EXTRACT FAN/EXHAUST FAN -3M Task Sheet

Park / Area Bollywood Asset Description


Building Name
Asset Code
& No
Specific Location Asset Tag
Task Scheduled Task Completed
Date Date

Corrective
Sl. No Description Check Box Remarks
Work order #
Prepare all the material that you will need (vacuum
1
cleaner, grease pump and grease, tool box, ladders...)

Check if the VFD/MCC corresponds to the EF in which


2
we are going to work, Exact tag and rotation

Inform BMS team before switch off the operating


3
button AOH.

4 Push the emergency button and check the functionality

5 Turn off the main switch.

Note: all indicator light should be working and replace if


6
the light is fused.

7 Lock out the main switch and tag out with LOTO tag

Check the dampers for smooth operation


8

Open the access panel. Use only proper tools (ring


spanner, open (ring spanner, open (ring spanner, open
9
the access panel.

Check and clean the motor's body with brush and


10 vacuum. Use protection mask.

Clean the impeller and all accessible parts. Grease


11 bearings (if grease type) use grease gun (type 3 grease)

Check all the ducts, instruments and surfaces.


12

Job Task Sheet Date: 21st Jan 2018


EXTRACT FAN/EXHAUST FAN -3M Task Sheet

Check DP switch if it is fitted properly. Ensure all


13 support is properly fixed.

Check, clean and make sure that all the flexibles are in
14 good condition. Replace if damaged.

Change the belt if necessary. When fan belt is driven,


15 check belt tension.

Check the alignment. NOTE: Do NOT overtight the belt


16 it will damage the bearings.

Re-install belt guard protection. Ensure all bolts and


17 screws are tightened correctly.

Adjust the spring’s compression to balance the weight


18 in the 4 supports.

Make sure that nothing is forgotten inside the system.


19 Close the access panel.

20 Release the emergency button.

Remove lock and safety LOTO tag. Turn on the power


21
switch.
Operate the system in hand mode and make sure that
22 there is no abnormal sound coming from the
equipment. Write on the PPM tasking sheets.
Make sure motorized damper is fully opened. Turn off
23
the lights when leaving the area.

Technicians:

1. Name: ______________________ Signature:_______________ Date:_________ Start Time:_______ Stop Time: _______

2. Name: ______________________ Signature:_______________ Date:_________ Start Time:_______ Stop Time: _______

3. Name: ______________________ Signature:_______________ Date:_________ Start Time:_______ Stop Time: _______

Supervisor:

Name: ________________________ Signature:___________________ Date:______________ Time:_____________

Reviewed By (Engineers):

Job Task Sheet Date: 21st Jan 2018


EXTRACT FAN/EXHAUST FAN -3M Task Sheet

Name: ________________________ Signature:___________________ Date:______________ Time:_____________