Vous êtes sur la page 1sur 4

Realisasi yang dapat Qty Remaining

total qty cum progressQty Remaining dikerjakan per minggu [minggu]


Underground cable 3900 750 3150 250 12.6
Digging 20
Qty Remaining [hari]
asumsi 1 minggu= 7
hari
88.2 54 142.2
Task Name
Contract
Drawing Approval ok
Technical Presentation With PLN Area Gorontalo ok
Drawing Approval Sign Of ok
Owner Drawing Approval ok
Land Acqusition ok
Socialization and Price Negotiation ok
- Molowahu Village ok
- Dunggala Village ok
- Isimu Utara Village ok
Transaction ok
-Payment For Span, Trees and Compensation ok
-Payment Document Signing ok
Procurement
Poles (Steel and Concrete) ok
PO ok
Fabrication ok
FAT ok
Shipment ok
From Surabaya To Anggrek Port ok
From Anggrek Port To Gorontalo ok
Accessories ok
PO ok
Fabrication ok
Shipment ok
From Surabaya To Anggrek Port ok
From Anggrek Port To Gorontalo ok
Cable, Conductor and Insulator ok
PO ok
Fabrication ok
FAT ok
Shipment ok
From Bogor To Tanjung Priok Port ok
From Tanjung Priok Port To Anggrek Port ok
From Anggrek Port To Gorontalo ok
Cubicle
PO
Fabrication
FAT
Shipment
From Bogor To Tanjung Priok Port
From Tanjung Priok Port To Anggrek Port
From Anggrek Port To Gorontalo
Constrution
Poles (Steel and Concrete)
Digging
Pole Erection
Accessories Installation
Conductor Stringing
Cable Underground NA2XSEYBY 3 X 300 mm2
Soil Excavation
Cable Laying
Soil Covering
Terminating and Jointing
Cubicle
Civil Modification 6 10 14 8.4
Cable Laying 2 10 14 2.8
Installation 1 10 14 1.4
Terminating 1 10 14 1.4
Commisioning and SLO
Megger Test
Hivolt Test
Ground Earth Test
Documentation
Document SLO
As Built Drawing
Document COD

Vous aimerez peut-être aussi