Vous êtes sur la page 1sur 11

142 Informatica Economică vol. 15, no.

2/2011

On Best Practices for Risk Management in Complex Projects

Dan BENŢA1, 2, Ioan Marius PODEAN1, 2, Cristian MIRCEAN1


1
Siemens AG., Corporate Technology, Project and Risk Management, Munich, Germany
2
Faculty of Economics and Business Administration,
Babeş-Bolyai University of Cluj-Napoca, Romania
dan.benta@econ.ubbcluj.ro, marius.podean@econ.ubbcluj.ro, cristian.mircean@siemens.com

Risk management shall be proactive. This is one of the key preliminaries to cope with the
challenges of complex projects. An overarching and consistent view on project risks and
uncertainties is necessary to follow a holistic approach in project risk management.
Uncertainty is inevitable since projects are unique and temporary undertakings based on
assumptions and constraints, delivering project results to multiple stakeholders with different
requirements. Project management can be seen as an attempt to control this uncertain
environment, through the use of structured and disciplined techniques such as estimating,
planning, cost control, task allocation, earned value analysis, monitoring, and review
meetings. Each of these elements of project management has a role in defining or controlling
inherent variability in projects. Project risk management provides approaches by which
uncertainty can be understood, assessed, and managed within projects. A number of
associations (e.g., Project Management Institute – PMI®, International Project Management
Association – IPMA,or Network of Nordic Project Management Associations - NORDNET)
work constantly in acquiring, improving, and standardizing best practices in project
management.Based on the industrial practice, this paper outlines strategies to identify,
prioritize, and mitigate risks for achievement of project’ or organizational objectives.
Keywords: Project Management, Risk Management, Best Practices of Management,
Standardization of Management, Maturity of Organizations

1 Introduction
As integral part of project management,
effective risk management is a critical
always less than 100%; and impact measured
in changes of the objectives. Risks may be
measured in costs (monetary risks) in time
success factor for delivering projects in (delay risks for time management) or quality
predefined cost, time, and quality. Project (usually affecting contracts thru monetary
risk management provides benefits when it is cost of improvement).
implemented according to good practice Interests in risk management are not new and
principles and with organizational in the late 90s, authors state that risk
commitment to taking the decisions and management was a significant step in most
performing actions in an open and unbiased organizations [7] [9]. While risk management
manner. Starting with the definition, risksare is a critical activity in construction project
uncertain events which when occur have management, existing industry practices
negative effect on at least one project goal – involve tools like risk registers, risk
e.g., time, costs, contents or quality. management spreadsheets, brain storming
Contrasting, the positive variability is desired sessions etc. As a result, many risks remain
and is called opportunity. unidentified, and proper risk management
Despite the simple explanation, the project becomes impossible [4]. Useful
managers often include into risksarea the acknowledged techniques for identifying
problems and technical or organizational risks, as presented in [9], include
issues. It is well to note: the risks are brainstorming and SWOT analysis
potential events in future which did not occur (Strengths, Weaknesses, Opportunities and
yet (while problems are risks that occurred). Threats). Whereas external consultants may
Risks are characterized by probability, be used, the effectiveness of the systems will
Informatica Economică vol. 15, no. 2/2011 143

depend on a comprehensive understanding of evaluation, the project passes a trajectory.


how the business operates in practice, and Risk may be described as the distance
any ‘standard solutions’ should be between the objectives (or stakeholder
approached with caution. expectations) and the current situation (or the
perceived current situation) in the upper
2 Role of risk management in project described multidimensional space. For this
lifecycle reason, targets require to be well defined,
In a multidimensional space of the project well known, and well documented for
objectives (or expectations), during project project.
phases and based on the stakeholders

Fig. 1. Processes in the sales (acquisition) phase of projects

In the sales phase of projects, each large execution phase, risks shall be detailed and
project crosses several phases that are regularly updated.
relevant in terms of project risk management. In lower figures (see Figure 2 and Figure 3)
The team of project sales (called sometimes we depict typical project life-cycles. We
acquisition) is distinct to the team of make a difference of solutions or large
execution. Some complex sales create a industrial projects vs. small project or
project-like team with a designated project services projects. A re-evaluation of risks is
manager of sales. advised at major milestones, especially at
The concept of risk management has become “order receipt” phase and before
important and central to corporate “dispatching”.In complex projects that
management andessential to successful involve warranties/service operation – some
project management in complex setting. Risk of risks extend during this phase. It is
management should be applied at major important to recognize them and actively
project milestones and hence be included in maintain risk management in
project plans and operational documents warranty/service operation phase. Project
becoming integral part of every aspect of Management Institute PMI® in the
managing the project, in every phase and in PMBOK® Guide – Fourth Edition defines
every process group.Because of the financial Risk Management as processes concerned
impact it may bring, risk management shall with conducting identification of risks,
be performed from the acquisition phase (i.e., analysis of impact (evaluation), responses
project sales) so that the organization may (mitigation process), and monitoring &
find easier decisions on the project path. An control of risks. Project Risk Management as
initial risk assessment at acquisition phase integrant part of management aims to
improves correctness of the earnings before increase the probability and impact of
interest and taxes(or operating profit) positive events, and decrease the probability
calculations and adjusts expectation of the and impact of negative events in the project.
project itself. Later as the project develops, In advance of their occurrence, risk
especiallyat handover and further in managementprioritizes risks and provides
action-oriented information to project
144 Informatica Economică vol. 15, no. 2/2011

managers. This orientation requires likelihood or probability of occurrence in


consideration of events that may or may not addition to other dimensions such as their
occur and are therefore described in terms of impact on objectives [5] [6].

Fig. 2. Project execution orservice preparation differentiated for large projects,


small projects or service projects

Fig. 3. Project closure and service preparation


Informatica Economică vol. 15, no. 2/2011 145

The philosophical treatment of causality unproven new technology, the lack of


extends over millennia. In the Western skilled personnel, or the fact that the
philosophical tradition, discussion stretches organization has never done a similar
back at least to Aristotle, and the topic project before.
remains a staple in contemporary philosophy. • Risks are uncertainties which, if they
Concerning risks in project management, a occur, would affect achievement of the
risk is considered to have at least one cause objectives negatively (threats). Similar,
and at least one effect. opportunities are uncertainties which, if
they occur would affectpositively the
project.Examples include the possibility
that planned productivity targets might
not be met, interest or exchange rates
might fluctuate, the chance that client
Fig. 4. Relationship between cause, uncertain expectations may be misunderstood, or
event which is risk if may produces an effect whether a contractor might deliver earlier
than planned. These uncertainties should
Specialists in decision theory, statistics and be proactively managed through the risk
other quantitative fields have defined management process.
uncertainty and risk more • Effects are unplanned variations from
specifically.Authors in [1]distinguish objectives, either positive or negative,
uncertainty and risk according to their which would arise as a result of risks
possible outcome: uncertainty as the lack of occurring.Examples include being
certainty, being the state of having limited early/late for a milestone,
knowledge where it is impossible to exactly increased/decreased operating profit,
describe future outcome; and risk as the state exceeding the authorized budget/being on
of uncertainty where some possible outcomes budget, failing to meet contractually
have an undesired effect or significant loss. agreed targets etc. Effects are contingent
Proposed measurement of uncertainty may events, unplanned potential future
include the application of a probability variations which will not occur unless
density function to continuous variables, risks happen.
while measurement of risk include
correlation of this possible outcomes 3 Best practices for risk management
(uncertainties) with the magnitudes of those Until 80’s,only event-risks were considered
losses – this also includes loss functions over typicallyas risks. In addition to these isolated
continuous variables. risks occurring from undesired events, the
Further, the article [2] distinguishes between intrinsic variability of the activities may
causes, risks and effectsof the respective generate as well risks. With preponderance in
risks for the project (see Figure 4): development projectsthat employ novel
• Causes are definite events, or sets of technologies –solutions may come after long
circumstances, which exist in the project search efforts, which require appropriate
or its environment, and which give rise to financing.Novel technology correlates often
uncertainty. Examples include the with delays, which aretaxed by customers in
requirement to implement a project in a form of liquidated/nonperformance damages.
developing country, the need to use an
146 Informatica Economică vol. 15, no. 2/2011

100,0%

80,0%

60,0%

40,0%

20,0%

0,0%
1.000 € 10.000 € 100.000 € 1.000.000 € 10.000.000 € 100.000.000 €

Fig. 5. Classical risk representation of occurrence probability vs. impact

Risk is typically represented based on performed at the level of the best practices
probability vs. impact. The risks calculated available. Risk management adds the
for contingencies shall be the product of perspective of project risk to the outputs of
risk’s probability and the impact. When risks those other processes and adds to their value
own a probability higher than 80% a full by taking risk into consideration.
impact shall be considered into the Many of the project management processes
contingencies. address planning the project, from concept to
Correlations of independent events and/or final design and from procurement through
variability are other sources of major risks. daily management of execution and close-
While the probability of independent events out. These processes often assume an
is the product of individual probabilities; the unrealistic degree of certainty about the
impact may increase by order of magnitude project and, therefore, they need to include
difference. Apart, complex/large projects treatment of project risks.Project Risk
span during long time. For such projects, the Management addresses this uncertainty in
environmental changes – e.g., change in project estimates and assumptions; it builds
stakeholders, buy/merges, customer financial upon, and extends other project management
capability, economic trends and disruptive processes. For instance, project scheduling
technologies – may influence the projects provides dates and critical paths based on
and be decisive for the risk spectrum. Here is activity durations and resource availability
the summary of our recommendations where assumed to be known with certainty.
to look for sources of variability in risk Quantitative risk analysis explores the
management: uncertainty in the estimated durations and
• Event- Risks which infers with the may provide alternative dates and critical
project; paths that are more realistic given the risks to
• Intrinsic variability in terms of the project. In addition to quantitative
costs/duration; measurements and contrasting to numbers,
• Correlations on events and variability; corporations may consider the qualitative
• Environmental changes during the risk analysis, where the “feeling about risks”
project. and the team-awareness in relation to
Project risk management requires that all respective risks is evaluated.
other management processes as planning, For meaningful results it is imperative that
resource allocation, budgeting, to be risk management to be applicable throughout
a project’s life cycle. The earlier in the
Informatica Economică vol. 15, no. 2/2011 147

project life cycle that the risks are reducing measures – performed by experts in
recognized, the more realistic the project risk analysis and moderation;
plans and expectations of results will be. An 2) a risk mitigation process, which refers to
early identification of a risk allows to prioritizing, implementing, and maintaining
minimize it and to reduce the negative effect the appropriate risk-reducing measures
it can have on achieving the initially set of recommended from the risk assessment
objectives. More, to certain risks one may process – owned by technical project
apply a set of mitigations. Often, mitigations manager;
address processes of the organizations, which 3) continual evaluation process and keys for
may require time from implementation to implementing a successful risk management
fruitful results. As example, if the risk is the program – owned by project manager and/or
poor communication between two teams, one quality management.
of mitigations may be “weekly meetings”. This risk analysis methodology can be
The risk of poor communication decreases tailored to the specific phase of a project
after a number of “weekly meetings” when ranging from project acquisition to customer
(part of) communication barrier is removed. acceptance and ensures a common
Several authors describes that the nature of understanding of project inherent risks and
risk management and the challenges uncertainties due to the involvement of
generated by its theoreticaland practice have project experts from different disciplines.
been in a state of evolution over the past 10 Major part of effort is at the beginning, when
years [8]. This process of evolution has setting the risks, updates are then less
created a number of difficulties for those demanding while some of risks close during
involved in the management of risk, who execution phase. In all phases, the project
now increasingly find lacking the necessary manager/head of the bid commission is the
capabilities to cope with this nature of this owner of the risk management process.
change – not least because of the increased Specialized, the effort may be delegated to
volume of information around the various the risk manager or a team of specialist that
sources of threat and the trans– disciplinary perform the risk assessments.
nature of the problems. Risk Identification Step
A project risk can be identified as individual A risk cannot be managed unless it is first
risk to one of activity inside the projector identified. The first step in the iterative
asoverall- project risk. Individual project risk management aims to identify all
risks/opportunities are those risks that might knowable risk to project objectives (see
positively or negatively affect one or more of Figure 6). The fact that some risks are
the project tasks objectives. Defining and unknown or emergent requires the risk
understanding individual risks can help to identification to be an iterative process. It is
decide and make a strategy about how to also important to achieve a full
apply efforts and resources to enhance the understanding of the present conditions in
chances of project success. Overall project which the organization operates. A careful
risk refers to the effect of uncertainty on the risk management framework must base on
project as a whole;it applies to the whole identification of the key risk factors inherent
project. To lead to successful achievement of in each single investment, and the
objectives is necessary to set realistic targets interdependencies among these factors [3].
for the cost and duration of a project. Early risk identification enables key project
Other authorsidentified three processes of decisions to take maximum account of risks
risk management [10] based on the inherent to the project. Also, as early as
ownership of the process: possible in the project lifecycle shall be
1) risk assessment process, which includes documented the conditions and events that
identification and evaluation of risks and risk represent material threats to the
impacts, and recommendation of risk- organization’s achievement of its objectives
148 Informatica Economică vol. 15, no. 2/2011

or represent areas to exploit for competitive [2]. Subsequent steps will tend to not close
advantage. and maintain the confusion state, while risk
One of the most common failings in the risk management cannot be effective. It is
management process is for the risk therefore essential to ensure that risk
identification step to identify incoherent identification identifies risks.
issues or irrelevant aspects that are not risks

Fig. 6. Steps to DO in risk identification and risk management

There are two key requirements for effective time, not limited to the risk identification
risk identification: the first is a clear events or the regular reviews.
understanding of what is meant by the term Defined the aim of the project, the broad
’risk’; the second is to be able to distinguish sources of risk should be taken into
risks from non-risks, particularly from their consideration. The event-risks should be
causes and effects. corroborated with correlations and project
Not all risk can be identified from beginning. environment conditions. It is necessary to
More, some are not quantifiable. determinate the contribution of each risk to
Environment changes and the risks close the aggregate risk profile, and prioritizing
during project lifecycle. A periodical, accordingly.
iterative risk identification preserve Risk management process should identify the
information to the required level. Risk opportunities and maximize conditions to
identification should be defined in the profitably achieve higher probability and
Quality Plan, useful to repeat at major higher impact.The risk identification process
milestones. Additionally, iterative should take into account a broad range of
identification of risks has a low cost after a project stakeholders to ensure that all
risk workshop was performed. perspectives are correctly represented.
Project and the organization should provide Limiting the identifications of risks to the
the processes and the capability to invoke the immediate project team decrease chances to
identification of the risks. The project risk evaluate all knowable risks.
management process shall permit emergent It should be the task of the risk identification
risks to be identified and reported at any to link the risks and opportunities to one
Informatica Economică vol. 15, no. 2/2011 149

project objective (time, cost, quality, scope the individual impact and the individual
etc.). This implies that project was evaluated probability) decreases.
and project’ objectives are clearly defined. On the basis we understand and know project
When the risks relate with several objectives, risks, there are several strategies to minimize
it should be noted. the effect of risk: first, is to avoiding the risk
Risks statements should provide enough itself by not performing the activities that
information so that any of team members is imply this risk. This some-how goes to the
able to unambiguously describe. Single cause of risk.An example would be to select
phrases as “resources” or “logistics” are projects with low risk, i.e., to perform
inadequate.Each risk should be described to a activities/projects belowa known threshold.
level of detail that permits assignment to a Still, from economic perspective this method
single risk owner (one individual) with clear is not always suitable; large
responsibility and accountability for its project/organizationprofit margin implies
management. Moderator should aim to risks.A second method aims toreduce the
preserve the discussions neutral and negative effect of the risk. This mitigation
unbiased. acts on the impact that may be monetary
After the risk analysis process is complete, it costs, delay or quality.But effective technical
is necessary to compare the estimated risks solutions are addressing both probability and
against risk criteria which the organization impact.For an unknown risk value, i.e. the
has established. The risk criteria may include product of risk probability and impact, when
associated costs and benefits, legal the risk has a high predictability, i.e. we may
requirements, socioeconomic and estimate the range of risk impact, and low
environmental factors, concerns of manageability – transferring the risk to
stakeholders etc. Risk evaluation therefore, is another party is a good solution. An example
used to make decisions about the significance includestaking insurance for transport
of risks to the organization and whether each ofcomponents. Pooling risks would be a good
specific risk should be accepted or treated. solution foraccepting some or all of the
Mitigations consequences of a particular risk.
Risk management shall advise on strategies After successful mitigation, risks are
to manage the risk. Because the project represented based on residual probability vs.
manager is the owner of the risks in the residual impact. Not all risk can be mitigated
project, he/she will decide on the method of or make sense to mitigate. After mitigation,
mitigation and the priorities. in case the probability decrease the risks are
When several risks are identified, each represented on a lower as a parallel shift with
characterized by probability of occurrence y-axis; in the case the impact decrease, risks
and impact, the priority shall focus on the shift left.
risks with high impact and high probability. Risk management continues to evolve and to
Another method to mitigate risks is to derive develop better strategies and practices for
a root cause of several risks and apply companies to achieve their objectives. New
improvements there. This method would aim tools and techniques are available for
to decrease the probability/impact/ corporate objectives, so, the transfer of risk
probability & impact of multiple risks that has expanded beyond the insurance industry.
are related to root cause. At end, but not Society development and trends have
least, the risks may be ranked based on increased the demand for professionals who
mitigation costs. It is easy to early approach can provide expanded risk management
the “low hanging fruits” – to mitigate the services. On opposite side, over-control and
risks that own a low cost mitigation. In suppressing risks can be as damaging to
result, the total project risk amount defined business interests as the lack of controls. Risk
as sum of identified risks (i.e., the product of management does not aim to eliminate risks,
but focus to actively manage risks in a
150 Informatica Economică vol. 15, no. 2/2011

business context [9]. Mitigation and visualizing mitigation costs and expected
enhancement are the most widely applicable residual risks with and without mitigation.
and widely used response strategies. Here, After mitigation actions and responsibilities
the approach is to identify actions that will for the measures are agreed and decided
decrease the probability and/or the impact of upon, the implementation of these actions
a threat, and increase the probability and/or need detailed planning and controlling.
the impact of an opportunity. According to the findings in the risk
When collecting mitigation options to mitigation phase the responsible action
actively reduce project risks, the Risk owners should be mandated by the project
Manager (or upon case the Project manager. Hence, the project manager needs
Manager) shall include the comprehensive to prioritize mitigation options and
description of mitigation including costs, corresponding costs and efforts to decide
responsibilities and due dates and the whether measures will be taken or not.
quantitative evaluation after successfully Performing agreed mitigation actions will
implemented mitigations as remaining risk. contribute to reduce the risk status and create
Mitigation actions should target those risks a new risk situation in the project. However,
associated with high leverage towards the implementation and controlling of the
minimizing the residual risk afterwards or mitigations will be driven by the project
acceptable mitigation costs. The risk team.
analysis methodology provides means of

100,0%

80,0%

60,0%

40,0%

20,0%

0,0%
1.000 € 10.000 € 100.000 € 1.000.000 € 10.000.000 € 100.000.000 €

Fig. 7. Risk representation after mitigation

Evaluation and assessment of risks hoc in a single analysis may be appropriate to


Changes in the business environment, quickly deep-dive into troubled projects to
completion of the project, will continue to provide a neutral view of the project status.
affect the risk situation inside projects. This The frequency of the monitoring activities
is the reason for performing the risk analysis depends on the projects risk exposure level
not only once but in iterative cycles along and on the respective organizational unit’s
major milestones or delivery baselines for the risk aversion/appetite.Continue development
customer project. To cope with the ever of the organizations leading to frequent
changing complexity of a long-term project internal changes. All these organizational
and in order to measure stabilizing risk changes mean that some old risks close, new
controls proactively over time, monitoring is risks will arise, and risks previously
recommended in continuous intervals. On the mitigated may again become a concern.
other hand performing the risk analysis ad
Informatica Economică vol. 15, no. 2/2011 151

Thus, the risk management process is commitments to others outside the project,
ongoing and evolving. interact with regulators, and comply with the
rules of accounting and law.
4 Conclusions Project Risk Management should be
Project risk management is an essential and conducted in compliance with these internal
determinant step towards successful projects. and external requirements. Project risk
All real risks that can affect one or more management should be conducted in a
objectives of the project must be identified manner consistent with existing
and managed.A detailed analysis and a organizational practices and policies. It is a
precise definition of risk can lead to valuable component for any project
successful achievement of objectives. Risk management step and it adds value to all
management helps project organizations to project management processes and provides
achieve performance and profitability and at benefits when it is implemented according to
the same time prevents loss of resources. It good practice principles and with
provides a positive potential return on organizational commitment to taking the
investment for organizational management, decisions and performing actions in an open
project stakeholders, project management, and unbiased manner.
and team members and helps an entity get to
where it wants to go and avoid pitfalls and Acknowledgments
surprises along the way. This work was jointly supported by Siemens
Changes in the project management plan that AG., Corporate Technology, Project and
result from the Project Risk Management Risk Management and by Romanian National
process may require decisions at the Authority for Scientific Research under the
appropriate level of management to reassign grant no. PN2 92-100/2008 SICOMAP.
personnel, establish or modify budgets, make

References
[1] H. Douglas,How to Measure Anything: [6] PMBOK® Guide – Fourth Edition, A
Finding the Value of Intangibles in guide to the Project Management Body
Business, John Wiley & Sons, 2007. of Knowledge, Project Management
[2] D. Hillson, When is a risk not a risk?, Institute, Inc, 2010.
Project Manager Today,January 2007 © [7] C. Smallman, “Knowledge Management
Project Manager Today, 2007. as Risk Management: A Need for Open
[3] R. Horwitz, Hedge fund risk Governance?,”Risk Management, vol. 1,
fundamentals: solving the risk no. 4, pp. 7-20, 1999.
management and transparency [8] D. Smith, M. Fischbachera, “The
challenge, Bloomberg Press Princeton, changing nature of risk and risk
ISBN 1-57660-163-3, 2004. management: The challenge of borders,
[4] V. Kumar, N.Viswanadham, “A CBR- uncertainty and resilience,”Risk
based Decision Support System Management, vol. 11, pp. 1–12,2009.
framework for Construction Supply [9] L. Spedding, A. Rose, Business Risk
Chain Risk Management,”Proceedings Management Handbook, Elsevier, ISBN:
of the 3rd Annual IEEE Conference on 978-0-7506-8174-2, 2008.
Automation Science and Engineering, [10] G. Stoneburner, A. Goguen,
Scottsdale, AZ, USA, Sept 22-25, 2007. A.Feringa,Risk Management Guide for
[5] PRM-PMI®,Practice standard for Information Technology Systems,
Project Risk Management, Project Recommendations of the National
Management Institute, Inc, 2010. Institute of Standards and Technology,
2002.
152 Informatica Economică vol. 15, no. 2/2011

Dan BENŢA has graduated the Faculty of Economics and Business


Administration from Babeş-Bolyai University of Cluj-Napoca in 2007. Since
2008, he is PhD. student in field of Cybernetics and Statistics under the
supervision of Prof. Ştefan Ioan Niţchi with the Business Information
Systems department of the Faculty of Economics and Business
Administration, Babeş-Bolyai University of Cluj-Napoca. During February
2010-July 2010, he held a research internship in Siemens AG., Corporate Technology, Project
and Risk Management, Munich, Germany. He is the author of several articles published in
journals and at national and international conferences. His main interests are in web services
and software integration, via IP applications and video surveillance for companies, and risk
management.

Marius Ioan PODEAN has graduated the Faculty of Economics and


Business Administration from Babeş-Bolyai University of Cluj-Napoca in
2007. Since 2008, he is PhD. student in field of Cybernetics and Statistics
under the supervision of Prof. Ştefan Ioan Niţchi with the Business
Information Systems department of the Faculty of Economics and Business
Administration, Babeş-Bolyai University of Cluj-Napoca. During February
2010-July 2010, he held a research internship in Siemens AG., Corporate
Technology, Project and Risk Management, Munich, Germany. He is the author of several
articles published in journals and at national and international conferences. His main interests
are in collaborative systems using an XML based approach, covering aspects as collaborative
content management and workflow in complex projects, and risk management.

Cristian MIRCEAN received the B.S. degree in electronics and


telecommunication engineering from the Technical University Cluj-Napoca,
Romania, in 1996, the M.S. degree in electromagnetic compatibility in
complex electronic systems from the Applied Electronics Department,
Technical University Cluj-Napoca, Romania, in 1998, and the Ph.D. degree
in signal processing from the Institute of Signal Processing, Tampere
University of Technology, Tampere, Finland, in2005. From 2000 to 2005, he
was Research Scientist at Tampere University of Technology, Finland, and from 2003 to
2005, a research intern at the University of Texas MD. Anderson Cancer Center.He currently
works with Siemens AG., Germanyon risk and project management for large projects.

Vous aimerez peut-être aussi