A DEMOLITION
1 Removal of existing door no 2 2000 4,000.00
2 installation of door frame no 10 2500 25,000.00
3 Removal of existing windows no 15 1500 22,500.00
4 New block work m2 10 4,000 40,000.00
5 Removal of existing POP ceiling m2 150 300 45,000.00
6 Re-plastering of window area (dressing) m 25.35 1,500 38,025.00
7 Plastering of new block work m2 20 1800 36,000.00
8 Installation of security doors no 2 5000 10,000.00
Sub-total 220,525
FLOOR TILING
21 Kitchen m2 17.3 8900 153970
22 Master bathroom m2 5.4 8900 48060
23 Bedroom 1 bathroom m2 3.6 8900 32040
24 Bedroom 2 bathroom m2 3.6 8900 32040
25 Visitor toilet m2 3.5 8900 31150
Sub-total 297260
POP CEILING
29 Sitting room/Lobby m2 43.15 4,600 198,490
30 Terrace m2 3.9 4,600 17,940
31 Master bedroom m2 28.2 4,600 129,720
32 Terrace m2 2 4,600 9,200
33 Bedroom 1 m2 23 4,600 105,800
34 Bedroom 2 m2 20 4,600 92,000
35 master bathroom m2 4.9 4,600 22,540
36 kitchen m2 15.7 4,600 72,220
37 bedroom 1 bathroom m2 3.3 4,600 15,180
38 Bedroom 2 bathroom m2 3.3 4,600 15,180
39 Visitor toilet m2 3.12 4,600 14,352
WALL SCREEDING
40 Sitting room/Lobby m2 76.7 700 53,690
41 Master bedroom m2 62.5 700 43,750
42 Bedroom 1 m2 54.8 700 38,360
43 Bedroom 2 m2 54.1 700 37,870
Sub-total 173,670