all wall


sheeting before starting the roof, as the eave trim
covers the top of the wall panel and fits under
the roof panel. Outside foam closures are placed
between the wall panel and the eave trim to
provide a dust free junction.

If there is no wall insulation, foam closures are used


between the panel and eave strut / base angle. Multi-level Man-basket
Zamil Steel Pre-Engineered Buildings I Erection Manual
4.3 Sheeting the Roof

Prepare the roof panels by segregating them by


their length shown on the roof sheeting plan. The
sequence of roofing is from eave to ridge on both
slopes finishing with the ridge panel.

To commence, it is advisable to temporarily fix


one run of panels accross the building to walk
on. The insulation can then be unrolled beside the
“walkway”.
Direction of sheeting installation
Double faced tape is applied to the eave struts, or
an intermediate purlin if the roll does not cover
the full width of the building. The insulation is
lifted into place and is retained in place by the
double faced tape. Before placing the roof panel,
the insulation end should be folded over to be
concealed at the eave. It is necessary to scrape
away the fibres on the folded portion. The inside
foam closure is placed on the fold at the eave strut,
and the panel is then positioned.

Adjust the line of the panel for squareness to avoid


“saw-toothing” at the eave line. Use a nylon line
projected from the eave strut by 65mm to give the
correct distance and line. Sheeting the roof

Screw the panel and move progressively panel by


panel up to the ridge. After completing several 22
runs of panel, the temporary “walkway” can be
lifted, insulated, and sheeted.

Panel end-laps require bead mastic. The bead


mastic should be carefully unrolled from the release
paper, and placed over the panel corrugations. Do
not stretch the bead, otherwise it may break when
the panel is placed over it Ensure that the panel
end-laps are as per drawing details.

Make sure that the panel ribs are kept in a straight Double face tapes
line from eave to ridge. Use a chalk line tomark
the purlin location and maintain a straight line
of screws, thus avoiding mis-drilling and possible
leakage. End-laps have additional screws as
detailed on the drawing.

Proceed with the next run of insulation, stepling


the side tabs together, before placing the next run
of panels. When both slopes of the roof panel
have been fixed, the ridge panel or ridge cap
is laid, connecting both slopes. If a ridge cap is
used then outside foam closures are used to fill
the panel profile, if a ridge panel is used as with
Type’S’ panel, it nests without foam closures. Bead mastic
4. Sheeting & Trimming

4.4 Miscellaneous Trimming

As work proceeds, it is important to keep the roof Upon completion of the roofing, gable trims are
area clean, a soft brush should always be readily installed. Outside foam closures are used against
available to sweep off drill swarf, metal filings the end-wall panel. The stitch screws securing the
or grinding dust, which will cause light surface gable trim also keep the foam closures in place.
corrosion if not removed.
Eave gutters are spliced using two runs of flowable
Stitch screws are fixed at panel side-laps at 500mm mastic and pop-rivets at 25 mm centres. The
centres, or as detailed. gutter is then hung by means of gutter straps
which are screwed through the roof panel with
suitable screws.

Down spout connections are cut with aviation


snips in locations shown on the roof plan. The
down spouts are assembled in straight sections
and a shoe, the complete unit is then attached to
Note: Roof panels are generally fixed in the gutter by pop rivets and to the wall panel by
the valley of the panels, unless straps and rivets.
noted otherwise.
Personnel doors are supplied in knock-down
form and are generally field-located. The frame
is assembled and installed. The wall panels are
carefully cut using an electric nibbler, final cutting
and fitting of head trim should be done with
aviation snips. The galvanized threshold support
is fitted and screwed to the concrete before
the frame is connected to the girt by clips, and
anchored to the floor with expansion bolts. Check
23 that the frame is plumb and square before final
fixing. Head trim, jamb trims and the door leaf are
now fitted.

Fixing Eave Trim Fixing Trims


Zamil Steel Pre-Engineered Buildings I Erection Manual
4.5 Fascia

Where interior liner panel is detailed, a base angle Fascia posts are bolted to brackets. Fascia girts are
is fixed to the floor as for the external panels. then attached to the posts. The girts consist of “C”
It shall be positioned 200 mm away from the and “Z” sections, which must be correctly aligned
exterior base angle. The liner panels are pre cut and levelled before commencing sheeting the
to length, but may require cutting vertically at fascia. Use temporary props if necessary. Prepare
columns, depending on the bay width. Closure the sheeting by installing the sill trim on the
trims are fitted at columns, and a head trim along bottom girt.
the top of the panel. Trims are fixed with 4.8 x 20
stitch screws, the panels with 5.5 x 25 self drilling Check the starting dimension from the corner of
screws. Sliding doors leafs are assembled on the framing. Set up the first panel. Clamp it with
the floor. The framing members are connected vice grips when adjusted to its correct position.
by mild steel bolts and clips. The sheeting is fixed Mark the girt line with a chalk line and then screw
before hanging the door. The trolley trucks are the panel to the girt.
located in the top member of the door leafs. The
adjusting nuts on the trolley trucks should be Continue installing panels on each elevation
set equally, final adjustments can be made after until sheeting is completed. The back-up panels
hanging the doors. are installed next; they are attached to the top
girt, and overlap the valley gutter at the base.
Once the doors are hung and positioned over The external corner trims are installed using 4.8
the bottom door guide, the stoppers, the landles x 20 stitch screws. The Cap flashing can now be
and the door hood are installed. Note that there installed using 4.8 x 20 stitch screws. Make sure
are two types of hood trim. One fits behind the that the flashing slopes into the building as shown
sheeting in the door opening, and the other fits in on the drawing. The overlapping joints of the
front of the sheeting on each side of the opening. flashing should be sealed with flowable mastic.
Complete details are on the drawing. Bottom
running doors are also available. The soffit panel edge trim is fitted to the wall
panel, make sure that it is level with the sill trim,
and is levelled around the building. Starting the 24
soffit in the correct place is important, if the soffit
panel and wall/fascia sheets are the same type,
the ribs should be aligned. Align the ribs, and fix
the panels as shown in the detail. Corner panels
should be mitred equally.
5
Care &
Handling
of Sheeting

5.1 Handling & Installation


of Sheeting
5.1.1 Unloading
25 5.1.2 Storage
5.1.3 Handling
5.1.4 Cutting & Fixing
5.1.5 Completion &
Inspection
5.1.6 Paint Repair
5.2 Water Test Procedures
for Roofing
5.3 General Tips
Zamil Steel Pre-Engineered Buildings I Erection Manual
5.1 Handling & Installation of Sheeting

It is important to use correct sized drill bits and


screws for secure fastening of panels. During
fixing, the panel should be correctly aligned and
temporarily clamped to ensure the holes are
drilled correctly.

Drilling of holes produces very hot metal chips


(swarf), which should be brushed off the panel.
This should be done immediately, if possible, and
the work area should be swept with a soft broom
at the end of each day work.

Care should be taken in walking on roof panels. Stand away from high corrugations
Workers on the roof should use soft footwear.
Metal studs or heel tips will cause damage to the
painted panels.

It is important to walk in the correct place on roof


panels. Always step in the valley of the panel,
which is in contact with the purlin. Standing on
the high corrugations may result in deformation
of the panel.

For achieving a quality job, use a screwgun with a Brushing metal chips
depth locator or torque adjuster, this will ensure
correct fixing of fasteners.

When drilling use a rubber or leather thimble 26


on the drill bit to prevent the chuck of the drill
damaging the panel paint when the drill goes
through the material.

5.1.1 Unloading

Sheets are packed in bundles, and may be unloaded


by a suitable forklift truck or crane. Care must be
taken not to “break the back” of the sheets when
unloading. If chains or cable slings are used for
unloading, good protection must be provided for
the corners of the bundle.
Step in the valleys of the panel
Note: Long panels may be difficult to handle by
lifting the bundle from beneath.
5. Care and Handling of Sheeting

5.1.2 Storage

Packs of sheets should be stored in a safe area


of the site. They should be stored clear of the
ground and elevated at one end to allow for water
drainage should they become wet. Preferably, the
bundles should be loosely covered with a tarpaulin;
this will afford additional protection but allow
air circulation.

5.1.3 Handling

Care should be taken when handling sheets.


Erectors should use clean gloves to avoid dirty
marks, oil or grease stains on sheets. When
Storage
handling individual panels from the stack, each
panel should be lifted clear, not dragged along,
which cause scratches.

5.1.4 Cutting & Fixing

Only proper tools should be used for cutting


profiled sheets. An electric nibbler should be
used for cutting across the ribs, an electric shear
for cutting longitudinally, and aviation snips for
small detail work. Never use a grinding desk for
cutting sheets

Storage and handling


27

Handling individual panels


Zamil Steel Pre-Engineered Buildings I Erection Manual
5.1.5 Completion & Inspection 5.3 General Tips

On completion, the sheeted area should be 1. Erection shall start from a braced bay and
inspected. Any ferrous objects such as pop-rivet the bracing shall be fixed before proceeding
stalks, bolts, nails, screws etc. left on the roofing to the other bays.
should be removed.
2. Purlins and girts shall be immediately fixed
Any accidental scratches or minor damage should to each erected bay to maintain the building
be touched-up with the appropriate paint. The stability during erection
area should be left clean.
3. Always check the starting position of roof
5.1.6 Paint Repair panels.

For minor scratches, a small brush can be used 4. Panels should be plumbed and held in place
to apply touch-up paint of matching color to the by Vice Grips before screwing.
damaged area.
5. The panel gauge should be marked on the
If damage has affected the galvanized coating, sheeting notch.
then the damaged area should be coated with
special primer followed by a special polyurethane 6. A line should be used to maintain a straight
finish coat. sheeting line at the eave.

5.2 Water Test Procedures for Roofing 7. A chalk line should be used to ensure the
screws are installed in a straight line, and
There is really no better way of water testing a avoid mis-drilling.
roof than actual rainfall, as to simulate even fall or
wind blown rain is impossible. 8. Roof sheets should be undamaged.

If medium to heavy rain has fallen after completion 9. Bead mastic must be carefully placed over the
of roofing, and no leakage is visible then the roof corrugations at end laps. 28
should be considered tested and satisfactory.
10. Insulation should be neatly folded at the
If the roofing has been completed during a dry base angle and eave. It can never be neatly
season, and testing is required, then the following cut off afterwards.
test can be carried out:
11. Pre-drilling is required when using stainless
A 25 to 30mm diameter hose will be required with steelfastner.
sufficient mains pressure, or a tank and electric
pump. Two tests can be done.

1. The hose should be positioned on the ridge,


or highest point of the roof. The water should
then cascade down each slope, down each
valley between panel ribs. The hose should not
be deliberately directed at the panel end-laps
and side-laps.

2. The second and longer test can be carried out


if desired by attaching a rotary garden sprinkler
to the hose and allow the whole roof to be
systematically “watered”. This is the nearest
method of stimulating rainfall as the sprinkler
system causes the water to bounce, thus finding
any weakness in lap conditions.
6
Maintenance
Procedure

6.1 Maintenance for Longer Life


6.2 Safety Notes
6.3 Exterior Maintenance
Procedure
6.4 Maintenance of Accessories
29 6.5 Record of Maintenance
Zamil Steel Pre-Engineered Buildings I Erection Manual
6.1 Maintenance for Longer Life 6.3 Exterior Maintenance Procedure

Now that your Zamil Steel Building is complete, t 1SFWFOUJWF NBJOUFOBODF TIBMM DPNNFODF
we recommend that you follow our simple immediately after a project is erected or
maintenance recommendations. By doing so modified.
you will substantially enhance the life of your
investment. t %FCSJT BOE TNBMM JUFNT TVDI BT TDSFXT  QPQ
rivets, drill bits or any ferrous object shall be
The frequency of maintenance is dependent removed by sweeping with a soft nylon brush.
upon the environmental zone in which the Large items such as sheet metal cut-offs shall be
building is located. The table below contains removed by hand to avoid damaging the surface
the recommended maintenance frequencies for of the roof panels. Such debris shall be removed
different building locations. after any trade (e.g., electricians, plumbers, air
conditioning technicians, steel erectors, etc.)
has worked on the roof.
Maintenance
Building Location t4BOEBOEEVTUSFUBJOTBMUBOENPJTUVSF XIJDI
Frequency
will eventually breakdown the paint and zinc
layers, resulting in corrosion of the base metal.
Within 5 km of the sea Every 3 months Sand and dust shall be removed by washing
with clean potable water and a soft nylon brush,
working from the highest point to the lowest,
High pollution industrial area Every 3 months followed by a final rinse using a hose and clean
potable water.
Medium pollution industrial area Every 4 months
t 5IF NPTU WVMOFSBCMF BSFBT PG UIF CVJMEJOH BSF
gutters, roof sheets, sheltered areas under eaves
Areas of high humidity Every 4 months or canopies and upper portions of walls or roof
extensions.
30
Low pollution industrial area Every 6 months t 'PSCVJMEJOHTMPDBUFEJOIJHIQPMMVUJPOJOEVTUSJBM
areas, or close to marine environments, water
alone may not be sufficient to remove saline
Dry desert regions Every 6 months deposits that have become encrusted on the
panels.

In such cases, a mild detergent shall be added


6.2 Safety Notes to the initial washing water. Panels shall be
washed with the mild detergent solution and
t &YFSDJTF FYUSFNF DBVUJPO XIFO XPSLJOH PO a soft nylon brush. A final rinse with clean
roofs. potable water should follow. Oil, grease, tar,
t 6TF QSPGFTTJPOBM NBJOUFOBODF TUBGG GPS wax or similar substances can be removed with
maintenance works. mineral spirits followed by a detergent solution
t &OTVSF UIBU BDDFTT MBEEFST SFBDI BU MFBTU POF and a clean potable water rinse.
meter above the step off poing.
t 4FDVSFMBEEFSTUPUIFCVJMEJOHBOEFOTVSFUIBU t %P OPU VTF DBVTUJD PS BCSBTJWF DMFBOFST  UIFZ
they are on a firm base. may damage the paint and zinc layers.
t %POPUTUFQPOTLZMJHIUT
t 8IFOXBMLJOHPOUIFSPPG TUFQJOUIFWBMMFZT  t (SPVOE MFWFM TIBMM CF NBJOUBJOFE BU MFBTU
of the panel, not on the ribs. 150mm below the base of the wall panel.
t 8IFOFWFSQPTTJCMF XBMLPOUIFQVSMJOMJOF JF  accoumulations of wind blown sand shall be
screws line. removed. Plants and shrubs surrounding the
t 1SPUFDUBSFBTPGSPPG TVCKFDUUPGSFRVFOUBDDFTT  building shall not touch the wall panel; They
by temporary or permanent walkways. may scratch the painted panels.
t 8IFO NBJOUBJOJOH PWFSIFBE DSBOF SVOXBZT 
immobilize the crane before commencement of
work.
t &BWF HVUUFST BOE WBMMFZ HVUUFST TIBMM CF
thoroughly cleaned with a mild detergent
solution and a soft nylon brush, followed by
a rinse of clean potable water. Downspouts
shall be clear of blockage and the downspout
discharge shall have adequate drainage area.

t .JOPS EBNBHF UP TIFFUJOH PS USJNT TIBMM CF


repaired as follows:
- Lightly abrade the affected area
- If base metal is exposed, apply one coat of
zinc chromate primer
- Apply one coat of matching touch-up paint

t &RVJQNFOU XIJDIJTMPDBUFEUISPVHIPSBEKBDFOU
to roof or wall panels may cause moisture
build up on or near the panel. The following
conditions shall be avoided:
- Water run-off from air conditioning units
- Open water storage tanks adjacent to panels
- Steam outlets
- Acid storage
- Copper pipes fastened to steel panels

6.4 Maintenance of Accessories

t #VJMEJOHTXJUI$SBOFT
- Every 6 months check that all bracing is tight
31 - Check that all high strenght bolts in the crane
beams and the main frame connections are
tight

t 1FSTPOOFM%PPST
- Lubricate hinges and lockset
- Remove dirt and girt from the threshould
- Ensure that the door cannor swing back and
strike the wall panels, as this will sprain the
hinges and damage the panel

t 4MJEJOH%PPS
- Regularly clean the bottom guide to recove
sand and stones

t 3PMMVQ%PPST
- Clean and lubricate the chain and reduction
drive gears

t 1PXFS7FOUT
- Clean fan blades to remove build-up of dust
and dirt

6.5 Record of Maintenance

A Periodic Maintenance Log Book shall be kept.


All maintenance dates shall be recorded and
signed by the maintenance staff.
Zamil Steel Pre-Engineered Buildings I Erection Manual
7Safety
Precautions

For safety reasons there are precautions that need


to be taken during erection.

7.1 Make daily check on all lifting equipment. 7.11 Ensure that high strength bolts are used
where indicated.
7.2 Make daily checks on all lifting slings,
check forfraying and kinking. 7.12 Ensure that high strength bolts are 32
correctly tightened.
7.3 Check that all access equipment is in
good condition, including scaffolding and 7.13 Maintain a clean and tidy site, thus
ladders. avoiding material loss or accidents.

7.4 Check weather conditions, strong winds 7.14 Tie down sheeting once the bundle is
are dangerous during erection and opened.
sheeting.
7.15 Sweep roof sheeting at the end of each
7.5 Check for overhead electric lines before day work, drill swarf will corrode the
moving in with a crane. panels if not removed.

7.6 Check that all erectors have the correct 7.16 When walking on the roof, step in the
personal safety equipment, hard hats, valley of the panels, not the ribs.
boots, safety harness etc.
7.17 If when waking on the roof step on the
7.7 Check electric cables for hand tools, purlinlines
discard frayed or split cables.
7.18 Use the correct tools for the job, wrong
7.8 Ensure that there are sufficient guy wires tools will damage materials and produce
on site for temporary bracing. poor quality.

7.9 Ensure that erection always starts at a 7.19 Do not step on the skylights while working
braced bay. on the roof

7.10 Ensure that permanent bracing and flange 7.20 Finally, acquire contractors all Risk
stays are installed as work proceeds. Insurance;
8
Quality
Control

Erection Quality Plan

The safety and Quality of Erection should be


ensured by engaging experienced and qualified
Engineers, Supervisors and Technicians on the job.

33 The Quality Control should be effective at various


stages of erection starting from receipt inspection
till the final handing over. To ensure this, Standard
Inspection and Testing Program (ITP) / Quality
plan (or) a project specific Inspection and Testing
Program - ITP / Quality Plan shall be followed.

The Quality Plan as a minimum should contain


the following:

a. ITP - Inspection and Testing Program Erection shall not start without:
(Attachment I, 2 pages) t 5IFTVCNJTTJPOPGUIF2VBMJUZ1MBO
t *EFOUJGZJOHBEFEJDBUFE2VBMJUZBOE
b. Erection Inspection Check list - EICL Safety Person
(Attachment II, 3 pages) t $POEVDUJOHB1SF*OTQFDUJPO.FFUJOH1*.

c. Method Statement See the Sample Quality Plan as attached.

d. Procedures and Inspection Forms referred in


the ITP

e. Bolt Tightening Procedure


(Attachment III, 3 pages)

f. Paint Touch up Procedure

g. Site Organization chart including a dedicated


qualified person for QC and Safety
Zamil Pre-Engineered Steel Buildings I Erection Manual
9
Basic Erection
Equipment

9.1 Main Erection Equipment


9.2 Electrical Equipment
& Tools
9.3 Measuring & Surveying
Equipment
9.4 Safety Equipment 34
9.5 Other Equipment
9. Basic Erection Equipment

9.1 Main Erection Equipment

Mobile Crane

Mobile Cranes are ideal for erecting pre-engineered steel buildings.


The required capacity of the crane varies. The capacity must be
calculated considering the heaviest member (or assemblies of
members), the building configuration and the site conditions.

Forklift

Forklift are ideal for unloading tralers, for meterial handling on site,
and in certain cases, for the erection of the main frames. Buildings
up to 6m eave height can be erected by rough terrain forklifts with
a 3-stage mast and a capacity of at least 3 MT. By attaching a man
platform, forklifts can be used for fixing wall sheeting, eave gutters,
trims, etc.

Telescopic Handler

Telescopic handlers are even more versatile than forklifts. They can
be used for many different operations of a construction site. Having
35 a wide range of accessories, they can be used for building erection
and other general construction work.

With a man platform attachment, telescopic handlers are suitable


for fixing wall sheeting and other external building accessories.

Scissor Lift

Scissor lifts are suitable for use on level, paved areas for fixing roof
liner panels. They are also very useful for other purposes such as
electromechanical works.

Lifting Beam

A purpose-made lifting beam (spreader bar) of 6 or 12 m long is


required for lifting long span rafters and frame assemblies.
Zamil Steel Pre-Engineered Buildings I Erection Manual
Slings

Purpose-made slings, used alone or in combination with lifting


beams, are used for lifting building components or assemblies.
One, two or four leg slings are available, with hooks or eyes, and
for different load capacities. They are available as a chain, wire or
polyester. The sizes and types of slings required shall be determined
by the weights of the components and assemblies to be lifted.

Guy Wires

Guy wires are steel wire ropes of 8 to 10 mm in diameter and


different lengths (length depends on building height). They are
used to provide temporary bracing for the building normally
used in combination with ratchet pullers. As a rule of thumb, the
minimum length guy wire should be at least 1.5 times the building
height. The guy wire should be attached to the rarter before it
is lifted into place and then tied-off to a fixed object to provide
temporary bracing during erection. The degree of bracing depends
on the size of the building and local weather conditions. Guy
wires are also used to achieve correct alignment of the building.

Important Note: Nylon ropes shall not be used for temporary 36


bracing.

Clamps

Clamps are used for attaching guy wires to rafters or holding


components (such as sheeting) in place prior to fixing.

Shackles

Shackles are used for connecting slings and / or guy wires. Note:
Shackles shall have the safe working load (S.W.L) clearly stamped
on them.

Clips

Clips are used for making eyes in guy wires or for adjusting their
lengths.
9. Basic Erection Equipment

Ratchet Puller

Ratchet & Tirfor pullers are used for tensioning the guy wires that
are used in temporary bracing and aligment of the building. Various
capacities of ratchet pullers are avialable.Normally one ton capacity
pullers are adequate for bracing and aligning most pre-engineered
buildings. Heavy duty pullers, Tirfors, are available when extra
capacity is required.

Light Duty Scaffolding

Access towers are mobile work platforms, useful for sheeting walls
and installing wall accessories and trims.

Ladders

37 Extension ladders are used to access roofs. mezzanines, catwalks,


etc. Step ladders are free standing ladders used for minor fixing and
trimmings.

9.2. Electrical Equipment & Tools

Generator

When a main electrical supply is not available, generators are


required for the power tools 5 KVA generators are suitable for most
electric hand tools.

Screw Gun

Electric screw guns are necessary for installing self drilling fastners
in roofs. In order to avoid over-tightening of the screws, screw guns
should have either torque or depth controls. The recommened
speed is 0 to 2000 RPM (revolutions per minute).
Zamil Steel Pre-Engineered Buildings I Erection Manual
Nibbler

Electric nibblers are required to cut openings in profiled sheets.


Cutting with nibblers guaranees controlled maneuverability
and excellent cutting quality, preventing meterial distrotion and
eliminating the risk of corrosion at the cut edges.

Grinder

In pre-engineered building erection, grinders are used for cutting


mild steel angles such as base and gable angles.

Note: Sheeting shall not be cut with angle grinders. Angle grinders
produce rough and unsightly cuts, which will very quickly corrode.

Hammer Drill

Hammer drills are mainly used for the installation of expansion 38


bolts.

Hole Cutter

In pre-engineered buildings, all holes are prepunched. Should


circumstance dictate changes, then the hole cutter is the ideal tool
for making the required site modifications.

Impact Wrench

The impact wrench is used for tightening high strength nuts and
bolts of the main frames. Both pneumatic and electric models are
available. Pneumatic models are heavy duty wrenches and are
suibable for the large diameter bolts. An air compressor is required
when using a pneumatic model.
9. Basic Erection Equipment

Electric Shear

Electrical shears produce a clean cut in flat sheet. They are not
suitable for cutting over corrugations of panels.

Heavy Duty Drill with Reamer

A heavy duty slow speed drill with a tapered reamer is used for
enlarging holes in steel members, if needed. The recommended
speed of the drill is 0 to 500 RPM (revolutions per minute).

Reciprocating Saw

A reciprocating saw is ideal for cutting insulated roof and wall


sandwich panels (Zamil Steel Tempcon panels).
39

Drill 10 mm

A 10 mm drill, with a speed of 0 to 2400 RPM (reolutions per


minute), is required for pre-drilling holes for pop rivets and any
other bolts that require field drilled holes.

Powder Actuated Tool

Powder actuated tools are used for fixing base angles to floor slabs
or tie beams. They can also be used to fix steel decking panels to
mazzanine joists.

Pop Rivet Puller

Pop rivet pullers are used for fixing pop rivets in trims and gutter
joints.
Zamil Steel Pre-Engineered Buildings I Erection Manual
Aviation Snips

(Left & Right Cut) Aviation snips are used for cutting trims and
small openings in sheet panels. This method of cutting produces a
very clean cut, which will not rust. They provide a fine control for
intricate cuts.

Vice Grips

Vice grips have many uses as a “third hand” and are essential to
clamp sheets and trims while fixing the screws or rivets.

Torque Wrench

(With Sockets) Zamil Steel recommends that high strength bolts


are tightened by the “turn-of-nut method” (see Chapter 3 of Zamil
Steel Erection Guide). If the torque requires checking, a torque
wrench (with different sockets sizes) should be used on which the
torque value is preset perior to checking.

Ratchet Spanner

(With 19 mm Socket) For quick tightening of purlin and girt bolts 40


and other machine bolts.

Staple Applicator

They are used for stapling tabs on fiberglass insulation.

Utility Knife

Utility Knives are used for cutting fiberglass insulation

Hacksaw

Hacksaws are used for cutting light gauge metal.


9. Basic Erection Equipment

Mastic Gun

Mastic guns are required for the application of the flowable mastic,
which is commonly used for sealing gutter joints and overlapping
flashing.

Spud Wrench

Spud wrenches are used during erection to align holes in two steel
members and to tighten the bolts. Various sizes of spud wrenches
are required that would suit the bolt sizes.

Drift Pin

Drift pins are used to align holes in two steel members. They can be
hammered if additional force is needed.

41
Miscellaneous Tools

Hammers Wood saws Screwdrivers Comination spanner sets


Sweeping brooms

Tool Belt & Bolt Bag

A tool belt & bolt bag provides a safe and convenient way of
carrying tools and bolts.

Chalk Line

Chalk lines are used for marking staight lines on the panel along the
position of purlins and girts. The marked line identifies the position
of the screws.
Zamil Steel Pre-Engineered Buildings I Erection Manual
9.3. Measuring & Surveying Equipment

Plumb Bob

Plumb bobs are used for plumbing vertical members up to a height


of 6 m.

Theodolite

Theodolites are used in setting out the building foundations and


anchor bolts. They are also used for checking the vertical alignment
of columns and the alignment of crane beams.

Automatic Level 42
Automatic levels are used to check the elevation of anchor bolts,
the finished floor level and the base plates of columns.

Spirit Level

Spirit levels are used for leveling individual components and for
plumbing.

Measuring Tape & Square

Measuring tapes are used for miscellaneous checking, setting out


and general easuring. A right angle square is used for setting out
90* angles.
9. Basic Erection Equipment

9.4. Safety equipment

Welding Hood

Welding hoods shall be used during welding.

Goggles

Goggles shall be used whilst cutting or grinding.

Gloves

Gloves shall be worn when handling steel components. Clean


gloves should be worn while handling sheets.

43

Safety Harness & Fall Arrest

Safety harnesses shall be worn when working over 2 meters above


the ground levels.

Safety Boots

Protective footwear shall be worn at all times while on working site


to avoid toe, sole or ankle injuries.

Hard Hat

Personal head protection shall be used be on site at all times.


Zamil Steel Pre-Engineered Buildings I Erection Manual
First Aid Box

First aid boxes should be on site at all times under a qualified


first aid person. All contents shall be maintained and expiry dates
checked periodically.

Cones and Ribbons

Cone and warning ribbons are used to indicate danger areas on


sites.

Portable Fire Extinguisher

Fire extinguishers shall be installed on vehicles and in areas where


welding or burning works are executed.

44
Ear Protection

Ear protection shall be used where noise is higher than 85 dB.

9.5. Other Equipment

Welding Machine

Electric welding machines are used for light duty welding such as
tack welding of light guage steel members.

Oxy-acetylene Cutting Outfit

Oxy-acetylene is used for cutting steel members.


10
Attachments

10.1 Inspection and Testing


Program (ITP-Standard Jobs)
10.2 Erection Inspection List
(EICL)
10.3 Tightening and Inspection
of High Strength Bolts
10.4 Anchor Bolt
Installation Guide
45
46

Zamil Steel Pre-Engineered Buildings I Erection Manual


Attachment I
10. Attachments

Attachment I

47
48

Zamil Steel Pre-Engineered Buildings I Erection Manual


Attachment II
10. Attachments

Attachment II

49
50

Zamil Steel Pre-Engineered Buildings I Erection Manual


Attachment II
10. Attachments

Attachment III

51
52

Zamil Steel Pre-Engineered Buildings I Erection Manual


Attachment III (Continuation)
10. Attachments

Attachment III (Continuation)

53
Zamil Steel Pre-Engineered Buildings I Erection Manual
Attachment IV

Anchor Bolt Installation Guide


Prior to pouring of concrete, anchor bolts may in the manner shows below.

54

Anchor Bolts whenever not supplied by Zamil should be of the sizes shown on Zamil’s Anchor Bolt Erection drawing and of a
quality to resist column reactions given.

Material should conform to ASTM A 36M (or Equivalent) (36 KSI=2500 kg/am2 Min, yeld) of equivalent, unless otherwise
specified. Embedment lengths are base on a minimum concrete compressive strength of 3 KSI = 200 kg/cm2 at 28 days.
Anchor bolts shall be accurately set as shown on Anchor Bolt plan with a tolerance of 2mm within a set.

Note:
1. All reinforcing steel for foundation walls and footings, tie rods, plywood template, mesh or any materials used
specifically for concrete application shall be designed by professional foundation engineer and supplied by others.
2. Foundation contractor shall fill all voids in concrete slab perimeter wall prior to erection of building. Placed fill shall
be properly compacted in layers and controlled moisture.
Glossary

Accessories : Additions to the basic building, such as doors, windows, louvers, ventilators etc.

Anchor Bolts : Hooked bolts cast in concrete foundations for anchorage of structural members.

Base Angle : Countinuous angle fixed to floor slab or grade beam for attachment of all panels.

Base Plate : The plate of a column or beam which rests on the supporting surface.

Beam : Horizontal Structural Member.

Brace Rods : Rods placed diagonally in roof and walls for transferring wind loads to
foundations and stabilizing the building.
Bridge Crane : Overhead travelling crane supported on beams and rails.

Built-up Member : (B.U.) Structural member formed by welding together web and flange plates.

Caulking : Sealant used in making watertight joints.

Clear Span : Building without internal columns.

Closure : (Foam Closure) Profiled foam material used inside or outside profiled roof or
wall panels to form weathertight seal.
Cold Formed : Various steel shapes manufactured by roll-forming or pressing.

Column : Vertical structural member.

55 Crane Beam : Support for overhead travelling bridge crane.

Crain Rails : Rails welded or bolted to crane beams to form the track for bridge crane wheels.

Curb : Raised flashing around roof openings to form waterproof opening.

Damper : Baffle plate in a ventilator.

Dead Load : Weight of the structure.

D.S.D : Double slide door.

Eave : Top of the sidewall.

Eave Height : Height from top of eave strut to finished floor level.

Eave Strut : Structural member at the eave which supports roof and wall panels.

Expansion Joint : A break in the construction to allow for thermal expansion.

Flange Brace : An angle from the flange of columns or rafters to girts and purlins to provide
lateral support and stability.
Girt : Secondary horizontal member to which wall panels are attached, usually cold
formed “Z”.
Grout : Non-shrinking sand cement mixture used under base plates to obtain uniform
bearing surface.
Zamil Steel Pre-Engineered Buildings I Erection Manual
Haunch : Intersection of column and rafter.

Header : Horizontal member over and opening in a wall.

H.S.B. : High strength bolts.

Hot Rolled : Steel shapes formed while the steel is semi-molten.

Jack Beam : A beam used to support a rafter instead of a column.

Jamb : Vertical member at the side of a wall opening.

Joist : Horizontal members for supporting floor or roof decking.

Knee : See Haunch.

Liner Panel : Interior wall sheeting.

Live Load : Any variable temporary load on the structure.

Main Frame : Primary members which support secondary members.

Mastic : See Caulking - Sealant.

M.B : Machine Bolt.

Mazzanine : Intermediate floor between ground floor and first floor or roof. 56
Mono-Slope : Single slope roof.

Multi-Span : Building with intermediate columns.

Parapet : Vertical wall extension above the eave line.

Partition : Internal wall.

Pitch : Slope of the roof.

Pop Rivet : Used for joining flashing and light guage metal trims.

Portal Frame : Column and beam bracing used in lieu of standard rod bracing to prvide
clear access.
Post & Beam (P&B) : Light end wall framing.

Primer Paint : Factory applied paint to structural members providing protection during
shipping and erection.
Purlin : Secondary horizontal member to which roof panels are attached usually
cold formed “Z”.
Rafter : Primary member supported on columns.

Ridge : Peak of a gabled building.


Glossary

Rigid Frame (R.F.) : Main frame of the building comprising columns and rafters

Sag Rod : Tie rods used to support flanges of girts or purlins.

Sealant : See Mastic - Caulking.

Secondary Framing : Secondary members of framing such as girts, purlins, eave struts etc.

S.D.S. : Self drilling screw - used for attaching panels and trims to girts and purlins.
Pre-drilling is not necessary.
S.T.S. : Self tapping screw. Same function as S.D.S. but needs pre-drilled holes.

Shims : Small steel plates used for levelling base plates or packing between
structural members.
Sill : The bottom horizontal member of a door or windows opening.

Skylight : Translucent fibreglass panel used in the roof to transmit natural light.

S.S.D. : Single Slide Door.

Soffit : Underside of canopy, fascia or roof extension.

Span : Distance from out to out of wall girts.

Splice Plate : Plate used to connect two members.

57 Stiffener : Plate welded to a member to prevent buckling.

Stitch Screw : Used to fasten side laps of panels.

Truss : Structural member made up of several individual parts welded or


bolted together, the completed unit acting as a beam.
V.G. : Valley Gutter.
Zamil Steel Pre-Engineered Buildings I Erection Manual
Commonly Used Abbreviations

ASSY : Assembly
BT PLT : Bent Plate
BOTT’M : Bottom
CC : Center to Center
CONC : Concrete
CL : Centre Line
DET : Detail
DRG : Drawing
DSD : Double Slide Door
EW : End Wall
EXP’N : Expansion
FO : Framed Opening
FNB : Fin Neck Bolt
HSB : High Strength Bolt
INT : Internal/Interior
LG : Long
MB : Machine Bolt
NS/FS : Near Side / Far Side
OA : Overall
OC : On Centre 58
O/O : Out to Out
PL-PLT : Plate
P&B : Post and Beam
R.F. : Rigid Frame
RUD : Roll-Up Door
SHT : Sheet
SHT’G : Sheeting
SDS : Self Drilling Screw
STS : Self Tapping Screw
SSD : Single Slide Door
STIFF : Stiffener
SW : Sidewall
TC : Tempcon
THK : Thick
TYP : Typical
TYP UN : Typical Unless Noted
ZS : Zamil Steel
HEAD OFFICE: PO Box 877 Dammam 31421 Saudi Arabia Phone (966 3) 847 1840 Fax (966 3) 847 1291
FACTORIES: Saudi Arabia, Ras Al-Khaimah, Egypt, India, Vietnam (North & South)

www.zamilsteel.com September 2012

Vous aimerez peut-être aussi