Académique Documents
Professionnel Documents
Culture Documents
Section (4)
ELECTRICAL WORKS
BILLS OF QUANTITIES
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
2.1 Sub Distribution boards as specified here
under and shown on the drawings :-
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
3.1 Sub Distribution boards as specified here
under and shown on the drawings :-
3.1.1 DB-L, 63A main isolator, TPN+E,12-ways 1 NO
3.2 Power Cables
Supply & install complete cables, for connection
of main power circuits & central AC units, water
pumps including supply of glands & lugs.
NB:- Stated cable lengths are approximate,
delivery shall be after exact measurement of
cable length on site
3.2.1 4 c x 10 mm2 ,CU , XLPE /SWA/ PVC 100 ML
3.3 Lighting & Small Power
3.3.1 Electrical Points
work to include laying of conduit , installation
of boxes & wiring from the distribution board
up to the point complete with all necessary
accessories :-
3.3.1.1 Light points ( wiring up to the switch ) 30 NO
3.3.1.2 General purpose socket–outlet point 12 NO
3.3.1.3 Ceiling fan point 8 NO
3.3.1.4 Air cooler switch point 4 NO
6.3.2 Electrical Devices
work to include, fixing of devices and wire
termination complete with all necessary
accessories :-
3.3.2.1 13 A , 3-pin switched socket out let 6 NO
3.5.2.2 16 A , 2-pin socket outlet 6 NO
3.5.2.3 1-gang, 1- way lighting switch 4 NO
3.5.2.4 1-gang, 2-way lighting switch 4 NO
3.5.2.5 Ceiling fan 56 ins. 8 NO
3.5.2.6 4000 cfm air cooler 4 NO
3.3.3 Light Fittings
work to include supply & fixing of lighting
fixtures and wire termination complete with all
necessary accessories , as per drawings,
specifications and schedule & subject to the
approval of the Engineer:-
3.3.3.1 1 x 18w IP55 weather proof outdoor type wall 10 NO
United Nations Development Programme - Sudan 6/23 Kadugli Training Centre
bracket lighting fixture
3.3.3.2 2 x 36w, 4ft, batten fluorescent fixture. 20 NO
3.4 Public Address System
work to include supply & fixing of devices,
conduits , wires , wire termination & testing
complete with all necessary accessories ,
preparation of drawings, specifications and
schedule subject to the approval of the
Engineer:-
3.4.1 5 watt amplifier 1 NO
3.4.2 Goose neck desk type microphone 2 NO
3.4.3 5 watt wall mounted speakers 2 NO
3.4 Main Earthing wire
work to include fixing & termination of main
earth wire to the sub distribution board
earthing bus bar & metal enclosures & cable
armour complete as required including all
necessary accessories
NB: - Stated wire lengths are approximate,
delivery shall be after exact measurement of
length on site.
3.4.1 1c×10 mm2 PVC insulated (Y/G) cu. conductor 100 ML
3.5 Lightning Protection System
Supply, install & test the following lightning
protection system
Earthing Pits
3.5.1 work to include driving of earthing rods,
testing & construction of earth pits manholes
3.5.1.1 Earthing pit 1 NO
3.5.1.2 Earthing rods including earth resistance
measurement
4 NO
NB: - Number of rods depends on the soil
characteristics.
3.5.1.3 Heavy duty manhole cover (30 x 30 cm ) 1 NO
3.5.2 Air terminals 4 NO
3.5.3 20×3 mm cu. tape down conductor 90 ML
3.5.4 Fixing & clamping accessories L L
Sum Sum
3.6 Fire Fighting
Supply, install & test the following fire fighting
fixtures.
3.6.1 6 kg Carbon Dioxide Fire Extinguisher 1 NO
3.6.2 Fire fighting hose reel 30m x 25mm hose 1 NO
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
4.1 Sub Distribution boards as specified here
under and shown on the drawings :-
4.1.1 DB-O, 63A main isolator, TPN+E,12-ways 1 NO
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
5.1 Sub Distribution boards as specified here
under and shown on the drawings :-
5.1.1 DB-O1, 63A main isolator, TPN+E,12-ways 1 NO
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
6.1 Sub Distribution boards as specified here
under and shown on the drawings :-
6.1.1 DB-R, 63A main isolator, TPN+E,24-ways 1 NO
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
7.1 Sub Distribution boards as specified here
under and shown on the drawings :-
7.1.1 DB-V, 100A main isolator, TPN+E,24-ways 1 NO
7.2 Power Cables
Supply & install complete cables, for connection
of main power circuits & central AC units, water
pumps including supply of glands & lugs.
NB:- Stated cable lengths are approximate,
delivery shall be after exact measurement of
cable length on site
7.2.1 4 c x 35 mm2 ,CU , XLPE /SWA/ PVC 180 ML
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
8.1 Sub Distribution boards as specified here
under and shown on the drawings :-
8.1.1 DB-Y, 63A main isolator, TPN+E,18-ways 2 NO
8.2 Power Cables
Supply & install complete cables, for connection
of main power circuits & central AC units, water
pumps including supply of glands & lugs.
NB:- Stated cable lengths are approximate,
delivery shall be after exact measurement of
cable length on site
8.2.1 4 c x 10 mm2 ,CU , XLPE /SWA/ PVC 250 ML
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
8.3.2 Electrical Devices
work to include, fixing of devices and wire
termination complete with all necessary
UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
RATE
Supply, install test commission and hand over
in good working conditions complete the
electrical system as shown on drawings,
specifications, IEE wiring regulations & as
required by Local Electrical Authorities (NEC)
for the complete project all up to the
satisfaction of the Engineer.
Note:
GENERATORS ARE NOT IN CONTRACT
Supply a stand-by diesel Generators as specified
having prime rating output at site conditions.
Work to include construction of concrete
foundation & steel cage, placing of genset ,
termination of cables, installation of power cable
& earthing , supply & erection of bulk fuel tank &
piping and any other works as required :-
10.10.1 250 KVA standby / 225 KVA prime rating,
1500 r.p.m, 415/ 240V, 50 Hz, diesel, water- 2 SET NIC NIC
cooled engine, generating set.
10.10.2 Manual Change Over Switch ,4-pole,400A 1 NO
10.10.3 20000 litres. cylindrical, horizontal steel fuel
tank
work to include construction of concrete 1 NO
foundation, placing of fuel tank & piping
connections
10.10.4 Installation, Testing, Commissioning of the above as
specified at site conditions with one year JOB JOB
maintenance
COST AMOUNT
BILL NO.
IN SDG
OVERALL TOTAL