ienzo Fin Predecesoras Sucesoras junio 2017 julio 2017 agosto 2017 septiembre 2017 octubre 2017 noviembre 2017 diciembre 2017
29 may '17 05 jun '17 12 jun '17 19 jun '17 26 jun '17 03 jul '17 10 jul '17 17 jul '17 24 jul '17 31 jul '17 07 ago '17 14 ago '17 21 ago '17 28 ago '17 04 sep '17 11 sep '17 18 sep '17 25 sep '17 02 oct '17 09 oct '17 16 oct '17 23 oct '17 30 oct '17 06 nov '17 13 nov '17 20 nov '17 27 nov '17 04 dic '17 11 dic '17 18 dic '17
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M
0 0 Cronograma Commissioning 146 días lun 18/09/17 mar 06/03/18
22 22 Chequeo Señales I/O 2 días mié 04/10/17 jue 05/10/17 17,20 23,27
23 23 Chequeo TC's & TT's 1 día vie 06/10/17 vie 06/10/17 22 24CC,41
24 24 Verificación de las comunicaciones con el sistema de control 2 días vie 06/10/17 sáb 07/10/17 23CC 25
28 28 Chequeo Alarmas & Fallas 5 días vie 06/10/17 mié 11/10/17 27CC 29
30 30 Sistemas Listos para Energizar 0 días vie 13/10/17 vie 13/10/17 25,29 32,57,62 13/10
37 37 Pruebas en Caliente Terminadas 0 días jue 16/11/17 jue 16/11/17 36,72 16/11
57 57 Chequeo Señales I/O 10 días sáb 14/10/17 mié 25/10/17 30 58,60CC+5 días
58 58 Chequeo TC's & TT's 4 días jue 26/10/17 lun 30/10/17 57 59CC
59 59 Verificación de las comunicaciones con el sistema de control 4 días jue 26/10/17 lun 30/10/17 58CC
63 63 Chequeo Alarmas & Fallas 15 días sáb 14/10/17 mar 31/10/17 62CC 64FC-7 días
65 65 Sistemas Listos para Energizar 0 días jue 09/11/17 jue 09/11/17 64,60 32,67,102 09/11
72 72 Pruebas en Caliente Terminadas 0 días jue 16/11/17 jue 16/11/17 71 137,37 16/11
100 100 I/O Test 3 días lun 23/10/17 mié 25/10/17 55 101,106CC
101 101 CT's & VT's Checks 3 días jue 26/10/17 sáb 28/10/17 100 102
102 102 Secundary Injection Tests 15 días vie 10/11/17 lun 27/11/17 101,65 103CC,104CC,120
Project: Cronograma Commission Cardine previsto Riepilogo previsto Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Previsione Slittamento
Id Id Task Name Duración Comienzo Fin Predecesoras Sucesoras junio 2017 julio 2017 agosto 2017 septiembre 2017 octubre 2017 noviembre 2017 diciembre 2017
29 may '17 05 jun '17 12 jun '17 19 jun '17 26 jun '17 03 jul '17 10 jul '17 17 jul '17 24 jul '17 31 jul '17 07 ago '17 14 ago '17 21 ago '17 28 ago '17 04 sep '17 11 sep '17 18 sep '17 25 sep '17 02 oct '17 09 oct '17 16 oct '17 23 oct '17 30 oct '17 06 nov '17 13 nov '17 20 nov '17 27 nov '17 04 dic '17 11 dic '17 18 dic '17
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M
103 103 Communication With Automation System 5 días vie 10/11/17 mié 15/11/17 102CC
104 104 Real Test (where applicable) 1 día vie 10/11/17 vie 10/11/17 102CC
105 105 Sistema da automatizacion y red de comunicacion 24 días lun 23/10/17 sáb 18/11/17
106 106 I/O Checks 12 días lun 23/10/17 sáb 04/11/17 100CC 107FF
107 107 Alarm & Fault Checks 6 días lun 30/10/17 sáb 04/11/17 106FF 108
108 108 Funtionality Tests 12 días lun 06/11/17 sáb 18/11/17 107 109
109 109 Finalización de Pre-comisionado / Listo para Pruebas Secas 0 días sáb 18/11/17 sáb 18/11/17 89,108 113,245 18/11
110 110 Pruebas y Puesta en Marcha U1 25 días lun 20/11/17 lun 18/12/17
113 113 Turbina - Control senales y operacion 2 días lun 20/11/17 mar 21/11/17 109 114CC
114 114 HPU - Control senales y operacion 2 días lun 20/11/17 mar 21/11/17 113CC 116
116 116 HPU - Control señales y operación 2 días mié 22/11/17 jue 23/11/17 114 117CC
117 117 Válvula - Control señales y operación 2 días mié 22/11/17 jue 23/11/17 116CC 119
119 119 Generador - Control señales y operación 3 días vie 24/11/17 lun 27/11/17 117 120
120 120 Pruebas Secas Finalizadas / Listo para Pruebas Húmedas 0 días lun 27/11/17 lun 27/11/17 119,102 123 27/11
123 123 Lógica de arranque 1 día mar 28/11/17 mar 28/11/17 120 124
124 124 Parada de emergencia 1 día mié 29/11/17 mié 29/11/17 123 125CC
125 125 Control de cierre del distribuidor 1 día mié 29/11/17 mié 29/11/17 124CC 127
127 127 Primer giro 1 día jue 30/11/17 jue 30/11/17 125 128CC
128 128 Complete no load test for 25% speed 1 día jue 30/11/17 jue 30/11/17 127CC 129CC,132CC
129 129 Complete no load test for 50% speed 1 día jue 30/11/17 jue 30/11/17 128CC 130CC
130 130 Complete no load test for 75% speed 1 día jue 30/11/17 jue 30/11/17 129CC 131
131 131 Complete no load test for 100% speed 1 día vie 01/12/17 vie 01/12/17 130 133
132 132 Speed Governor Adjustements 2 días jue 30/11/17 vie 01/12/17 128CC 133
133 133 Heat Run Bearing (No Load) 1 día sáb 02/12/17 sáb 02/12/17 132,131 135
134 134 Pruebas de Unidad Sin Carga 2 días lun 04/12/17 mar 05/12/17
135 135 Main Phase Sequence Tests 1 día lun 04/12/17 lun 04/12/17 133 136CC
136 136 Start-Up Tests Without Voltage 1 día lun 04/12/17 lun 04/12/17 135CC 137
137 137 Start-Up Tests With Voltage (AVR) 1 día mar 05/12/17 mar 05/12/17 136,72 139
138 138 Pruebas Funcionales de Unidad Con Carga 5 días mié 06/12/17 lun 11/12/17
139 139 First Synchronization and Coupling 2 días mié 06/12/17 jue 07/12/17 137 140
140 140 Perform Excitation Control (AVR) 2 días vie 08/12/17 sáb 09/12/17 139 141
141 141 Electrical Protections Real Tests 1 día lun 11/12/17 lun 11/12/17 140 142CC
142 142 Mechanical Protections Real Tests 1 día lun 11/12/17 lun 11/12/17 141CC 144
143 143 Pruebas Operacionales de Unidad con Carga 6 días mar 12/12/17 lun 18/12/17
144 144 Perform Auto& Manual Start Sequence 1 día mar 12/12/17 mar 12/12/17 142 145CC
145 145 Perform Normal Stopping Sequence 1 día mar 12/12/17 mar 12/12/17 144CC 146CC
146 146 Perform Quick Stopping Sequence 1 día mar 12/12/17 mar 12/12/17 145CC 147CC
147 147 Perform Emergency Stopping Sequence 1 día mar 12/12/17 mar 12/12/17 146CC 148
148 148 Heat Run Bearing 1 día mié 13/12/17 mié 13/12/17 147 149
149 149 Load Rejection Test at 25% of Load 1 día jue 14/12/17 jue 14/12/17 148 150CC
150 150 Load Rejection Test at 50% of Load 1 día jue 14/12/17 jue 14/12/17 149CC 151CC
151 151 Load Rejection Test at 75% of Load 1 día jue 14/12/17 jue 14/12/17 150CC 152CC
152 152 Load Rejection Test at 100% of Load 1 día jue 14/12/17 jue 14/12/17 151CC 153
153 153 Pruebas de reguladores (Posicion, Potencia, Nivel) 3 días vie 15/12/17 lun 18/12/17 152 154
154 154 Fin de Puesta en Marcha U1 0 días lun 18/12/17 lun 18/12/17 153 158,245 18/12
155 155 Pruebas y Puesta en Marcha U2 25 días lun 08/01/18 lun 05/02/18
158 158 Turbina - Control señales y operación 1 día lun 08/01/18 lun 08/01/18 154 159
159 159 HPU - Control señales y operación 1 día mar 09/01/18 mar 09/01/18 158 161
161 161 HPU - Control señales y operación 2 días mié 10/01/18 jue 11/01/18 159 162
162 162 Válvula - Control señales y operación 1 día vie 12/01/18 vie 12/01/18 161 164
164 164 Generador - Control señales y operación 1 día sáb 13/01/18 sáb 13/01/18 162 165
165 165 Pruebas Secas Finalizadas / Listo para Pruebas Húmedas 0 días sáb 13/01/18 sáb 13/01/18 164 168
168 168 Lógica de arranque 1 día lun 15/01/18 lun 15/01/18 165 169
169 169 Parada de emergencia 1 día mar 16/01/18 mar 16/01/18 168 170CC
170 170 Control de cierre del distribuidor 1 día mar 16/01/18 mar 16/01/18 169CC 172
172 172 Primer giro 1 día mié 17/01/18 mié 17/01/18 170 173
173 173 Complete no load test for 25% speed 1 día jue 18/01/18 jue 18/01/18 172 174CC
174 174 Complete no load test for 50% speed 1 día jue 18/01/18 jue 18/01/18 173CC 175CC,177CC
175 175 Complete no load test for 75% speed 1 día jue 18/01/18 jue 18/01/18 174CC 176
176 176 Complete no load test for 100% speed 1 día vie 19/01/18 vie 19/01/18 175 178
177 177 Speed Governor Adjustements 2 días jue 18/01/18 vie 19/01/18 174CC 178
178 178 Heat Run Bearing (No Load) 1 día sáb 20/01/18 sáb 20/01/18 177,176 180
179 179 Pruebas de Unidad Sin Carga 2 días lun 22/01/18 mar 23/01/18
180 180 Main Phase Sequence Tests 1 día lun 22/01/18 lun 22/01/18 178 181CC
181 181 Start-Up Tests Without Voltage 1 día lun 22/01/18 lun 22/01/18 180CC 182
182 182 Start-Up Tests With Voltage (AVR) 1 día mar 23/01/18 mar 23/01/18 181 184
183 183 Pruebas Funcionales de Unidad Con Carga 5 días mié 24/01/18 lun 29/01/18
184 184 First Synchronization and Coupling 2 días mié 24/01/18 jue 25/01/18 182 185
185 185 Perform Excitation Control (AVR) 2 días vie 26/01/18 sáb 27/01/18 184 186
186 186 Electrical Protections Real Tests 1 día lun 29/01/18 lun 29/01/18 185 187CC
187 187 Mechanical Protections Real Tests 1 día lun 29/01/18 lun 29/01/18 186CC 189
188 188 Pruebas Operacionales de Unidad con Carga 6 días mar 30/01/18 lun 05/02/18
189 189 Perform Auto& Manual Start Sequence 1 día mar 30/01/18 mar 30/01/18 187 190CC
190 190 Perform Normal Stopping Sequence 1 día mar 30/01/18 mar 30/01/18 189CC 191CC
191 191 Perform Quick Stopping Sequence 1 día mar 30/01/18 mar 30/01/18 190CC 192CC
192 192 Perform Emergency Stopping Sequence 1 día mar 30/01/18 mar 30/01/18 191CC 193
193 193 Heat Run Bearing 1 día mié 31/01/18 mié 31/01/18 192 194
194 194 Load Rejection Test at 25% of Load 1 día jue 01/02/18 jue 01/02/18 193 195CC
195 195 Load Rejection Test at 50% of Load 1 día jue 01/02/18 jue 01/02/18 194CC 196CC
196 196 Load Rejection Test at 75% of Load 1 día jue 01/02/18 jue 01/02/18 195CC 197CC
197 197 Load Rejection Test at 100% of Load 1 día jue 01/02/18 jue 01/02/18 196CC 198
198 198 Pruebas de reguladores (Posicion, Potencia, Nivel) 3 días vie 02/02/18 lun 05/02/18 197 199
199 199 Fin de Puesta en Marcha U2 0 días lun 05/02/18 lun 05/02/18 198 203,245
200 200 Pruebas y Puesta en Marcha U3 25 días mar 06/02/18 mar 06/03/18
203 203 Turbina - Control señales y operación 1 día mar 06/02/18 mar 06/02/18 199 204
204 204 HPU - Control señales y operación 1 día mié 07/02/18 mié 07/02/18 203 206
Project: Cronograma Commission Cardine previsto Riepilogo previsto Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Previsione Slittamento
Id Id Task Name Duración Comienzo Fin Predecesoras Sucesoras junio 2017 julio 2017 agosto 2017 septiembre 2017 octubre 2017 noviembre 2017 diciembre 2017
29 may '17 05 jun '17 12 jun '17 19 jun '17 26 jun '17 03 jul '17 10 jul '17 17 jul '17 24 jul '17 31 jul '17 07 ago '17 14 ago '17 21 ago '17 28 ago '17 04 sep '17 11 sep '17 18 sep '17 25 sep '17 02 oct '17 09 oct '17 16 oct '17 23 oct '17 30 oct '17 06 nov '17 13 nov '17 20 nov '17 27 nov '17 04 dic '17 11 dic '17 18 dic '17
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M
206 206 HPU - Control señales y operación 2 días jue 08/02/18 vie 09/02/18 204 207
207 207 Válvula - Control señales y operación 1 día sáb 10/02/18 sáb 10/02/18 206 209
209 209 Generador - Control señales y operación 1 día lun 12/02/18 lun 12/02/18 207 210
210 210 Pruebas Secas Finalizadas / Listo para Pruebas Húmedas 0 días lun 12/02/18 lun 12/02/18 209 213
213 213 Lógica de arranque 1 día mar 13/02/18 mar 13/02/18 210 214
214 214 Parada de emergencia 1 día mié 14/02/18 mié 14/02/18 213 215CC
215 215 Control de cierre del distribuidor 1 día mié 14/02/18 mié 14/02/18 214CC 217
217 217 Primer giro 1 día jue 15/02/18 jue 15/02/18 215 218
218 218 Complete no load test for 25% speed 1 día vie 16/02/18 vie 16/02/18 217 219CC
219 219 Complete no load test for 50% speed 1 día vie 16/02/18 vie 16/02/18 218CC 220CC,222CC
220 220 Complete no load test for 75% speed 1 día vie 16/02/18 vie 16/02/18 219CC 221
221 221 Complete no load test for 100% speed 1 día sáb 17/02/18 sáb 17/02/18 220 223
222 222 Speed Governor Adjustements 2 días vie 16/02/18 sáb 17/02/18 219CC 223
223 223 Heat Run Bearing (No Load) 1 día lun 19/02/18 lun 19/02/18 222,221 225
224 224 Pruebas de Unidad Sin Carga 2 días mar 20/02/18 mié 21/02/18
225 225 Main Phase Sequence Tests 1 día mar 20/02/18 mar 20/02/18 223 226CC
226 226 Start-Up Tests Without Voltage 1 día mar 20/02/18 mar 20/02/18 225CC 227
227 227 Start-Up Tests With Voltage (AVR) 1 día mié 21/02/18 mié 21/02/18 226 229
228 228 Pruebas Funcionales de Unidad Con Carga 5 días jue 22/02/18 mar 27/02/18
229 229 First Synchronization and Coupling 2 días jue 22/02/18 vie 23/02/18 227 230
230 230 Perform Excitation Control (AVR) 2 días sáb 24/02/18 lun 26/02/18 229 231
231 231 Electrical Protections Real Tests 1 día mar 27/02/18 mar 27/02/18 230 232CC
232 232 Mechanical Protections Real Tests 1 día mar 27/02/18 mar 27/02/18 231CC 234
233 233 Pruebas Operacionales de Unidad con Carga 6 días mié 28/02/18 mar 06/03/18
234 234 Perform Auto& Manual Start Sequence 1 día mié 28/02/18 mié 28/02/18 232 235CC
235 235 Perform Normal Stopping Sequence 1 día mié 28/02/18 mié 28/02/18 234CC 236CC
236 236 Perform Quick Stopping Sequence 1 día mié 28/02/18 mié 28/02/18 235CC 237CC
237 237 Perform Emergency Stopping Sequence 1 día mié 28/02/18 mié 28/02/18 236CC 238
238 238 Heat Run Bearing 1 día jue 01/03/18 jue 01/03/18 237 239
239 239 Load Rejection Test at 25% of Load 1 día vie 02/03/18 vie 02/03/18 238 240CC
240 240 Load Rejection Test at 50% of Load 1 día vie 02/03/18 vie 02/03/18 239CC 241CC
241 241 Load Rejection Test at 75% of Load 1 día vie 02/03/18 vie 02/03/18 240CC 242CC
242 242 Load Rejection Test at 100% of Load 1 día vie 02/03/18 vie 02/03/18 241CC 243
243 243 Pruebas de reguladores (Posicion, Potencia, Nivel) 3 días sáb 03/03/18 mar 06/03/18 242 244
244 244 Fin de Puesta en Marcha U3 0 días mar 06/03/18 mar 06/03/18 243 245
245 245 End Of Commissioning Certificate/PAC 0 días mar 06/03/18 mar 06/03/18 109,199,244,154
Project: Cronograma Commission Cardine previsto Riepilogo previsto Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Previsione Slittamento