Vous êtes sur la page 1sur 18

RECONSTRUCTION OF A CONCRETE BRIDGE ON

PR 318

BORE PILING

CONSTRUCTION METHODOLOGY
and
ACTUAL WORKS COMPLETED
( 2nd April, 2009 – 6th July, 2009 )

by:

KHAOU CHULY MKK Co. Ltd.


Construction and Engineering
CONTENTS

PART I : Introduction

PART II : Work Statement

PART III : Machineries

PART IV : Materials

PART V : Manpower

PART VI : Summary
PART I : Introduction.

The Ministry of Public Works and Transport has receive a budget from the Royal
Government of Cambodia to improve the condition of infrastructure within the
Kingdom of Cambodia. The work will be carried out under the supervision of
Road Rehabilitation and Bridge Reconstruction (RRBR) project, administratively
located and supervised by Road Infrastructure Department, General Directorate
of Public Works, Ministry of Public Works and Transport. (refer to as MPWT).

The project name is Reconstruction of a Concrete Bridge on PR 318, located


in Prey Veng Province, Kampong Seong commune and started last 15 th of
January, 2009 and to be completed on 15 th September, 2010. The bridge had a
length of 97.15 meters center to abutments. The width of the concrete bridge
from outer face is exactly 11.00 meters.

The bridge is composed of two abutments, and four column piers. Abutment A1 is
supported by 21 numbers of 400 X 400 mm X 12 m. RC piles. Abutment A2 is
supported by 21 numbers of 400 X 400 mm X 18 m. RC piles. Pier 1 is supported
by a 30 pcs. 400 X 400 mm X 18m RC piles as well as Pier 4. Pier 2 and 3 are
both supported by 600 mm diameter bore piles at 21 number each.
PART II : Work Statement

STEP 1: Backfilling

Backfill with soil the projected bore pile driving location on shore of river. Using
10 m³ dump trucks and an stand by bulldozer to push soil in an inward method in
order to push out mud and unsuitable materials on the river bed.

Both area of Piers 2 and 3 will be backfilled keeping the center of the river 13
meters apart for water to flow and for river traffic.

Photo 1: Backfilling of Pier 3 location.

Photo 2 : Backfilling of Pier 2 location.


STEP 2 : Shoring Works

Shoring works for the backfilled soil on both Piers 2 and 3 are compose of 50 mm
diameter steel pipes, chain link wires , sacks, and C channel sheet piles.
 Drive the 50 mm steel piles through the surveyed area at an interval of
1.00 meters apart.
 Lay horizontally the chain link fence on the inside part of the 50 mm steel
pipes. The pipes will serve as a column support for the chain link fence.
 Fill in with soil the sacks and must be riprap alternately along the chain
link fence, which this is serve as an retaining wall for the soil to be
backfilled.
 Drive the sheet piles on outer part, just outside the 50 mm steel pipes,
using a vibration hammer or an excavator whichever is more suitable.
 Make sure that all 50 mm steel pipes are weld connected and penetrated
at required depth to withstand load pressure from the soil backfill.

PHOTO 3 : 50 mm dia. steel pipe driving.


PHOTO 4 : Chain link installation

PHOTO 5 : Survey, river traffic and sand bag protection


PHOTO 6 : Backfilling and sand bag installation.

PHOTO 7 : Shoring works and river traffic.

PHOTO 8 : Sheet pile driving.


STEP 3 : Bore pile location survey

Locate all the exact coordinate using a total station machine by KC MKK Survey
Engineer. All datum collected will be approved by KC MKK Site Manager and
RRBR Supervisor prior to bore piling.

STEP 4 : Bore piling.

Using BENOTO machine, bore piling will be performed as follows.

 Locate the center of pile to be driven.


 Install steel plates around the bore pile location serving as platform for the
BENOTO machine.
 The inside diameter of the casing to be driven is 600 mm. and the outside
diameter is 620 mm. The outside diameter on the tread area is 710 mm.
 The length of each casing to be driven is 1,200 mm including 100 mm
tread connection.
 Each casing is driven by a steel weight at 750 kgs. to 1,000 kgs, depends
on the availability.
 After driving each casing, Hammer Glove is lowered down to the hole to
collect all soils deposits inside the steel pipe casing.
 Hammer Glove is supported by a triangular Benoto Machine and being
powered by a Compressor machine.
 After reaching the required depth of 25 meters at pile cap bottoms. Steel
reinforcement will be installed using a 40 ton crane.
 Reinforcement installed and pouring of concrete. Concrete is pour at a
slow rate and using a tremie pipe with 200 mm diameter.
 The bottom of tremie pipe must be always lower than the height of
concrete poured.
 Grade of concrete is at 45 Mpa.
 Concrete is mixed Sikament R4 and Antisol E to delay the settling of
concrete in order to pull out the casing smoothly.
 Casing bottom must be always lower than the concrete poured.
 While pulling of casing, the diameter of bore pile will become bigger due to
spaces create by casing and concrete will automatically fill all gaps
underground.
 Pulling out of casing is with the use of a 40 ton crane and the BENOTO
machine.
 The last 3 meter length under the bottom of pile cap are being kept and
not to be pulled out.
 There are two machine used simultaneously and completion of bore pile is
at 1.50 pieces per day.

PHOTO 9 : Bore piling works

PHOTO 10 : Reinforcement installation.


PHOTO 11 : Bore pile concreting

PART III : Machineries


Listed is the machineries used. ( 2 sets/ 2 teams )

PHOTO 12 : 200 mm diameter tremie pipes

PHOTO 13: 600 mm diameter steel casing.


PHOTO 14: 750 kilograms hammer

PHOTO 15 : Hammer Glove and Air compressor.

PHOTO 16 : BENOTO Machine


PHOTO 17 : Concrete Batching Plant

PHOTO 18 : Wheel loader ( 1 nos. )

PHOTO 19 : 4.50 m³ Concrete truck mixer ( 3 nos. )


PHOTO 20 : 40 ton crane

PART IV : Materials
Listed is all the materials used.

PHOTO 21 : Coarse aggregate for 45 Mpa Concrete

PHOTO 22 : Sand for 45 MPa concrete


PHOTO 23 : Type I Portland cement for 45 MPa concrete

PHOTO 24 : Admixture for concrete

PHOTO 25 : Bore pile reinforcements


PHOTO 26 : Bore pile reinforcements
PART V : Manpower
Designation Number

Site Supervisor 1

Material / Laboratory Head 1

Surveyor 1

Survey Assistant 2

Batching Plant workers 10

Wheel Loader Operator 1

Concrete Truck Drivers 3

40 ton crane Operator 1

Excavator Operator 1
Bulldozer Operator 1

Benoto Machine Operator 2

Bore piling workers 8

Rebar Fabricators 8

Total 40 persons

PART VI: Summary


A. Work span
2nd April, 2009 to 6th July, 2009 : : 96 calendar days

B. Manpower
Site Supervisor 1 X 96 X $ 13.85 : $ 1,329.60
Material/Laboratory 1 X 96 X $ 10.00 : 960.00
Surveyor 1 X 96 X $ 13.08 : 1,255.68
Survey Assistant 2 X 96 X $ 5.00 : 960.00
Batching Plant workers 10 X 96 X 4.00 : 3,840.00
Wheel Loader Operator 1 X 96 X $ 7.31 : 701.54
Excavator Operator 1 X 96 X $ 7.70 : 739.20
Bulldozer Operator 1 X 96 X $ 7.31 : 701.54
Concrete Truck Drivers 3 X 96 X $ 7.31 : 2,105.28
40 ton Crane Operator 1 X 96 X $ 9.62 : 923.52
Benoto Machine Operator 2 X 96 X $ 35.00 : 6,720.00
Bore piling workers 8 X 96 X $ 10.00 : 7,680.00
Rebar Fabricators 8 X 96 X $ 8.00 : 6,144.00
--------------------------------------------------------------------------------
SUB TOTAL 1: Manpower : $ 34,060.06

C. Materials
Grade 400 Steel bars 49.98 ton X $ 1,102.00: $ 55,077.96
Grade 45 MPa Concrete 285.01 m³ X $ 134.26 : $ 38,265.44
Tie Wire 3,000.00 ton X $ 0.925 : $ 2,775.00
Soil Backfill 10,000.00 m³ X $ 1.70 : $17,000.00
Sacks 5,000.00 pcsX $ 0.50 : $ 2,500.00
Diesel ( 11 X 60L X 96 d )X $ 0.65 : $ 41,184.00
50 mm Steel Pipe 250.00 pcsX$ 12.00 : $3,000.00
Chain Link 400.00 m X$ 1.75 : $700.00
Steel casing 600mmX3mX42.0 pcsX$ 270.00 : $ 34,020.00
------------------------------------------------------------------------------------
SUB TOTAL 2: Materials $ 194,522.40

D. Machinery
40 ton crane 768 hour X $ 45.00 : $ 34,560.00
Excavator 768 hour X $ 20.00 : 15,360.00
Bulldozer 768 hour X $ 20.00 : 15,360.00
Air compressor 2 X 768 hour X $ 20.00 : 30,720.00
---------------------------------------------------------------------------------
SUB TOTAL 3: Machinery $ 96,000.00

SUB TOTAL 1: Manpower : $ 34,060.08

SUB TOTAL 2: Materials : $ 194,522.40

SUB TOTAL 3: Machinery : $ 96,000.00


--------------------------------------------------------------------------
TOTAL : $ 324,582.48

( Additional 30% Company Profit) : $ 97,374.74

GRAND TOTAL : $ 421,957.22

Reported by:

------------------------------
Mr. Froilan J. Villarin
Site Manager KCMKK

Vous aimerez peut-être aussi