PROJECT S-CURVE
Customer Representative
Name
□ Reviewed & Approved
With No Comment
Signature
□ Reviewed & Approved
With Comment
Date
1 31-Jan-17 AR FW HK AS-BUILT
0 17-Nov-16 AR FW HK Issued for Approval
Rev Date Prep’d Chk’d Apr’d Description
Document No.
PEMASANGAN BARU P160075-PTM-GP-SCV-1001
PLC ESD SYSTEM GAS PLANT
Rev : 0
(AKYLASI, C4 POLYMER, BB DISTILATE)
Status : AS-BUILT
PT. PERTAMINA (PERSERO) RU III
PLAJU Date : 31 Jan 2017
Page : 2 / 3
TABLE OF CONTENTS
PLAN WEEK
No. PROJECT DETAIL ACTIVITIES COMPOSITION vs 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 BASTP-1 13 14 15 BASTP-2
REMARKS
ACTUAL 17-Nov-16 24-Nov-16 1-Dec-16 8-Dec-16 15-Dec-16 22-Dec-16 29-Dec-16 5-Jan-17 12-Jan-17 19-Jan-17 26-Jan-17 2-Feb-17 9-Feb-17 16-Feb-17 23-Feb-17 27-Feb-17 6-Mar-17 13-Mar-17 20-Mar-17 29-Mar-17
1 PREPARATION WORKS
1.1 Kick Off Meeting, Detail Site Survey 0.10% Plan 0.10%
100%
Actual
2.1 Review and Reverse Engineering Gas Plant Existing 2.88% Plan 1.44% 1.44%
Actual
2.2 All New Gas Plant Engineering Documents 5.35% Plan 5.35%
Actual
3 PROGRAMMING WORKS
Actual
4 FABRICATION WORKS
Actual
4.2 Internal Wiring Annunciator Panel and Fabrication Junction Boxes 3.81% Plan 1.90% 1.90%
Actual
4.3 Factory Acceptance Test and Punch List Clearance 5.46% Plan 5.46%
Actual
5 PACKING AND SHIPMENT MAIN EQUIPMENT
50%
Actual
6.3 Installation Annunciator Panel and Junction Box 1.54% Plan 1.54%
Actual
6.4 Installation Field Instrument (Full) 3.80% Plan
6.4.1 Installation Field Instrument (Existing Unit) 0.38% Plan 0.19% 0.19%
6.4.2 Installation Field Instrument (New Unit) 3.42% Plan 3.42%
6.4.3 Installation Field Instrument (Existing Unit) Actual
6.4.4 Installation Field Instrument (New Unit) Actual
6.5 Running Instrument Cable New Field Instrument 6.89% Plan 3.44% 3.44%
Actual
6.6 Installation Tray Cable 3.98% Plan 1.99% 1.99%
Actual
6.7 Commissioning, System Start-Up and Monitoring(Full) 7.02% Plan
6.7.1 Commissioning, System Start-Up and Monitoring(with PLC Demo Unit) 4.21% Plan 4.21%
6.7.2 Commissioning, System Start-Up and Monitoring(with PLC New Unit) 2.81% Plan 2.81%
6.7.3 Commissioning, System Start-Up and Monitoring(with PLC Demo Unit) Actual
6.7.4 Commissioning, System Start-Up and Monitoring(with PLC New Unit) Actual
7 CLEANING WORKS AREA
8.1 Training 6 Batch (Max 5 Persons for 5 Days) 1.26% Plan 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
Actual
TOTAL 100.00% Legend : ♦Plan ■ Actual
BI-WEEKLY PROGRESS 11.48% 49.59% 16.02% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 21.65% 0.00% 0.00% 0.00% 0.00%
PLAN :
COMMULATIVE PROGRESS 11.48% 61.07% 77.09% 77.30% 77.51% 77.72% 77.93% 78.14% 78.35% 78.35% 78.35% 78.35% 78.35% 78.35% 78.35% 100.00% 100.00% 100.00% 100.00% 100.00%
BI-WEEKLY PROGRESS 0.00%
ACTUAL :
COMMULATIVE PROGRESS 0.00%
DEVIATION :