Culture Documents
STF PALONG TIMUR REV.00 RUN ALL BS 28.04.2018 330.0d 155.0d -125.0d 02-Oct-17 08:00 27-Oct-18 08:00 94.97% 51.14%
AM A AM
Milestone 330.0d 0.0d -125.0d 02-Oct-17 08:00 AM A
27-Oct-18 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -125.0d 27-Oct-18 08:00 AM 27-Oct-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
External Finishes 18.0d 18.0d -78.0d 02-Jul-18 08:00 AM 22-Jul-18 05:00 PM 100% 0%
A1350 External plastering & painting 18.0d 18.0d -78.0d 02-Jul-18 08:00 AM 22-Jul-18 05:00 PM 100% 0%
Internal Floor & Wall Finishes 18.0d 18.0d -78.0d 02-Jul-18 08:00 AM 22-Jul-18 05:00 PM 100% 0%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 18.0d -78.0d 02-Jul-18 08:00 AM 22-Jul-18 05:00 PM 100% 0%
Ceiling Finishes 18.0d 18.0d -78.0d 23-Jul-18 08:00 AM 12-Aug-18 05:00 PM 100% 0%
A1370 Install frame, ceiling & painting 18.0d 18.0d -78.0d 23-Jul-18 08:00 AM 12-Aug-18 05:00 PM 100% 0%
Pipeworks 161.0d 54.0d -41.0d 20-Dec-17 08:00 AM30-Jun-18
A 05:00 PM 100% 60.5%
A1550 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -101.0d 26-Aug-18 08:00 AM 08-Sep-18 05:00 PM 100% 0%
Existing Sedimentation Tank 167.0d 48.0d -35.0d 06-Dec-17 08:00 AM23-Jun-18
A 05:00 PM 100% 65.22%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM30-Mar-18
A 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM21-Apr-18
A 05:00 PM A 100% 100%
Installation 48.0d 48.0d -35.0d 29-Apr-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
A1580 Submersible Sludge Pump 24.0d 24.0d -35.0d 29-Apr-18 08:00 AM 27-May-18 05:00 PM 100% 0%
A1590 Pipes, Fittings & Valves 24.0d 24.0d -35.0d 28-May-18 08:00 AM23-Jun-18 05:00 PM 100% 0%
Polymer Plant 251.0d 132.0d -119.0d 06-Dec-17 08:00 AM29-Sep-18
A 05:00 PM 90.65% 25.86%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 60.0d -59.0d 06-Dec-17 08:00 AM07-Jul-18
A 05:00 PM 100% 60%
A1610 Metering Pumps (Diaphragm type) 60.0d 60.0d -119.0d 06-Dec-17 08:00 AM07-Jul-18
A 05:00 PM 100% 60%
A1620 Crane / Lifting Equipment 30.0d 30.0d -29.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1630 Static Mixer & Sludge Blender 30.0d 30.0d -29.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
Fabrication 36.0d 36.0d -95.0d 08-Jul-18 08:00 AM 18-Aug-18 05:00 PM 100% 0%
A1640 Mixing & Service Tank 36.0d 36.0d -119.0d 08-Jul-18 08:00 AM 18-Aug-18 05:00 PM 100% 0%
A1650 Hopper, Feeder & Pump Skid 36.0d 36.0d -119.0d 08-Jul-18 08:00 AM 18-Aug-18 05:00 PM 100% 0%
A1660 Local Control Panel 30.0d 30.0d -89.0d 08-Jul-18 08:00 AM 11-Aug-18 05:00 PM 100% 0%
Installation 36.0d 36.0d -119.0d 19-Aug-18 08:00 AM 29-Sep-18 05:00 PM 63.89% 0%
A1670 Mixing & Service Tank 24.0d 24.0d -119.0d 19-Aug-18 08:00 AM 15-Sep-18 05:00 PM 95.83% 0%
A1680 Hopper, Feeder & Pump Skid 24.0d 24.0d -119.0d 19-Aug-18 08:00 AM 15-Sep-18 05:00 PM 95.83% 0%
A1690 Dosing Pipeworks 24.0d 24.0d -119.0d 19-Aug-18 08:00 AM 15-Sep-18 05:00 PM 95.83% 0%
A1700 Local Control Panel 12.0d 12.0d -119.0d 16-Sep-18 08:00 AM29-Sep-18 05:00 PM 0% 0%
A1710 Crane / Lifting Equipment 12.0d 12.0d -119.0d 16-Sep-18 08:00 AM29-Sep-18 05:00 PM 0% 0%
A1720 Static Mixer & Sludge Blender 12.0d 12.0d -119.0d 16-Sep-18 08:00 AM29-Sep-18 05:00 PM 0% 0%
Pipeworks 161.0d 30.0d -24.0d 20-Dec-17 08:00 AM30-Jun-18
A 05:00 PM 100% 30.77%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
A1730 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM29-Mar-18
A 05:00 PM A 100% 100%
Installation 24.0d 24.0d -35.0d 28-May-18 08:00 AM23-Jun-18 05:00 PM 100% 0%
A1740 Excavation & backfilling works 24.0d 24.0d -35.0d 28-May-18 08:00 AM23-Jun-18 05:00 PM 100% 0%
A1750 Pipe laying & jointing 24.0d 24.0d -35.0d 28-May-18 08:00 AM23-Jun-18 05:00 PM 100% 0%
Testing 6.0d 6.0d -24.0d 24-Jun-18 08:00 AM 30-Jun-18 05:00 PM 100% 0%
A1760 Cleaning & testing works 6.0d 6.0d -24.0d 24-Jun-18 08:00 AM 30-Jun-18 05:00 PM 100% 0%
Miscellaneous Works 197.0d 90.0d -77.0d 20-Dec-17 08:00 AM11-Aug-18
A 05:00 PM 96.74% 57.49%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
Procurement 61.0d 60.0d -86.0d 13-Jan-18 08:00 AM 0
A7-Jul-18 05:00 PM 100% 76.07%
A1780 Booster Pump 30.0d 30.0d -86.0d 13-Jan-18 08:00 AM 0
A2-Jun-18 05:00 PM 100% 60%
A1790 Air Compressor Set 30.0d 30.0d -86.0d 13-Jan-18 08:00 AM 0
A2-Jun-18 05:00 PM 100% 60%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 30.0d -86.0d 13-Jan-18 08:00 AM 0
A2-Jun-18 05:00 PM 100% 90%
A1810 Portable Water jet 12.0d 0.0d 13-Jan-18 08:00 AM 2
A1-Apr-18 05:00 PM A 100% 100%
A1820 Penstock & Valves 60.0d 60.0d -86.0d 13-Jan-18 08:00 AM 0
A7-Jul-18 05:00 PM 100% 80%
A1830 FAT Penstock / Valves 1.0d 0.0d 26-Mar-18 08:00 AM26-Mar-18
A 05:00 PM A 100% 100%
Installation 60.0d 60.0d -77.0d 03-Jun-18 08:00 AM 11-Aug-18 05:00 PM 83.33% 0%
A1840 Booster Pump Set 18.0d 18.0d -65.0d 03-Jun-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
A1850 Air Compressor Set 18.0d 18.0d -65.0d 03-Jun-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
A1860 Penstock / Valves 30.0d 30.0d -77.0d 08-Jul-18 08:00 AM 11-Aug-18 05:00 PM 63.33% 0%
Electrical Works 242.0d 138.0d -125.0d 08-Nov-17 08:00 AM06-Oct-18
A 05:00 PM 89.81% 53.52%
Training, Testing, Commissioning & Maintenance 17.0d 17.0d -125.0d 07-Oct-18 08:00 AM 25-Oct-18 05:00 PM 0% 0%
A2070 Preparation of testing & report 12.0d 12.0d -125.0d 07-Oct-18 08:00 AM 20-Oct-18 05:00 PM 0% 0%
A2080 Pre-commissioning 6.0d 6.0d -125.0d 07-Oct-18 08:00 AM 13-Oct-18 05:00 PM 0% 0%
A2090 Setting to work 3.0d 3.0d -125.0d 14-Oct-18 08:00 AM 16-Oct-18 05:00 PM 0% 0%
A2100 Commissioning & training 7.0d 7.0d -125.0d 17-Oct-18 08:00 AM 24-Oct-18 05:00 PM 0% 0%
A2110 Handing over to Client 1.0d 1.0d -125.0d 25-Oct-18 08:00 AM 25-Oct-18 05:00 PM 0% 0%