MONTHLY TIME SUSPENSION REPORT

For JULY 2015

#REF! Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road
Standards (HDM-4 Project Analysis) (Intermittent Sections) along Acop – Kapangan – Kibungan – Bakun Road,
K0322+115 – K0326+935
#REF! #REF!
Date Weather Remarks Time Suspension Recommended
1 Cloudy/Rainy
2 Rainy Work Suspended 1
3 Cloudy/Rainy
4 Rainy Work Suspended 1
5 Typhoon Work Suspended 1
6 Typhoon Work Suspended 1
7 Typhoon Work Suspended 1
8 Typhoon Work Suspended 1
9 Typhoon Work Suspended 1
10 Typhoon Work Suspended 1
11 Rainy Work Suspended 1
12 Rainy Work Suspended 1
13 Rainy Work Suspended 1
14 Rainy Work Suspended 1
15 Rainy Work Suspended 1
16 Rainy Work Suspended 1
17 Rainy Work Suspended 1
18 Rainy Work Suspended 1
19 Cloudy/Light Rain Work Suspended 1
20 Cloudy/Light Rain
21 Rainy Work Suspended 1
22 Rainy Work Suspended 1
23 Cloudy/Light Rain
24 Cloudy/Light Rain
25 Cloudy/Light Rain
26 Rainy Work Suspended 1
27 Rainy Work Suspended 1
28 Rainy Work Suspended 1
29 Cloudy/Rainy Work Suspended 1
30 Rainy
31 Fair
TOTAL SUSPENSION TIME RECOMMENDED FOR THIS MONTH 23
TOTAL SUSPENSION TIME RECOMMENDED PREVIOUSLY
GRAND TOTAL TO DATE 23
TOTAL PREDETERMINED UNWORKABLE RAINY DAYS 48
TOTAL NUMBER OF UNWORKABLE RAINY DAYS CONSIDERED FOR TIME EXTENSION
ORIGINAL CONTRACT TIME (Calendar Days) 285
ORIGINAL EXPIRY DATE #REF!
REVISED EXPIRY DATE due to approved Variation Orders
REVISED EXPIRY DATE due to approved Time Extensions due RROW
REVISED EXPIRY DATE due to approved Time Extensions due to Adverse Weather Condition
REVISED EXPIRY DATE DUE TO THIS SUSPENSION EXTENSION #REF!
PERCENT TIME ELAPSED 11.23%

Prepared by: Concurred by:

#REF! #REF!
Project Engineer General Manager
(DPWH) (Contractor)

Submitted by: RECOMMENDING APPROVAL:

CLIFTON D. VALENCERINA ALBERTO N. GAHID


Chief, Construction Division OIC-Assistant Regional Director
APPROVED:

EDILBERTO P. CARABBACAN, CESO IV


Regional Director
MONTHLY TIME SUSPENSION REPORT
For August 2015

#REF! Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road
Standards (HDM-4 Project Analysis) (Intermittent Sections) along Acop – Kapangan – Kibungan – Bakun Road,
K0322+115 – K0326+935
#REF! #REF!
Date Weather Remarks Time Suspension Recommended
1 Fair
2 Rainy Work Suspended 1
3 Rainy Work Suspended 1
4 Light Rain
5 Fair
6 Fair
7 Light Rain
8 Cloudy/Light Rain
9 Cloudy/Light Rain
10 Rainy Work Suspended 1
11 Rainy Work Suspended 1
12 Rainy Work Suspended 1
13 Light Rain
14 Light Rain
15 Light Rain
16 Fair
17 Fair
18 Cloudy/Light Rain
19 Cloudy/Light Rain
20 Typhoon Work Suspended 1
21 Typhoon Work Suspended 1
22 Typhoon Work Suspended 1
23 Rainy Work Suspended 1
24 Rainy Work Suspended 1
25 Rainy Work Suspended 1
26 Rainy Work Suspended 1
27 Rainy Work Suspended 1
28 Fair Work Suspended 1
29 Rainy Work Suspended 1
30 Rainy Work Suspended 1
31 Rainy Work Suspended 1
TOTAL SUSPENSION TIME RECOMMENDED FOR THIS MONTH 17
TOTAL SUSPENSION TIME RECOMMENDED PREVIOUSLY 23
GRAND TOTAL TO DATE 40
TOTAL PREDETERMINED UNWORKABLE RAINY DAYS 48
TOTAL NUMBER OF UNWORKABLE RAINY DAYS CONSIDERED FOR TIME EXTENSION
ORIGINAL CONTRACT TIME (Calendar Days) 285
ORIGINAL EXPIRY DATE #REF!
REVISED EXPIRY DATE due to approved Variation Orders
REVISED EXPIRY DATE due to approved Time Extensions due RROW
REVISED EXPIRY DATE due to approved Time Extensions due to Adverse Weather Condition
REVISED EXPIRY DATE DUE TO THIS SUSPENSION EXTENSION #REF!
PERCENT TIME ELAPSED 22.11%

Prepared by: Concurred by:

#REF! #REF!
\ General Manager
(DPWH) (Contractor)

Submitted by: RECOMMENDING APPROVAL:

CLIFTON D. VALENCERINA ALBERTO N. GAHID


Chief, Construction Division OIC-Assistant Regional Director
APPROVED:

EDILBERTO P. CARABBACAN, CESO IV


Regional Director
MONTHLY TIME SUSPENSION REPORT
For September 2015

#REF! Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road
Standards (HDM-4 Project Analysis) (Intermittent Sections) along Acop – Kapangan – Kibungan – Bakun Road,
K0322+115 – K0326+935
#REF! #REF!
Date Weather Remarks Time Suspension Recommended
1 Rainy Work Suspended 1
2 Rainy Work Suspended 1
3 Rainy Work Suspended 1
4 Rainy Work Suspended 1
5 Rainy Work Suspended 1
6 Rainy Work Suspended 1
7 Rainy Work Suspended 1
8 Rainy Work Suspended 1
9 Rainy Work Suspended 1
10 Rainy Work Suspended 1
11 Cloudy/Rainy Work Suspended 1
12 Fair Work Suspended 1
13 Fair Work Suspended 1
14 Fair Work Suspended 1
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
TOTAL SUSPENSION TIME RECOMMENDED FOR THIS MONTH 14
TOTAL SUSPENSION TIME RECOMMENDED PREVIOUSLY 40
GRAND TOTAL TO DATE 54
TOTAL PREDETERMINED UNWORKABLE RAINY DAYS 48
TOTAL NUMBER OF UNWORKABLE RAINY DAYS CONSIDERED FOR TIME EXTENSION 6
ORIGINAL CONTRACT TIME (Calendar Days) 285
ORIGINAL EXPIRY DATE #REF!
REVISED EXPIRY DATE due to approved Variation Orders
REVISED EXPIRY DATE due to approved Time Extensions due RROW
REVISED EXPIRY DATE due to approved Time Extensions due to Adverse Weather Condition
REVISED EXPIRY DATE DUE TO THIS SUSPENSION EXTENSION #REF!
PERCENT TIME ELAPSED 27.37%

Prepared by: Concurred by:

#REF! #REF!
Project Engineer General Manager
(DPWH) (Contractor)

Submitted by: RECOMMENDING APPROVAL:


CLIFTON D. VALENCERINA ALBERTO N. GAHID
Chief, Construction Division OIC-Assistant Regional Director

APPROVED:

EDILBERTO P. CARABBACAN, CESO IV


Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 9

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective October 1, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 8

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 26, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 7

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 22, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 6

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 16, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 5

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 11, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 4

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 7, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 3

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION Baguio City
: Sections
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 1, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 2

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections

STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681


LOCATION : Baguio City
CONTRACTOR : 3K ROCK ENGINEERING

DATE : June 24, 2015

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective June 24, 2015.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 1

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections

STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681


LOCATION : Baguio City
CONTRACTOR : 3K ROCK ENGINEERING

DATE : June 21, 2015

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to resume all construction operations effective June 21, 2015.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 3

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 1, 2014
due to the road right of way.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . 12 calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 1

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and Management-4
(HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent Sections
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
LOCATION : Baguio City
CONTRACTOR : 3K ROCK ENGINEERING

DATE : June 03, 2015

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective June 3, 3015
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . 220 calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . 14 calendar days
Days remaining ...................... 206 calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 2

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections
STATION LIMIT : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
LOCATION : Baguio City
Contractor : 3K ROCK ENGINEERING

DATE : June 22, 2015

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective June 22, 2015
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . . 220 calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . 33 calendar days
Days remaining ...................... 187 calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 4

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 1, 2014
due to road right of way.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 5

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 7, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 6

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 14, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 7

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 19, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 8

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 24, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 9

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 30, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO WEATHER

FOR THE MONTH OF : June 2015

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections
STATION LIMITS : #REF!
LOCATION : Baguio City

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

June 3, 4, 5, 6, 7, 8,
Time extension due to adverse weather
9, 10, 11, 12, 13, 14,
15, 16, 17, 18, 19, 20,
Heavy Rainfall condition and unworkable road base due to 18 Day
oversaturation of materials
2015
Time extension due to adverse weather
June 22, 23, 2015 Heavy Rainfall condition and unworkable road base due to 2 Days
oversaturation of materials

TOTAL CALENDARS DAYS 20 Days

Total Extension of Time Recommended ============================ == 20 DAYS


Total Extension of Time Recommended Previously====================== == DAYS
Grand total to date ======================================== == 20 DAYS
Original contract time======================================= == 220 DAYS
Revised contract time due to approved extensions/suspensions============== == 240 DAYS
Date of effectivity of contract ================================== == May 19, 2015
Original Expiry Date ======================================== == December 24, 2015
Revised Expiry Date due to Approved Time Extension/Suspension No. 1======== == January 13, 2016
Percent of Time Elapse ====================================== == 17.92%

PREPARED BY: CONCURRED BY;

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
WORK RESUMPTION ORDER NO. 1

Contract I.D No. : 15P00014


Name of Project
: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads
Including Drainage, Based on Pavement Management System/ Highway
Development and Management-4 (HDM-4) Along Quirino Highway (Baguio-
Bauang) (S00420LZ) Intermittent Sections K300+134 - K0300+911; K0301+195 -
K0305+000; K0305+290 - K0305+681

Location : Baguio City


Date : June 21, 2015

To: `

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

Effective to date, you are directed to resume construction operations in the project site in
view of the good weather condition and workable, dried road base.

Hereunder is the historical dat of your approved Work Suspension Order and Contract
Time Extension.

Approved Contract
Original Contract Approved Work Suspension
Time Extension: 18 Days Used to Date: 33 CD
Time: 220 CD Order: 18 CD
CD
Contract Time W.S.O No. 1: 18 CD C.T.E. No. 1: 18 CD
including extension: W.S.O No. 2: C.T.E. No. 2:
Total: 18 CD Due to V.O.: Days remaining: 205 CD
238 CD
Total: 18 CD

Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is for your file.

ISMAEL B. DELA CRUZ


Project Engineer

NOTED:

CLIFTON D. VALENCERINA
Chief, construction Division

RECOMMENDING APPROVAL: APPROVED:

ALBERTO N. GAHID EDILBERTO P. CARABBACAN


Assistant Regional Director Regional Director
I hereby acknowledge receipt of the above notice.

DATE:

3K ROCK ENGINEERING
Contractor
By:

Authorized Representative
WORK SUSPENSION ORDER NO. 2

Contract I.D No. : 15P00014


Name of Project
: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads
Including Drainage, Based on Pavement Management System/ Highway
Development and Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang)
(S00420LZ) Intermittent Sections K300+134 - K0300+911; K0301+195 -
K0305+000; K0305+290 - K0305+681

Location : Baguio City


Date : June 22, 2015

To: `

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend construction operations effective June 22, 2015 due to
adverse weather condition and unworkable road base due to oversaturation of materials.

Hereunder is the historical dat of your approved Work Suspension Order and Contract
Time Extension.

Original Contract Approved Work Suspension Approved Contract Time


Days Used to Date: 33 CD
Time: 220 CD Order: 18 CD Extension: 18 CD

Contract Time W.S.O No. 1: 18 CD C.T.E. No. 1: 18 CD


including extension: W.S.O No. 2: 2 CD C.T.E. No. 2
Total: 20 CD Due to V.O. Days remaining: 205 CD
238 CD
Total:

Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is for your file.

ISMAEL B. DELA CRUZ


Project Engineer

NOTED:

CLIFTON D. VALENCERINA
Chief, construction Division

RECOMMENDING APPROVAL: APPROVED:

ALBERTO N. GAHID EDILBERTO P. CARABBACAN


Assistant Regional Director Regional Director
I hereby acknowledge receipt of the above notice.

DATE:

3K ROCK ENGINEERING

By:

Authorized Representative
WORK RESUMPTION ORDER NO. 2

Contract I.D No. : 15P00014


Name of Project
: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads
Including Drainage, Based on Pavement Management System/ Highway
Development and Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang)
(S00420LZ) Intermittent Sections K300+134 - K0300+911; K0301+195 -
K0305+000; K0305+290 - K0305+681

Location : Baguio City


Date : June 24, 2015

To: `

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

Effective to date, you are directed to resume construction operations in the project site in
view of the good weather condition and workable, dried road base.

Hereunder is the historical dat of your approved Work Suspension Order and Contract
Time Extension.

Original Contract Approved Work Suspension Approved Contract


Days Used to Date: 36 CD
Time: 220 CD Order: 20 CD Time Extension: 20 CD

Contract Time W.S.O No. 1: 18 CD C.T.E. No. 1: 18 CD


including extension: W.S.O No. 2: 2 CD C.T.E. No. 2: 2 CD
Total: 20 CD Due to V.O.: Days remaining: 204 CD
240 CD
Total: 20 CD

Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is for your file.

ISMAEL B. DELA CRUZ


Project Engineer

NOTED:

CLIFTON D. VALENCERINA
Chief, construction Division

RECOMMENDING APPROVAL: APPROVED:

ALBERTO N. GAHID EDILBERTO P. CARABBACAN


Assistant Regional Director Regional Director
I hereby acknowledge receipt of the above notice.

DATE:

3K ROCK ENGINEERING
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO RROW

FOR THE MONTH OF : August 2014

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
STATION LIMITS : Drainage,
#REF! Based on Pavement Management System/ Highway Development and
LOCATION : Management-4
### (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

Fair & Light


August 24-31, 2014
Rainfall
Time extension due to Road Right of Way 8 Days

TOTAL CALENDARS DAYS 8 Days

Total Extension of Time Recommended ============================ == 8 DAYS


Total Extension of Time Recommended Previously====================== == 20 DAYS
Grand total to date ======================================== == 28 DAYS
Original contract time======================================= == 269 DAYS
Revised contract time due to Variation Order ======================== == 309 DAYS
Revised contract time due to approved extensions/suspensions============== == 337 DAYS
Date of effectivity of contract ================================== == August 6, 2014
Original Expiry Date ======================================== == May 1, 2015
Revised expiry date due to Variation Order No. 01 ===================== == June 10, 2014
Revised Expiry Date due to Approved Time Extension/Suspension No. 1======== == July 8, 2015
Percent of Time Elapse ====================================== == 1.50%

PREPARED BY: CONCURRED BY;

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO RROW

FOR THE MONTH OF : September 2014

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
STATION LIMITS : Drainage,
#REF! Based on Pavement Management System/ Highway Development and Management-
LOCATION : 4 (HDM-4)
Baguio Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent Sections
City

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

Fair & Light


September 1-6, 2014
Rainfall
Time extension due to Road Right of Way 6 Days

TOTAL CALENDARS DAYS 6 Days

Total Extension of Time Recommended ============================ == 6 DAYS


Total Extension of Time Recommended Previously====================== == 28 DAYS
Grand total to date ======================================== == 34 DAYS
Original contract time======================================= == 269 DAYS
Revised contract time due to Variation Order ======================== == 309 DAYS
Revised contract time due to approved extensions/suspensions============== == 343 DAYS
Date of effectivity of contract ================================== == August 6, 2014
Original Expiry Date ======================================== == May 1, 2015
Revised expiry date due to Variation Order No. 01 ===================== == June 10, 2014
Revised Expiry Date due to Approved Time Extension/Suspension No.1========= == July 14, 2015
Percent of Time Elapse ====================================== == 1.70%

PREPARED BY: CONCURRED BY;

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO WEATHER

FOR THE MONTH OF : September 2014

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
STATION LIMITS : Drainage, Based on Pavement Management System/ Highway Development and Management-
#REF!
LOCATION : 4 (HDM-4)
Baguio Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent Sections
City

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

Time extension due to adverse weather


September 7-10, 2014 Heavy Rainfall condition and unworkable road base due to 4 Days
oversaturation of materials
Time extension due to adverse weather
September 14-15, 2014 Heavy Rainfall condition and unworkable road base due to 2 Days
oversaturation of materials
Time extension due to adverse weather
September 19-21, 2014 Heavy Rainfall condition and unworkable road base due to 3 Days
oversaturation of materials
Time extension due to adverse weather
September 24-25, 2014 Heavy Rainfall condition and unworkable road base due to 2 Days
oversaturation of materials
Time extension due to adverse weather
September 30, 2014 Heavy Rainfall condition and unworkable road base due to 1 Days
oversaturation of materials

TOTAL CALENDARS DAYS 12 Days

Total Extension of Time Recommended ============================ == 12 DAYS


Total Extension of Time Recommended Previously====================== == 34 DAYS
Grand total to date ======================================== == 46 DAYS
Original contract time======================================= == 269 DAYS
Revised contract time due to Variation Order ======================== == 309 DAYS
Revised contract time due to approved extensions/suspensions============== == 355 DAYS
Date of effectivity of contract ================================== == August 6, 2014
Original Expiry Date ======================================== == May 1, 2015
Revised expiry date due to Variation Order No. 01 ===================== == June 10, 2014
Revised Expiry Date due to Approved Time Extension/Suspension No.1========= == July 26, 2015
Percent of Time Elapse ====================================== == 5.10%

PREPARED BY: CONCURRED BY;

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
LOWER KALINGA
DISTRICT ENGINEERING OFFICE
CORDILLERA ADMINISTRATIVE REGION
Bulanao, Tabuk City, Kalinga

SUMMARY OF TIME SUSPENSION / EXTENSION

Contract ID : 18PL0059
Name of Project : Construction of Flood Control along Chico River, Malin-awa, Tabuk City, Kalinga
Location : Malin-awa, Tabuk City, Kalinga
Contractor : TRIBU DESIGN AND CONSTRUCTION
Date Started : February 26, 2018
Original Expiry Date : June 25, 2018
Original Contract Time : 120 CD
Original Expiry Date due to approved T.E No. 1 : July 25, 2018 Revised Expiry Date: August 24, 2018
Revised Contract Time due to approved T.E No. 1: : 150 CD Revised Contract Time: 180 CD

APPROVED REVISED CONTRACT TIME REVISED EXPIRY DATE


TIME EXTENSION/ NO. OF DAYS ORIGINAL CONTRACT DAYS
MONTH/YEAR DATE SUSPENDED DATE RESUMED TIME INCLUDING DUE TO EXTENSION/ REASON FOR SUSPENSION/ EXTENSION
SUSPENSION SUSPENDED DURATION TIME USED REMAINING
EXTENSION EXTENSION/SUSPENSION SUSPENSION

February, 26, 27, 28,


Monthly Time Suspension February, 2018 3 120 0 120 June 25, 2018 3 117
2018

March
Monthly Time Suspension March, 2018 4,5,11,17,23,24,25,29 10 120 0 120 June 25, 2018 34 86
,30,31, 2018

April
Approved Time Extension No. 1 due to Adverse
Monthly Time Suspension April, 2018 6,7,8,9,18,22,23,24,2 11 120 4 124 June 29, 2018 64 60
Weather Condition.
5,26,27, 2018

May,
1,4,5,8,9,12,13,14,15,
Monthly Time Suspension May, 2018 15 120 15 139 July 14, 2018 95 44
19,20,24,25,30,31,
2018

June,
Monthly Time Suspension June, 2018 1,2,3,4,5,6,7,8,9,10,1 15 120 11 150 July 25, 2018 112 38
2,13,14,15,16, 2018

June,
13,14,15,16,19,20,21,
Monthly Time Suspension June, 2018 14 120 14 164 August 8, 2018 125 39
22,23,25,26,28,30,
2018 Request for Time Extension No. 2 is due to
July, Unfavorable Weather Condition at the project site
1,2,3,4,5,6,7,8,10,12,
Monthly Time Suspension July, 2018 16 120 16 180 August 24, 2018 144 36
13,14,15,16,18,19,
2018

TOTAL 60

Time Extension due to Variation Order 0 CD


Time Extension due to Work Suspension and Monthly Time Suspension 60 CD
Total Time Extension 60 CD

NOTE: The Contractor, Tribu Design and Construction, will not file any monetary claim by virtue of this Extension of Contract Time and with the consent/conformity of the Contractor's Bondsman.

Conformed by: Prepared by: Submitted by: Recommending Approval: Approved by:

TRIBU DESIGN AND CONSTRUCTION PAULINO D. BANGANAN ERNESTO O. VECALDO RUBY A. UYAM IRENEO S. GALLATO
Contractor Project Engineer Chief, Constructopn Section Assistant District Engineer District Engineer
DPWH-LKDEO DPWH-LKDEO DPWH-LKDEO DPWH-LKDEO DPWH-LKDEO