STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.

2018 R Classic Schedule Layout 19-Apr-18 04:43 PM


Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

383.0d 172.0d
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Projection -111.0d 02-Oct-17 08:00 AM 20-Oct-18 08:00 AM 76.79% 57.09%
A
Milestone 323.0d 0.0d -95.0d 02-Oct-17 08:00 AM A 20-Oct-18 08:00 AM 0% 0%

STF1000 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A 02-Oct-17 08:00 AM A 100% 100%
STF1010 Milestone Finish STF 0.0d 0.0d -95.0d 20-Oct-18 08:00 AM* 20-Oct-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%

Documentation 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%


Preparation & Submission 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
STF1020 Preparation of Performance Bond 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1030 Preparation of Insurances Policies / Public Liability / Workmen's Compensation
14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1040 Preparation & Submission of Levy of CIDB 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1050 Site Registration of JKKP (DOSH) 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1060 Submission Copy of SPAN Certificate 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1070 Preparation & Submission of Lithography Expenses 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1080 Preparation & Submission of PQP / Method Statements 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
STF1090 Preparation of Works (Contractor Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
STF1100 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
STF1110 Preparation of Works (General Obligation, Project Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
STF1120 Preparation of Works (Authorities Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
STF1130 Preparation of Works (Environmental Protection & Enhancement)18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
Civil & Structures 187.5d 46.5d 13.5d 11-Dec-17 08:00 AM A 16-Jun-18 12:00 PM 51.72% 52.42%

Underground Tank & Building 187.5d 46.5d 13.5d 11-Dec-17 08:00 AM A 16-Jun-18 12:00 PM 51.72% 52.42%
Wash Water Collection & Sludge Balancing Tank 166.0d 9.0d 51.0d 11-Dec-17 08:00 AM A 09-May-18 05:00 PM 97.32% 94.48%
Site Measurement & Site Preparation 55.0d 0.0d 11-Dec-17 08:00 AM A 03-Feb-18 05:00 PM A 100% 100%
STF1140 Site survey 11.0d 0.0d 11-Dec-17 08:00 AM A 21-Dec-17 05:00 PM A 100% 100%
STF1150 Site clearance 14.0d 0.0d 22-Dec-17 08:00 AM A 04-Jan-18 05:00 PM A 100% 100%
STF1160 Excavation, levelling & compaction works 26.0d 0.0d 05-Jan-18 08:00 AM A 30-Jan-18 05:00 PM A 100% 100%
STF1170 Install formwork 3.0d 0.0d 31-Jan-18 08:00 AM A 02-Feb-18 05:00 PM A 100% 100%
STF1180 Lay of 75mm thick lean concrete 1.0d 0.0d 03-Feb-18 08:00 AM A 03-Feb-18 05:00 PM A 100% 100%
Slab for All excluding Drywells 19.0d 0.0d 04-Feb-18 08:00 AM A 22-Feb-18 05:00 PM A 100% 100%
STF1190 Erect formwork, install reinforcement, kicker & waterstop 15.0d 0.0d 04-Feb-18 08:00 AM A 19-Feb-18 05:00 PM A 100% 100%
STF1200 Inspection 1.0d 0.0d 19-Feb-18 08:00 AM A 19-Feb-18 05:00 PM A 100% 100%

Page 1 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF1210 Concreting & curing works 2.0d 0.0d 20-Feb-18 08:00 AM A 21-Feb-18 05:00 PM A 100% 100%
STF1220 Dismantle formwork 1.0d 0.0d 22-Feb-18 08:00 AM A 22-Feb-18 05:00 PM A 100% 100%
Slab for Drywells 10.0d 0.0d 03-Mar-18 08:00 AM A 12-Mar-18 05:00 PM A 100% 100%
STF1230 To excavate, level & compact 1.0d 0.0d 03-Mar-18 08:00 AM A 03-Mar-18 05:00 PM A 100% 100%
STF1240 Lay of 75mm thick lean concrete 1.0d 0.0d 03-Mar-18 08:00 AM A 03-Mar-18 05:00 PM A 100% 100%
STF1250 Erect formwork, install reinforcement, kicker & waterstop 3.0d 0.0d 04-Mar-18 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
STF1260 Inspection 1.0d 0.0d 06-Mar-18 08:00 AM A 08-Mar-18 05:00 PM A 100% 100%
STF1270 Concreting & curing works 2.0d 0.0d 10-Mar-18 08:00 AM A 11-Mar-18 05:00 PM A 100% 100%
STF1280 Dismantle formwork 1.0d 0.0d 12-Mar-18 08:00 AM A 12-Mar-18 05:00 PM A 100% 100%
Wall '1' - 1st Lift (1.5m) 26.0d 0.0d 22-Feb-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
STF1290 Erect scaffold & stagging 1.0d 0.0d 28-Feb-18 08:00 AM A 13-Mar-18 05:00 PM A 100% 100%
STF1300 Erect formwork, install reinforcement, kicker & waterstop 4.0d 0.0d 22-Feb-18 08:00 AM A 14-Mar-18 05:00 PM A 100% 100%
STF1310 Inspection 1.0d 0.0d 13-Mar-18 08:00 AM A 15-Mar-18 05:00 PM A 100% 100%
STF1320 Concreting works 1.0d 0.0d 15-Mar-18 08:00 AM A 15-Mar-18 05:00 PM A 100% 100%
STF1330 Curing works 3.0d 0.0d 16-Mar-18 08:00 AM A 19-Mar-18 05:00 PM A 100% 100%
STF1340 Dismantle formwork, scaffold & stagging 1.0d 0.0d 19-Mar-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
Wall '2' - 1st Lift (1.5m & 2.4m) 34.0d 0.0d 27-Feb-18 08:00 AM A 06-Apr-18 05:00 PM A 100% 100%
STF1350 Erect scaffold & stagging 1.0d 0.0d 01-Mar-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
STF1360 Erect formwork, install reinforcement, kicker & waterstop 4.0d 0.0d 27-Feb-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
STF1370 Install 4 units of 100mm dia. Pipes 2.0d 0.0d 17-Mar-18 08:00 AM A 18-Mar-18 05:00 PM A 100% 100%
STF1380 Inspection 1.0d 0.0d 26-Mar-18 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
STF1390 Concreting works 1.0d 0.0d 29-Mar-18 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
STF1400 Curing works 3.0d 0.0d 30-Mar-18 08:00 AM A 02-Apr-18 05:00 PM A 100% 100%
STF1410 Dismantle formwork, scaffold & stagging 1.0d 0.0d 31-Mar-18 08:00 AM A 06-Apr-18 05:00 PM A 100% 100%
Wall '1' - 2nd Lift (2.1m) 38.0d 0.0d 01-Mar-18 08:00 AM A 13-Apr-18 05:00 PM A 100% 100%
STF1420 Erect scaffold & stagging 1.0d 0.0d 13-Mar-18 08:00 AM A 03-Apr-18 05:00 PM A 100% 100%
STF1430 Erect formwork, install reinforcement 4.0d 0.0d 01-Mar-18 08:00 AM A 03-Apr-18 05:00 PM A 100% 100%
STF1440 Install 2 units of 300mm dia. of pipes (level - 22.50) 1.0d 0.0d 31-Mar-18 08:00 AM A 02-Apr-18 05:00 PM A 100% 100%
STF1450 Inspection 1.0d 0.0d 31-Mar-18 08:00 AM A 03-Apr-18 05:00 PM A 100% 100%
STF1460 Concreting works 1.0d 0.0d 03-Apr-18 08:00 AM A 03-Apr-18 05:00 PM A 100% 100%
STF1470 Curing works 3.0d 0.0d 04-Apr-18 08:00 AM A 06-Apr-18 05:00 PM A 100% 100%
STF1480 Dismantle formwork, scaffold & stagging 1.0d 0.0d 07-Apr-18 08:00 AM A 13-Apr-18 05:00 PM A 100% 100%

Page 2 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m) 50.0d 0.0d 05-Mar-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
STF1490 Erect scaffold & stagging 1.0d 0.0d 13-Mar-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1500 Erect formwork, install reinforcement 5.0d 0.0d 05-Mar-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1510 Inspection 1.0d 0.0d 07-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1520 Concreting works 1.0d 0.0d 20-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1530 Curing works 3.0d 0.0d 21-Apr-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
STF1540 Dismantle formwork, scaffold & stagging 1.0d 0.0d 22-Apr-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
Cantilever Beam, Walkway Slab & Overflow Slab/Wall 23.0d 0.0d 04-Apr-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
STF1550 Erect scaffold & stagging 1.0d 0.0d 04-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1560 Erect & install formwork, t-props, soffit and reinforcement 4.0d 0.0d 04-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1570 Install 2 units of 200mm dia. of pipes at Overflow Wall A & C 1.0d 0.0d 19-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1580 Inspection 1.0d 0.0d 16-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1590 Concreting works 1.0d 0.0d 20-Apr-18 08:00 AM A 20-Apr-18 05:00 PM A 100% 100%
STF1600 Curing works 3.0d 0.0d 21-Apr-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
STF1610 Dismantle formwork, t-props, soffit, scaffold & stagging 1.0d 0.0d 22-Apr-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
Partial Backfilling (Drywells Area) 10.0d 0.0d 18-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1620 Repair of cold joints & honeycomb at affected area 1.0d 0.0d 18-Apr-18 08:00 AM A 18-Apr-18 05:00 PM A 100% 100%
STF1630 Partial backfilling & compaction (1st stage) 1.0d 0.0d 24-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1640 Reinstate existing sump 2.0d 0.0d 25-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1650 Reinstate existing sewer pipes 1.0d 0.0d 26-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1660 Partial backfilling & compaction (2nd stage) 1.0d 0.0d 27-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
Repair of Cold Joints, Waterproofing & Painting 38.0d 0.0d 18-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1670 Repair of cold joints & honeycomb 2.0d 0.0d 18-Apr-18 08:00 AM A 18-Apr-18 05:00 PM A 100% 100%
STF1680 Waterproofing of internal wall 1.0d 0.0d 23-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1690 Painting (1 coat resistant primer & 2 coats anti-fungus) 1.0d 0.0d 24-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1700 Cleanup site 1.0d 0.0d 25-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
Water Tighness Testing & Backfilling 9.0d 9.0d 51.0d 01-May-18 08:00 AM 09-May-18 05:00 PM 58.21% 0%
STF1710 To fill up WWCT & SBT with water 1.0d 1.0d 51.0d 01-May-18 08:00 AM* 01-May-18 05:00 PM 100% 0%
STF1720 Monitoring 3.0d 3.0d 51.0d 02-May-18 08:00 AM* 04-May-18 05:00 PM 100% 0%
STF1730 To backfill & compact outer perimeter of WWCT & SBT 5.0d 5.0d 51.0d 05-May-18 08:00 AM* 09-May-18 05:00 PM 20% 0%
Dewatering Platform (Geotube) 130.1d 41.8d 8.3d 01-Feb-18 01:00 PM A 11-Jun-18 02:00 PM 15.4% 20.44%
Excavation Works & Hardcore 9.0d 1.0d 9.0d 23-Apr-18 08:00 AM A 01-May-18 05:00 PM 100% 80%

Page 3 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF1740 Site measurement & marking 1.0d 0.0d 23-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1750 To excavate, level & compact ground 3.0d 0.0d 24-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF1760 To lay, spread & compact Crusher-run as hardcore (0.3m Thk) 1.0d 1.0d 9.0d 01-May-18 08:00 AM* 01-May-18 05:00 PM 100% 0%
Drain (Base) 99.1d 10.1d 8.9d 01-Feb-18 07:00 PM A 12-May-18 09:00 AM 42.25% 12.5%
STF1770 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 9.0d 02-May-18 08:00 AM* 03-May-18 05:00 PM 100% 0%
STF1780 Erect formwork, install reinforcement 5.0d 5.0d 13.3d 01-Feb-18 07:00 PM A 07-May-18 09:00 AM 60% 30%
STF1790 Inspection 1.0d 1.0d 8.9d 07-May-18 09:00 AM* 08-May-18 09:00 AM 0% 0%
STF1800 Concreting works 2.0d 2.0d 8.9d 08-May-18 09:00 AM* 10-May-18 09:00 AM 0% 0%
STF1810 Curing works 1.0d 1.0d 8.9d 10-May-18 09:00 AM* 11-May-18 09:00 AM 0% 0%
STF1820 Dismantle formwork 1.0d 1.0d 8.9d 11-May-18 09:00 AM* 12-May-18 09:00 AM 0% 0%
Drain (Wall - 2 sides) 110.0d 10.9d 8.5d 01-Feb-18 07:00 PM A 22-May-18 05:00 PM 0% 16.15%
STF1830 Erect formwork, install reinforcement 7.0d 7.0d 12.8d 01-Feb-18 07:00 PM A 16-May-18 08:00 PM 0% 30%
STF1840 Inspection 1.0d 1.0d 8.5d 17-May-18 08:00 AM* 17-May-18 05:00 PM 0% 0%
STF1850 Concreting works 2.0d 2.0d 8.5d 18-May-18 08:00 AM* 19-May-18 05:00 PM 0% 0%
STF1860 Curing works 1.0d 1.0d 8.5d 20-May-18 08:00 AM* 20-May-18 05:00 PM 0% 0%
STF1870 Dismantle formwork & backfilling works 2.0d 2.0d 8.5d 21-May-18 08:00 AM* 22-May-18 05:00 PM 0% 0%
Ground Slab 122.1d 11.8d 9.3d 01-Feb-18 01:00 PM A 03-Jun-18 02:00 PM 0% 15%
STF1880 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 9.5d 23-May-18 08:00 AM* 24-May-18 05:00 PM 0% 0%
STF1890 Erect formwork, install reinforcement 7.0d 7.0d 14.3d 01-Feb-18 01:00 PM A 29-May-18 02:00 PM 0% 30%
STF1900 Inspection 1.0d 1.0d 9.4d 29-May-18 02:00 PM* 30-May-18 02:00 PM 0% 0%
STF1910 Concreting works 2.0d 2.0d 9.4d 30-May-18 02:00 PM* 01-Jun-18 02:00 PM 0% 0%
STF1920 Curing works 1.0d 1.0d 9.4d 01-Jun-18 02:00 PM* 02-Jun-18 02:00 PM 0% 0%
STF1930 Dismantle formwork 1.0d 1.0d 9.4d 02-Jun-18 02:00 PM* 03-Jun-18 02:00 PM 0% 0%
Ramp 123.1d 12.8d 8.3d 01-Feb-18 01:00 PM A 04-Jun-18 02:00 PM 0% 8.57%
STF1940 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 8.5d 23-May-18 08:00 AM* 24-May-18 05:00 PM 0% 0%
STF1950 Erect formwork, install reinforcement 4.0d 4.0d 12.8d 01-Feb-18 01:00 PM A 27-May-18 02:00 PM 0% 30%
STF1960 Inspection 1.0d 1.0d 8.4d 27-May-18 02:00 PM* 28-May-18 02:00 PM 0% 0%
STF1970 Concreting works 2.0d 2.0d 8.4d 28-May-18 02:00 PM* 30-May-18 02:00 PM 0% 0%
STF1980 Curing works 1.0d 1.0d 8.4d 30-May-18 02:00 PM* 31-May-18 02:00 PM 0% 0%
STF1990 Dismantle formwork 1.0d 1.0d 8.4d 31-May-18 02:00 PM* 01-Jun-18 02:00 PM 0% 0%
STF2000 Install cheuque plate covers 1.0d 1.0d 8.4d 01-Jun-18 02:00 PM* 02-Jun-18 02:00 PM 0% 0%
STF2010 To clean up site condition including levelling & compaction 2.0d 2.0d 8.4d 02-Jun-18 02:00 PM* 04-Jun-18 02:00 PM 0% 0%

Page 4 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Geotube 49.5d 7.0d 8.4d 23-Apr-18 09:00 AM A 11-Jun-18 02:00 PM 0% 30%


STF2020 Delivery of 30 units of geotube to site 3.0d 0.0d 23-Apr-18 09:00 AM A 30-Apr-18 09:00 AM A 0% 100%
STF2030 Setting of site ready for installation works 1.0d 1.0d 8.4d 04-Jun-18 02:00 PM* 05-Jun-18 02:00 PM 0% 0%
STF2040 Installation of geotube and necessarry works 5.0d 5.0d 8.4d 05-Jun-18 02:00 PM* 10-Jun-18 02:00 PM 0% 0%
STF2050 Cleanup site 1.0d 1.0d 8.4d 10-Jun-18 02:00 PM* 11-Jun-18 02:00 PM 0% 0%
Polymer Building 135.5d 46.5d 13.5d 01-Feb-18 08:00 AM A 16-Jun-18 12:00 PM 5.7% 12.07%
Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk) 92.0d 4.0d 4.0d 01-Feb-18 07:00 PM A 04-May-18 05:00 PM 59.7% 72.73%
STF2060 To excavate, level & compact ground to receive foundation 1.0d 0.0d 23-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF2070 Install formwork, lay of 50mm thick lean concrete 1.0d 0.0d 25-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF2080 Erect formwork & install reinforcement 3.0d 0.0d 01-Feb-18 07:00 PM A 29-Apr-18 05:00 PM A 100% 100%
STF2090 Inspection 1.0d 0.0d 27-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF2100 Concreting works 1.0d 0.0d 29-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 0% 100%
STF2110 Curing works 2.0d 2.0d 4.0d 30-Apr-18 08:00 AM A 02-May-18 05:00 PM 0% 50%
STF2120 Dismantle formwork 1.0d 1.0d 4.0d 03-May-18 08:00 AM* 03-May-18 05:00 PM 0% 0%
STF2130 Backfilling & compaction works to the level of top stump 1.0d 1.0d 4.0d 04-May-18 08:00 AM* 04-May-18 05:00 PM 0% 0%
Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk) 103.0d 10.0d 4.0d 01-Feb-18 08:00 AM A 14-May-18 05:00 PM 0% 10%
STF2140 Erect formwork surround the outer of stump 1.0d 1.0d 4.0d 01-Feb-18 08:00 AM A 05-May-18 05:00 PM 0% 30%
STF2150 Backfilling & compaction works to the level of bottom slab 2.0d 2.0d 4.0d 06-May-18 08:00 AM* 07-May-18 05:00 PM 0% 0%
STF2160 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 4.0d 08-May-18 08:00 AM* 08-May-18 05:00 PM 0% 0%
STF2170 Install reinforcement both ground beam & slab 3.0d 3.0d 5.9d 01-Feb-18 07:00 PM A 10-May-18 05:00 PM 0% 30%
STF2180 Inspection 1.0d 1.0d 4.0d 10-May-18 08:00 AM* 10-May-18 05:00 PM 0% 0%
STF2190 Concreting works 1.0d 1.0d 4.0d 11-May-18 08:00 AM* 11-May-18 05:00 PM 0% 0%
STF2200 Curing works 2.0d 2.0d 4.0d 12-May-18 08:00 AM* 13-May-18 05:00 PM 0% 0%
STF2210 Dismantle formwork 1.0d 1.0d 4.0d 14-May-18 08:00 AM* 14-May-18 05:00 PM 0% 0%
Column - 5.5m (0.25mm x 0.25mm) 110.0d 8.0d 6.0d 01-Feb-18 08:00 AM A 21-May-18 05:00 PM 0% 9%
STF2220 Install reinforcement 2.0d 2.0d 5.9d 01-Feb-18 08:00 AM A 15-May-18 12:00 PM 0% 30%
STF2230 Erect formwork & bracing 1.0d 1.0d 5.9d 01-Feb-18 01:00 PM A 15-May-18 11:00 PM 0% 30%
STF2240 Inspection 1.0d 1.0d 6.0d 15-May-18 08:00 AM* 16-May-18 08:00 AM 0% 0%
STF2250 Concreting works 2.0d 2.0d 6.0d 16-May-18 08:00 AM* 17-May-18 05:00 PM 0% 0%
STF2260 Curing works 3.0d 3.0d 6.0d 18-May-18 08:00 AM* 20-May-18 05:00 PM 0% 0%
STF2270 Dismantle formwork & bracing 1.0d 1.0d 6.0d 21-May-18 08:00 AM* 21-May-18 05:00 PM 0% 0%
Roof Beam (0.25mm x 0.5mm) 111.9d 8.0d 4.0d 01-Feb-18 09:00 AM A 23-May-18 05:00 PM 0% 9%

Page 5 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF2280 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 5.9d 16-May-18 08:00 AM* 16-May-18 05:00 PM 0% 0%
STF2290 Install reinforcement including L-Plates for roof truss 2.0d 2.0d 5.9d 01-Feb-18 07:00 PM A 17-May-18 11:00 PM 0% 30%
STF2300 Erect formwork 1.0d 1.0d 5.9d 01-Feb-18 09:00 AM A 18-May-18 08:00 PM 0% 30%
STF2310 Inspection 1.0d 1.0d 4.0d 18-May-18 08:00 AM* 19-May-18 08:00 AM 0% 0%
STF2320 Concreting works 1.0d 1.0d 4.0d 19-May-18 08:00 AM* 19-May-18 05:00 PM 0% 0%
STF2330 Curing works 3.0d 3.0d 4.0d 20-May-18 08:00 AM* 22-May-18 05:00 PM 0% 0%
STF2340 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 4.0d 23-May-18 08:00 AM* 23-May-18 05:00 PM 0% 0%
Intermediate Beam (0.25mm x 0.5mm) 111.9d 8.0d 4.0d 01-Feb-18 09:00 AM A 23-May-18 05:00 PM 0% 9%
STF2350 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 5.9d 16-May-18 08:00 AM* 16-May-18 05:00 PM 0% 0%
STF2360 Install reinforcement 2.0d 2.0d 5.9d 01-Feb-18 07:00 PM A 17-May-18 11:00 PM 0% 30%
STF2370 Erect formwork 1.0d 1.0d 5.9d 01-Feb-18 09:00 AM A 18-May-18 08:00 PM 0% 30%
STF2380 Inspection 1.0d 1.0d 4.0d 18-May-18 08:00 AM* 19-May-18 08:00 AM 0% 0%
STF2390 Concreting works 1.0d 1.0d 4.0d 19-May-18 08:00 AM* 19-May-18 05:00 PM 0% 0%
STF2400 Curing works 3.0d 3.0d 4.0d 20-May-18 08:00 AM* 22-May-18 05:00 PM 0% 0%
STF2410 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 4.0d 23-May-18 08:00 AM* 23-May-18 05:00 PM 0% 0%
Roof Truss, Covering & Accessories 10.0d 10.0d 27.0d 23-May-18 08:00 AM 01-Jun-18 05:00 PM 0% 0%
STF2420 Deliver prefabricated light gauge MS roof truss on-site 1.0d 1.0d 13.0d 23-May-18 08:00 AM* 23-May-18 05:00 PM 0% 0%
STF2430 Install prefabricated light gauge MS roof truss & bracing 2.0d 2.0d 13.0d 24-May-18 08:00 AM* 25-May-18 05:00 PM 0% 0%
STF2440 Install purlins 2.0d 2.0d 13.0d 26-May-18 08:00 AM* 27-May-18 05:00 PM 0% 0%
STF2450 Inspection 1.0d 1.0d 13.0d 27-May-18 08:00 AM* 27-May-18 05:00 PM 0% 0%
STF2460 Install concrete roof tiles & ridge cap 4.0d 4.0d 13.0d 28-May-18 08:00 AM* 31-May-18 05:00 PM 0% 0%
STF2470 Install fascia board & bracket for gutter 1.0d 1.0d 13.0d 01-Jun-18 08:00 AM* 01-Jun-18 05:00 PM 0% 0%
STF2480 Inspection 1.0d 1.0d 27.0d 01-Jun-18 08:00 AM* 01-Jun-18 05:00 PM 0% 0%
Floor, Wall, Ceiling & Accessories 19.0d 19.0d 6.1d 23-May-18 07:00 PM 05-Jun-18 03:00 PM 0% 0%
STF2490 Install 225mm thk. brickwall, tie with mortar - Team A & B 3.0d 3.0d 6.1d 23-May-18 07:00 PM* 25-May-18 08:00 PM 0% 0%
STF2500 Install roller shutter & frame for door and window 2.0d 2.0d 6.1d 25-May-18 08:00 PM* 27-May-18 09:00 AM 0% 0%
STF2510 Electrical wiring works - carry out by specialist team 4.0d 4.0d 6.1d 25-May-18 08:00 PM* 28-May-18 02:00 PM 0% 0%
STF2520 External plastering - Team A 3.0d 3.0d 6.1d 28-May-18 02:00 PM* 30-May-18 02:00 PM 0% 0%
STF2530 Internal plastering - Team B 3.0d 3.0d 6.1d 28-May-18 02:00 PM* 30-May-18 02:00 PM 0% 0%
STF2540 Install frame & ceiling (external) - Team A 2.0d 2.0d 6.1d 30-May-18 02:00 PM* 31-May-18 08:00 PM 0% 0%
STF2550 Install frame & ceiling (internal) - Team B 2.0d 2.0d 6.1d 30-May-18 02:00 PM* 31-May-18 08:00 PM 0% 0%
STF2560 Install gutter & UPVC downpipes 1.0d 1.0d 6.1d 31-May-18 08:00 PM* 01-Jun-18 03:00 PM 0% 0%

Page 6 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF2570 Rendering of floor, install tiles & skirting 4.0d 4.0d 6.1d 31-May-18 08:00 PM* 03-Jun-18 03:00 PM 0% 0%
STF2580 Painting of wall (external & internal) & ceiling - undercoat - Team A3.0d 3.0d 6.1d 03-Jun-18 03:00 PM* 05-Jun-18 03:00 PM 0% 0%
STF2590 Painting of wall (external & internal) & ceiling - finish coat - Team B3.0d 3.0d 6.1d 03-Jun-18 03:00 PM* 05-Jun-18 03:00 PM 0% 0%
STF2600 Install door & windows 1.0d 1.0d 6.1d 03-Jun-18 03:00 PM* 04-Jun-18 10:00 AM 0% 0%
STF2610 Install GI tray / condiut 1.0d 1.0d 6.1d 04-Jun-18 10:00 AM* 04-Jun-18 09:00 PM 0% 0%
U-Shaped Drain - Team C 128.9d 8.5d 13.5d 01-Feb-18 01:00 PM A 10-Jun-18 12:00 PM 0% 10.91%
STF2620 Excavation & levelling works 2.0d 2.0d 13.0d 02-Jun-18 08:00 AM* 03-Jun-18 05:00 PM 0% 0%
STF2630 Erect formwork 1.0d 1.0d 19.8d 01-Feb-18 07:00 PM A 04-Jun-18 12:00 PM 0% 30%
STF2640 Install reinforcement 3.0d 3.0d 19.8d 01-Feb-18 01:00 PM A 06-Jun-18 12:00 PM 0% 30%
STF2650 Inspection 1.0d 1.0d 13.5d 05-Jun-18 01:00 PM* 06-Jun-18 12:00 PM 0% 0%
STF2660 Concreting works 1.0d 1.0d 13.5d 06-Jun-18 01:00 PM* 07-Jun-18 12:00 PM 0% 0%
STF2670 Curing works 2.0d 2.0d 13.5d 07-Jun-18 01:00 PM* 09-Jun-18 12:00 PM 0% 0%
STF2680 Dismantle formwork 1.0d 1.0d 13.5d 09-Jun-18 01:00 PM* 10-Jun-18 12:00 PM 0% 0%
Apron & Ramp - Team C 134.9d 5.9d 13.5d 01-Feb-18 01:00 PM A 16-Jun-18 12:00 PM 0% 11.25%
STF2690 Backfilling, levelling & compaction works 1.0d 1.0d 13.5d 10-Jun-18 01:00 PM* 11-Jun-18 12:00 PM 0% 0%
STF2700 Erect formwork, install reinforcement 3.0d 3.0d 19.8d 01-Feb-18 01:00 PM A 13-Jun-18 12:00 PM 0% 30%
STF2710 Inspection 1.0d 1.0d 13.5d 12-Jun-18 01:00 PM* 13-Jun-18 12:00 PM 0% 0%
STF2720 Concreting works 1.0d 1.0d 13.5d 13-Jun-18 01:00 PM* 14-Jun-18 12:00 PM 0% 0%
STF2730 Curing works 1.0d 1.0d 13.5d 14-Jun-18 01:00 PM* 15-Jun-18 12:00 PM 0% 0%
STF2740 Dismantle formwork & cleanup site 1.0d 1.0d 13.5d 15-Jun-18 01:00 PM* 16-Jun-18 12:00 PM 0% 0%
Pipeworks (200mm & 300mm Dia. Pipe) 174.0d 55.0d 4.0d 01-Jan-18 08:00 AM A 24-Jun-18 05:00 PM 100% 72.5%

Procurement & Installation Works 174.0d 55.0d 4.0d 01-Jan-18 08:00 AM A 24-Jun-18 05:00 PM 100% 72.5%
STF2750 To procure & deliver 100mm & 300mm Pipes to site 24.0d 0.0d 01-Jan-18 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
STF2760 Excavation & backfilling works 24.0d 24.0d 5.0d 23-Apr-18 08:00 AM A 24-May-18 05:00 PM 100% 80%
STF2770 Pipe laying & jointing 24.0d 24.0d 5.0d 23-Apr-18 08:00 AM A 24-May-18 05:00 PM 100% 80%
STF2780 Connection to existing Chamber / Pipes 24.0d 24.0d 5.0d 23-Apr-18 08:00 AM A 17-Jun-18 05:00 PM 100% 50%
STF2790 Miscellaneous works 18.0d 18.0d 11.0d 02-Jan-18 08:00 AM A 11-Jun-18 05:00 PM 100% 70%
STF2800 Cleaning & testing works 6.0d 6.0d 4.0d 18-Jun-18 08:00 AM 24-Jun-18 05:00 PM 100% 0%
Mechanical Works 249.0d 120.0d -61.0d 23-Dec-17 08:00 AM A 28-Aug-18 05:00 PM 84.28% 53.06%

Drawing & Material Approval 24.0d 0.0d 23-Dec-17 08:00 AM A 21-Jan-18 05:00 PM A 100% 100%
STF2810 Submission of Drawing / Material for approval 12.0d 0.0d 23-Dec-17 08:00 AM A 07-Jan-18 05:00 PM A 100% 100%
STF2820 Review & approval for Drawing / Material 12.0d 0.0d 08-Jan-18 08:00 AM A 21-Jan-18 05:00 PM A 100% 100%

Page 7 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Tank & Plant 233.0d 120.0d -61.0d 01-Jan-18 08:00 AM A 28-Aug-18 05:00 PM 83.85% 51.94%
Wash Water Collection & Sludge Balancing Tank 161.0d 48.0d 4.0d 01-Jan-18 08:00 AM A 17-Jun-18 05:00 PM 61.04% 62.93%
Procurement & Delivery 109.0d 30.0d -2.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 76% 93.14%
STF2830 Horizontal Screw Pump & Subermisble Supernatant Pump 79.0d 0.0d 01-Jan-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF2840 FAT Wash Water Recovery Pumpset 6.0d 0.0d 27-Mar-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
STF2850 Pipes, Fittings & Valves 30.0d 0.0d 01-Jan-18 08:00 AM A 31-Mar-18 05:00 PM A 53.33% 100%
STF2860 Submersible Mixer 30.0d 30.0d -2.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 53.33% 100%
STF2870 Crane / Lifting Equipment, High Pressure Rubber Hose 30.0d 30.0d -2.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 53.33% 60%
Installation Works 48.0d 48.0d 4.0d 01-May-18 08:00 AM 17-Jun-18 05:00 PM 14.29% 0%
STF2880 Construction of Horizontal Screw Pump Pit 24.0d 24.0d 10.0d 01-May-18 08:00 AM 24-May-18 05:00 PM 50% 0%
STF2890 Horizontal Screw Pump & Submersible Supernatant Pump 18.0d 18.0d 10.0d 25-May-18 08:00 AM 11-Jun-18 05:00 PM 0% 0%
STF2900 Pipeworks, Fittings & Valves 18.0d 18.0d 10.0d 25-May-18 08:00 AM 11-Jun-18 05:00 PM 0% 0%
STF2910 Submersible Mixer 12.0d 12.0d 10.0d 25-May-18 08:00 AM 05-Jun-18 05:00 PM 0% 0%
STF2920 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -2.0d 06-Jun-18 08:00 AM 17-Jun-18 05:00 PM 0% 0%
Existing Sedimentation Tank / Basin 203.0d 90.0d -44.0d 01-Jan-18 08:00 AM A 29-Jul-18 05:00 PM 95.66% 63.31%
Procurement & Delivery 61.0d 30.0d -12.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 100% 96.7%
STF2930 Submersible Sludge Pump 61.0d 0.0d 01-Jan-18 08:00 AM A 30-Mar-18 05:00 PM A 100% 100%
STF2940 Pipes, Fittings & Valves 30.0d 30.0d -12.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 100% 90%
Installation Works 90.0d 90.0d -44.0d 01-May-18 08:00 AM 29-Jul-18 05:00 PM 83.33% 0%
STF2950 Submersible Sludge Pump 24.0d 24.0d -2.0d 01-May-18 08:00 AM 24-May-18 05:00 PM 100% 0%
STF2960 Pipes, Fittings & Valves 24.0d 24.0d -44.0d 06-Jul-18 08:00 AM* 29-Jul-18 05:00 PM 66.67% 0%
Polymer Plant 233.0d 119.0d -74.0d 01-Jan-18 08:00 AM A 28-Aug-18 05:00 PM 87.46% 31.91%
Procurement & Delivery 60.0d 60.0d -28.0d 01-Jan-18 08:00 AM A 10-Jul-18 05:00 PM 100% 65.22%
STF2970 Engineering Design for Polymer Plant & Dosing System 18.0d 0.0d 08-Jan-18 08:00 AM A 28-Jan-18 05:00 PM A 100% 100%
STF2980 Metering pumps (Diaphragm type) 60.0d 60.0d -64.0d 01-Jan-18 08:00 AM A 10-Jul-18 05:00 PM 100% 60%
STF2990 Crane / Lifting Equipment 30.0d 30.0d 2.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 100% 60%
STF3000 Static Mixer & Sludge Blender 30.0d 30.0d 2.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 100% 60%
Fabrication Works 36.0d 36.0d -58.0d 11-Jul-18 08:00 AM 21-Aug-18 05:00 PM 98.04% 0%
STF3010 Mixing & Service Tank 36.0d 36.0d -64.0d 11-Jul-18 08:00 AM 21-Aug-18 05:00 PM 97.22% 0%
STF3020 Hopper, Feeder & Pump Skid 36.0d 36.0d -58.0d 11-Jul-18 08:00 AM 21-Aug-18 05:00 PM 97.22% 0%
STF3030 Local Control Panel 30.0d 30.0d -58.0d 11-Jul-18 08:00 AM 14-Aug-18 05:00 PM 100% 0%
Installation Works 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%

Page 8 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF3040 Mixing & Service Tank 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
STF3050 Hopper, Feeder & Pump Skid 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
STF3060 Dosing Pipeworks 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
STF3070 Local Control Panel 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
STF3080 Crane / Lifting Equipment 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
STF3090 Static Mixer & Sludge Blender 7.0d 7.0d -74.0d 22-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
Pipeworks (100mm Dia. Pipe & Below) 154.0d 31.0d 4.0d 01-Jan-18 08:00 AM A 24-Jun-18 05:00 PM 100% 30.77%
Procurement & Installation Works 154.0d 31.0d 4.0d 01-Jan-18 08:00 AM A 24-Jun-18 05:00 PM 100% 30.77%
STF3100 Procurement & Delivery of Pipes 24.0d 0.0d 01-Jan-18 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
STF3110 Excavation, Backfilling Works 24.0d 24.0d 5.0d 25-May-18 08:00 AM 17-Jun-18 05:00 PM 100% 0%
STF3120 Pipe Laying, Jointing 24.0d 24.0d 5.0d 25-May-18 08:00 AM 17-Jun-18 05:00 PM 100% 0%
STF3130 Cleaning & Testing works 6.0d 6.0d 4.0d 18-Jun-18 08:00 AM 24-Jun-18 05:00 PM 100% 0%
Miscellaneous Works 200.0d 100.0d -55.0d 01-Jan-18 08:00 AM A 09-Aug-18 05:00 PM 92.59% 63.56%
Procurement & Delivery 79.0d 60.0d -48.0d 01-Jan-18 08:00 AM A 10-Jul-18 05:00 PM 100% 86.74%
STF3140 Engineering Design for Motive Water System & Air Compressor 18.0d 0.0d 22-Jan-18 08:00 AM A 11-Feb-18 05:00 PM A 100% 100%
STF3150 Booster Pump 30.0d 30.0d -48.0d 01-Jan-18 08:00 AM A 05-Jun-18 05:00 PM 100% 60%
STF3160 Air Compressor Set 30.0d 0.0d 01-Jan-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF3170 Submersible Pump (Portable & Gasoline Engine) 30.0d 0.0d 01-Jan-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
STF3180 Portable Water Jet 12.0d 0.0d 01-Jan-18 08:00 AM A 23-Apr-18 05:00 PM A 100% 100%
STF3190 Penstock & Valve 60.0d 60.0d -48.0d 01-Jan-18 08:00 AM A 10-Jul-18 05:00 PM 100% 80%
STF3200 FAT Penstock / Valve 1.0d 0.0d 26-Mar-18 08:00 AM A 26-Mar-18 05:00 PM A 100% 100%
Installation Works 65.0d 65.0d -55.0d 06-Jun-18 08:00 AM 09-Aug-18 05:00 PM 62.12% 0%
STF3210 Booster Pump 18.0d 18.0d -38.0d 06-Jun-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
STF3220 Air Compressor Set 18.0d 18.0d -38.0d 06-Jun-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
STF3230 Penstock & Valve 30.0d 30.0d -55.0d 11-Jul-18 08:00 AM 09-Aug-18 05:00 PM 16.67% 0%
Electrical Works 298.0d 156.0d -111.0d 11-Dec-17 08:00 AM A 04-Oct-18 05:00 PM 58.03% 52.69%

Drawing & Material Approval 24.0d 0.0d 11-Dec-17 08:00 AM A 09-Jan-18 05:00 PM A 100% 100%
STF3240 Submission Drawing/Material for Approval 12.0d 0.0d 11-Dec-17 08:00 AM A 24-Dec-17 05:00 PM A 100% 100%
STF3250 Review & Approval for Drawing/Material 12.0d 0.0d 26-Dec-17 08:00 AM A 09-Jan-18 05:00 PM A 100% 100%
Panel & Cabling Works 298.0d 156.0d -111.0d 11-Dec-17 08:00 AM A 04-Oct-18 05:00 PM 54.39% 49.32%
Switchboard / MCC Panel 256.0d 129.0d -84.0d 01-Feb-18 08:00 AM A 07-Sep-18 05:00 PM 83.49% 44.35%
STF3260 Procurement & Fabrication of Panel 84.0d 84.0d -95.0d 01-Feb-18 08:00 AM A 07-Aug-18 05:00 PM 100% 60%

Page 9 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF3270 FAT Electrical Control and Switchboards 1.0d 1.0d -72.0d 01-Feb-18 08:00 AM A 08-Aug-18 05:00 PM 100% 60%
STF3280 Installation Works 30.0d 30.0d -84.0d 09-Aug-18 08:00 AM 07-Sep-18 05:00 PM 13.33% 0%
Submain Cabling Works for MCC-SDP-Palong 124.0d 58.0d -111.0d 02-Jan-18 08:00 AM A 04-Oct-18 05:00 PM 47.73% 54.44%
STF3290 Procurement & Delivery of Cable 24.0d 24.0d -95.0d 01-Feb-18 08:00 AM A 04-Sep-18 05:00 PM 87.5% 60%
STF3300 Installation & Cabling Works 30.0d 30.0d -111.0d 02-Jan-18 08:00 AM A 04-Oct-18 05:00 PM 0% 50%
Distribution & Earthing System 181.0d 58.0d -111.0d 01-Feb-18 08:00 AM A 04-Oct-18 05:00 PM 47.73% 26.67%
STF3310 Procurement & Delivery of Cable 24.0d 24.0d -95.0d 01-Feb-18 08:00 AM A 04-Sep-18 05:00 PM 87.5% 60%
STF3320 Installation Works 30.0d 30.0d -111.0d 05-Sep-18 08:00 AM 04-Oct-18 05:00 PM 0% 0%
Compund Lighting System 181.0d 58.0d -111.0d 01-Feb-18 08:00 AM A 04-Oct-18 05:00 PM 47.73% 26.67%
STF3330 Procurement & Delivery 24.0d 24.0d -95.0d 01-Feb-18 08:00 AM A 04-Sep-18 05:00 PM 87.5% 60%
STF3340 Installation & Cabling Works 30.0d 30.0d -111.0d 05-Sep-18 08:00 AM 04-Oct-18 05:00 PM 0% 0%
Miscellaneous Works 52.0d 30.0d -111.0d 11-Dec-17 08:00 AM A 04-Oct-18 05:00 PM 0% 95%
STF3350 Relocations Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM A 04-Jan-18 05:00 PM A 0% 100%
STF3360 Miscellaneous Works 30.0d 30.0d -111.0d 02-Jan-18 08:00 AM A 04-Oct-18 05:00 PM 0% 90%
Instrumentation Works 271.0d 129.0d -84.0d 11-Dec-17 08:00 AM A 07-Sep-18 05:00 PM 85.53% 54.24%

Drawing & Material Approval 24.0d 0.0d 11-Dec-17 08:00 AM A 09-Jan-18 05:00 PM A 100% 100%
STF3370 Submission Drawing/Material for Approval 12.0d 0.0d 11-Dec-17 08:00 AM A 24-Dec-17 05:00 PM A 100% 100%
STF3380 Review & Approval for Drawing/Material 12.0d 0.0d 26-Dec-17 08:00 AM A 09-Jan-18 05:00 PM A 100% 100%
Panel & Cabling Works 256.0d 129.0d -84.0d 01-Feb-18 08:00 AM A 07-Sep-18 05:00 PM 82.22% 44.7%
Procurement & Installation Works 256.0d 129.0d -84.0d 01-Feb-18 08:00 AM A 07-Sep-18 05:00 PM 82.22% 44.7%
STF3390 Procurement & Fabrication of Instrument Panel 84.0d 84.0d -71.0d 01-Feb-18 08:00 AM A 07-Aug-18 05:00 PM 100% 60%
STF3400 FAT 1.0d 0.0d 28-Mar-18 08:00 AM A 28-Mar-18 05:00 PM A 100% 100%
STF3410 Installation & Signal Cabling Works 30.0d 30.0d -84.0d 09-Aug-18 08:00 AM 07-Sep-18 05:00 PM 6.67% 0%
Infrastructure Works 10.0d 10.0d 8.4d 11-Jun-18 02:00 PM 21-Jun-18 02:00 PM 0% 0%

Reinstatement of Damaged Existing Road 10.0d 10.0d 8.4d 11-Jun-18 02:00 PM 21-Jun-18 02:00 PM 0% 0%
STF3420 Site clearance, levelling & compaction 7.0d 7.0d 8.4d 11-Jun-18 02:00 PM 18-Jun-18 02:00 PM 0% 0%
STF3430 Lay & compact crusher-run & premix (binder and wearing coarse)10.0d 10.0d 8.4d 11-Jun-18 02:00 PM 21-Jun-18 02:00 PM 0% 0%
Site Handover Works 13.5d 13.5d -110.5d 06-Oct-18 08:00 AM 19-Oct-18 12:00 PM 0% 0%

Project Completions 13.5d 13.5d -110.5d 06-Oct-18 08:00 AM 19-Oct-18 12:00 PM 0% 0%


Training, Testing, Commissioning & Maintenance 13.5d 13.5d -110.5d 06-Oct-18 08:00 AM 19-Oct-18 12:00 PM 0% 0%
STF3440 Preparation of Testing & Report 8.0d 8.0d -96.0d 06-Oct-18 08:00 AM 14-Oct-18 05:00 PM 0% 0%

Page 10 of 11 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.04 ALL RUN BS 30% 30.04.2018 R Classic Schedule Layout 19-Apr-18 04:43 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF3450 Pre-commissioning 4.0d 4.0d -96.0d 06-Oct-18 08:00 AM 09-Oct-18 05:00 PM 0% 0%


STF3460 Setting to Work 3.0d 3.0d -96.0d 10-Oct-18 08:00 AM 13-Oct-18 05:00 PM 0% 0%
STF3470 Commissioning & Training of Works 5.0d 5.0d -96.0d 14-Oct-18 08:00 AM 18-Oct-18 05:00 PM 0% 0%
STF3480 Handing Over to Client 1.0d 1.0d -164.1d 18-Oct-18 07:00 PM 19-Oct-18 12:00 PM 0% 0%