Road Concreting of Ventilacion Street, Brgy. Lagao, General Santos City , Brgy. Lagao, General Santos City
B.5 Project Billboard/ Signboard 2.00 each 7,092.00 15.0% 10.0% 25.00% P 1,773.00 P 443.25 P 2,216.25 P 9,308.25 P 4,654.13
B.9 Mobilization/Demobilization 1.00 lumpsum 27,800.00 0.0% 0.0% 0.00% P - P 1,390.00 P 1,390.00 P 29,190.00 P 29,190.00
PART C EARTHWORK
102(1) Surplus Common Excavation 1555.09 cu.m. 188,888.11 15.0% 10.0% 25.00% P 47,222.03 P 11,805.51 P 59,027.53 P 247,915.64 P 159.42
201(1) Aggregate Base Course 854.37 cu.m. 541,297.08 15.0% 10.0% 25.00% P 135,324.27 P 33,831.07 P 169,155.34 P 710,452.42 P 831.55