J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-
KERJA BERKAITAN.

WEEKLY WORK PROGRESS (FROM 22nd APRIL 2018 - 28th APRIL 2018)

NO LOCATION Description of Work Progress This Week Actual (%) Schedule (%) Variance
(From
22nd April 2018 - 28th April 2018)
A WASH WATER COLLECTION & SLUDGE Weekly percentage 4.18 0.00 +4.18
BALANCING TANK (WWCT & SBT) Overall WWCT & SBT percentage as at 28.04.2018 85.53 100.00 -14.47
A1 WALL '2' - 2nd Lift (2.1m, 1.45m & 2.15m) Continue curing works
*Refer 'Attachment C' in the email Dismantle formwork, scaffold & stagging
Housekeeping
A2 Walkway Slab & Overflow Slab/Wall Continue curing works
*Refer 'Attachment D' in the email Dismantle formwork, t-props, soffit, scaffold & stagging
Housekeeping
A3 Honeycomb & Waterproofing Repair honeycomb
Apply waterproofing for internal wall
A4 Backfilling Partial backfilling & compaction (1st stage)

B DEWATERING PLATFORM (GEOTUBE) Weekly percentage 1.77 0.00 +1.77


Overall Geotube percentage as at 28.04.2018 38.46 100.00 -61.54
B1 Formwork & Reinforcement Erect formwork
Fabricate reinforcement
B2 Geotube Delivery of geotube
Site measurement
C POLYMER BUILDING Weekly percentage 0.13 0.00 +0.13
Overall Polymer Building percentage as at 28.04.2018 10.43 100.00 -89.57
C1 Formwork & Reinforcement Erect formwork
Fabricate reinforcement
C2 Site Preparation Site measurement & marking
Trim muddy topsoil
D PIPEWORKS Weekly percentage 4.05 0.00 +4.05
Overall Pipeworks percentage as at 28.04.2018 60.50 100.00 -39.50
D1 Site Preparation Site measurement
Check and confirm level of pipes to be installed
D2 Installation Pipes (200mm & 300mm) Excavation works
(From Sedimentation Tank & Filter to WWCT & Installation & jointing of pipes
SBT) Connection of pipes to existing chamber
Backfilling works
E ELECTRICAL WORKS Weekly percentage 0.72 1.15 -0.43
Overall Electrical Works percentage as at 28.04.2018 53.52 89.81 -36.29
E1 Submain Cabling Works Site measurement
Check and confirm level of pipes to be installed
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 14.91 for WWCT & SBT

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 2/1/2018 49.01 7.31
2 3/10/2018 69.97 10.43 3.12
3 3/17/2018 78.35 11.68 1.25
4 3/24/2018 86.73 12.93 1.25
5 3/31/2018 94.76 14.13 1.20
6 4/7/2018 100.00 14.91 0.78
7 4/14/2018 100.00 14.91 0.00
8 4/21/2018 100.00 14.91 0.00
9 4/28/2018 100.00 14.91 0.00
Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 2/1/2018 11.06 1.65
2 3/10/2018 44.68 6.66 5.01
3 3/17/2018 48.94 7.30 0.64
4 3/24/2018 48.94 7.30 0.00
5 3/31/2018 52.34 7.80 0.50
6 4/7/2018 54.04 8.06 0.26
7 4/14/2018 54.89 8.18 0.12
8 4/21/2018 57.45 8.57 0.39
9 4/28/2018 85.53 12.75 4.18
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 7.05 for Dewatering Platform (Geotube)

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 2/1/2018 63.69 4.49
2 3/10/2018 87.14 6.14 1.65
3 3/17/2018 91.68 6.46 0.32
4 3/24/2018 96.22 6.78 0.32
5 3/31/2018 100.00 7.05 0.27
6 4/7/2018 100.00 7.05 0.00
7 4/14/2018 100.00 7.05 0.00
8 4/21/2018 100.00 7.05 0.00
9 4/28/2018 100.00 7.05 0.00
Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 2/1/2018 13.33 0.94
2 3/10/2018 13.33 0.94 0.00
3 3/17/2018 13.33 0.94 0.00
4 3/24/2018 13.33 0.94 0.00
5 3/31/2018 13.33 0.94 0.00
6 4/7/2018 13.33 0.94 0.00
7 4/14/2018 13.33 0.94 0.00
8 4/21/2018 13.33 0.94 0.00
9 4/28/2018 38.46 2.71 1.77
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 4.30 for Polymer Building

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 2/1/2018 34.54 1.49
2 3/10/2018 91.63 3.94 2.45
3 3/17/2018 94.59 4.07 0.13
4 3/24/2018 97.54 4.19 0.12
5 3/31/2018 100.00 4.30 0.11
6 4/7/2018 100.00 4.30 0.00
7 4/14/2018 100.00 4.30 0.00
8 4/21/2018 100.00 4.30 0.00
9 4/28/2018 100.00 4.30 0.00
Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 2/1/2018 7.54 0.32
2 3/10/2018 7.54 0.32 0.00
3 3/17/2018 7.54 0.32 0.00
4 3/24/2018 7.54 0.32 0.00
5 3/31/2018 7.54 0.32 0.00
6 4/7/2018 7.54 0.32 0.00
7 4/14/2018 7.54 0.32 0.00
8 4/21/2018 7.54 0.32 0.00
9 4/28/2018 10.43 0.45 0.13
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 13.51 for Pipeworks

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 2/1/2018 44.44 6.00
2 3/10/2018 87.41 11.81 5.81
3 3/17/2018 92.59 12.51 0.70
4 3/24/2018 98.89 13.36 0.85
5 3/31/2018 100.00 13.51 0.15
6 4/7/2018 100.00 13.51 0.00
7 4/14/2018 100.00 13.51 0.00
8 4/21/2018 100.00 13.51 0.00
9 4/28/2018 100.00 13.51 0.00
Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 2/1/2018 10.00 1.35
2 3/10/2018 10 1.35 0.00
3 3/17/2018 10 1.35 0.00
4 3/24/2018 12 1.62 0.27
5 3/31/2018 20 2.70 1.08
6 4/7/2018 27.5 3.72 1.02
7 4/14/2018 27.5 3.72 0.00
8 4/21/2018 30.5 4.12 0.40
9 4/28/2018 60.5 8.17 4.05
J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN
POLIMER DAN PELANTAR GEOTUBE SERTA KERJA-KERJA BERKAITAN.

***All data obtained from Primavera P6 15.2


***Weightage = 14.42 for Pipeworks

Cumulative Weekly
NO DATE Schedule % Complete Remarks
Weightage Weightage
1 2/1/2018 27.91 4.02
2 3/10/2018 40.86 5.89 1.87
3 3/17/2018 46.84 6.75 0.86
4 3/24/2018 52.82 7.62 0.87
5 3/31/2018 59.12 8.53 0.91
6 4/7/2018 65.89 9.50 0.97
7 4/14/2018 73.86 10.65 1.15
8 4/21/2018 81.84 11.80 1.15
9 4/28/2018 89.81 12.95 1.15
Cumulative Weekly
NO DATE Units % Complete Remarks
Weightage Weightage
1 2/1/2018 36.70 5.29
2 3/10/2018 36.7 5.29 0.00
3 3/17/2018 36.7 5.29 0.00
4 3/24/2018 41.05 5.92 0.63
5 3/31/2018 41.05 5.92 0.00
6 4/7/2018 45.21 6.52 0.60
7 4/14/2018 46.87 6.76 0.24
8 4/21/2018 48.53 7.00 0.24
9 4/28/2018 53.52 7.72 0.72