J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN POLIMER DAN PELANTAR GEOTUBE SERTA
KERJA-KERJA BERKAITAN.

NO LOCATION Description of Work Progress This Week Actual (%) Schedule (%) Variance
(From 18th March 2018 - 24th March 2018)
A WASH WATER COLLECTION & SLUDGE 0.33 0.75 -0.42
BALANCING TANK (WWCT & SBT)
A1 1st Lift (1.5m) - WALL '1' Curing works
Dismantle formwork
A2 1st Lift (1.5m & 2.4) - WALL '2' Installation of reinforcement bar (Y12 & Y16)
*Refer 'Attachment B' in the email Installation of scaffold & stagging
Removing concrete debris along kickers surface
Installation of waterstop
Installation of foamties
Installation of formwork
Installation of 4 units 100mm dia. Pipes
A3 PIPES - PUDDLE FLANGE (700mm) Delivery of 3 units of 300mm ductile pipes
Inspection of material (DI Pipes)
A4 Prevention Action (JKKP / DOSH) Install frame for hording
Install red-white of tape to barricade site area
Install culvert for earth drain
housekeeping of rebar, formwork & other materials
Erect scaffold as staircase at WWCT & SBT area
Lay canvas along slope area
Secure access along perimeter of the excavation area
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 14.91 for WWCT & SBT

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 3/10/2018 54.93 8.19
2 3/17/2018 58.44 8.71 0.52
3 3/24/2018 63.45 9.46 0.75

Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 3/10/2018 56.7 8.45
2 3/17/2018 63.48 9.46 1.01
3 3/24/2018 65.69 9.79 0.33