Vous êtes sur la page 1sur 4

8/6/2018

ARBT 5
Lift-Slab construction

Lift-Slab Construction
Lift-slab construction is a method of construction where the concrete floors and
roof slabs are cast atop one another at ground level and then are lifted into their
final position by means of jacks. The method was invented and developed in the
early 1950s by a collaboration of Philip N. Youtz and Thomas B. Slick. resulting
Youtz-Slick Lift-Slab Method of Construction.

Lift-slab construction can be more economic than conventional construction when


the building is vertically uniform, such as for hotels, apartment buildings, and
dormitories, and where the slab designs are repetitive.

1
8/6/2018

Factors to Consider

01 Weight of the Slabs

02 Height of the Building

03 Lifting Capacity of Jacks

Cross Sectional Area of Columns during


04 initial lifting

Tools and Materials


Hydraulic Jacks Lifting Collars Shear blocks Bond Breaker
This jack is a hydraulic piece of Lifting collars are cast into each Shear blocks is a steel component The main function of bond breakers is
equipment which has positive slab around each column used to hold the lifted slab in its to minimize dynamic loads during
lifting or stripping of precast members
safety devices on it. The jack can providing a means to lift the slab final elevation.
and permit their complete, clean
lift slabs on columns loaded up to and also providing shear
separation from casting slabs or
100,000 pounds at speeds of up reinforcement, they are fixed to
molds. In lift-slab construction bond-
to 14 feet an hour. columns by welding shear blocks breaking compounds permit the slabs
to plates welded column flanges to be separated cleanly and easily
and to the collar after the slab has from one another.
been raised in position.

2
8/6/2018

Construction Sequences

Foundation Separating Medium


01 The steel or concrete columns are first put position
04 The first floor slab is cast inside edge formwork on
and rigidly connected to the foundation then the top of the ground floor slab and when it is mature it is
ground floor slab is cast. in turn coated or covered with the separating medium.

Bond Breaker Casting of Slabs


02 When it has matured it is sprayed with two or three
05 The casting of the other slabs continues until all the
coats of a separating medium consisting or what is floors and roof have been cast one on the other on
called bond breaker. the ground.

Lifting collars Lifting


03 Lifting collars are cast into each slab around each
06 The slabs are lifted by jacks , operating on the top of
column. each column, which lift a pair of steel rods attached
to each lifting collar in the slab being raised.

Construction
Sequences
for mid-rise
buildings

3
8/6/2018

Advantages

Concrete floor construction at ground


level is convenient and requires no
shores, scaffolds or cranes.

Lift-slab construction method becomes


more advantageous in buildings with
similar floor plans throughout the height
of the building

Advantage of erecting concrete buildings


using lift slab construction is elimination
of most formwork, an especially
important factor in areas where labor
costs are high.

Disadvantages

Limitations Lateral Forces


The Lift-Slab Construction is not to be used for multistorey The Lift-Slab Construction has a weak resistance against lateral
building, only use for 15-16 storey building. forces but this can alleviated by applying a cross bracing in the
structural design of building.

Vous aimerez peut-être aussi