Académique Documents
Professionnel Documents
Culture Documents
A H Chowdhury
Professor, EEE, BUET
Table of Contents
2
2
Substation Reliability Evaluation Methods
• Fault tree analysis build a diagram of all elements that may contribute to a
system failure, and then trace back the groups of elements that will
necessarily lead to system’s undesired situation
3
3
Substation Reliability Evaluation Methods
AND gate
OR gate
4
4
Substation Reliability Evaluation Methods
Fault tree for series connection system Fault tree for parallel connection system
1
1 2 n 2
5
Substation Reliability Evaluation Methods
Busbar A
CB_A CB_D
CT
CB_E
85% 15%
CB_B
CB_F
CB_C
Busbar B
6
Substation Reliability Evaluation Methods
Success State 2
Failure
Initiating
event CB
Success State 3
Failure
State 4
Failure
7
Substation Reliability Evaluation Methods
8
Substation Reliability Evaluation Methods
A(pri) A(CB)
U(ini) U(ini)*A(pri) U(ini)*A(pri) *A(CB) U(ini)*A(pri) *A(CB) 1
Success Success
U(CB)
U(ini)*A(pri) *U(CB) U(ini)*A(pri) *U(CB) 2
Failure
Back-up protection
U(pri) A(back-up)
U(ini)*U(pri) U(ini)*U(pri) *A(bac) U(ini)*A(pri) *A(bac) 3
Failure Success
U(back-up)
U(ini)*U(pri) *U(bac) U(ini)*A(pri) *U(bac) 4
Failure
9
Table of Contents
10
10
Effect of Short Circuits & Breaker Operation
Fig. A
Consider only short circuit failures of – Failure of T1: input breaker B3 should operate,
transformers and subsequent effect on interruption of load point L1
the indices of the two load points – Failure of T2: input breaker B4 should operate,
interruption of load point L1
B3 T1 B1
• Outage time of load points will be the repair
X X L1 or replacement time for appropriate
transformer
B4 T2 B2 – Load point reliability indices
Fig. A X X L2
T1 B1
X L1
B3 • Fig. B
X – Failure of T1: input breaker B3 should operate,
T2 B2
X L2 interruption of load points L1 and L2
Fig. B
– Failure of T2: input breaker B3 should operate,
interruption of load points L1 and L2
11
11
Effect of Short Circuits & Breaker Operation
• Both load points will remain disconnected until this has been achieved
12
12
Effect of Short Circuits & Breaker Operation
13
13
Effect of Short Circuits & Breaker Operation
Logistics Aspects
• Misconceptions occasionally arise in regard to outage times values, particularly
switching or isolation time
• Outage time must be measured from the instant the failure occurs to the instant
at which load is reconnected
• Both repair and switching times contain several logistic aspects
a) time for a failure to be noted (if S/S not on-line, includes time it takes for a customer to
notify utility of supply failure)
b) time to locate failed component
c) time to travel to location of failed component and relevant disconnects (isolators) and
breakers
d) time required to make appropriate operating decisions
e) time to perform required action itself
• Therefore, switching times in particular are very much greater than actual time
needed to complete switching sequence itself
14
14
Effect of Short Circuits & Breaker Operation
B4 T2 B2
Fig. A X X L2
T1 B1
B3 X L1 Isolation is possible
X
T2 B2
Fig. B X L2
15
15
Effect of Short Circuits & Breaker Operation
Example
Reliability data for system
16
16
Effect of Short Circuits & Breaker Operation
17
17
Effect of Short Circuits & Breaker Operation
• Generally one spare transformer and other system components used to service
several operating transformers
• Economic appraisal necessary to judge merits of investing in one or more spares and
benefits accruing
– It is assumed that number of failures is less than or equal to number of spares available and
that spares can be restocked or components repaired before further failures occur
18
Table of Contents
19
19
Operating & Failure States of Components
20
20
Operating & Failure States of Components
21
21
Operating & Failure States of Components
• In the case of a normally open breaker operating and failure states are:
1) closes successfully when required to do so
22
22
Table of Contents
23
23
Open & Short Circuit Failures
• Fault manifests itself therefore only on the component that has failed and
other system components remain energized
• This type of failure treated the same way as a short circuit failure of the
component
24
24
Open & Short Circuit Failures
25
Open & Short Circuit Failures
Short circuits
• Basic method for assessing the impact of short circuits on reliability is intuitive
– identifies protection breakers that trip following short circuit failure of a component
– deduces whether these cause interruption of load point being analyzed
– evaluation is relatively simple for most system components
26
Open & Short Circuit Failures
a) the breakers cannot clear their own faults and therefore the indices
b) the breakers can clear some of their own faults and therefore the indices
27
Open & Short Circuit Failures
• breaker is neglected as a component but its inadvertent opening indices combined with
reliability indices of the next component in the branch in which the breaker exists
28
Open & Short Circuit Failures
29
Table of Contents
30
30
Active and Passive Failures
• When breakers are not required to operate, (open circuits and inadvertent
operation of breakers) two-state model only is necessary
i. state before the fault
ii. state after the fault but before repair is completed
• If the repair process same in both cases, the two models can be superimposed
31
31
Active and Passive Failures
Repair Repair
Repair Switching Switching
Passive Passive
U = up state failure failure
S = switching or isolation state
R R R
R = repair state
Three-state component model Two-state component model State space diagram for
active and passive failures
32
32
Active and Passive Failures
Passive event
• A component failure mode that does not cause operation of protection breakers
and therefore does not have an impact on remaining healthy components
– Service restored by repairing or replacing
– Examples: open circuits and inadvertent opening of breakers
33
Active and Passive Failures
Active event
• A component failure mode that causes operation of primary protection zone
around failed component and can therefore cause removal of other healthy
components and branches from service
– Actively failed component isolated and protection breakers reclosed
– Leads to service being restored to some or all load points
– Failed component itself can be restored to service only after repair or replacement
34
Active and Passive Failures
interest is concerned
35
Active and Passive Failures
• If a passive event leads to failure of a given load point, i.e. state R is a load
point failure event, then an active event on same component also leads to
failure of load point
– Reverse situation may not be true, state R need not be a load point failure event when
state S is
36
Active and Passive Failures
1 1
Active failure Passive failure
U S
2
X
2
X
of breaker 6
3 3
Repair
4 6 4 6
X
X
X
X
Passive Switching
failure
R 5 7 5 7
X
L1, L2 being supplied 3
(a) 4 6 (c)
X
X
(b) State following active failure of breaker Active failure Isolation
6 (state S), L1, L2 disconnected of breaker 6 of breaker 6
5 7
(c) State following passive failure of
breaker 6 or following switching after
active failure of breaker 6 (state R), L1 (b)
being supplied, L2 disconnected L1 L2
37
Active and Passive Failures
1
• Failure events of load point L1
2
X
3
(a) passive events: 1P, 2P, 3P, 4P, 5P 4 6
X
X
(b) active events: 1A, 2A, 3A, 4A, 5A, 6A
5 7
• For each passive event, there is a corresponding active event
(c) grouped events: 1(P + A), 2(P + A), 3(P + A), 4(P + A), 5(P+ A), 6A
38
Active and Passive Failures
1
• Separate identity of passive event lost
2
X
3
– it can be combined with its corresponding active event to produce a
4 6
X
X
total failure event
5 7
• Therefore component reliability data required is:
39
Active and Passive Failures
5 1
Identification failure modes 6
X
7
• Failure events of load-point L1 10
X
8 2
(a) Total failure events
9 3
X
4 1+5 2+5 3+5
X
11 4
1+6 2+6 3+6
(b) First-order active failures: L1
1+7 2+7 3+7 3A
1+8 2+8 3+8 9A
(c) Second-order active failures:
1+9 2+9 3+9
10A+1
• Above second-order events are 10A+2
associated with overlapping forced 10A+3
outages and a forced outage • Total outage in above failure events may be due
overlapping a maintenance outage to a forced outage or a maintenance outage
40
Table of Contents
41
41
Example: Event Tree Method
Example
• Assessing effect of intermediate substation configurations on reliability of power
transmission corridor
42
Example: Event Tree Method
43
Example: Event Tree Method
Transmission
corridor with
intermediate one
and a half circuit
breaker substation
44
Example: Event Tree Method
45
Example: Event Tree Method
46
Example: Event Tree Method
47
Example: Event Tree Method
48
Example: Event Tree Method
49
Example: Event Tree Method
50
Example: Event Tree Method
51