STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 300.0d 155.0d -95.0d 02-Oct-17 08:00 22-Sep-18 08:00 78.21% 38.66%
AM A AM
Milestone 300.0d 0.0d -95.0d 02-Oct-17 08:00 AM A
22-Sep-18 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -95.0d 22-Sep-18 08:00 AM22-Sep-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
External Finishes 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1350 External plastering & painting 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Internal Floor & Wall Finishes 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Ceiling Finishes 18.0d 18.0d -48.0d 18-Jun-18 08:00 AM 08-Jul-18 05:00 PM 72.22% 0%
A1370 Install frame, ceiling & painting 18.0d 18.0d -48.0d 18-Jun-18 08:00 AM 08-Jul-18 05:00 PM 72.22% 0%
Pipeworks 155.0d 78.0d -35.0d 20-Dec-17 08:00 AM23-Jun-18
A 05:00 PM 98.89% 12%
A1550 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -71.0d 22-Jul-18 08:00 AM 04-Aug-18 05:00 PM 0% 0%
Existing Sedimentation Tank 197.0d 108.0d -65.0d 06-Dec-17 08:00 AM28-Jul-18
A 05:00 PM 89.62% 39.13%
Procurement 60.0d 60.0d -41.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1560 Submersible Sludge Pump 60.0d 60.0d -65.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1570 Pipes, Fittings & Valves 30.0d 30.0d -11.0d 06-Dec-17 08:00 AM28-Apr-18
A 05:00 PM 100% 60%
Installation 48.0d 48.0d -65.0d 03-Jun-18 08:00 AM 28-Jul-18 05:00 PM 60.42% 0%
A1580 Submersible Sludge Pump 24.0d 24.0d -65.0d 03-Jun-18 08:00 AM 30-Jun-18 05:00 PM 100% 0%
A1590 Pipes, Fittings & Valves 24.0d 24.0d -65.0d 01-Jul-18 08:00 AM 28-Jul-18 05:00 PM 20.83% 0%
Polymer Plant 221.0d 132.0d -89.0d 06-Dec-17 08:00 AM25-Aug-18
A 05:00 PM 70.5% 25.86%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 60.0d -29.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1610 Metering Pumps (Diaphragm type) 60.0d 60.0d -89.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1620 Crane / Lifting Equipment 30.0d 30.0d 1.0d 06-Dec-17 08:00 AM28-Apr-18
A 05:00 PM 100% 60%
A1630 Static Mixer & Sludge Blender 30.0d 30.0d 1.0d 06-Dec-17 08:00 AM28-Apr-18
A 05:00 PM 100% 60%
Fabrication 36.0d 36.0d -65.0d 03-Jun-18 08:00 AM 14-Jul-18 05:00 PM 85.29% 0%
A1640 Mixing & Service Tank 36.0d 36.0d -89.0d 03-Jun-18 08:00 AM 14-Jul-18 05:00 PM 80.56% 0%
A1650 Hopper, Feeder & Pump Skid 36.0d 36.0d -89.0d 03-Jun-18 08:00 AM 14-Jul-18 05:00 PM 80.56% 0%
A1660 Local Control Panel 30.0d 30.0d -59.0d 03-Jun-18 08:00 AM 07-Jul-18 05:00 PM 96.67% 0%
Installation 36.0d 36.0d -89.0d 15-Jul-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
A1670 Mixing & Service Tank 24.0d 24.0d -89.0d 15-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1680 Hopper, Feeder & Pump Skid 24.0d 24.0d -89.0d 15-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1690 Dosing Pipeworks 24.0d 24.0d -89.0d 15-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1700 Local Control Panel 12.0d 12.0d -89.0d 12-Aug-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
A1710 Crane / Lifting Equipment 12.0d 12.0d -89.0d 12-Aug-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
A1720 Static Mixer & Sludge Blender 12.0d 12.0d -89.0d 12-Aug-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
Pipeworks 155.0d 78.0d -18.0d 20-Dec-17 08:00 AM23-Jun-18
A 05:00 PM 98.39% 18.46%
Procurement 24.0d 24.0d -5.0d 20-Dec-17 08:00 AM21-Apr-18
A 05:00 PM 100% 60%
A1730 To procure & deliver Pipes to site 24.0d 24.0d -5.0d 20-Dec-17 08:00 AM21-Apr-18
A 05:00 PM 100% 60%
Installation 24.0d 24.0d -29.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
A1740 Excavation & backfilling works 24.0d 24.0d -29.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
A1750 Pipe laying & jointing 24.0d 24.0d -29.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
Testing 6.0d 6.0d -18.0d 17-Jun-18 08:00 AM 23-Jun-18 05:00 PM 83.33% 0%
A1760 Cleaning & testing works 6.0d 6.0d -18.0d 17-Jun-18 08:00 AM 23-Jun-18 05:00 PM 83.33% 0%
Miscellaneous Works 177.0d 100.0d -57.0d 20-Dec-17 08:00 AM18-Jul-18
A 05:00 PM 90.22% 46.88%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
Procurement 61.0d 61.0d -57.0d 13-Jan-18 08:00 AM 0
A3-Jun-18 05:00 PM 98.77% 60%
A1780 Booster Pump 30.0d 30.0d -57.0d 13-Jan-18 08:00 AM 2
A8-Apr-18 05:00 PM 100% 60%
A1790 Air Compressor Set 30.0d 30.0d -57.0d 13-Jan-18 08:00 AM 2
A8-Apr-18 05:00 PM 100% 60%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 30.0d -57.0d 13-Jan-18 08:00 AM 2
A8-Apr-18 05:00 PM 100% 60%
A1810 Portable Water jet 12.0d 12.0d -57.0d 13-Jan-18 08:00 AM 0
A7-Apr-18 05:00 PM 100% 60%
A1820 Penstock & Valves 60.0d 60.0d -57.0d 13-Jan-18 08:00 AM 0
A2-Jun-18 05:00 PM 98.33% 60%
A1830 FAT Penstock / Valves 1.0d 1.0d -57.0d 26-Mar-18 08:00 AM03-Jun-18
A 05:00 PM 0% 60%
Installation 70.0d 70.0d -57.0d 29-Apr-18 08:00 AM 18-Jul-18 05:00 PM 54.55% 0%
A1840 Booster Pump Set 18.0d 18.0d -35.0d 29-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1850 Air Compressor Set 18.0d 18.0d -35.0d 29-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1860 Penstock / Valves 30.0d 30.0d -57.0d 14-Jun-18 08:00 AM 18-Jul-18 05:00 PM 0% 0%
Electrical Works 251.0d 138.0d -95.0d 08-Nov-17 08:00 AM01-Sep-18
A 05:00 PM 52.82% 41.05%
Training, Testing, Commissioning & Maintenance 17.0d 17.0d -95.0d 02-Sep-18 08:00 AM20-Sep-18 05:00 PM 0% 0%
A2070 Preparation of testing & report 12.0d 12.0d -95.0d 02-Sep-18 08:00 AM15-Sep-18 05:00 PM 0% 0%
A2080 Pre-commissioning 6.0d 6.0d -95.0d 02-Sep-18 08:00 AM08-Sep-18 05:00 PM 0% 0%
A2090 Setting to work 3.0d 3.0d -95.0d 09-Sep-18 08:00 AM11-Sep-18 05:00 PM 0% 0%
A2100 Commissioning & training 7.0d 7.0d -95.0d 12-Sep-18 08:00 AM19-Sep-18 05:00 PM 0% 0%
A2110 Handing over to Client 1.0d 1.0d -95.0d 20-Sep-18 08:00 AM20-Sep-18 05:00 PM 0% 0%