Vous êtes sur la page 1sur 79

MANUAL OF CONTRACT DOCUMENTS FOR ROAD WORKS

VOLUME 1 SPECIFICATION FOR ROAD WORKS

SERIES 600
EARTHWORKS
Contents
Clause Title Page
601 Classification, Definitions and Uses of Earthworks Materials 2
602 General Requirements 4
603 Forming of Cuttings and Cutting Slopes 6
604 Excavation for Foundations 8
605 Special Requirements for Class 3 Material 8
606 Watercourses 8
607 Explosives and Blasting for Excavation 9
608 Construction of Fills 11
609 Geotextiles Used to Separate Earthworks Materials 10 13
610 Fill to Structures 14
611 Fill Above Structural Concrete Foundations 15
612 Compaction of Fills 15
613 Sub-formation and Capping 21
614 Cement Stabilisation to Form Capping 22
615 Lime Stabilisation to Form Capping 24
616 Preparation and Surface Treatment of Formation 26
617 Use of Sub-formation or Formation by Construction Plant 27
618 Topsoiling 28
619 Earthwork Environmental Bunds 31
620 Landscape Areas 32
621 Strengthened Embankments 32
622 Earthworks for Reinforced Soil and Anchored Earth Structures 32
623 Earthworks for Corrugated Steel Buried Structures 34
624 Ground Anchorages 35
625 Crib Walling 36
626 Gabions 36
627 Swallow Holes and Other Naturally Occurring Cavities 36
628 Disused Mine Workings 37
629 Instrumentation and Monitoring 37
630 Ground Improvement 37
631 Earthworks Materials Tests 39
632 Determination of Moisture Condition Value (MCV) of Earthworks Materials 39
633 Determination of Undrained Shear Strength of Remoulded Cohesive Material 39
634 Determination of Saturation Moisture Content (SMC) of Chalk 40
635 10% Fines Value and Other Tests of Particle Soundness 40
636 Determination of Effective Angle of Internal Friction (./) and Effective Cohesion (c/)
of Earthworks Materials 40
637 Determination of Resistivity (rs) to Assess Corrosivity of Soil, Rock or Earthworks Materials 41
638 Determination of Redox Potential (Eh) to Assess Corrosivity of Earthworks Materials for
Reinforced Soil and Anchored Earth Structures 42
639 Determination of Coefficient of Friction and Adhesion Between Fill and Reinforcing
Elements or Anchor Elements for Reinforced Soil and Anchored Earth Structures 42
640 Determination of Permeability of Earthworks Materials 43
641 Determination of Available Lime Content of Lime for Stabilized Capping 43
642 Determination of the Constrained Soil Modulus (M*) of Earthworks Materials
for Corrugated Steel Buried Structures 44
643 Lime and Cement Stabilization to Form Capping 28 Tables 6/1 to 6/5 45
Tables 6/1 to 6/5

ume 1 home page


EARTHWORKS

March 2003 1
Volume 1 Series 600
Specification for Road Works Earthworks

601 Classification, Definitions and


Uses of Earthworks Materials a) material similar to:

b) logs, stumps and perishable


General Classification material;

1 Earthworks materials shall fall into one c) materials in a frozen


or other of the following general condition;
classifications:
d) clay having a liquid limit
(i) Acceptable material: material determined in accordance
excavated from within the Site or with BS 1377 : Part 2,
imported on to the Site which exceeding 80 or plasticity
meets the requirements of Table index determined in
6/1 and Appendix 6/1 for accordance with BS 1377 :
acceptability for use in the Part 2, exceeding 55;
Permanent Works;
e) material susceptible to
(ii) Unacceptable material Class U1 as spontaneous combustion
defined in sub-Clause 2 of this
Clause: material excavated from f) non-hazardous materials
within the Site which, unless other than those permitted in
processed so that it meets the Table 6/1 and Appendix 6/1.
requirements of Table 6/1 and
Appendix 6/1, shall not be used in 3 Unacceptable material Class U2 shall
the Permanent Works; be:

(iii) Unacceptable material Class U2 as (i) material having hazardous


defined in sub-Clause 3 of this chemical or physical properties
Clause: material excavated from requiring special measures for its
within the Site, which shall not be excavation, handling, storing,
used in the Permanent Works. transportation, deposition and
disposal.
2 Unacceptable material Class U1 shall
be: 4 Where required in Appendix 6/1
unacceptable material shall be processed
(i) material which does not comply by mechanical, chemical or other means
with the permitted constituents and to render the material acceptable for use
material properties of Table 6/1 in the Permanent Works in accordance
and Appendix 6/1 for acceptable with the requirements of Table 6/1 and
material; Appendix 6/1.

(ii) material, or constituents of Definitions


materials, composed of the
following unless otherwise 5 Chalk shall mean:
described in Appendix 6/1:

March 2003 2
Volume 1 Series 600
Specification for Road Works Earthworks

(ii) Any porous material of natural ‘recycled aggregate except recycled


origin composed essentially of asphalt’ is used in this Series, the
calcium carbonate and identified aggregate shall have been tested in
as chalk on the maps produced by accordance with Clause 710 and shall
the Maltese Geological Survey; not contain any mineral aggregate with a
bituminous binder, and the content of all
(iii) Material designated as Class 3 in foreign materials shall not exceed 1%.
Appendix 6/1.
Use of Fill Materials
6 Argillaceous rock shall mean shale
mudstones siltstones slates and 11 In addition to any grading
micaceous schists composed of particles requirements the maximum particle size
of clay and silt and mica. of any fill material shall be no more than
two-thirds of the compacted layer
7 Formation shall be the top surface of thickness except that cobbles having an
capping. Where no capping is required equivalent diameter of more than 150
formation shall be the surface of the mm shall not be deposited beneath
subgrade or embankment directly below verges or central reserves within 1.30 m
the pavement, unless otherwise shown of the finished surface.
on the Drawings.
12 Isolated boulders with a equivalent
8 Sub-formation shall be the top surface diameter less than 250mm may be
of earthworks at the underside of incorporated in embankments not of
capping. rock fill provided the specified
compaction requirements are met. These
9 Stabilization shall mean the spreading boulders shall not be placed less than
of cement or lime or both on a layer of 600mm below formation level of
deposited or intact granular or cohesive carriageways or hard-shoulders where
material, and the subsequent process of there is no capping; or less than 600mm
pulverizing and mixing followed by below sub formation where there is
appropriate compaction to form the capping.
whole or a constituent layer of a
capping. In Malta the term cement 13 Materials with a water soluble sulfate
stabilization is used for cement bound content exceeding 0.25 grams of sulfate
material, which is a constituent layer of (expressed as SO3) per liter when tested
the pavement. in accordance with BS 1377 : Part 3
shall not be deposited within 500 mm, or
10 Where ‘recycled aggregate’ is used in other distances described in Appendix
this Series, the material shall be 6/3, of metallic items forming part of the
aggregate resulting from the processing Permanent Works.
of material used in a construction
process. The aggregate shall have been 14 For recycled aggregate, the
tested in accordance with Clause 710, requirements for water soluble sulfate
and the content of all foreign materials content shall be defined and tested in
(including wood, plastic and metal) shall accordance with BS 812: Part 118,
not exceed 1% by mass. Where Clause 5.

March 2003 3
Volume 1 Series 600
Specification for Road Works Earthworks

excavated material occupied shall be


provided by the Contractor.
602 General Requirements
5 Acceptable material (other than Class
1 The Contractor shall employ only plant 5A or any Class 5B material replacing
and working methods which are suited to Class 5A material in accordance with
the materials to be handled and sub-Clause 3 of this Clause) surplus to
traversed. He shall be responsible for the total requirements of the Permanent
maintaining the nature of the acceptable Works and all unacceptable material
material so that when it is placed and Class U2 and Class U1 not required to
compacted it remains acceptable in be processed shall, unless indicated
accordance with the Contract. otherwise in Appendix 6/1, be run to
Acceptability shall be determined in spoil in tips provided by the Contractor.
accordance with Table 6/1 and any In the case of unacceptable material
special requirements in Appendix 6/1. Class U2 the Contractor shall comply
with any specific requirements for
2 Haulage of material to embankments disposal described in Appendix 6/2.
or other areas of fill shall proceed only
when sufficient spreading and 6 Where the excavation reveals a
compaction plant is operating at the combination of acceptable and
place of deposition to ensure compliance unacceptable materials the Contractor
with Clause 612. shall, unless indicated otherwise in
Appendix 6/3, carry out the excavation
3 No excavated acceptable material or in such a manner that the acceptable
unacceptable material required to be materials are excavated separately for
processed, other than surplus to the use in the Permanent Works without
requirements of the Contract, shall be contamination by the unacceptable
removed from the Site unless indicated materials. Unless otherwise described in
otherwise in Appendix 6/1. Material, the Contract Classes of fill material
which is unacceptable only by reason of required to be deposited separately shall
being frozen, shall be retained on Site be excavated separately without
when in that condition. Where the contamination by other Classes of
Contractor is permitted to remove material.
acceptable material, or unacceptable
material required to be processed, from 7 The Contractor shall make his own
the Site to suit his operational procedure, arrangements for stockpiling of
then he shall make good any consequent acceptable material, and unacceptable
deficit of material arising therefrom. material to be processed, and for the
4 If any acceptable material or provision of sites for the purpose.
unacceptable material required to be
processed is, where permitted by 8 The Contractor shall ensure that he
Appendix 6/1, used by the Contractor for does not adversely affect the stability of
purposes other than for general fill, excavations or fills by his methods of
sufficient acceptable fill material to stockpiling materials, use of plant or
occupy, after full compaction, a volume sitting of temporary buildings or
corresponding to that which the structures.

March 2003 4
Volume 1 Series 600
Specification for Road Works Earthworks

where they are required in Appendix 6/3


9 Existing topsoil material shall, except to be left in position.
where it is to be left in place in the
locations described in Appendix 6/8, be 13 Excavations requiring backfilling
stripped to depths as described in shall remain open only for the minimum
Appendix 6/8 for Class 5A material from period necessary.
all areas of cutting and from all areas to
be covered by embankment or by other 14 Excavations requiring backfilling in
areas of fill. existing paved or other surfaces,
including those paved areas to be
10 Topsoil shall wherever practicable be reconstructed or repaired, shall be
used immediately after its stripping and carried out and reinstated in compliance
if not shall be stored in stockpiles of with Clause 706.
heights not exceeding 2 m or other
heights stated in Appendix 6/8. Unless 15 The Contractor shall keep earthworks
otherwise stated in Appendix 6/8, topsoil free of water including:
shall not be stockpiled for more than two
years. Topsoil shall not be unnecessarily (i) Arranging for the rapid removal of
trafficked either before stripping or water:
when in a stockpile. Stockpiles shall not
be surcharged or otherwise loaded and a. Shed on to the earthworks;
multiple handling shall be kept to a
minimum. b. Entering the earthworks
from any source;
11 All Class 5A topsoil arising from the
Site, or any Class 5B material replacing (ii) Lowering and maintaining by
Class 5A material in accordance with appropriate measures, the water
sub-Clause 3 of this Clause, in excess of level in excavations, sufficiently to
the requirements for topsoiling, shall be enable the Permanent Works to be
subject to the requirements described in constructed.
Appendix 6/8.
16 In carrying out the requirements of
12 Excavations for foundations and sub-Clause 15 of this Clause the
trenches in unstable subgrade shall be Contractor shall:
adequately supported at all times, and
except where otherwise described in (i) form and maintain cuttings,
Appendix 6/3, shall not be battered. embankments and other areas of
Where excavations are permitted to be fill with appropriate falls and
battered they shall be benched as gradient and sealed surfaces;
described in Appendix 6/3 prior to
backfilling and compaction. The (ii) provide where necessary
additional work and materials shall be temporary watercourses, drains,
provided by the Contractor. Sheeting and pumping and the like;
other excavation supports shall be
removed as filling proceeds except (iii) discharge accumulated water and
groundwater into the permanent

March 2003 5
Volume 1 Series 600
Specification for Road Works Earthworks

outfalls of the drainage system least 300 mm of material as a weather


where practicable; protection is left in place above the
formation or above the sub-formation,
(iv) provide adequate means for subject to the requirements of Clauses
trapping silt on temporary systems 613 and 616. Where directed by the
discharging into permanent Engineer for the purpose of improving
drainage systems. the strength of the sub-grade, the
Contractor shall install the permanent
17 The Contractor shall carry out and drainage as soon as practicable but in
maintain any groundwater lowering or any event before the bulk excavation
other treatment required in Appendix reaches a level 300mm above formation.
6/1. The base of cuttings shall be kept well
drained at all times. The contractor shall
18 Where materials are designated in the ensure that plant utilized in the
Contract as Class U2 hazardous material, earthworks operation does not in any
the Contractor shall carry out any special way damage or alter the location or
requirements for their handling levels of drainage works already
described in Appendix 6/2. Where constructed.
hazardous materials are encountered
during the progress of the Works, the (i) to achieve a natural appearance,
Contractor shall make all necessary when the stratum permits and
arrangements for their safe handling and when pre-split blasting is not
disposal as Class U2 material after adopted, have the face left
consultation with the Engineer and the irregular within tolerances as
appropriate statutory bodies agreed with the Engineer; and

(ii) have boulders or other rock


603 Forming of Cuttings and Cutting fragments that can be moved by
Slopes hand without tools, removed; and

1 Cuttings shall be excavated to the lines (iii) where required in Appendix 6/3
and levels described in Appendix 6/3. have material that can be blown
away by airline hose, having
2 Cutting slopes or toes of cuttings shall pressures no greater than those
only be undercut when required in the stated therein, so removed; and
Contract for trench or other excavations.
Such excavations shall be restricted in (iv) have adequate access to enable
extent as described in Appendix 6/3 and inspection to be carried out to
where they require backfilling shall determine the extent of work
remain open only for the minimum required by this sub-Clause.
period necessary, so as to prevent risk to
the Permanent Works. 6 Where required in Appendix 6/3,
faces of cuttings which are not
3 Except where otherwise described in required to receive topsoil shall
Appendix 6/3, the excavation of cuttings have one or more of the following
may be halted at any stage providing at measures carried out as

March 2003 6
Volume 1 Series 600
Specification for Road Works Earthworks

appropriated and as agreed with weep holes all in accordance with


the Engineer: requirements in Appendix 6/3.

(i) Isolated patches of soft, (iv) Netting or other sheet covering as


fragmented and insecure material described in Appendix 6/3 or rock
shall each be excavated to a depth bolts as described in Appendix
of at least 200 mm unless other 6/10.
depths are stated in Appendix 6/3
and replaced as soon as practicable 7 Where required in Appendix 6/3 or
with concrete mix (Series 2600) where required by the Engineer, faces of
well rammed into the cleaned out cuttings which are to receive topsoil
void. shall have one or more of the following
measures carried out as appropriates and
(ii) Areas of cutting face requiring as agreed with the Engineer:
their surface to be made stable
shall be trimmed back by a (i) Be benched to retain topsoil as
nominal 50 mm or other amount described in Appendix 6/3.
required in Appendix 6/3 and the
resulting surface together with an (ii) Be harrowed to a depth of 50 mm.
area of any surrounding intact Such harrowing shall be carried
material as detailed in Appendix out immediately prior to
6/3, shall have a suitable cement topsoiling, diagonally, at an angle
based grout or sprayed concrete, between 5º to 45º to the line of the
applied by pressure to form a total toe, measured on the plane of the
nominal thickness of 40 mm slope.
unless the required thickness is
stated in Appendix 6/3. Where (iii) Isolated patches of soft,
required in Appendix 6/3, fragmented or insecure material
reinforcement shall be fixed to the shall be excavated and either:
surface before application of the
concrete or grout. Weep holes (a) filled by well ramming in a
using permanent formers shall be Class of fill with similar
constructed to the requirements of characteristics as the
Appendix 6/3 and at the locations surrounding intact material;
described in Appendix 6/3 or as or
required by the Engineer.
(b) excavated and dealt with as
(iii) Soft or insecure material, described in sub-Clause 6(i)
interlayered with rock shall be of this Clause.
excavated to the depth behind the
face described in Appendix 6/3. (iv) Other areas required to be made
The resulting cavity shall be filled stable shall be dealt with as stated
with concrete mix ST2 or with in Appendix 6/3.
masonry infill complying with the
Series 2400 and provided with 8 The concrete, referred to in sub-
Clauses 6(i) and 6(iii) of this Clause,

March 2003 7
Volume 1 Series 600
Specification for Road Works Earthworks

permanently exposed on the face of the earthworks materials, with mix


cutting shall have surface features as ST1 concrete;
nearly as possible matching those of the
adjacent intact face. Such concrete and (ii) any additional excavation at or
the grout referred to in sub-Clause 6(ii) below the bottom of foundations,
of this Clause shall have a consistent including that resulting from
colour as nearly as possible matching removal of material which the
that of the adjacent intact face. Contractor has allowed to
deteriorate, with mix ST1 concrete
(or other material required by
604 Excavation for Foundations Appendix 6/3) except that under
corrugated steel buried structures
1 The bottom of all foundation Class 6K lower bedding material
excavations shall be formed to the lines shall be used.
and levels shown on the Drawings.
Pockets of soft soil or loose rock shall be 3 Class 6K lower bedding material
removed and the resulting voids and any referred to in this Clause shall be
natural voids shall be filled with mix deposited and compacted in compliance
ST1 concrete (Series 2600) (or other with Clauses 608 and 612 and Table 6/1.
material as required by Appendix 6/3)
except in excavations for corrugated
steel buried structures when Class 6K 605 Not Used
lower bedding fill material complying
with Table 6/1 shall be used.
606 Watercourses
After placing of any blinding concrete
shown on the Drawings, no trimming of 1 The clearance and modification of
the side faces of the excavation shall be existing, or the construction of new
carried out for 24 hours. watercourses, including ditches, streams,
rivers, lagoons and ponds, shall be as
2 The Contractor shall make good: described in Appendix 6/3 including any
protection, lining, revetment or other
(i) any lateral over break of the works and shall comply with sub-
excavation above the bottom of the Clauses 2 to 4 of this Clause.
foundation greater than the net
volume required for the Permanent 2 Clearance of existing watercourses
Works with material of the same shall include the removal of vegetation,
Class as used for fill above vegetable matter and all other deposits
structural concrete foundations to within the watercourse profile. Materials
comply with Clause 611 (except resulting from this clearance shall be
that for corrugated steel buried dealt with as unacceptable material.
structures Class 6K lower bedding
material shall be used) or, where 3 New watercourses and cleared existing
the excavation is too narrow to watercourses shall be maintained in a
allow the compaction of clear condition.

March 2003 8
Volume 1 Series 600
Specification for Road Works Earthworks

4 Redundant watercourses shall, where and their disposition, for use in the
required in Appendix 6/3, be drained and main blasting operations, so as not
cleared in accordance with sub-Clause 2 to exceed the values for vibrational
of this Clause and material outside the amplitude and vibrational peak
watercourse profile excavated and dealt particle velocity stated in (iv)
with as unacceptable material. The Below at the positions described
excavations shall be to the dimensions therein;
stated in the Contract and the whole
filled with general or selected fills of the (iv) Determine danger zones likely to
Class described in Appendix 6/3 be created by the blasting
complying with Table 6/1 deposited and operations, including trial
compacted in compliance with Clause explosions, within which blasted
608 and 612. Where the surface is to material may be projected and
remain exposed it shall be topsoiled and utilise suitable arrangements
seeded, or receive other treatment, all as including Temporary Works, to
described in Appendix 6/3. retain such projectiles and ensure
that no injury or damage is caused
to persons or property thereby;
607 Explosives and Blasting for
Excavation (v) Limit blasting to a small number
of events during permitted hours
1 Blasting for excavation shall not be per day, where an event shall
employed unless permitted or required in comprise a single explosion or a
Appendix 6/3 and such blasting shall be group of explosions each separated
confined to the locations and to within by a short time interval, the group
the time limits stated therein. lasting less than a minute;

2 The Contractor shall: (vi) Ensure that:

(i) Not carry out plaster shooting; (a) Structures and earthworks,
existing or under
(ii) For each location where blasting is construction, on and off the
to be undertaken, give written Site, do not experience,
notice to the Overseeing during blasting operations
Organisation of the programme of including trial explosions, a
blasting, including trial explosions, vibrational amplitude
at least 10 days before it exceeding 0.2 mm and a
commences and give written resultant peak particle
notice of each blasting event as velocity exceeding 50 mm
described in (v) below, at least 12 per second, or other limits
hours beforehand; stated in Appendix 6/3, at
the same time or
(iii) Carry out trial explosions starting individually; and
with reduced quantities of Volume 1 home page
explosive in order to determine the (b) Peak overpressures, of
size of the actual explosive charges magnitude such as to

March 2003 9
Volume 1 Series 600
Specification for Road Works Earthworks

endanger windows and


glazed areas of structures, do (vii) Take measurements of vibrational
not occur. amplitude and peak particle
velocity in each of three mutually
(vi) Where instrumentation and perpendicular planes and
monitoring is appropriate: determine the peak value, taken as
the maximum resultant calculated
(a) rigidly fix to structures and by vector summation of the three
insert in earthworks components of amplitude and
described in (vi) (a) above, velocity respectively, measured as
suitable instruments to instantaneously as the resolution of
measure the vibrational the recording instrument permits;
amplitude and resultant
vibrational peak particle (viii) Ensure that noise from blasting
velocity, and peak operations is controlled in
overpressures, experienced accordance with Clause 109;
during blasting operations
including trial explosions; (ix) Use explosives in the quantities
and in the manner recommended
(b) make available details of the by the manufacturer;
proposed instrumentation
within the Site; (x) Store explosives in registered
premises in a licensed store or
(c) unless otherwise stipulated magazine provided with a separate
in Appendix 6/3, make his compartment for detonators or use
own arrangements for them under an Immediate Use
installing instruments on Certificate issued by the police;
property off the Site
including negotiating with (xi) Only permit explosives to be used
landowners and other or handled by or under the
interested parties; immediate control of a competent
person;
(d) read such instruments and
take measurements
throughout the period of (xii) Ensure there is no unauthorized
blasting operations, issue or improper use of explosives
including trial explosions; brought on the Site and maintain a
strict check on quantities issued
(e) for instruments on structures and consumed;
or earthworks on the Site
and, where required in (xiii) Comply with the requirements of
Appendix 6/3, on property BS 6657 in respect of the use of
off the Site, make available electrical detonators in the vicinity
the results to the Overseeing of static and mobile radio
Organisation at the end of transmitters, including normal
each day’s blasting. radio and television broadcasting

March 2003 10
Volume 1 Series 600
Specification for Road Works Earthworks

stations and radar units associated (iv) to the requirements of this Clause
with aircraft movements, and any other requirements for fill
electricity generating plant and in this Series.
transmission lines.
2 Starter layers of Classes 6B or 6C
materials as described in Appendix 6/3
608 Construction of Fills shall be deposited as the first layer or
layers of fill above existing ground level
1 All fills, including embankments, shall or, if appropriate, above any ground
be constructed: improvement required by Appendix
6/13. Plant movement across starter
(i) in the locations described in layer material shall be restricted to that
Appendix 6/3 to the lines and plant which is necessary for its
levels stated therein; deposition, spreading and compaction in
compliance with this Clause and Clause
(ii) of Classes of materials required or 612 and any plant required to carry out
permitted in Appendix 6/1, any ground improvement beneath it if
complying with Table 6/1 with, required by Clause 630. The Contractor
unless otherwise described in the shall take all reasonable measures to
Contract, only Class 6A material prevent damage to the underlying strata,
deposited into open water; which may include use of lighter
spreading plant or a reduction of the
(iii) by depositing, as soon as number of passes of compaction plant.
practicable after excavation, in
layers to meet the compaction 3 Coarse granular material Classes 1C
requirements of Clause 612 as and 6B shall, before compaction, be
required for each Class of material spread in layers by a crawler tractor of
in Table 6/1, except that: not less than 15 tonnes total mass. After
compaction each layer shall, if voids
a. material requiring end remain, be blinded with an approved
product compaction shall be Class of granular material complying
deposited in layers not with Table 6/1 so that all surface voids
exceeding 250 mm are filled before the next layer and
uncompacted thickness; before any capping or sub-base is
b. material placed into open constructed.
water shall be deposited by
end tipping without 4 Embankments and other areas of fill
compaction; shall, unless otherwise required in the
Contract, be constructed evenly over
c. material deposited in areas to their full width and their fullest possible
receive dynamic compaction extent and the Contractor shall control
complying with Clause 630 and direct constructional plant and other
shall be deposited and vehicular traffic uniformly over them.
compacted to the Damage by constructional plant and
requirements therein. other vehicular traffic shall be made
good by the Contractor with material

March 2003 11
Volume 1 Series 600
Specification for Road Works Earthworks

having the same characteristics and Appendix 5/1 to be constructed other


strength as the material had before it was than in a trench, the fill shall be brought
damaged. up to and over them equally on both
sides. The fill shall be deposited in even
5 Embankments and other areas of layers and shall not be heaped above the
unsupported fills shall not be constructed pipe. Spreading and compaction shall be
with steeper side slopes, or to greater carried out evenly without dislodging,
widths than those described in Appendix distorting or damaging the pipe. Power
6/3, except to permit adequate rammers are not to be used within 300
compaction at the edges before trimming mm of any part of the pipe or joint.
back, or to obtain the final profile
following any settlement of the fill and 9 The last 600 mm depth of fill up to
the underlying material. However any sub-formation level, or formation level
oversteepening or increase in width shall as appropriate, shall, unless otherwise
not exceed any limits described in required in the Contract, be carried out
Appendix 6/3 and shall remain only for for the full width of embankments, or
the minimum periods necessary between the outer extremities of the
consistent with the safety of the verges in other areas of fill, in a
Permanent Works. continuous operation. The Contractor
shall then continue without delay to
6 Staged construction of fills and any carry out either (i) or (ii) below:
controlled rates of filling, shall be
carried out, in accordance with any (i) form the sub-formation or
requirements described in Appendix 6/3 formation, all in accordance with
including installation of instrumentation Clauses 613 and 616, following
and its monitoring, in compliance with immediately either by:
Clause 629.
a. the construction of the full
7 Where required in Appendix 6/3 the thickness of capping or sub-
Contractor shall surcharge embankments base as appropriate; or
or other areas of fill, as described therein
for the periods stated. If settlement of b. if permitted in Appendix 6/3,
surcharged fill results in any surcharging the construction of a lesser
material, which is unacceptable for use thickness of capping or sub-
in the fill being surcharged, lying below base as described therein laid
the formation or, where there is a as a weather protection layer;
capping, the sub-formation, the (ii) place an additional 300 mm
Contractor shall remove this minimum compacted thickness of
unacceptable material and dispose of it material above subformation level
in accordance with Clause 602. He shall or formation level as appropriate
then bring the resultant level up to for the full width of the filling to
formation or sub-formation, as form a weather protection. This
appropriate, with acceptable material. weather protection shall be
composed of the same material as
8 Where pipes in embankments or in the sub-formation or formation and
other areas of fill are permitted in compacted in compliance with

March 2003 12
Volume 1 Series 600
Specification for Road Works Earthworks

Table 6/1. The material shall be at least the life period required in
provided from the Contractor’s Appendix 6/5.
own resources and the protection
layer shall be constructed in a 3 Geotextiles shall be protected at all
continuous operation. For times against mechanical or chemical
stabilised capping, the protective damage. Those susceptible to damage by
layer shall consist of unstabilised light shall not be uncovered between
material. manufacture and incorporation in the
Permanent Works. Temporary exposure
10 Whenever fill is to be deposited shall not exceed 5 hours.
against the face of a natural slope, or
sloping earthworks face including 4 The method of selection and the
embankments, cuttings, other fills and required number of samples are as
excavations, such faces shall be benched described in Appendix 6/5. Samples
or otherwise shaped as required in shall be taken from the consignment of
Appendix 6/3 immediately before geotextile to be used in the Permanent
placing the subsequent fill. Works. Samples and test pieces cut from
them shall comply with sub-Clause 7 of
11 All permanent faces of side slopes of this Clause and test pieces shall be tested
embankments and other areas of fill at a laboratory to prove that the
formed in Classes 2 or 7 cohesive geotextile meets the following criteria or
materials, shall, subsequent to any other criteria described in Appendix 6/5:
trimming operations, be re-worked and
sealed by tracking a tracked vehicle, (i) The geotextile shall sustain a
suitable for the purpose, on the slope, or tensile load of not less than that
by other suitable methods. value given in Appendix 6/5,
determined in a ‘wide strip’ tensile
test carried out in accordance with
609 Geotextiles Used to Separate BS 6906 : Part 1. The
Earthworks Materials characteristic strength shall be
taken as the value of the strength
1 Geotextiles required as part of the of the material below which not
Permanent Works to separate earthworks more than 5% of the test results
materials at locations described in may be expected to fall. This
Appendix 6/5 shall be manufactured represents the strength at 1.64
from synthetic or other fibres as required standard deviations below the
therein and be in the form of thin mean strength.
permeable membranes.
(ii) The geotextile shall allow water to
2 The Contractor shall provide evidence flow through it, at right angles to
to the Overseeing Organisation, before its principal plane, in either
the geotextile is incorporated in the direction, at a rate of not less than
Permanent Works, that the geotextile 10 litres/m²/s under a constant
will be sufficiently durable, when head of water of 100 mm,
installed in contact with the materials to determined in accordance with BS
be separated, to maintain its integrity for 6906 : Part 3. The flow rate

March 2003 13
Volume 1 Series 600
Specification for Road Works Earthworks

determined in the test shall be conditioned and brought into equilibrium


corrected to that applicable to a at a temperature of 20° ± 2°C, and a
temperature of 15°C using relative humidity of 65 ± 5%. The dry
published data on variation in weight of the geotextile tested shall be
viscosity of water with quoted in g/m².
temperature.
8 The number of tests on samples shall
(iii) The geotextile shall have a size be as required in Appendix 6/5.
distribution of pore openings such
that the mean 090, is between 100
microns and 300 microns, 610 Fill to Structures
determined in accordance with BS
6906 : Part 2. 1 This Clause shall apply to fill to
structures other than:
5 The geotextile shall be laid and lapped
as described in this Clause or as (i) fill for reinforced earth structures,
described in Appendix 6/5 and where including associated drainage
lapping is employed adjacent sheets or layers;
strips of geotextile shall be overlapped
by at least 300 mm, or other dimension (ii) fill for anchored earth structures
described in Appendix 6/5. including associated drainage
layers;
6 The layer of material on which the
geotextile is to be placed shall not have (iii) fill for surround and bedding of
protrusions or sharp projections which corrugated steel buried structures;
are likely to damage the geotextile
during installation or in service. The (iv) fill above structural concrete
method of installation shall ensure that foundations unless otherwise
the geotextile is in continuous contact required in Appendix 6/6.
with the surface on which it is to be
placed and the geotextile shall not be 2 Materials, as required or permitted in
stretched or bridged over hollows or Appendix 6/6 of Classes 6N and 6P and
humps. Operation of construction plant complying with Table 6/1 shall be used
directly on the installed geotextile will as fill to structures, in the locations
not be permitted and its covering with described in Appendix 6/6.
fill material shall take place immediately
after its laying. 3 The Contractor shall compact, in
compliance with Clause 612, end-
7 All samples and test pieces cut from product compaction, Class 6N and 6P,
them shall be maintained in a clean and material to satisfy the compaction
dry condition, except for normal requirements for those Classes as listed
contamination and wetting during in Table 6/1, but subject to the
testing, and shall be retained by the restrictions in sub-Clauses 4 and 5 of
Contractor in accordance with Appendix this Clause.
6/5. Prior to determination of pore size
and tensile strength, test pieces shall be

March 2003 14
Volume 1 Series 600
Specification for Road Works Earthworks

4 Where fill to structures is required to 611 Fill Above Structural Concrete


the same level on more than one side of Foundations
a structural element or buried structure
(except where Clause 623 applies) it 1 Fill deposited above structural
shall be maintained at heights not concrete foundations shall be, as shown
differing by more than 250 mm after on the Drawings:
compaction on opposing sides of the
structural element as filling proceeds. (i) Class 6N or 6P selected fill
material complying with Clause
5 The Contractor shall restrict 610 including compaction
compaction plant used on fill to requirements;
structures, within 2 m of a structure, to
the following items as described in sub- (ii) Class 6M selected fill material,
Clause 612.10 and deposited and compacted in
listed in Table 6/4: accordance with Clause 623, above
the foundation of arch profile
(i) vibratory roller having a mass per corrugated steel buried structures;
metre width of roll, as determined
by sub-Clause 612.10, not (iii) another class of selected fill or
exceeding 1,300 kg with a total general fill complying with Table
mass not exceeding 1,000 kg; 6/1 deposited and compacted in
compliance with Clauses 608 and
(ii) vibrating plate compactor having a 612 and in addition be subject to
mass not exceeding 1,000 kg; sub- Clauses 610.4 and 5.

(iii) vibro-tamper having a mass not


exceeding 75 kg. 612 Compaction of Fills General

The compacted level of the fill within 1 Except for dynamic compaction, which
this zone shall not differ during shall comply with Clause 630, and
construction from the compacted level of unless otherwise described in Appendix
the remainder of the adjoining fill to 6/3, the Contractor shall carry out
structures by more than 250 mm. compaction in compliance with this
Clause, as soon as practicable after
6 Where required in Appendix 6/6, Class deposition, on all those Classes of fill in
6N and 6P material shall be shown, by Table 6/1 which require to be
means of a trial utilizing not less than 20 compacted.
m³ of the material, deposited and 2 Compaction shall be either method or
compacted in accordance with this end-product as required for the Class of
Clause, to be stable, when it is trimmed fill in Table 6/1, using plant appropriate
to a slope of 1 vertical to 1½ horizontal, to the Class of fill and the site
or other slope described in Appendix conditions.
6/6.
3 The Contractor shall obtain permission
from the Overseeing Organisation before

March 2003 15
Volume 1 Series 600
Specification for Road Works Earthworks

carrying out compaction outside normal defined in Appendix 6/3. If the results of
working hours. field tests show densities which indicate
the state of compaction to be inadequate,
Method Compaction then if this is due to failure of the
Contractor to comply with the
4 Where method compaction is required requirements of the Contract, the
to be adopted it shall comply with sub- Contractor shall carry out such further
Clauses 5 to 10 of this Clause. work as is required to comply with the
Contract.
5 Except as stated in sub-Clause 6 of this
Clause, method compaction shall be 10 For the purposes of Table 6/4 the
undertaken using the plant and methods following shall apply:
in Table 6/4 appropriate to the
compaction requirements as listed in (i) The minimum number of passes N
Table 6/1 for the Class of material being is the minimum number of times
compacted. that each point on the surface of
the layer being compacted shall be
6 Plant and methods not included in traversed by the item of
Table 6/4 shall only be used providing compaction plant in its operating
the Contractor demonstrates at site trials mode, or struck by power rammers
that a state of compaction is achieved by or falling weight compactors. D is
the alternative method equivalent to that the maximum depth of the
obtained using the specified method. compacted layer.

7 Earthmoving plant shall not be (ii) In column headed N # the number


accepted as compaction equipment nor of passes shown is to be doubled
shall the use of a lighter category of for material Classes 1A, 1B, 2A,
plant to provide any preliminary 2B, 2C and 2D when such
compaction to assist the use of heavier materials occur within 600 mm of
plant be taken into account when subformation (if capping is
assessing the amount of compaction required) or formation. Such extra
required for any layer. compaction shall, unless otherwise
described in Appendix 6/3, either
8 If more than one Class of material is be carried out for the full width of
being used in such a way that it is not the embankment or, in other areas
practicable to define the areas in which of fill which are to receive a
each Class occurs, the Contractor shall pavement, between the outer
compact with plant operating as if only extremities of the verges.
the material which requires the greater (iii) The compaction plant in Table 6/4
compactive effort is being compacted. is categorised in terms of static
mass. The mass per metre width of
9 The Contractor or Overseeing roll is the total mass on the roll
Organisation may carry out field dry divided by the total roll width.
density tests as described in sub- Clause Where a smooth wheeled roller has
15 of this Clause on material compacted more than one axle the category of
to method requirements at a frequency the machine shall be determined

March 2003 16
Volume 1 Series 600
Specification for Road Works Earthworks

on the basis of the axle giving the a machine having a means of


highest value of mass per metre applying mechanical vibration to
width. one or more rolls. The roll or rolls
have projecting feet where the
(iv) A grid roller is a machine with a height of each foot exceeds 10% of
compacting roll or rolls the radius of the roll drum, the
constructed of heavy steel mesh of projected end area of each foot
square pattern. exceeds 0.1% of the roll drum
surface area, and the sum of the
(v) A deadweight tamping roller is a areas of the feet exceeds 10% of
machine with a roll or rolls from the area of the cylinder swept by
which ‘feet’ project and where the the ends of the feet. The
projected end area of each ‘foot’ requirements for the operation of
exceeds 0.01 m² and the sum of the vibratory tamping rollers shall be
areas of the feet exceeds 15% of the same as those stated for
the area of the cylinder swept by vibratory rollers in sub- Clause
the ends of the feet. The (viii) except that vibratory tamping
requirements for tamping rollers rollers operating without vibration
apply to machines that have 2 rolls will be classified as deadweight
in tandem. If only one tamping roll tamping rollers.
traverses each point on the surface
of the layer on any one pass of the (viii) Vibratory rollers are self-propelled
machine, the minimum number of or towed smooth-wheeled rollers
passes shall be twice the number having means of applying
given in Table 6/4 plus any further mechanical vibration to one or
doubling required to satisfy (ii) more rolls except that vibratory
above. rollers employed for Method 5
compaction shall be single roll
(vi) For pneumatic-tyred rollers the types. Vibratory rollers operating
mass per wheel is the total mass of without vibration will be classified
the roller divided by the number of as smooth-wheeled rollers. The
wheels. In assessing the number of requirements for vibratory rollers
passes of pneumatic-tyred rollers are based on the use of the lowest
the effective width shall be the gear on a self propelled machine
sum of the widths of the individual with mechanical transmission and
wheel tracks together with the sum a speed of 1.5 to 2.5 km/h for a
of the spacings between the wheel towed machine, or a self-propelled
tracks provided that each spacing machine with hydrostatic
does not exceed 230 mm. Where transmission. If higher gears or
the spacings exceed 230 mm the speeds are used an increased
effective width shall be the sum of number of passes shall be provided
the widths of the individual wheel in proportion to the increase in
tracks only. speed of travel. Where the
mechanical vibration is applied to
(vii) A vibratory tamping roller, which two rolls in tandem, the minimum
may be self-propelled or towed, is number of passes shall be half the

March 2003 17
Volume 1 Series 600
Specification for Road Works Earthworks

number given in Table 6/4 for the condition by its area in


appropriate mass per meter width contact with compacted
of one vibrating roll but if one roll material;
differs in mass per metre width
from the other the number of b. vibrating-plate compactors
passes shall be calculated as for shall be operated at the
the roll with the smallest value. frequency of vibration
Alternatively the minimum recommended by the
number of passes may be manufacturers. They shall
determined by treating the normally be operated at
machine as having a single travelling speeds of less than
vibrating roll with a mass per 1 km/h but if higher speeds
metre width equal to that of the are necessary the number of
roll with the higher value. passes shall be increased in
Vibratory rollers shall be operated proportion to the increase in
with their vibratory mechanism speed of travel.
operating only at the frequency of
vibration recommended by the (xi) Vibro-tampers are machines in
manufacturers. Where more than which an engine-driven
one amplitude setting is available reciprocating mechanism acts on a
and/or a range of frequencies is spring system through which
recommended, the machine shall oscillations are set up in a base-
be operated at the maximum plate.
amplitude setting and at the
maximum recommended (xii) Power rammers are machines
frequency for that setting. which are actuated by explosions
in an internal combustion cylinder,
(ix) Vibratory rollers shall be equipped each explosion being controlled
or provided with devices manually by the operator.
indicating the frequency at which
the mechanism is operating and the (xiii) Dropping weight compactors are
speed of travel. Both devices shall machines in which a dead weight
be capable of being read by an is dropped from a controlled height
inspector alongside the machine. using a hoist mechanism and they
include self-propelled machines
(x) Vibrating-plate compactors are with mechanical traversing
machines having a base-plate to mechanisms capable of
which is attached a source of compacting soil in trenches and
vibration consisting of one or two close to structures.
eccentrically weighted shafts and:
(xiv) In the case of power rammers and
a. the mass per square metre of dropping weight compactors one
the baseplate of a vibrating- pass will be considered as made
plate compactor is calculated when the compacting shoe has
by dividing the total mass of made one strike on the area in
the machine in its working question.

March 2003 18
Volume 1 Series 600
Specification for Road Works Earthworks

system, in order to monitor the


(xv) For items marked * in the Method compacted density);
3 column of Table 6/4 the roller
shall be towed by track-laying (ii) a graph of density plotted against
tractors. Self-propelled rollers are moisture content from which each
unsuitable. of the values in (i) above of
maximum dry density and
(xvi) Where combinations of different optimum moisture content were
types or categories of plant are determined and, for Class 7A
used, the following shall apply:(a) material, a plot of the 5% air voids
the depth of layer shall be that for curve for each sub-division.
the type of plant requiring the least
depth of layer; and 13 Once the information contained in
sub-Clause 12 of this Clause has been
a. the number of passes shall be made available to the Overseeing
that for the type of plant Organisation it shall form the basis for
requiring the greatest compaction.
number of passes.
14 Fill compacted to end-product
End-product Compaction requirements shall have a field dry
density, measured in accordance with
11 Where end-product compaction is sub-Clause 15 of this Clause, equal to or
required it shall comply with sub- greater than the percentage given in
Clauses 12 to 15 of this Clause. Table 6/1 of the maximum dry density
for the relevant Class of fill previously
12 The Contractor shall at least 7 days made available to the Overseeing
before commencement of end-product Organisation in accordance with sub-
compaction make available the Clause 12 of this Clause.
following to the Overseeing
Organisation: 15 In general the following requirements
for the compaction degree based on the
(i) the values of maximum dry density Standard Proctor according BS 5835
and the optimum moisture content should be achieved.
obtained in accordance with BS
1377 : Part 4 using the 2.5 kg
rammer method or vibrating
hammer method as appropriate for
each of the fills he intends to use a. Course soils (DIN 18196)
which meet the requirements of the
permitted Class or Classes (where 1. Up to a depth of 0.5m
within any Class of material the below formation level:
fill contains material having Dpr≥ 100%
different maximum dry densities
and optimum moisture contents the 2. Below 0.5m up to the
Class shall be further sub-divided, fill base: Dpr≥ 98%
by extending the identification

March 2003 19
Volume 1 Series 600
Specification for Road Works Earthworks

b. Composite soils and fine The requirements of the ‘Directives for


soils (Din 18196) the standardization of Pavements For
Traffic Areas’ concerning the reaction
1. Up to a depth of 0.5m modules Ev2 have to be observed. The
below formation level: relations of table 6.6 for cause soils may
Dpr ≥ 100% be applied.

2. Below 0.5m up to the Table 6.6 Guidelines for the relation


fill base: Dpr ≥ 97% between Dpr and Ev2 for course soils

Soil Group Compaction degree Dpr (%) Reaction Modules Ev2 (MN/m²)

CW, GI ≥ 100 ≥ 100


≥ 98 ≥ 80
≥ 97 ≥ 70

GE, SE, SW, SI ≥ 100 ≥ 80


≥ 98 ≥ 70
≥ 97 ≥ 60

Additionally the relations Ev2/Ev1 of table 6.2 may be used to evaluate the compaction
condition of the soils of table 6.7

Table 6.7: Guidelines for the relative between Dpr and Ev2/Ev1

Compaction degree Dpr (%) Relative Ev2/Ev1

≥ 100% ≤ 2.3
≥ 98% ≤ 2.5
≥ 97% ≤ 2.6

16 The field dry density referred to in


sub-Clause 14 of this Clause shall be
measured in accordance with BS 1377 :
Part 9, except that nuclear methods
shall only be used where required
or permitted in Appendix 6/3. Where
nuclear methods are used, the gauge
shall be calibrated in accordance with
BS 1377 : Part 9.

613 Sub-formation and Capping the bearing capacity requirements on


formation level (See Directive) shall be
1 Capping to facilitate construction provided only in those locations, and to
works on cohesive subgrade, or to meet the extent, particularly stated in

March 2003 20
Volume 1 Series 600
Specification for Road Works Earthworks

Appendix 6/7 to be constructed with carry out one of the following


capping. It shall comply with this Clause procedures:
and in addition, for stabilized capping,
with Clauses 614, 615 and 643 as (i) for Class 6F1, 6F2 or 6F3 capping,
appropriate. excavate below formation level to
a depth to accept the capping, trim
2 Capping shall be constructed with the surface to form the
Class 6F1, 6F2, 6F3, 9A, 9B, 9D, 9E or subformation and immediately
9F material as required or permitted in compact with one pass of a
Appendix 6/7 and complying with Table smooth-wheeled roller having a
6/1. mass per m width of roll not less
than 2,100 kg or a vibratory roller
3 Unless otherwise described in having a mass per m width of roll
Appendix 6/7, capping shall either not less than 700 kg or a vibrating
consist of one Class of capping material plate compactor having a mass per
throughout its depth laid in one or more m² of not less than 1,400 kg, and
layers of compacted thickness immediately deposit and compact
complying with Clause 612, or be above it a capping in Class 6F1,
formed of not more than two elements of 6F2 or 6F3 material; or
different capping materials. Each
element shall be formed of one or more (ii) for Class 9A, 9B,9D, 9E or 9F
layers of the same capping material, capping material construct the
each of compacted thickness complying capping by stabilizing the intact
with Clause 612. Class 9D or 9E material, providing it complies
stabilized capping material shall not be with Class 6E, 6R 7E, 7F, 7G or 7I
placed or constructed above Class 6F material requirements,
granular capping material. immediately below formation to
form Class 9A, 9B, 9D, 9E or 9F
4 Unless otherwise stated in Appendix material, respectively; or
6/7, the subformation shall have the
same longitudinal gradient, crossfall and (iii) excavate below formation to
surface level tolerances as the formation. sufficient depth to enable
stabilization of intact Class 6E, 6R,
5 The Contractor shall limit any 7E, 7F, 7G or 7I material to be
unprotected area of sub-formation, carried out, to produce Class 9A,
which is to receive capping to suit the 9B, 9D 9E or 9F material forming
output of the plant in use and the rate of the lower element of the capping
deposition of capping. (after stabilization of this element,
6 No unprotected subformation, which is the capping shall be completed by
to receive capping, shall remain depositing a further layer or layers
continuously exposed to rain causing of Class 6E, 6R 7E, 7F, 7G, or 7I
degradation, nor be left uncovered material and stabilizing it to form
overnight. Class 9A, 9B, 9D, 9E or 9F
capping or depositing and
7 In cuttings the Contractor shall, as compacting Class 6F1, 6F2 or 6F3
permitted or required in Appendix 6/7

March 2003 21
Volume 1 Series 600
Specification for Road Works Earthworks

material to form the upper element (iii) for multi-element capping,


of the capping); or incorporating stabilized material,
construct the embankment to
(iv) excavate to sub-formation level sufficient height to carry out the
and deposit material complying work described in 8(ii) above and
with Classes 6E, 6R, 7E, 7F, 7G, immediately construct above it one
or 7I to be stabilized to form a or more layers of Class 6F1, 6F2
capping of Class 9A, 9B, 9D, 9E or 6F3 capping.
or 9F layers. Where a stabilized
layer is directly overlain by Class Where a stabilized layer is directly
6F1, 6F2 or 6F3 material the overlain by Class 6F1, 6F2 or 6F3
stabilized layer shall be compacted material the stabilized layer shall be
as for a sub-formation in 7 (i) compacted as for a sub-formation in 8(i)
above. above.

8 On embankments and other areas of


fill the Contractor shall, as permitted or 614 Cement Stabilization to Form
required in Appendix 6/7 carry out one Capping
of the following procedures:
1 Where capping is to consist of, either
(i) complete the embankment to form wholly or in part, cement stabilized
the subformation or remove any material Class 9A or 9B this Clause shall
protection layer and trim the apply to the construction of those parts
surface to form the subformation, which are stabilized with cement.
and in both cases compact with
one pass of a smooth-wheeled 2 Material to be stabilized with cement
roller having a mass per m width shall be Class 6E or Class 7F materials
of not less than 2,100 kg or a all complying with Clause 601 and Table
vibratory roller of not less than 6/1. Unless otherwise described in
700 kg per m width or a vibrating Appendix 6/7 cement shall be Portland
plate compactor having a mass per cement complying with Clause 1001.
m² of not less than 1,400 kg, and
immediately construct above it, in 3 Class 6E or class 7F material to be
one or more layers, Class 6F1, 6F2 stabilized shall have added to it, at any
or 6F3 capping; or point, that quantity of cement measured
as a percentage of its dry weight as
(ii) construct the embankment to determined on the demonstration area, to
sufficient height and carry out meet the required. Ev2 value in
stabilization to form a capping of Appendix 6/1, subject to a minimum of
Class 9A, 9B, 9D, 9E or 9F 2% cement.
material in one or more layers
utilizing where appropriate any 4 The appropriate quantity of cement
protection layer previously shall be uniformly spread, by a suitable
constructed; or spreading machine, on top of the layer to
be processed. Using a collecting tray and
balance the Contractor shall check the

March 2003 22
Volume 1 Series 600
Specification for Road Works Earthworks

rate of spread of the machine once for 9 The stabilizing machine shall be
every 500 m² of cement spread. equipped with a device for controlling
the depth of processing which shall be
5 Unless indicated otherwise in maintained at the correct setting at all
Appendix 6/7, Class 6E or 7F material times. An overlap of 150 mm shall be
shall be stabilized in a single layer if its made between adjacent passes of the
compacted thickness is 250 mm or less. stabilizing machine. Where a subsequent
If its compacted thickness is greater, the layer of material is placed on a layer
material shall be stabilized in layers not previously stabilized the tines or blades
less than 130 mm and not more than 250 of the stabilizing machine shall be set so
mm thick, including any cutting-in that they cut into the previously
required by sub-Clause 9 of this Clause. stabilized layer below by at least 20 mm.

6 The Contractor shall not carry out 10 Each layer of Class 9A or 9B


cement stabilization when the shade processed material shall be compacted as
temperature is below 3°C unless on a soon as possible after the final pass of
rising thermometer above 0°C. Cement the stabilizing machine. Compaction
stabilization shall not be carried out shall be completed within 2 hours
during periods of rain or when rain is following the mixing of the cement into
imminent. When cement is spread on the material to be stabilized.
material likely to cause premature Immediately before compaction Class
hydration, processing in accordance with 9B processed material shall have a
sub-Clause 7 of this Clause shall follow Moisture Condition Value (MCV) of not
immediately. greater than 12 nor less than the figure
stated in Appendix 6/1 for Class 9B
7 Unless indicated otherwise by cement stabilized material, both as
Appendix 6/7, Class 6E or 7F material determined in accordance with Clause
forming the layer to be stabilized shall 632. Water shall be added if necessary in
be processed by pulverising and mixing a uniform manner to enable this MCV
in the cement by means of a sufficient requirement to be met.
number of passes of a suitable mobile
stabilizing machine until 95% of the silt 11 The compaction of each layer of
and clay fraction is reduced to particles Class 9A or 9B material shall comply
or lumps passing a BS 28 mm sieve after with Clause 612, Table 6/4 Method 6 or
dry sieving and the pulverisation Method 7 respectively, except that if
complies with Table 6/1. layers of Class 9A or 9B greater than
250 mm thickness are to be constructed,
8 During processing, only sufficient the number of passes of the compaction
water shall be available in the material to plant shall be determined from the
hydrate the cement and enable results of a demonstration area as
satisfactory mixing and compaction to detailed in Appendix 6/7.
be achieved. Any added water shall be
through an integral spray-bar on the 12 Class 9A or 9B materials shall be
stabilizing machine. cured in accordance with Clause 1035.
During periods when the air temperature
is forecast to drop below 3°C or when

March 2003 23
Volume 1 Series 600
Specification for Road Works Earthworks

ground frost is forecast Class 9A or 9B defined in Appendix 6/7 during periods


material shall be protected, to prevent when lime stabilization is carried out.
freezing, for a period of 7 days from the
time of completion of compaction. Such 5 Class 7E material to be stabilized shall
protection shall be sealed to prevent the have added to it, at any point, the
ingress of moisture. percentage of its dry weight of lime, as
determined on the demonstration area, to
13 Class 9A or 9B materials shall not meet the required Ev2 value in Appendix
have other material deposited or 6/1, subject to a minimum of 2½% by
compacted above them until such time as weight of ‘available lime’ as a
the required Ev2 value in Appendix 6/1 percentage of the dry weight of the Class
has been achieved. The relaxation 7E material.
allowed in sub-Clause 617.2 shall not
apply before this time. 6 Lime of quantity complying with sub-
Clause 5 of this Clause shall be
uniformly spread by a suitable spreading
615 Lime Stabilization to Form machine on top of the layer to be
Capping stabilized. Using a collecting tray and
balance the Contractor shall check the
1 This Clause shall apply only to those rate of spread by weight, once for every
capping materials which are to be 500 m² of lime spread or a different rate
stabilized with lime to form material of testing for the rate of spread as
Class 9D. described in Appendix 6/7. At the same
time the Contractor shall collect samples
2 Material to be stabilized with lime of lime deposited on the tray and test
shall be Class 7E material complying them for available lime content in
with Clause 601 and Table 6/1. accordance with Clause 641.

3 Lime for lime stabilization shall, as 7 Unless indicated otherwise in


required in Appendix 6/7, be either Appendix 6/7, the material shall be
quicklime or hydrated lime complying stabilized in a single layer if its
with BS 890. Quicklime shall when compacted thickness is 250 mm or less.
sieved have 100% passing a BS 10 mm If its compacted thickness is greater, the
sieve and at least 95% by mass passing a material shall be stabilized in layers not
BS 5 mm sieve. less than 130 mm and not more than 250
mm thick, including any cutting-in
4 The Contractor shall make available to required by sub-Clause 12 of this
the Overseeing Organisation for each Clause.
source of lime a report of a chemical
analysis for ‘available lime’ made in 8 Unless indicated otherwise in
accordance with sub-Clause 641.2. Such Appendix 6/7 lime stabilization shall not
reports shall be made available to the be carried out during periods of rain or
Overseeing Organisation prior to the when rain is imminent and when the
incorporation of lime in the Permanent shade temperature is not below 7°C.
Works at weekly or other intervals Only when the specified Ev2 value is
attainable at a shade temperature less

March 2003 24
Volume 1 Series 600
Specification for Road Works Earthworks

than 7°C, may lime stabilization be this Clause, adding water uniformly if
carried out at such lower temperature. necessary.
Lime stabilization shall be suspended if
rainfall will have an adverse effect on 12 The stabilizing machine shall be
the material being stabilized. The equipped with a device for controlling
spreading of lime shall not be carried out the depth of processing which shall be
in a manner or under conditions that will maintained at the correct setting at all
result in lime being blown from the site times. An overlap of 150 mm shall be
onto adjacent land or property. made between adjacent passes of the
stabilizing machine. Where a subsequent
9 Unless indicated otherwise in layer of material is placed on a layer
Appendix 6/7, the material forming the previously stabilized the tines or blades
layers to be stabilized shall be processed of the stabilizing machine shall be set so
by pulverising and mixing in the lime by that they cut into the previously
means of sufficient number of passes of stabilized layer below by at least 20 mm.
a suitable mobile stabilizing machine
until 95% of the Class 9D processed 13 Each layer of Class 9D processed
material passes a BS 28 mm sieve after material shall be compacted as soon as
dry sieving and the pulverisation possible after the final pass of the
complies with Table 6/1. stabilizing machine. Immediately before
compaction the processed material shall
10 During processing only sufficient have a Moisture Condition Value
water shall be available in the material to (MCV) of not greater than nor less than
slake the quicklime (if used) and to the figures stated in Appendix 6/1, for
enable satisfactory mixing and Class 9D lime stabilized material, both
compaction to be achieved. Any added as determined in accordance with Clause
water shall be through an integral spray- 632.
bar on the stabilizing machine.
14 If there is a delay following the final
11 The layer shall receive at least two pass and before commencement of
passes of the stabilising machine to compaction the surface shall be sealed
pulverise and mix the lime and soil, after by not less than 2 passes of a smooth-
which the processing shall be interrupted wheeled roller having a mass per metre
by a period of not less than 24 hours and width of not less than 2,700 kg or of a
not greater than 72 hours, to enable the pneumatic tyred roller of not less than
lime to react with the soil. Before this 1,000 kg mass per wheel. On
period commences the surface of the recommencement and before
layer shall be sealed with one pass of a compaction the layer shall be re-
smooth wheeled roller having a mass per processed without the addition of lime,
metre width of roll of not less than 2700 by a sufficient number of passes of the
kg or a pneumatic tyred roller of not less stabilising machine to meet the MCV
than 1000 kg per wheel. At the end of requirements of sub-Clause 13 of this
this period the layer shall receive one Clause adding water uniformly if
further pass of the stabilizing machine or necessary.
more if required to enable the material to
comply with sub-Clauses 9 and 13 of

March 2003 25
Volume 1 Series 600
Specification for Road Works Earthworks

15 The compaction of each layer shall (ii) The formation shall immediately
comply with Clause 612, Table 6/4 be compacted, in addition to the
Method 7 except that if layers more than compaction required for the fill.
250 mm thick are constructed the This additional compaction shall
number of passes of the compaction for this purpose be assumed to be
plant shall be those determined from as for a layer of 250 mm finished
results obtained on a demonstration area thickness compacted in
as detailed in Appendix 6/7. compliance with Clause 612 and
Table 6/4 Method 6 except for
16 Class 9D material shall not have Class 3 materials where Method 4
other material deposited or compacted shall be used. Immediately after
above it until such time as the required the additional compaction the
Ev2 value ratio in Appendix 6/1 has been formation shall be trimmed to
achieved. The relaxation allowed in sub- achieve the tolerances of this sub-
Clause 617.2 shall not apply before this Clause.
time.
2 Where the tolerances in sub-Clause 1
of this Clause are exceeded, the
616 Preparation and Surface Contractor shall determine the full extent
Treatment of Formation of the area which is out of tolerance and
shall make good the formation as
1 The formation shall, after completion follows:
of any subgrade drainage, and
immediately before laying subbase on (i) if the surface is too high it shall be
areas of completed formation, have a re-trimmed and re-compacted in
surface level tolerance within ±20 mm or compliance with Clause 612 and
±25 mm according to table 7.1 of clause sub-Clause 1 of this Clause;
70, or other level of tolerance defined in
Appendix 6/7 relative to its designed (ii) if the surface is too low it shall be
level after completion of the following corrected by the addition of
operations as necessary: acceptable material complying
with Table 6/1 having
(i) Any protection layer shall be characteristics and strength
removed and any soft or damaged matching the overlaid material,
areas shall be rectified by deposited and compacted in
excavating them and replacing compliance with Clause 608 and
with acceptable material having 612 and sub-Clause 1 of this
the same characteristics and Clause. In cohesive materials
strength as the surrounding Classes 2 and 7, where this low
material. The surface of the surface is less than 150 mm below
formation shall be trimmed and formation, material shall be
immediately cleaned free from removed to a depth of at least 150
mud and slurry which shall be mm below formation before the
dealt with as unacceptable material additional material is deposited
Class U1. and compacted.

March 2003 26
Volume 1 Series 600
Specification for Road Works Earthworks

3 After trimming, or re-trimming if 6 The preparation of formation on


necessary, the formation shall be rolled existing sub-base material shall be
with one pass of a smooth-wheeled roller completed as described in Appendix 6/7.
having a mass per metre width of roll not
less than 2100 kg or, a vibratory roller
having a mass per metre width of 617 Use of Sub-formation or
vibrating roll of not less than 700 kg or a Formation by Construction Plant
vibrating plate compactor having a mass
per m² under the base plate of not less 1 Construction plant and other vehicular
than 1,400 kg. traffic (except that required for the
construction of capping) shall not be
4 Where required in Appendix 6/7 or operated on the sub-formation, unless
where the tolerances in sub-Clause 1 of adequate protection, if necessary in
this Clause cannot be achieved in the addition to any weather protection, is
preparation of formation in rock then provided.
one of the following shall be carried out
so as to achieve the above tolerances: 2 Construction plant and other vehicular
traffic (except for that required for
(i) the material shall be excavated preparation of the formation in
below formation to the depth compliance with Clause 616) shall not
described in Appendix 6/7. The be operated on the formation unless
excavated material shall be adequate protection, if necessary in
processed as described in addition to any weather protection is
Appendix 6/7 and re-deposited and provided.
compacted in compliance with
Clauses 608 and 612 and Table 6/4 3 In addition to the requirements of sub-
Method 6 in compacted layers not Clauses 1 and 2 of this Clause, the
greater than 250 mm thick; or Contractor shall make available to the
Overseeing Organisation his proposals
(ii) where the rock surface is tabular it for the protection of the sub-formation or
shall be regulated by depositing formation in areas where they are within
and compacting cement bound 300 mm of the existing ground level,
material as described in Appendix after topsoil has been stripped, before
6/7, complying with the 1000 using construction plant or other
Series, or mix ST1 concrete. vehicular traffic at or above sub-
formation or formation.
5 The Contractor shall limit any areas of
completed formation to suit the output of
plant in use and the rate of deposition of
sub-base. No formation of cohesive
material Classes 2 and 7 shall remain
continuously exposed to rain causing
degradation or be left uncovered 618 Topsoiling, Grass seeding and
overnight. Turfing

March 2003 27
Volume 1 Series 600
Specification for Road Works Earthworks

1 Topsoiling shall be carried out using unless otherwise permitted in


Class 5 material complying with Table Appendix 6/8; and
6/1.
b. dimensions greater than 50
2 Imported topsoil, Class 5B material, mm equivalent diameter
shall only be imported when required in which lie within 50 mm of
Appendix 6/8 or when permitted or the surface;
instructed by the Engineer.
(iii) be graded to smooth contours,
3 When required in Appendix 6/8 topsoil eliminating all mounds and
shall not be excavated from stockpiles, depressions where water may
whether on site or imported: collect;

(i) which have been exposed to a (iv) not have stones or other debris
cumulative rainfall exceeding 100 protruding above the surface by
mm, or other figure stated in more than 30 mm, and comply
Appendix 6/8, over the preceding with the further requirements of
28 days measured at a point Clauses 3004 and 3005.
detailed in Appendix 6/8; or
5. The areas to be grassed shall receive
(ii) when heavy rain is falling; or one of the following treatments as
described in Appendix 6/8:
(iii) with a tracked vehicle.
Volume 1 home page Treatment 1: topsoiled, fertilized and
4 Topsoil shall: seeded Fertilizer and seed may, unless
otherwise stated in Appendix 6/8 be
(i) be deposited and spread on the applied by hydraulic mulch.
areas, to the thicknesses described
in Appendix 6/8, in layers not Treatment II: Topsoiled, fertilized and
exceeding 150 mm. Each layer turfed
shall be firmed before spreading
the next. The thickness shall be Treatment III: Left untopsolied but
reduced where necessary to allow fertilized and seeded by hydraulic
for any subsequent turfing required mulch.
in Appendix 30/5 (it shall not be
spread using a tracked vehicle, 6. Cutting slopes which are to receive
when so stipulated in Appendix Treatment I or II shall:
6/8);
be benched when required in Appendix
(ii) have stones and other debris 6/3 to retain topsoil
removed and disposed off Site
which have: unless otherwise stated in appendix 6/8
or directed by the Engineer, be harrowed
a. dimensions greater than 100 to a depth of 50mm. Such harrowing
mm equivalent diameter, shall be carried out, immediately prior to
topsoiling, diagonally, at an angle

March 2003 28
Volume 1 Series 600
Specification for Road Works Earthworks

between 5° to 45° to the line of the to, evenly distributed and raked
measured on the plane of the slope. in, at a rate not less than 75g
per m² or other rate required
7. Topsoil in treatment I and II shall: in Appendix 6/8 or agreed
with the Engineer. If
(i) be deposited and spread to the hydraulic mulch seeding is
thicknesses described in Appendix used such fertilizer may be
6/8, which thickness shall be incorporated in the mulch
reduced where necessary to allow and no raking in is
for any subsequent turfing required necessary.
in Appendix 6/8 or permitted by
the Engineer it shall not be spread 8. Seeding in Treatment 1 shall:
using a tracked vehicle, when so
stipulated in Appendix 6/8): (i) employ a mixture of seed
complying with sub-clause 14 of
(ii) have stone and other debris this clause and
removed and disposed off site
which have: (ii) be carried out by evenly
distributing such seed at a rate of
a) dimensions greater than not less than 20g/m² for side slopes
100mm equivalent diameter, of both embankments and cuttings
unless otherwise permitted and not less than 10g/m² elsewhere
by the Engineer, and or other rate required in Appendix
6/8 or agreed by the Engineer; and
b) dimensions greater than
50mm equivalent diameter (iii) by immediately followed by
which lie within 50mm of lightly ranking, by use of a chain
the surface. horrow or other plant approved by
the Engineer, the surface of the
(iii) not have stone or other debris topsoil to cover the seeds except
protruding above the saurface by that no ranking is required
moe than 30min and following hydraulic mulch
seeding.
(iv) immediately prior to sowing of
seed, including that applied by 9.Turf in Treatment II shall:
hydraulic mulch and before laying
of turf have: (i) be laid in the areas described in
Appendix 6/8 or in other area as
a) its upper 50mm thickness permitted by the Engineer or
reduced to a fine tilth by use
of a chain harrow or other (ii) consist of class 5C imported turf
plant producing a similar complying with table 6/1 or when
fine tilth; and permitted by the Engineer; turf
arising on Site and required to be
b) fertilizer complying with sub excavated as Class 5 A material;
clause 13 of this clause and

March 2003 29
Volume 1 Series 600
Specification for Road Works Earthworks

requirements in Appendix 6/8. All areas


(iii) be laid well bonded and lightly shall unless permitted otherwise by he
tamped and when on slope be laid Engineer, be left clear of glass cutting
diagonally; and following each mowing, by raking or
other method approved by the Engineer
(iv) where required in Appendix 6/8 be and arising disposed of site.
retained in position by methods
described therein; and 12. At the times (Which may include
times within the period of maintenance)
(v) be regularly watered as necessary and within the area instructed by the
during prolonged dry weather Engineer, a selective herbicide, approved
by the engineer, especially formulated
for the prediction of docks, thistles,
10 Hydraulic mulch seeding shall: ragwort and other pernicious agricultural
weeds shall be applied by spot treatment
(i) be applied by a process and consist spray to such plants individually; the use
of a mulch approved by the of spray boom will not be permitted.
Engineer; and
13 Fertilizer, including where approved
(ii) where required in Appendix 6/8 by the Engineer that incorporated in
have as part of those mulch, glass hydraulic mulch, shall consist of a
fiber or other material to form a compound containing not less than 10%
retaining agent during Nitrogen, 15% Phosphoric Acid and
establishment of swarm growth; 10& Potash and samples shall be
and submitted to the Engineer for approval
prior to its use in the Permanent works.
(iii) for treatment III have as part of the
mulch additional additives for 14. Grass seed, including where
promotion of grass growth on the approved by the Engineer, that
material to be grassed. incorporated in a hydraulic mulch, shall
be tested mixture and certificates of
11 Except on areas not required to be germination and purity shall be provided
mown or to be mown three times all as before sowing, together with the names
described in Appendix 6/8, areas of of the varieties used in the mixture.
grass resulting from treatment I to III Unless otherwise required in Appendix
shall be mown twice to leave a nominal 6/8 or agreed by the Engineer, this shall
75mm height. The first mowing shall be contain the seeds listed in Table 6/6 to
carried out ounce the grass has reached f the proportions therein.
height of between 100mm and 150mm,
the second when it has regrown to
between 150mm and 200mm. The plant
used for mowing shall comply with any

March 2003 30
Volume 1 Series 600
Specification for Road Works Earthworks

Table 6/5: records and Reports – Information Required

Ground Treatment In situ Testing

For each column/area treated: For each area tested:

Date Date
Contract title Contract Title
Area identification Area identification
Unique Grid location Test position, co-ordinates and level
Ground Level at Commencement Method of test used
Material used All information required by appropriate British Standard
Approximate column diameter test procedure
Depth of penetration of each compaction point
Vibrator power compaction during operation
Jetting pressure (where applicable)
Duration of penetration
Duration of compaction
Obstructions and delays
Number of tests carried out

Table 6/6: Grass Seed Mixture per 50kg

Kg %

Perennial Rye Grass 12.5 25


Strong Creeping Red Fescue 10.0 20
Hard Fescue 15.0 30
Smooth-stalked Meadow Grass 5.0 10
Highland Brown top Bent 5.0 10
Huia White Clover 2.5 5

619 Earthwork Environmental Bunds shall be constructed in compliance with


Clauses 2502 and 622.
1 Earthwork environmental bunds shall
be constructed in the locations described 3 Earthwork environmental bunds
in Appendix 6/9 with fill materials formed of strengthened embankments
complying with the requirements therein shall be constructed in accordance with
and Clause 601 and Table 6/1. Clause 621.
Deposition shall be in accordance with
Clause 608 and compaction with the 4 Where required in Appendix 6/9
requirements of Table 6/1 unless earthwork environmental bunds shall be
otherwise described in Appendix 6/9 or top soiled and seeded, or topsoiled and
the requirements of sub- Clauses 2 or 3 turfed, all in accordance with Clause
of this Clause apply. 618.
620 Landscape Areas and Screening
2 Earthwork environmental bunds Mounds
formed of reinforced or anchored earth

March 2003 31
Volume 1 Series 600
Specification for Road Works Earthworks

1 Landscape areas and screening


mounds shall be constructed in the 1 The construction of earthworks for
locations shown in Appendix 6/9 with reinforced soil and anchored earth
Class 4 material as described therein and structures together with assembly and
complying with Table 6/1. erection of reinforcing and anchor
elements and associated components
2 Unless method compaction to Clause shall be in compliance with this Clause
612 is required in Appendix 6/9 the and Clause 2502.
degree of compaction of Class 4 material
shall be sufficient to remove large voids 2 Excavation shall be carried out in
and to produce a coherent mass whilst compliance with Clause 604.
preventing over-compaction and any
build up of excess pore pressures. 3 Fill for reinforced soil structures shall,
except for their associated drainage
3 Following completion of filling of layers, be of Class 6I, 6J, 7C or 7D
landscape areas, and screening mounds selected material complying with Table
Class 4 material shall where required in 6/1 as permitted in Appendix 6/1
Appendix 6/9, be shaped as described together with any other additional
therein. requirements therein.
Volume 1 home page
4 Class 4 material shall be deposited in 4 Fill for anchored earth structures shall,
landscape areas or screening mounds except for their associated drainage
after any adjoining embankment or other layers, be of 6I or 6J selected material
area of fill has been completed. Where complying with Table 6/1 as permitted
permitted in Appendix 6/9 and provided in Appendix 6/1 together with any other
the adjoining embankment or other area additional requirements therein.
of fill is always kept at least 1 m higher
than the landscape area fill, construction 5 Drainage layers to reinforced soil and
of such landscape area may proceed until anchored earth structures shall be one of
completion. the following as appropriate:

5 Landscape areas and screening (i) Class 6H material complying with


mounds shall be topsoiled and seeded or Table 6/1 and Appendix 6/1.
turfed in accordance with Clause 618 to
the requirements of Appendix 6/9. (ii) Type B filter drain material
complying with Clause 505 for use
621 Strengthened Embankments only in horizontal drainage layers.
Vertical layers of drainage layer
1 Strengthened embankments shall be material shall be brought up at the
constructed in the locations and to the same rate as the adjoining fill
details described in Appendix 6/9 with material without mixing or
fill materials and strengthening materials contamination.
described therein.
6 In addition to the requirements of sub-
622 Earthworks for Reinforced Earth Clauses 7 and 8 of this Clause, fill for
and Anchored Earth Structures reinforced earth and anchored earth

March 2003 32
Volume 1 Series 600
Specification for Road Works Earthworks

structures shall be deposited and sub- Clause 612.10 and listed in


compacted in compliance with Clauses Table 6/4:
608 and 612 and Table 6/1. Drainage
layer material other than Class 6H shall a. vibratory roller having a
be deposited in accordance with Clause mass per metre width of roll
608 and compacted as described in not exceeding 1,300 kg with
Appendix 6/3. a total mass not exceeding
1,000 kg;
7 Reinforced earth and anchored earth
structures shall have: b. vibrating plate compactor
having a mass not exceeding
(i) the deposition and compaction 1,000 kg;
carried out so that all layers of
reinforcing and anchor elements c. vibro tamper having a mass
are fixed at the required levels on not exceeding 75 kg;
top of compacted fill;
(vi) at the Contractor’s option, the
(ii) the deposition, spreading, leveling reinforced earth and anchored
and compaction of the fill carried earth fill beyond the 2 m zone
out generally in a direction parallel referred to in (v) above, raised in
to the facing and executed in thicker layers than within the 2 m
stages to alternate with the placing zone, providing this is compatible
and fixing of the reinforcing and with the arrangement of the
anchor elements and the facing reinforcing and anchor elements
elements; and the difference in compacted
level does not exceed 300 mm;
(iii) the reinforcing and anchor
elements kept as free as possible (vii) during construction of the
from damage or displacement reinforced earth or anchored earth
during deposition, spreading, structure the retained fill at the rear
leveling and compaction of the fill of the structure, as defined in sub-
(also the programme of filling Clause 8 of this Clause,
shall be arranged so that no maintained at the same level as the
machines or vehicles run on the adjoining reinforced earth or
reinforcing or anchor elements); anchored earth fill;

(iv) all construction plant, and all other (viii) if the retained material at the rear
vehicles, having a mass exceeding of the reinforced soil or anchored
1,000 kg, kept at least 2 m away earth structure, as defined in sub-
from the back of the facing; Clause 8 of this Clause, is an
existing earthwork or natural slope
(v) within 2 m of the back of the which requires supporting by
facing, the plant used for temporary shoring, this shoring
compacting the fill restricted to the shall be removed progressively as
following items as described in the work proceeds to prevent the
formation of voids.

March 2003 33
Volume 1 Series 600
Specification for Road Works Earthworks

material which shall be uncompacted) be


8 The rear of the reinforced soil or end-product compacted in compliance
anchored earth structure is the position with Clause 612 and Table 6/1, except
coinciding with the ends of the that the compacted layers shall not
reinforcing or anchor elements furthest exceed 150 mm thickness. The
from the facing units. compaction and testing requirements for
Class 6K lower bedding and Class 6M
surround materials shall also comply
623 Earthworks for Corrugated Steel with any additional requirements given
Buried Structures in Appendix 6/3.

1 The construction of earthworks for 5 Class 6K lower bedding material shall


corrugated steel buried structures have its top surfaced shaped during
together with assembly and erection of compaction to match the steel structure
their components shall be in compliance profile. A uniform layer of
with this Clause and Clause 2501. uncompacted Class 6L upper bedding
material, shall be deposited, before the
2 Excavation shall be carried out in placing of any part of the steel structure,
compliance with Clause 604 and any over the whole width of the shaped
additional requirements given in lower bedding material and shall be of
Appendix 6/3. sufficient depth to fill the corrugations of
Volume 1 home page the underside of the structure.
3 Fill for corrugated steel buried
structures shall be of the following 6 Class 6M surround material shall be
selected granular materials complying used for filling all excavations above the
with Table 6/1: bedding, except those in hard material
for which Class 6K lower bedding
(i) Lower bedding material Class 6K. material shall be used throughout.
Additional requirements for making
(ii) Upper bedding material Class 6L. good are given in Clause 604.

(iii) Surround material Class 6M and 7 Class 6M surround material shall be


the overlying fill shall be one of deposited and compacted uniformly on
the following: either side of the structure. The
maximum difference in fill level on
(iv) Well graded, uniformly graded or opposite sides of the structure shall be
coarse, granular material Class 6Q. no more than 250mm at all times unless
otherwise permitted in Appendix 6/3.
(v) Wet, dry, stony or silty cohesive
material. 8 Class 6M surround material shall be
deposited and compacted in accordance
4 In addition to the requirements of sub- with sub-Clause 4 of this Clause, above
Clauses 5 to 14 of this Clause, Class 6K, the concrete foundations of arch-profile
6L and 6M materials shall be deposited corrugated steel buried structures.
in compliance with Clause 608 and shall
(except for Class 6L upper bedding

March 2003 34
Volume 1 Series 600
Specification for Road Works Earthworks

9 Class 6M surround material under the shall not deviate by more than 25 mm,
structure shall be well compacted by and the rotational displacement in any 10
hand using a suitably sized pole or m length of structure shall not be greater
length of rectangular timber between the than 25 mm.
corrugations, or by another suitable
method. 13 Only that compaction plant described
in sub-Clause 10 of this Clause, shall be
10 Plant for compaction of Class 6M used in the vicinity of the structure
surround material within 1 m of either unless the depth of compacted Class 6M
side of the structure and up to a height of surround material placed above the
1 m, or one fifth of the span if greater, crown of the structure is more than 1 m,
above the crown, shall be restricted to or one fifth of the span, whichever is the
the following items, as described in sub- greater. The structure shall not be
Clause 612.10 and listed in Table 6/4: subjected to a surcharge greater than the
depth of fill required in the Contract and
(i) vibratory rollers having a mass per permitted depth of any protection layer
metre width of roll not exceeding given in Appendix 6/3.
750 kg;
14 No material shall be placed by
(ii) vibrating plate compactors having tipping either onto the structure or within
mass not exceeding 750 kg; a distance on either side of the structure
of 2 m or half the span of the structure,
(iii) vibro-tampers. whichever is the greater.

11 Fill placed above the level of the 15 Method compaction shall be used for
crown of the structure, including Class the overlying fill (Classes 6Q and 7H)
6M surround material, shall be according to Clause 612; the method
deposited, spread and compacted in such used being that for the corresponding
a manner that any out of balance forces generalfill in Table 6/1.
transmitted to the culvert are kept to a Volume 1 hom
minimum. This will require that
trafficking by construction plant is not 624 Ground Anchorages
all in one direction and that the
compacted surface of the fill is kept as 1 The Contractor shall design the ground
near horizontal as practicable. anchorages required as part of the
Permanent Works and listed in
12 During all operations of filling, Appendix 1/11, in accordance with the
compaction, road pavement construction design requirements described in
and of any other traffic movements Appendix 6/10. The ground anchorages
which affect the shape of the structure, shall be installed and where required in
the changes in the horizontal and vertical Appendix 6/10 proof loaded, in
diameters of the structure shall not accordance with the requirements
exceed ± 5% for circular structures and therein.
± 2% for structures of other cross-
sections. The longitudinal straightness 2 Ground anchorages not forming part of
over any 10 m length of the structure the Permanent Works will only be

March 2003 35
Volume 1 Series 600
Specification for Road Works Earthworks

permitted where such anchorage will not minimum core diameter of 2.0
affect the Permanent Works. mm, unless otherwise described in
Appendix 6/10.

625 Crib Walling (ii) A geomesh, being a grid of plastic


material suitable for use in
1 The Contractor shall design the crib earthworks, having the properties
walling listed in Appendix 1/10 in described in Appendix 6/10.
accordance with the design specification
and procedures in Appendix 6/10 and 4 All wire shall be galvanized in
Standard BD 68. compliance with BS 443 and be coated
with a minimum thickness of 0.55 mm
of PVC for extruded coatings and 0.25
626 Gabions mm of PVC for bonded coatings. The
PVC shall be capable of resisting the
1 Gabions shall be constructed in effects of immersion in sea water,
compliance with this Clause and with exposure to ultra violet light and
any additional requirements in Appendix abrasion, when tested for a period not
6/10. less than 3000 hours in accordance with
BS 2782 : Part 5 : Method 540B (ISO
2 Gabion units shall be assembled in 4892).
accordance with the manufacturer’s
instructions and shall be sufficiently 5 The size of mesh openings and grading
filled with Class 6G material complying of fill shall be as described in Appendix
with Table 6/1 and any other 6/10, but the maximum size of fill
requirements in Appendix 6/1, with an material shall not exceed two thirds of
allowance for consolidation of fill, so as the minimum dimension of the gabion
to minimize distortion during compartment or 200 mm whichever is
construction. Gabion units shall, where smaller and the minimum size of the fill,
appropriate, be maintained square and unless otherwise stated in Appendix
with vertical sides during filling. Internal 6/10, shall be not less than the size of the
tie wires shall be inserted and units shall mesh opening.
be tensioned in accordance with the
manufacturer’s instructions. Gabion 6 Mechanical equipment may only be
units shall be constructed so as to used for filling gabion units provided
maintain tightness of mesh and that the results are equivalent to filling
shall be laced securely with wire, by hand.
complying with sub-Clause 3(i) of this
Clause.

3 The gabion mesh shall be one of the


following unless otherwise described in
Appendix 6/10:

(i) A mesh manufactured from wire 627 Swallow Holes and Other
complying with BS 1052 having a Naturally Occurring Cavities

March 2003 36
Volume 1 Series 600
Specification for Road Works Earthworks

Dynamic Compaction
1 Infilled swallow holes and other
naturally occurring cavities shall where 1 Dynamic compaction, carried out to
required in Appendix 6/11 be excavated, either method or end-product as required
filled and capped as described in in Appendix 6/13 and achieved by
Appendix 6/11. dropping a free-falling heavy mass
(pounder) a number of times at pre-
2 Open swallow holes and other shallow determined spacing on the surface of the
cavities shall where required in ground or fill, shall be applied to the
Appendix 6/11 be flushed, cleared of areas described in Appendix 6/13.
rubbish where to do so would not
endanger operatives, and filled and 2 Dynamic compaction shall be
capped as described in Appendix 6/11. completed before the commencement of
construction of any Permanent Works, or
work on the placement or diversion of
628 Disused Mine Workings Statutory Undertaker’s equipment,
within that part of the Site defined in
1 Disused mine workings shall, where Appendix 6/13 which contains the area
required in Appendix 6/11 be to be dynamically compacted.
investigated, inspected, monitored,
cleared, flushed, filled, capped or have 3 The Contractor shall ensure that no
any other treatment carried out, all as damage or injury is caused to persons or
described in Appendix 6/11. property on or off the Site as a result of
the dynamic compaction.

629 Instrumentation and Monitoring Vibrated Stone Columns

1 Instrumentation, other than that 4 Vibrated stone columns in existing


required in compliance with Clause 607, natural soils or fill by vibro replacement
shall be as described in Appendix 6/12 or vibro displacement shall be formed in
and shall be installed in the locations the manner and in the areas described in
shown therein. Appendix 6/13.

2 Monitoring of instrumentation shall be 5 Unless otherwise described in


carried out as required in Appendix 6/12 Appendix 6/13, materials shall comply
and the results supplied to the with the Series 600 and the Series 800 as
Overseeing Organisation as required appropriate.
therein.
6 The Contractor shall report
Volume 1 ho immediately to the Overseeing
Organisation any circumstance which
indicates that in the Contractor’s opinion
the ground conditions differ from those
expected from his interpretation of the
630 Ground Improvement ground investigation reports.

March 2003 37
Volume 1 Series 600
Specification for Road Works Earthworks

7 Columns shall be installed as shown 12 Plate bearing tests are loading tests
on the Drawings and within the carried out using a plate on treated
permitted tolerances stated in Appendix ground. The test is described in BS 1377
6/13. : Part 9 : 1990 Method 4.1.

Materials Zone Tests

8 The material used to form the columns 13 Zone tests are loading tests carried
shall be clean, hard, inert material and out with a slab, intended to test bearing
shall be sand, crushed rock, crushed pressure over a wider and deeper zone
hardcore or crushed concrete. The than in the plate tests. The test is
material shall be appropriate to the described in BS 1377: Part 9: 1990
ground conditions in which the stone Method 4.2.
columns are formed and its use shall not
be detrimental to any other work on site. Penetration Tests
The material shall be nominally single 14 In granular soils the static cone
sized within the range 20 mm to 75 mm (Dutch cone) penetration test, the
or a graded material complying with standard penetration test (SPT) or
Clause 804 (granular sub-base type 2) dynamic cone penetration tests shall be
except the material passing the BS employed as described in Appendix
425ìm sieve shall be non-plastic when 6/13.
tested in accordance with BS1377: Part
2. Trial Areas

Testing of Ground Treatment 15 Trial areas are to be treated and tested


where required in Appendix 6/13. Trial
9 Testing of treated ground shall be areas, which meet the performance
undertaken for control purposes during requirements, may form part of the
the treatment and on completion of the Permanent Works.
ground treatment. The performance
criteria for treated ground are given in 16 Equipment and materials used in trial
Appendix 6/13. areas shall be identical to those proposed
for the Permanent Works.
10 Improvement in treated ground shall
be measured in accordance with the 17 Testing in trial areas shall be carried
criteria stated in Appendix 6/13. out as given in Appendix 6/13.

Types of Test 18 Detailed reports shall be prepared for


all testing as defined in Table 6/6.
11 The following tests or alternatives
permitted in Appendix 6/13 shall be
carried out at the positions and
frequency given in Appendix 6/13.
Records and Reports
Plate tests

March 2003 38
Volume 1 Series 600
Specification for Road Works Earthworks

19 Complete records of plant, equipment 3 Where permitted in Appendix 6/1 the


and materials shall be maintained during rapid assessment procedure for material
all ground treatment operations. acceptability also given in BS 1377 :
Part 4 may be used.
20 Records shall be made available to
the Overseeing Organisation including
all information identified in Table 6/6
and any other information required by
Appendix 6/13. All records pertaining to
a particular day’s operations shall be
made available to the Overseeing
Organisation at the start of the following 633 Determination of Undrained
day’s operations. Shear Strength of Remolded Cohesive
Material
Other Methods
1 Where required in Appendix 6/1, the
21 Other methods of ground undrained shear strength of cohesive soil
improvement shall be carried out where under total stress conditions shall be
required in Appendix 6/13 and as determined from triaxial compression
described therein. tests performed on remolded specimens
and tested under conditions where the
lateral pressure is maintained constant
631 Earthworks Materials Tests and there is no change in total water
content of the specimens. Unless
1 Unless otherwise described in the otherwise required in Appendix 6/1, the
Contract sampling and testing of tests shall be in accordance with BS
earthworks materials shall be carried out 1377 : Part 7 and the additional
in accordance with BS 1377: Part 1 to requirements of sub-Clauses 2 to 4 of
Part 9 inclusive. this Clause.

2 The specimens shall be prepared in


632 Determination of Moisture accordance with BS 1377 : Part 7 using
Condition Value (MCV) of remoulded material compacted into a
Earthworks Materials split mould of nominal diameter 100 mm
and nominal height 200 mm. The soil
1 Where the Moisture Condition Value shall be at its natural moisture content
(MCV) is to be determined, the and compacted in accordance with BS
determination shall be carried out in 1377: Part 1 using the 2.5 kg rammer
accordance with BS 1377: Part 4. method described in BS 1377 : Part 4.

2 The determination of the 3 The specimens shall be tested at an


MCV/moisture content relation in operating cell pressure of 200 ± 10
accordance with BS 1377: Part 4 shall be kN/m² and an axial strain rate of 1% per
carried out when required in Appendix minute. Where Appendix 6/1 requires c
6/1. and φ to be determined, the test shall be

March 2003 39
Volume 1 Series 600
Specification for Road Works Earthworks

modified to enable Mohr circles to be otherwise required in Appendix 6/1, the


plotted and φ reported. tests shall be in accordance with the
requirements in sub-Clauses 2 to 6 of
4 Where stated and described in this Clause.
Appendix 6/1, other tests may be used
during construction to supplement the Shear Box Tests
test described above, provided the results
have been correlated to ensure 2 For Classes 6N, 6P, 6I and 6J granular
compatibility. materials, the tests shall be carried out in
accordance with BS 1377 : Part 7 and
the following:

634 Not Used (iii) The plan size of the shear box shall
be nominally 300 mm square.

635 10% Fines Value and Other Tests (iv) Three samples shall be tested, each
for Particle Soundness sample occupying the full depth of
the shear box and shall be
10% Fines Value (TFV) compacted at the optimum
moisture. content to a dry density
1 The 10% fines value shall be the value of 92% ± 2% of the maximum dry
determined in accordance with BS 812: density determined in accordance
Part 111 with samples tested in a soaked with BS 1377 : Part 4 using the
condition. vibrating hammer method. The
samples shall not be immersed in
Other Tests for Particle Soundness water.

2 Where Appendix 6/1 requires (v) Each of the samples shall be


magnesium sulfate soundness tests to be subjected to a different normal
carried out, they shall be carried out in stress equal to the maximum
accordance with BS 812 : Part 121. vertical pressure in the fill at the
Where Appendix 6/1 requires slake base, quarter height and mid-
durability, point load or other tests for height of the structure respectively.
soundness to be carried out, they shall be Each of the samples shall be
carried out in accordance with the sheared in a single stage test
procedures given therein. within one hour of compaction and
the rate of shearing shall be such
that no pore water pressure is
636 Determination of Effective Angle generated.
of Internal Friction (φ) and Effective
Cohesion (c) of Earthworks Materials (vi) The values of φ reported shall be
those corresponding to the
1 The effective angle of internal friction maximum strength envelope.
φ effective cohesion shall be determined
by shear box or triaxial tests as required 3 For Classes 7A, 7C and 7D cohesive
in Table 6/1 and Appendix 6/1. Unless materials, the tests shall be carried out in

March 2003 40
Volume 1 Series 600
Specification for Road Works Earthworks

accordance with BS 1377 : Part 7 and used for the subsequent quality
the following: control of the fill.

(i) The shear boxes shall be nominally Triaxial Tests


300 mm square and nominally 60
mm square. 4 Where Class 7A cohesive fill to
structures is to be tested by a
(ii) For the initial determination of fill consolidated drained triaxial test, the test
properties three samples shall be shall be in accordance with BS 1377 :
tested in each size of shear box. Part 8 using the sample size and
The samples shall occupy the full preparation procedure in Clause 633 and
depth of the shear box and shall be the requirements of Appendix 6/1.
compacted at the optimum
moisture content to a dry density 637 Determination of Resistivity (rs) to
of 92% ± 2% of the maximum dry Assess Corrosivity of Soil, Rock or
density determined in accordance Earthworks Materials
with BS 1377 : Part 4 using the 4.5
kg rammer method. To allow the Method of Test
samples to soften, the shear box
assembly shall then be immersed 1 Where the resistivity of the ground or
in water for a minimum period of of material to be used in the Permanent
24 hours. Works is required to be determined, this
shall be obtained by in situ tests as
(iii) Each of the three samples in a set described in sub-Clause 2 of this Clause
shall be subjected to a different or, when required in Appendix 6/1, by
effective normal stress equal to the laboratory tests on samples in
maximum vertical pressure in the accordance with BS 1377 : Part 3.
fill at the base, quarter height and
mid-height of the structure In Situ Resistivity Tests
respectively. Normal stresses shall
be applied to the softened sample 2 In situ resistivity shall be determined
for a minimum period of 24 hours at the site of the structure or the cutting
prior to shearing in a single stage or the proposed borrow pit or on
test. The rate of shearing shall be stockpiles in accordance with BS 1377 :
such that no pore water pressure is Part 9 and the requirements of Appendix
generated. 6/1.

(iv) The values of cand reported shall 3 Details of the area and volume of
be those corresponding to the material to be tested shall be made
maximum strength envelope. available to the Overseeing Organisation
together with the arrangement of
(v) The test results obtained using the electrodes in each test. The Overseeing
300 mm square box shall be taken Organisation shall be given notice of the
as the properties of the fill. The date, time and location of each test.
initial test results obtained using
the 60 mm square box shall be

March 2003 41
Volume 1 Series 600
Specification for Road Works Earthworks

4 At any test location, at each selected required in Appendix 6/1, by laboratory


depth, two measurements shall be made tests on samples in accordance with BS
such that the electrode alignment for the 1377: Part 3.
second measurement is approximately at
right angles to the electrode alignment In Situ Redox Potential Tests
for the first measurement.
2 In situ redox potential shall be
5 At any test location, the first selected determined in undisturbed ground at the
depth shall be no more than 1.5 m below site of the cutting or the proposed
the ground surface or no more than 1.5 borrow pit or on stockpiles in
m below the upper surface of the accordance with BS 1377 : Part 9 and
material to be tested, whichever is the requirements of Appendix 6/1.
appropriate. Following the
measurements at the first selected depth, 3 Details of the area and volume of
further measurements shall be made at material to be tested shall be made
selected depths increasing by available to the Overseeing Organisation
approximately 2 m each time until together with the locations of the test
measurements have been carried out on pits.
the full depth of ground or material to be
tested. 4 The Overseeing Organisation shall be
given notice of the date, time and
6 Where the depth of material to be location of each test.
tested is too great to be tested from the
surface within the confines of the Site, 5 At each test location the tests shall be
the Contractor shall undertake all carried out in a test pit not less than 600
necessary arrangements for testing such mm square in plan excavated to a depth
material, including subsequent tests given in Appendix 6/1.
which may be required at a lower level
following excavation. Details of his 6 At each test location, a sample shall be
arrangements shall be made available to taken from the base of the excavation
the Overseeing Organisation. and kept in a hermetically sealed
container for determining the pH value
of the fill which shall be obtained in
638 Determination of Redox Potential accordance with BS 1377 : Part 3.
(Eh) to Assess Corrosivity of
Earthworks Materials for Reinforced
Soil and Anchored Earth

Structures Method of Test

1 Where the redox potential of material


to be incorporated into reinforced earth
or anchored earth structures is required
to be determined, this shall be obtained
by in situ tests as described in sub-
Clauses 2 to 6 of this Clause or, when

March 2003 42
Volume 1 Series 600
Specification for Road Works Earthworks

639 Determination of Coefficient of


Friction and Adhesion Between Fill A sample of the fill material to be used
and Reinforcing Elements or Anchor in the Permanent Works, of sufficient
Elements for Reinforced Soil and size to carry out the tests, and within the
Anchored Earth Structures range of moisture contents permitted in
Table 6/1 for such material, shall be
Reinforcing Elements sieved to obtain a test sample passing the
20 mm BS sieve, of sufficient quantity
1 The coefficient of friction and the after compaction to fill the top half of
adhesion shall be determined by tests the shear box. The top and bottom of the
carried out in a 300 mm size shear box shear box shall be fixed together and the
with the element material fixed at the top test sample of the sieved fill materials
of the lower half of the box and the fill immediately placed and compacted in
sample occupying the top half only. the top half of the box as described in
Clause 636.
2 The test shall be carried out following
the procedure given in Clause 636 for 3 The value of the coefficient of friction
the determination of the effective angle between the fill and the reinforcing
of internal friction and effective element shall be obtained by plotting the
cohesion of earthworks materials except values of peak shear stress, obtained in
that: the tests, against applied normal stress
and by measuring the slope of the
(i) The apparatus shall in addition resulting straight line graph. The
include a steel block fitting closely adhesion between the fill and the
inside the lower half of the shear reinforcement shall be obtained by
box and equal in height to it less taking the shear stress corresponding
the thickness of the reinforcing with zero normal stress.
element material. (The flat toothed
grid fitting the bottom of the shear 4 The following additional information
box is not required). shall be recorded for each test:

(ii) The preparation of test specimens (i) Normal stress applied (kN/m²).
shall be as follows:
(ii) Peak shear stress (kN/m²).
Element material shall be cut to fit the
interior plan shape of the shear box (iii) Strain at peak shear stress (%).
using a sufficient number of strips of
such material abutting to completely fill (iv) Moisture content of fill after test
the interior plan area without overlap. (Classes 7C and 7D).
They shall be firmly fixed to the top of
the steel block so that the top face of the Anchor Elements
material is flush with the top edge of the
lower half of the box and aligned so that 5 Where required in Appendix 6/1, tests
shearing occurs in a direction parallel to shall be carried out as described therein
the longitudinal axis of a reinforcing to assess the interaction between the fill
element. and the element.

March 2003 43
Volume 1 Series 600
Specification for Road Works Earthworks

(ii) From the results of Standard


Penetration resistance tests (SPT)
640 Determination of Permeability of on non-cohesive materials in
Earthworks Materials accordance with BS 1377: Part 9.

1 Where required in Table 6/1 or (iii) From the values of the coefficient
Appendix 6/1 the permeability of of volume compressibility (Mv)
earthworks materials shall be determined from one-dimensional
as described in Appendix 6/1. consolidation tests on undisturbed
soil specimens of cohesive
materials, in accordance with BS
641 Determination of Available Lime 1377: Part 5.
Content of Lime for Lime Stabilised
Capping Plate Loading Tests

1 The available lime content of lime for 2 When testing compacted granular fill
lime or lime and cement stabilised materials the test surface shall be
capping to be determined on Site shall prepared by either:
be carried out as described in BS 6463:
Part 1 except that the sample increments (i) removing the surface layer
shall be taken from the collecting tray carefully using hand tools to
used to check the rate of spread at perform the test at a depth of 100
intervals of one increment per 500 m. mm below the surface; or

2 The available lime content shall be (ii) compacting the surface, after the
determined as calcium oxide in required compaction has been
accordance with BS 6463: Part 2, applied, with two additional passes
Method 20, and the results reported as: with no vibration to remove the
Available lime (as CaO) = ......% by overstressing in the surface layer.
mass. If necessary, the plate shall be
bedded onto the fill using a small
quantity of dry sand to remove any
642 Determination of the Constrained slight unevenness of the surface of
Soil Modulus (M*) of Earthworks the fill. The field dry density and
Materials for Corrugated Steel Buried moisture content shall be
structures General determined at the position of each
plate loading test in accordance
1 When required in Appendix 6/1, the with Clause 612 and BS 1377 :
constrained soil modulus M* shall be Part 2 or equivalent, respectively.
determined by one of the following
methods: 3 When using the plate loading test to
determine M* of the material existing on
(i) From plate loading tests in site a smooth surface shall be prepared
accordance with BS 1377: Part 9. by careful hand excavation and the plate
bedded onto the soil using either sand or
quick setting gypsum plaster depending

March 2003 44
Volume 1 Series 600
Specification for Road Works Earthworks

on whether the soil is granular or shall be determined from the


cohesive. relationship:

4 The loading test shall be carried out 0.39N1.4


under a series of maintained loads. The M* = ____________ (N/mm²)
maximum load should be such that the γm
average pressure applied to the plate is
in excess of 350 kN/m². The elastic Where N = uncorrected SPT value and
modulus Es shall be determined as the m = 1.3
secant modulus between average
pressures applied to the plate of 150 and One-dimensional Consolidation Tests
350 kN/m² in the first load cycle. A
value of Poisson’s ratio of 0.3 shall be 7 The constrained soil modulus M* of
assumed. A second load cycle testing undrained cohesive materials existing on
shall also be conducted and the results of site shall be determined from the
this test compared with the first load formula:
cycle. 1
M* = ______ (N/mm²)
Generally a maximum load of mv
500KN/m² will be applied and the elastic
modulus determined between pressures where mv (mm²/N) is the coefficient of
of 0.3 x maximum load and 0.7 x volume compressibility The value of mv
maximum load: to be used in the formula is that
calculated from the test results for the
E= 1.5 x 0.3m x ∆T loading increment in the consolidation
∆S test corresponding to the in situ effective
overburden pressure at the level of the
It is preferred to determine Ev by a crown of the structure.
polynom.
Number of Tests
5 The constrained soil modulus M* shall
be determined from the elastic modulus 8 Three tests for M* shall be carried out
Ev using the equation: on the soil occurring on each side of the
structure, one of which is to be at the
(1 - v)Ev level of the maximum span, unless
M* = ___________________ (N/mm²) otherwise described in Appendix 6/1.
(1 + v)(1 - 2v)

where v = Poisson’s ratio to be taken as 643 Lime and Cement Stabilization to


0.3 and Es = Elastic modulus of the soil Form Capping
(N/mm²)
1 Where capping is to consist of, either
Standard Penetration resistance Tests wholly or in part, lime and cement
stabilized material Class 9E or 9F, this
6 The constrained soil modulus M* of Clause shall apply to the construction of
non-cohesive materials existing on site

March 2003 45
Volume 1 Series 600
Specification for Road Works Earthworks

those parts which are stabilized with 7 The Contractor shall not carry out lime
lime and cement. and cement stabilization when the shade
temperature is below 3°C unless on a
2 Material to be stabilized with lime and rising thermometer above 0°C. Lime and
cement shall be Class 6R or 7I material cement stabilization shall not be carried
all complying with Clause 601 and Table out during periods of rain or when rain is
6/1. imminent. When cement is spread on
material likely to cause premature
3 Lime for lime and cement stabilization hydration, processing in accordance with
shall, as required in Appendix 6/7, be sub-Clause 16 of this Clause shall follow
either quicklime or hydrated lime immediately.
complying with BS890. Quicklime shall
when sieved have 100% passing a BS 10 8 Lime of quantity complying with sub-
mm sieve and at least 95% by mass Clause 6 of this Clause shall be
passing a BS 5 mm sieve. uniformly spread by an approved
spreading machine on top of the layer to
4 The Contractor shall make available to be stabilized. Using a collecting tray and
the Overseeing Organisation for each balance the Contractor shall check the
source of lime a report of a chemical rate of spread by weight, once for every
analysis for ‘available lime’ made in 500 m² of lime spread or a different rate
accordance with sub-Clause 641.2. Such of testing for the rate of spread as
reports shall be submitted to the described in Appendix 6/7. At the same
Overseeing Organisation prior to the time the Contractor shall collect samples
incorporation of lime in the Permanent of lime deposited on the tray and test
Works at weekly or other intervals them for available lime content in
defined in Appendix 6/7 during periods accordance with Clause 641.
when lime and cement stabilization is
carried out. 9 Unless indicated otherwise in
Appendix 6/7, the material shall be
5 Cement for lime and cement stabilized in a single layer if its
stabilization shall be Portland cement compacted thickness is 250 mm or less.
complying with Clause 1001, unless If its compacted thickness is greater, the
otherwise described in Appendix 6/7. material shall be stabilized in layers not
less than 130 mm and not more than 250
6 Classes 6R and 7I material to be mm thick, including any cutting-in
stabilized shall have added to it, at any required by sub-Clause 13 of this
point, the percentage of its dry weight of Clause.
lime and cement as determined on the
demonstration area, to meet the required 10 Unless indicated otherwise in
bearing ratio in Appendix 6/1, subject to Appendix 6/7, the material forming the
a minimum of 1% by weight of layer to be stabilized shall be processed
‘available lime’ and 2% cement as a by pulverising and mixing in the lime by
percentage of the dry weight of the 6R means of sufficient number of passes of
and 7I materials. an approved mobile stabilizing machine
until 95% of the Class 9E or 95% of the
silt and clay fraction of Class 9F

March 2003 46
Volume 1 Series 600
Specification for Road Works Earthworks

processed material passes a BS 28 mm spreading machine, on top of the layer


sieve after dry sieving and the previously processed with lime. Using a
pulverisation complies with Table 6/1. collecting tray and balance the
Contractor shall check the rate of spread
11 During processing only sufficient of the machine once for every 500 m² of
water shall be available in the material to cement spread.
slake the quicklime (if used) and to
enable satisfactory mixing and 15 Unless indicated otherwise in
compaction to be achieved. Any added Appendix 6/7, the material previously
water shall be through an integral spray- mixed with lime shall be stabilized with
bar on the stabilizing machine. cement in a single layer or in layers of
the same compacted thickness as for the
12 The layer shall receive at least two lime mixed material layers, including
passes of the stabilizing machine to any cutting-in required by sub-Clause 13
pulverise and mix the lime and soil, after of this Clause.
which the processing shall be interrupted
by a period of not less than 24 hours and 16 Unless indicated otherwise in
not greater than 72 hours to enable the Appendix 6/7, the material forming the
lime to react with the soil. Before this layer to be stabilized shall be processed
period commences the surface of the by pulverising and mixing in the cement
layer shall be sealed with one pass of a by means of a sufficient number of
smooth wheeled roller having a mass per passes of an approved mobile stabilizing
metre width of roll of not less than 2700 machine until 95% of the silt and clay
kg or a pneumatic tyred roller of not less fraction is reduced to particles or lumps
than 1000 kg per wheel. At the end of passing a BS 28 mm sieve after dry
this period the layer shall receive one sieving and the pulverization complies
further pass of the stabilizing machine or with Table 6/1.
more if required to enable the material to
comply with sub-Clauses 10 of this 17 During processing, only sufficient
Clause. water shall be available in the material to
hydrate the cement and enable
13 The stabilizing machine shall be satisfactory mixing and compaction to
equipped with a device for controlling be achieved. Any added water shall be
the depth of processing which shall be through an integral spray-bar on the
maintained at the correct setting at all stabilizing machine.
times. An overlap of 150 mm shall be
made between adjacent passes of the 18 The stabilizing machine shall be
stabilizing machine. Where a subsequent equipped with a device for controlling
layer of material is placed on a layer the depth of processing which shall be
previously stabilized the tines or blades maintained at the correct setting at all
of the stabilizing machine shall be set so times. An overlap of 150 mm shall be
that they cut into the previously made between adjacent passes of the
stabilized layer below by at least 20 mm. stabilizing machine. Where a subsequent
layer of material is placed on a layer
14 The appropriate quantity of cement previously stabilized the tines or blades
shall be uniformly spread, by a suitable of the stabilizing machine shall be set so

March 2003 47
Volume 1 Series 600
Specification for Road Works Earthworks

that they cut into the previously allowed in sub-Clause 617.2 shall not
stabilized layer below by at least 20 mm. apply before this time.

19 Each layer of Class 9E or 9F Volume 1 home page


processed material shall be compacted as
soon as possible after the final pass of
the stabilizing machine. Compaction
shall be completed within 2 hours
following the mixing of the cement into
the material to be stabilized.
Immediately before compaction Class
9E processed material shall have a
Moisture Condition Value (MCV) of not
greater than 12 nor less than the figure
stated in Appendix 6/1 both as
determined in accordance with Clause
632. Water shall be added if necessary in
a uniform manner to enable this MCV
requirement to be met.

20 The compaction of each layer of


Class 9E or 9F material shall comply
with Clause 612, Table 6/4 Method 7,
except that if layers of Class 9E or 9F
greater than 250 mm thickness are to be
constructed, the number of passes of the
compaction plant shall be determined
from the results of a demonstration area
as detailed in Appendix 6/7.

21 Class 9E and 9F materials shall be


cured in accordance with Clause 1035.
During periods when the air temperature
is forecast to drop below 3°C or when
ground frost is forecast Class 9E and 9F
material shall be protected, to prevent
freezing, for a period of 7 days from the
time of completion of compaction. Such
protection shall be sealed to prevent the
ingress of moisture.

22 Class 9E and 9F materials shall not


have other material deposited or
compacted above them until such time as
the required bearing ratio in Appendix
6/1 has been achieved. The relaxation

March 2003 48
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 49
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 50
Volume 1 Series 600
Specification for Road Works Earthworks

pulverized fuel ash


cohesive material
Not available in
Reclaimed

Malta

March 2003 51
Volume 1

March 2003
Specification for Road Works

Not available
in Malta
Series 600
Earthworks

5 C - Imported turf Turfing Material Complying with BS 3969 - - - - - 5 C -

52
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 53
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 54
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 55
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 56
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 57
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 58
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 59
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 60
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 61
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 62
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 63
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 64
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 65
Volume 1 Series 600
Specification for Road Works Earthworks

Not available
in Malta

March 2003 66
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 67
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 68
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 69
Volume 1 Series 600
Specification for Road Works Earthworks

cohesive material
conditioned PFA

(Not available in
Selected

Matla

March 2003 70
Volume 1 Series 600
Specification for Road Works Earthworks

Not available
in Malta

March 2003 71
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 72
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 73
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 74
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 75
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 76
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 77
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 78
Volume 1 Series 600
Specification for Road Works Earthworks

March 2003 79

Vous aimerez peut-être aussi