Académique Documents
Professionnel Documents
Culture Documents
From
Daniel R. Lewin
Department of Chemical Engineering
Technion
Technion,, Haifa, Israel
1
9/26/2009
2
9/26/2009
4 fatalAcc 1 10 incidents
8
0.4
10 hrs 1000 Workers 1 fatalAcc
3
9/26/2009
Unsafe
Safe Grey Area
H > 10-3/year
H < 10-5/year
hazard rate, H
Some definitions.
HAZARD RATE (H) – The rate (occasions/year) at
which hazards occur: e.g., the rate at which the
pressure of a vessel exceeds the design pressure.
PROTECTIVE SYSTEM – A device installed to prevent
the hazard occuring: e.g., a relief valve or a high
level trip.
TEST INTERVAL (T) – The time interval between the
testing of a protective system, and its replacement
if necessary.
DEMAND RATE (D) – The rate (occasions/year) at
which a protective system is called to act.
FAILURE RATE (f) – The rate at which a protective
system develops faults (occasions/year) (fail-
danger/fail-safe).
4
9/26/2009
Some definitions.
FRACTIONAL DEAD TIME (FDT) – The fraction of
the time that a protective system is inactive:
FDT = 0.5fT, assuming failure occurs half-way
between tests.
A hazard results when a demand occurs during a
dead period, hence: H = D x FDT.
If the protective system never fails to operate
when required, H = 0.
If there is no protective system, H = D.
Applying.
Example 1. Relief valves
Relief valves tests show that fail-danger
faults occur at f = 0.01/year (once in 100
years).
If T = 1 year, and say, D = 1/year,
then FDT = 0.5 x fT = 0.005/year (once in 200
years).
5
9/26/2009
Applying.
Example 2. Simple trips (actuators)
Assume that:
1. Fail-danger faults develop at f = 0.5/year
(once every two years)
2. Test interval T = 1 week (0.02 year – rather
frequent)
3. D = 1/year (example)
Applying.
Example 2. Simple trips (actuators) Solution:
6
9/26/2009
Applying.
Example 3. Frequent demands on a trip
Assume that:
1. Fail-danger faults develop at f = 0.5/year (once
every two years)
2. Test interval T = 0.1 year (5 weeks, a typical
value)
3. D = 100/year (much greater than before)
Applying.
Example 3. Frequent demands on a trip - Solution:
7
9/26/2009
8
9/26/2009
9
9/26/2009
From
Daniel R. Lewin
Department of Chemical Engineering
Technion
Technion,, Haifa, Israel
10
9/26/2009
A A
B Z B Z
C C
Downstream
equipment plugged
Inlet valve
failed open Flow in > flow out
at pressure
Pressure surge danger level
on feed line
Other
11
9/26/2009
Emergency Response
in Community
Emergency Response
in Process Unit
The intervention of well-trained
operators is a vital layer in Relief
Pressure
Pressure System
Relief System
Kletz, T.A., HAZOP and HAZAN, Institute of Chemical Engineers, Rugby, U.K., 1983
Controller
fails
Pressure
0.8/year
rises Vessel
Operator 1/year Overpressured
error Relief 0.005/year
0.2/year Valve dead
0.005
12
9/26/2009
13