Vous êtes sur la page 1sur 5

IMPLEMENTATION OF A SCADA/EMS SYSTEM

IN METROPOLITAN ELECTRICITY AUTHORITY


THAILAND

Wiwat Amornimit
Metropolitan Electricity Authority
Wiwat.pcd@mea.or.th

Abstract: Controlling and monitoring work of the entire MEA electricity transmission and
distribution system usually require a lot of utility specific information and knowledge.
Implementation of this SCADA/EMS system together with an reliable fiber optic communications
system assist MEA’s operators to distribute electricity as efficiently and economically as allowed
under all practical constraints. This paper presents some technical details of MEA’s SCADA/EMS
system and its communications system. The real situation, principal functions, and operation of
MEA’s two control centers are described. The SCADA protocols used for communication between
two control centers and various kinds of RTUs are discussed. Furthermore, the detail of real-time
data exchange between EGAT and MEA SCADA systems is presented. The major functions and
applications that employed for MEA’s power system control are summarized. Finally, the future
direction concerning IEC61850 standard and DMS which MEA plan to follow is also proposed.

Keywords: Supervisory Control and Data Acquisition (SCADA), Energy Management System
(EMS), Real-time Data Exchange

1. INTRODUCTION system, the third generation in the series,


were commissioned in May 2003 to take
Metropolitan Electricity Authority (MEA) over the control and monitoring work of the
provides electricity, supplied by the entire MEA electricity transmission and
Electricity Generating Authority of Thailand distribution system.
(EGAT), to over two million customers in
Bangkok and two adjacent provinces,
covering about 3,200 square kilometers.

Before 1984, there was no Supervisory


Control and Data Acquisition (SCADA)
system in Metropolitan Electricity Authority.
In the old days, the operators working in the
power system control department used only
the radio communications system to monitor
and control the power system.

In 1984, a SCADA system and an


Fig.1 MEA’s two control centers
associated radio communications system,
with the capacity to monitor and control up
to 80 substations, was installed and 2. TWO CONTROL CENTERS
commissioned at the Chidlom Control
Center. After 10 years' of service, this As shown in Figure 1, two Control Centers,
SCADA system was replaced by a more Chidlom and Jangwatana Control Centers,
advanced and well-equipped one in 1994 to with the capacity up to 240 RTUs each,
increase the capacity to 120 substations. which are manned 24 hours around the
clock, act as the nerve Centers of the MEA's
The existing SCADA/EMS systems together electricity transmission and distribution
with a reliable fiber optic communications system.
Their principal functions are: characterized by easy upgradeability and
extensibility. They operate on the HP Alpha
• to remotely monitor and control the platform using Tru-64 operating system and
Company's power system; Oracle relational database, and support full
• to co-ordinate equipment outages; graphic man-machine-interface (MMI). Both
systems are built with full redundancy for all
• to handle power system
hardware including LAN to ensure that no
emergencies; and
function is lost due to a single point of
failure. In addition to the normal SCADA
Guiding Control Center operators in carrying functions, the systems also come with
out these functions are the following special advanced EMS applications and
principal objectives: links to EGAT’s SCADA/EMS systems such
that timely, relevant and accurate
• to distribute electricity as efficiently information plus analytical tools are
and economically as allowed under available to Control Center Operators for
all practical constraints; effective control and operation of the MEA
• to ensure personnel safety and power system as well as prediction and
power system security; and management of contingencies.
• to exhibit a sense of social
responsibility by having regard to 4. SCADA PROTOCOLS
the interests of the customers.
Two proprietary protocols, Meidensha and
Two Control Centers reached a new Wisp+ protocols, are used for
milestone in May 2003 when their new communications between the two control
Supervisory Control and Data Acquisition centers and existing legacy RTUs,
(SCADA)/ Energy Management System manufactured by Meidensha, Westinghouse
(EMS) systems and an associated fiber optic UK, Remdaq, and CC & P. To solve the
communications system were commissioned problem of compatibility, conformance, and
at Chidlom Control Center to replace the old interoperability, a new open industry
system and at Jangwatana Control Center to standard protocol, Distributed Network
manage its own area and serve as the Protocol (DNP3), is used for
backup system. communications to new RTUs. Right now,
only serial DNP3 protocol is implemented for
The design of the control centers take into MEA’s SCADA system.
accounts of operational needs and place
special attention on human factors. By
nature of its function, the Chidlom Control
Center is divided into two control rooms,
namely, Transmission Control room, and
Distribution Control room. The former
monitors and controls the transmission
network while the latter monitors and
controls the distribution network in its own
area of responsibility. Three Distribution
Control rooms in Jangwatana Control Center
monitor and control the distribution system
in its own area of responsibility.

3. SUPERVISORY CONTROL AND DATA


ACQUISITION (SCADA)/ ENERGY Fig.2 MEA’s communication system
MANAGEMENT SYSTEM (EMS)
5. FIBER OPTIC COMMUNICATIONS
The new SCADA/EMS systems employ a SYSTEM
distributed open system architecture and
use state of the art technology and are
For reliability of communication system,
three rings of 24 cores ADSS fiber optic
cables form the backbone communications
networks for MEA. By installing ATM
switches, Gigabit LAN switches, and SDH
switches, this backbone links 14 district
offices and two control centers together. For
security, the SDH network is designed to
use only for SCADA/EMS system. From
each SDH node of the backbone to
substations, 6 cores ADSS fiber optic cables
are installed as a spur link. The data from
RTU in substations are transmitted to SDH Fig.3 MEA’s EMS system
node via the spur link and to control center
through the backbone. 8. MEA-EGAT REAL-TIME DATA
EXCHANGE
6. BACKUP SCADA/EMS SYSTEM
By using the standard protocol for real-time
A special feature of the new SCADA/EMS data exchange, Inter Control Center
systems in the control centers is that each Communications Protocol (ICCP) or
manages its own area and at the same Telecontrol Application Service Element.2
serves as a backup for the second control (TASE.2) or IEC 60870-6, real-time data are
center system, capable of quickly taking exchanged between EGAT’s SCADA/EMS
over responsibility for the complete service system and MEA’s SCADA/EMS systems.
area of MEA if necessary. The fiber optic The schedule to exchange the real-time data
communications system provides access to is as follows:
each RTU from both control centers as well
as communications between the two control • From MEA to EGAT
centers systems.
• Analog every 3 seconds
7. MAN-MACHINE INTERFACES (MMI) • Status by exception

Two user interface terminals with multiple • From EGAT to MEA


CRT units are provided in each Control
Room for the on duty Control Center
Operators to control and monitor the power • Analog every 15 seconds
system. The full graphic capability of the • Status by exception
new systems is exploited to enhance user
interface. Zooming and panning of one-line In the near future, the real-time data
diagrams are now possible such that only exchange between three utilities in Thailand
relevant information is presented. Color (EGAT, MEA, PEA) will be established.
schemes are devised to convey vital Right now, the existing 6 core ADSS fiber
information such as voltage level, or whether optic link with speed up to 2 Mbps between
a circuit is dead or live (de-energized or MEA SDH node and EGAT node is used as
energized), etc. to the users. a physical link for more reliable. There is no
physical communication link between MEA
and PEA but the real-time data exchange
between two utilities is performed by using
ICCP servers at EGAT as an exchanged
points.
9. LOAD MODELS • Historical Information System
(HIS) Extremely large volume of
Presently, only 109 RTUs are connected to historical and future data can be
and communicate with two control centers. stored and retrieved. The system
In addition to data transmitted from MEA’s uses Oracle relational database as
substations and real-time data exchange the database engine.
from EGAT’s control center, load models or • Operator Training Simulator This
load profiles of MEA’s substations without provides hands-on training for the
RTUs, about 28 substations and mostly Control Center Operators for
small substations, and MEA’s HV customers normal, emergency and restorative
directly connected to MEA’s control of the power system.
subtransmission line, around 60 customers,
are entered into the database to run the 11. FUTURE DIRECTION
EMS applications. Furthermore, in case the
failures of the communications system or To obtain good results from state estimator,
RTUs occur, the load models are used the load models or load profiles of MEA’s
instead of real-time data. substations without RTUs and MEA’s HV
customers have to be frequently updated.
10. MAJOR FUNCTIONS AND This activity consumes a lot of time and
APPLICATIONS money. Therefore, it is necessary for MEA to
install RTUs for these small substations and
customers to get an accurate result.
• Supervisory Control and Data However, from a financial point of view, the
Acquisition (SCADA) SCADA cost of fiber optic communication is too high
performs two essential tasks; it for these substations and customers. MEA
telemeters data back from remote have a plan to perform a study to select an
sites and facilitates remote control optimum solution for the communication link
from the Control Centers. between the two control centers and them.
• Alarm Processing Alarm
Using an open and standard protocol is a
processing processes the data
direction which MEA plan to follow. MEA
collected and alerts the Control
plans to implement a new standard protocol,
Center Operators immediately if an
IEC61850, for communications between the
alarm condition is detected.
two control centers and RTUs after finishing
• Tagging and Interlock Checking
the feasibility study next year.
Tagging and Interlock Checking
functions help to prevent inadvertent
Moreover, to manage and minimize loss in
errors and ensure the safety of all
MEA’s distribution network, the distribution
persons working with the electricity
management system (DMS) will play the
network as well as supply reliability.
importance role for MEA in the near future.
• Analytical and Forecast Tools MEA plans to design and implement the
Analytical and forecast tools such as DMS within the next two years.
State Estimator, Contingency
Analysis, Security Enhancement, 12. CONCLUSION
Short Term Load Forecast are
provided in the EMS to assist the Controlling and monitoring work of the entire
Control Center Operators to MEA electricity transmission and distribution
evaluate the status of its power system is one of the most demanding tasks
network, forecast the system in power system operation. Due to time
demand in future, analyze and pressure and stress, the involvement of the
determine the outages of SCADA/EMS system for information support
transmission and generating is desired. The SCADA system and EMS
facilities, etc. in short, to manage the application functions together with an
system in a reliable and effective operators’ training simulator ensures that
manner. operators can control the power system to
distribute electricity as efficiently and
economically as allowed under all practical
constraints. Nevertheless, MEA needs to
implement the distribution management
system (DMS) to manage and minimize loss
in the distribution system.

13. REFERENCE

[1] UCI’s Specification of the SCADA/EMS


and its communications system, Utility
Consulting International, Cupertino,
California, USA

[2] AREVA’s Functional Specification


Design Documents and User’s Manuals,
AREVA, France

Vous aimerez peut-être aussi