Item Descripción Rep. Cantidad Largo Ancho Altura Parcial Total
d
02 TRABAJOS PRELIMINARES GENERALES
02.03 TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO
02.03.01 TRAZO Y REPLANTEO DE OBRA m2 271.95
1.00 1.00 24.50 11.10 271.95

03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACIONES
03.01.01 EXCAVACION DE ZANJAS Y ZAPATAS MANUAL, Rt=0.87 kg/cm2, Df=1.70m m3 223.24
EJE 18 1.00 1.00 28.06 1.75 1.70 83.48
EJE 20 1.00 1.00 28.06 1.50 1.70 71.55

EJE A" 1.00 1.00 5.35 0.90 1.70 8.19

EJE B" 1.00 1.00 5.35 1.40 1.70 12.73

EJE C" 1.00 1.00 5.35 1.40 1.70 12.73

EJE E" 1.00 1.00 5.35 1.40 1.70 12.73

EJE G" Y H" 1.00 1.00 5.35 1.50 1.70 13.64

EJE I" 1.00 1.00 5.35 0.90 1.70 8.19

03.02 RELLENOS
03.02.01 RELLENO C/MATERIAL PROPIO PARA RELLENAR ZANJAS m3 113.63
EJE 18 1.00 1.00 28.06 1.75 0.85 41.74
EJE 20 1.00 1.00 28.06 1.50 0.85 35.78

EJE A" 1.00 1.00 5.35 0.90 0.85 4.09

EJE B" 1.00 1.00 5.35 1.40 0.85 6.37

EJE C" 1.00 1.00 5.35 1.40 0.85 6.37

EJE E" 1.00 1.00 5.35 1.40 0.85 6.37

EJE G" Y H" 1.00 1.00 5.35 1.50 1.10 8.83

EJE I" 1.00 1.00 5.35 0.90 0.85 4.09

03.02.03 RELLENO C/ARENILLA COMPACTADA m3 13.15


EJE 18 1.00 1.00 28.11 1.75 0.10 4.92
EJE 20 1.00 1.00 28.11 1.50 0.10 4.22

EJE A" 1.00 1.00 5.35 0.90 0.10 0.48

EJE B" 1.00 1.00 5.35 1.40 0.10 0.75

EJE C" 1.00 1.00 5.35 1.40 0.10 0.75

EJE E" 1.00 1.00 5.35 1.40 0.10 0.75

EJE G" Y H" 1.00 1.00 5.35 1.50 0.10 0.80

EJE I" 1.00 1.00 5.35 0.90 0.10 0.48

03.03 ESCARIFICADO
03.03.01 ESCARIFICADO Y COMPACTACION CON RODILLO m2 271.95
1.00 1.00 24.50 11.10 271.95

03.04 ELIMINACION DE EXCAVACIONES


03.04.01 ACARREO INTERNO DE MATERIAL EXCEDENTE CON CARRETILLA m3 142.50
Coef.
1.00 1.00 109.62 1.30 142.50

03.04.02 ELIMINACION DE DESMONTE,P/DEMOLICION DE ESTRUCT. CONCR, LADRIL. DIST.=5 m3 142.50


1.00 1.00 142.50 142.50
04 CONCRETO SIMPLE
04.01 SOLADOS
04.01.01 SOLADO PARA ZAPATAS Y CIMIENTOS: CONCRETO C:H 1:12 e=4".. m2 26.30
EJE 18 1.00 1.00 28.11 1.75 0.20 9.84
EJE 20 1.00 1.00 28.11 1.50 0.20 8.43

EJE A" 1.00 1.00 5.35 0.90 0.20 0.96

EJE B" 1.00 1.00 5.35 1.40 0.20 1.50

EJE C" 1.00 1.00 5.35 1.40 0.20 1.50

EJE E" 1.00 1.00 5.35 1.40 0.20 1.50

EJE G" Y H" 1.00 1.00 5.35 1.50 0.20 1.61

EJE I" 1.00 1.00 5.35 0.90 0.20 0.96

04.03 CIMIENTOS CORRIDOS


04.03.01 CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 3.18
SECCION A-A 2.00 1.00 1.53 0.50 0.90 1.38
2.00 1.00 1.57 0.50 0.90 1.41

SECCION G-G 4.00 1.00 0.82 0.60 0.20 0.39

04.04 SOBRECIMIENTO
04.04.01 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO m2 135.04
EJE 2.00 2.00 2.02 0.15 0.40 6.46
2.00 2.00 3.15 0.15 0.40 10.08
2.00 2.00 2.12 0.15 0.40 6.78
2.00 2.00 3.12 0.15 0.40 9.98
2.00 2.00 0.65 0.15 0.40 2.08

EJE 20 2.00 1.00 3.70 0.15 0.40 5.92


2.00 1.00 3.02 0.15 0.40 4.83
2.00 3.00 3.12 0.15 0.40 14.98
2.00 2.00 2.80 0.15 0.40 8.96

EJE A 2.00 2.00 2.90 0.15 0.40 9.28

EJE B 2.00 2.00 2.90 0.15 0.40 9.28

EJE C 2.00 2.00 2.90 0.15 0.40 9.28

EJE E 2.00 2.00 2.90 0.15 0.40 9.28

EJE G 2.00 2.00 2.90 0.15 0.40 9.28

EJE H 2.00 2.00 2.90 0.15 0.40 9.28

EJE I 2.00 2.00 2.90 0.15 0.40 9.28

04.04.02 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 10.13


EJE 2.00 2.00 2.02 0.15 0.40 0.48
2.00 2.00 3.15 0.15 0.40 0.76
2.00 2.00 2.12 0.15 0.40 0.51
2.00 2.00 3.12 0.15 0.40 0.75
2.00 2.00 0.65 0.15 0.40 0.16

EJE 20 2.00 1.00 3.70 0.15 0.40 0.44


2.00 1.00 3.02 0.15 0.40 0.36
2.00 3.00 3.12 0.15 0.40 1.12
2.00 2.00 2.80 0.15 0.40 0.67

EJE A 2.00 2.00 2.90 0.15 0.40 0.70

EJE B 2.00 2.00 2.90 0.15 0.40 0.70

EJE C 2.00 2.00 2.90 0.15 0.40 0.70

EJE E 2.00 2.00 2.90 0.15 0.40 0.70

EJE G 2.00 2.00 2.90 0.15 0.40 0.70

EJE H 2.00 2.00 2.90 0.15 0.40 0.70

EJE I 2.00 2.00 2.90 0.15 0.40 0.70

05 CONCRETO ARMADO
05.02 VIGA DE CIMENTACION 72.89
05.02.01 VIGA DE CIMENTACION 210 KG/M2 m3
Area
EJE 18 1.00 1.00 28.06 1.00 28.03
EJE 20 1.00 1.00 28.06 0.82 23.04

EJE A" 1.00 1.00 5.35 0.48 2.57

EJE B" 1.00 1.00 5.35 0.77 4.14

EJE C" 1.00 1.00 5.35 0.77 4.12

EJE E" 1.00 1.00 5.35 0.77 4.12

EJE G" Y H" 1.00 1.00 5.35 0.80 4.31

EJE I 1.00 1.00 5.35 0.48 2.57

05.02.02 ENCOFRADO Y DESENCOFRADO EN CIMIENTOS REFORZADOS m2 45.77


EJE 18 1.00 1.00 28.11 2.00 0.50 14.06
EJE 20 1.00 1.00 28.11 1.40 0.50 14.06

EJE A" 1.00 1.00 5.35 0.60 0.50 2.68

EJE B" 1.00 1.00 5.35 0.60 0.50 2.68

EJE C" 1.00 1.00 5.35 0.60 0.50 2.68

EJE E" 1.00 1.00 5.35 0.55 0.50 2.68

EJE F" 1.00 1.00 5.35 0.60 0.50 2.68


EJE G" Y H" 1.00 1.00 5.35 1.05 0.50 2.68

EJE I 1.00 1.00 5.35 0.60 0.50 1.61

05.02.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA CIMIENTOS kg 4,404.71


EJEJ 18 VIGA DE CIMENTACION VCC-B Traslape long. Coef.
5/8" 1.00 5.00 1.20 28.00 1.55 260.40
3/4" 1.00 4.00 1.20 28.00 2.24 301.06
1/2" 1.00 2.00 1.20 28.00 1.00 67.20
Parrilla 5/8" 1.00 6.00 1.20 28.00 1.55 312.48
5/8" 1.00 130.23 1.40 1.55 282.60
ESTRIVOS 3/8" 1.00 160.00 2.50 0.56 224.00

EJEJ 20 VIGA DE CIMENTACION VCC-A Traslape long. Coef.


5/8" 1.00 3.00 1.20 28.00 1.55 156.24
3/4" 1.00 4.00 1.20 28.00 2.24 301.06
1/2" 1.00 2.00 1.20 28.00 1.00 67.20
Parrilla 5/8" 1.00 6.00 1.20 28.00 1.55 312.48
5/8" 1.00 107.69 1.40 1.55 233.69
ESTRIVOS 3/8" 1.00 160.00 2.50 0.56 224.00

EJEJ A" VIGA DE CIMENTACION VCC-1 Traslape long. Coef.


5/8" 1.00 4.00 1.20 7.50 1.55 55.80
3/4" 1.00 2.00 1.20 7.50 2.24 40.32
1/2" 1.00 - 1.20 7.50 1.00 -
Parrilla 5/8" 1.00 4.00 1.20 7.50 1.55 55.80
5/8" 1.00 34.88 1.00 1.55 54.07
ESTRIVOS 3/8" 1.00 42.86 1.50 0.56 36.00

EJEJ B" VIGA DE CIMENTACION VCC-4 Traslape long. Coef.


5/8" 1.00 2.00 1.20 7.50 1.55 27.90
3/4" 1.00 4.00 1.20 7.50 2.24 80.64
1/2" 1.00 2.00 1.20 7.50 1.00 18.00
Parrilla 5/8" 1.00 4.00 1.20 7.50 1.55 55.80
5/8" 1.00 34.88 1.00 1.55 54.07
ESTRIVOS 3/8" 1.00 42.86 1.50 0.56 36.00

EJEJ C" VIGA DE CIMENTACION VCC-4 Traslape long. Coef.


5/8" 1.00 2.00 1.20 7.50 1.55 27.90
3/4" 1.00 4.00 1.20 7.50 2.24 80.64
1/2" 1.00 2.00 1.20 7.50 1.00 18.00
Parrilla 5/8" 1.00 4.00 1.20 7.50 1.55 55.80
5/8" 1.00 34.88 1.00 1.55 54.07
ESTRIVOS 3/8" 1.00 42.86 1.50 0.56 36.00

EJE E" VIGA DE CIMENTACION VCC-4 Traslape long. Coef.


5/8" 1.00 2.00 1.20 7.50 1.55 27.90
3/4" 1.00 4.00 1.20 7.50 2.24 80.64
1/2" 1.00 2.00 1.20 7.50 1.00 18.00
Parrilla 5/8" 1.00 4.00 1.20 7.50 1.55 55.80
5/8" 1.00 34.88 1.00 1.55 54.07
ESTRIVOS 3/8" 1.00 42.86 1.50 0.56 36.00

EJEJ G" Y H" VIGA DE CIMENTACION VCC-2 Traslape long. Coef.


5/8" 1.00 6.00 1.20 7.50 1.55 83.70
3/4" 1.00 4.00 1.20 7.50 2.24 80.64
1/2" 1.00 - 1.20 7.50 1.00 -
PARILLA 5/8" 1.00 4.00 1.20 7.50 1.55 55.80
5/8" 1.00 42.86 2.00 1.55 132.86

ESTRIVOS 3/8" 1.00 42.86 1.50 0.56 36.00

EJE I" VIGA DE CIMENTACION VCC-1 Traslape long. Coef.


5/8" 1.00 4.00 1.20 7.50 1.55 55.80
3/4" 1.00 2.00 1.20 7.50 2.24 40.32
1/2" 1.00 - 1.20 7.50 1.00 -
Parrilla 5/8" 1.00 2.00 1.20 7.50 1.55 27.90
5/8" 1.00 34.88 1.00 1.55 54.07
ESTRIVOS 3/8" 1.00 42.86 1.50 0.56 36.00

05.03 SOBRECIMIENTO REFORZADO


05.03.01 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO m2 49.97
EJE 18 1.00 1.00 2.02 0.25 0.55 1.11
2.00 1.00 3.12 0.25 0.55 3.43
2.00 1.00 2.12 0.25 0.55 2.33
2.00 1.00 0.65 0.25 0.55 0.72

EJE 20 1.00 1.00 3.70 0.25 0.55 2.04


1.00 1.00 3.02 0.25 0.55 1.66
3.00 1.00 3.12 0.25 0.55 5.15
1.00 1.00 2.79 0.25 0.55 1.53
1.00 1.00 2.82 0.25 0.55 1.55

EJE A" 2.00 1.00 2.90 0.25 0.75 4.35

EJE B" 2.00 1.00 2.90 0.25 0.75 4.35

EJE C" 2.00 1.00 2.90 0.25 0.75 4.35

EJE E" 2.00 1.00 2.90 0.25 0.75 4.35

EJE G" 2.00 1.00 2.90 0.25 0.75 4.35


EJE H" 2.00 1.00 2.90 0.25 0.75 4.35

EJE I" 2.00 1.00 2.90 0.25 0.75 4.35

05.03.02 SOBRE-CIMIENTO REFORZADO: ACERO FY=4200 kg/cm² kg 1,110.26

EJE 20 Traslape long. Coef.

3/8" 1.00 4.00 1.20 28.00 0.56 75.26


3/8" 1.00 2.00 1.20 28.00 0.56 37.63
ESTRIVOS 3/8" 1.00 160.00 2.00 0.56 179.20

EJE 18 Traslape long. Coef.

3/8" 1.00 4.00 1.20 28.00 0.56 75.26


3/8" 1.00 2.00 1.20 28.00 0.56 37.63
ESTRIVOS 3/8" 1.00 160.00 2.00 0.56 179.20

EJE A" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE B" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE C" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE E" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE G" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE H" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE A" Traslape long. Coef.

3/8" 1.00 4.00 7.70 0.56 17.25


3/8" 1.00 2.00 7.70 0.56 8.62
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

05.03.03 CONCRETO f'c=210 kg/cm2 PARA SOBRECIMIENTO m3 12.49


EJE 18 1.00 1.00 2.02 0.25 0.55 0.28
2.00 1.00 3.12 0.25 0.55 0.86
2.00 1.00 2.12 0.25 0.55 0.58
2.00 1.00 0.65 0.25 0.55 0.18

EJE 20 1.00 1.00 3.70 0.25 0.55 0.51


1.00 1.00 3.02 0.25 0.55 0.42
3.00 1.00 3.12 0.25 0.55 1.29
1.00 1.00 2.79 0.25 0.55 0.38
1.00 1.00 2.82 0.25 0.55 0.39

EJE A" 2.00 1.00 2.90 0.25 0.75 1.09

EJE B" 2.00 1.00 2.90 0.25 0.75 1.09

EJE C" 2.00 1.00 2.90 0.25 0.75 1.09

EJE E" 2.00 1.00 2.90 0.25 0.75 1.09

EJE G" 2.00 1.00 2.90 0.25 0.75 1.09

EJE H" 2.00 1.00 2.90 0.25 0.75 1.09

EJE I" 2.00 1.00 2.90 0.25 0.75 1.09

05.05 COLUMNAS
05.05.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 44.18
Area
C-1 4.00 1.00 0.1875 9.50 7.13
C-2 4.00 1.00 0.2750 9.50 10.45
C-3 6.00 1.00 0.2625 9.50 14.96
C-4 7.00 1.00 0.1250 9.50 8.31
P-1 2.00 1.00 0.1750 9.50 3.33

05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 426.08


perimetro
C-1 4.00 1.00 2.00 9.50 76.00
C-2 4.00 1.00 2.60 9.50 98.80
C-3 6.00 1.00 2.60 9.50 148.20
C-4 7.00 1.00 1.50 9.50 99.75
P-1 2.00 1.00 0.1750 9.50 3.33

05.05.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg 7,782.76


C-1 Traslape long. Coef.
5/8" 4.00 8.00 1.20 9.50 1.55 565.44
1/2" 4.00 4.00 1.20 9.50 1.00 182.40
ESTRIVO 3/8" 4.00 54.29 2.00 0.56 243.20
ESTRIVO 3/8" 4.00 11.43 1.65 0.56 42.24
S 3/8" 8.00 54.29 0.35 0.56 85.12

C-2 Traslape long. Coef.

3/4" 4.00 5.00 1.20 9.50 2.24 510.72


5/8" 4.00 12.00 1.20 9.50 1.55 848.16
1/2" 4.00 6.00 1.20 9.50 1.00 273.60
ESTRIVO 3/8" 4.00 54.29 2.70 0.56 328.32
ESTRIVO 3/8" 4.00 15.43 1.80 0.56 62.21
S 3/8" 12.00 54.29 0.35 0.56 127.68

C-3 Traslape long. Coef.

3/4" 6.00 3.00 1.20 9.50 2.24 459.65


5/8" 6.00 8.00 1.20 9.50 1.55 848.16
1/2" 6.00 6.00
ESTRIVO 3/8" 6.00 54.29 2.70 0.56 492.48
ESTRIVO 3/8" 6.00 54.29 1.80 0.56 328.32
S 3/8" 18.00 54.29 0.35 0.56 191.52

C-4 Traslape long. Coef.

5/8" 7.00 4.00 1.20 9.50 1.55 494.76


1/2" 7.00 4.00 9.50 1.00 266.00
ESTRIVO 3/8" 7.00 54.29 2.70 0.56 574.56
ESTRIVO 3/8" 7.00 15.43 1.80 0.56 108.86

P-1 Traslape long. Coef.


3/4" - - 1.20 9.50 2.24 -
5/8" 2.00 12.00 1.20 9.50 1.55 424.08
1/2" - - 9.50 1.00 -
ESTRIVO 3/8" 2.00 54.29 2.50 0.56 152.00
ESTRIVO 3/8" 2.00 54.29 2.50 0.56 152.00
S 3/8" 2.00 54.29 0.35 0.56 21.28

05.06 COLUMNETAS
05.06.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2 m3 2.64
EJE 20 CA 32.00 2.00 0.25 0.15 1.10 2.64

05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 28.16


EJE A' CA 32.00 2.00 0.25 0.15 1.10 28.16

05.06.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNETAS kg 310.95


Traslape long. Coef.
EJE A' CA 3/8" 64.00 4.00 2.30 0.56 114.69
ESTRIVO 1/4" 64.00 15.33 0.70 0.25 196.27

05.07 VIGAS
05.07.01 CONCRETO EN VIGAS f'c=210 kg/cm2 m3 39.74
1er PISO
EJE 20 VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72
2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE 18 VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72


2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE 17' VS - 102 (.20X.55) 4.00 1.00 3.12 0.20 0.55 1.37
2.00 1.00 3.65 0.20 0.55 0.80
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE A' VP - 101(.25x.40) 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 3.12 0.25 0.55 0.43

EJE B' VP - 101(.25x.55) 1.00 1.00 2.50 0.25 0.55 0.34


1.00 1.00 2.92 0.25 0.55 0.40

EJE C' VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE D' VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE E' VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE F' VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE G' VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE H' VP - 101(.25x.40) 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 2.50 0.25 0.55 0.34

EJE I' VP - 101(.25x.55 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 2.50 0.25 0.55 0.34

2DO PISO
EJE 20 VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72
2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE 18 VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72


2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE 18 CORREDOR VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72
2.00 1.00 3.02 0.25 0.55 0.83

EJE 17' VS - 202 (.20X.55) 4.00 1.00 3.12 0.20 0.55 1.37
2.00 1.00 3.65 0.20 0.55 0.80
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE A' VP - 201(.25x.40) 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 3.12 0.25 0.55 0.43

EJE B' VP - 201(.25x.55) 1.00 1.00 2.50 0.25 0.55 0.34


1.00 1.00 2.92 0.25 0.55 0.40

EJE C' VP -202(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE D' VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE E' VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE F' VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE G' VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE H' VP - 2101(.25x.40) 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 2.50 0.25 0.55 0.34

EJE I' VP - 201(.25x.55 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 2.50 0.25 0.55 0.34

VS-203 (.15x.28) 4.00 1.00 3.12 0.15 0.28 0.52


2.00 1.00 3.02 0.15 0.28 0.25

05.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 397.58

EJE 20 VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85


2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE 18 VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85


2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE 17' VS - 102 (.20X.55) 4.00 1.00 3.12 0.20 0.55 16.22
2.00 1.00 3.65 0.20 0.55 9.49
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE A' VP - 101(.25x.40) 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 3.12 0.25 0.55 4.21

EJE B' VP - 101(.25x.55) 1.00 1.00 2.50 0.25 0.55 3.38


1.00 1.00 2.92 0.25 0.55 3.94

EJE C' VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE D' VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE E' VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE F' VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE G' VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE H' VP - 101(.25x.40) 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 2.50 0.25 0.55 3.38

EJE I' VP - 101(.25x.55 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 2.50 0.25 0.55 3.38
2DO PISO
EJE 20 VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85
2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE 18 VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85


2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE 18 CORREDOR VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85
2.00 1.00 3.02 0.25 0.55 8.15

EJE 17' VS - 202 (.20X.55) 4.00 1.00 3.12 0.20 0.55 16.22
2.00 1.00 3.65 0.20 0.55 9.49
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE A' VP - 201(.25x.40) 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 3.12 0.25 0.55 4.21

EJE B' VP - 201(.25x.55) 1.00 1.00 2.50 0.25 0.55 3.38


1.00 1.00 2.92 0.25 0.55 3.94

EJE C' VP -202(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE D' VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE E' VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE F' VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE G' VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE H' VP - 2101(.25x.40) 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 2.50 0.25 0.55 3.38

EJE I' VP - 201(.25x.55 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 2.50 0.25 0.55 3.38

VS-203 (.15x.28) 4.00 1.00 3.12 0.15 0.28 8.86


2.00 1.00 3.02 0.15 0.28 4.29

05.07.03 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS kg 13,680.35


1ER PISO
Traslape long. Coef.
EJE 20 VS - 101 (.25X.55) 5/8" 4.00 1.00 28.00 1.55 173.60
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 160.00 1.70 0.56 609.28

Traslape long. Coef.


EJE 18 VS - 101 (.25X.55) 5/8" 4.00 1.00 28.00 1.55 173.60
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 160.00 1.70 0.56 609.28

Traslape long. Coef.


EJE 17 VS - 102 (.20X.55) 5/8" 4.00 1.00 28.00 1.55 173.60
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 160.00 1.70 0.56 609.28

Traslape long. Coef.


EJE A'' VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE B'' VP - 102(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE C'' VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE D'' VP - 102(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60
Traslape long. Coef.
EJE E'' VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE F'' VP - 102(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE G'' VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE H'' VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE I'' VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

2DO PISO
Traslape long. Coef.
EJE 20 VS - 201 (.25X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


EJE 18 VS - 201 (.25X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


VS - 202 (.20X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


EJE 17 VS - 202 (.20X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


EJE A' VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE B'' VP - 202(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE C'' VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE D'' VP - 202(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE E'' VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE F'' VP - 202(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE G'' VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE H'' VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE I'' VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


VS-203 (.15x.28) 5/8" 4.00 1.00 27.00 1.55 167.40
ESTRIVOS 3/8" 4.00 154.29 0.80 0.56 276.48

VIGETAS
CONCRETO EN VIGETAS f'c=210 kg/cm2 m3 1.23
1ER PISO
SECCION T-T EJE 18 7.00 1.00 3.30 0.15 0.10 0.35
SECCION T-T EJE 20 5.00 1.00 2.25 0.15 0.10 0.17
2.00 1.00 3.30 0.15 0.10 0.10

2DO PISO
SECCION T-T EJE 18 7.00 1.00 3.30 0.15 0.10 0.35
SECCION T-T EJE 20 5.00 1.00 2.25 0.15 0.10 0.17
2.00 1.00 3.30 0.15 0.10 0.10

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGETAS m2 8.19

1ER PISO
SECCION T-T EJE 18 7.00 1.00 3.30 0.10 2.31
SECCION T-T EJE 20 5.00 1.00 2.25 0.10 1.13
2.00 1.00 3.30 0.10 0.66

2DO PISO
SECCION T-T EJE 18 7.00 1.00 3.30 0.10 2.31
SECCION T-T EJE 20 5.00 1.00 2.25 0.10 1.13
2.00 1.00 3.30 0.10 0.66

ACERO fy=4200 kg/cm2 GRADO 60 en VIGETAS kg 104.93

1ER PISO Traslape long. Coef.


SECCION T-T EJE 18 3/8" 7.00 1.00 3.60 0.56 14.11
ESTRIVO 1/4" 7.00 18.00 0.30 0.25 9.45
SECCION T-T EJE 20 3/8" 5.00 3.00 2.50 0.56 21.00
ESTRIVO 1/4" 5.00 12.50 0.30 0.25 4.69
3/8" 2.00 3.00 3.30 0.10 1.98
ESTRIVO 1/4" 1.00 16.50 0.30 0.25 1.24

2DO PSIO Traslape long. Coef.


SECCION T-T EJE 18 3/8" 7.00 1.00 3.60 0.56 14.11
ESTRIVO 1/4" 7.00 18.00 0.30 0.25 9.45
SECCION T-T EJE 20 3/8" 5.00 3.00 2.50 0.56 21.00
ESTRIVO 1/4" 5.00 12.50 0.30 0.25 4.69
3/8" 2.00 3.00 3.30 0.10 1.98
ESTRIVO 1/4" 1.00 16.50 0.30 0.25 1.24

05.09 LOSA MACIZA


05.09.01 LOSAS MACIZAS.- ENCOFRADO Y DESENCOFRADO m2 15.96
1ER PISO
ESCALERA 1.00 1.00 4.20 1.90 7.98
2DO PISO
ESCALERA 1.00 1.00 4.20 1.90 7.98

05.09.02 LOSAS MACIZAS.- CONC.175 kg/cm2 m3 3.19


1ER PISO
ESCALERA 1.00 1.00 4.20 1.90 0.20 1.60
2DO PISO
ESCALERA 1.00 1.00 4.20 1.90 0.20 1.60

05.09.03 LOSA MACIZA: ACERO FY=4200 kg/cm² kg 131.60


2DO PISO Traslape long. Coef.
ESCALERA 3/8" 2.00 12.50 4.70 0.56 65.80
2.00 23.50 2.50 0.56 65.80

05.08 LOSAS ALIGERADAS


05.08.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 50.14
1ER PISO Coef.
aula 6.00 1.00 6.80 3.35 0.11 15.03
corredor 6.00 1.00 3.35 2.60 0.11 5.75
ESCALERA 1.00 1.00 4.20 2.30 0.11 1.06

2DO PISO Coef.


aula 6.00 1.00 6.80 3.35 0.11 15.03
corredor 6.00 1.00 3.35 2.30 0.11 5.09
ESCALERA 1.00 1.00 6.80 4.20 0.11 3.14
1.00 1.00 4.20 1.35 0.11 0.62
1.00 1.00 4.20 2.30 0.11 1.06
volado 6.00 1.00 3.76 1.35 0.11 3.35

05.08.02 ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS m2 455.86


1ER PISO
aula 6.00 1.00 6.80 3.35 136.68
corredor 6.00 1.00 3.35 2.60 52.26
ESCALERA 1.00 1.00 4.20 2.30 9.66

2DO PISO
aula 6.00 1.00 6.80 3.35 136.68
corredor 6.00 1.00 3.35 2.30 46.23
ESCALERA 1.00 1.00 6.80 4.20 28.56
1.00 1.00 4.20 1.35 5.67
1.00 1.00 4.20 2.30 9.66
volado 6.00 1.00 3.76 1.35 30.46

05.08.03 LADRILLO ARCILLA PARA TECHO 15X30X30 CM u 3,797.28


1ER PISO Coef.
aula 6.00 1.00 6.80 3.35 8.33 1,138.54
corredor 6.00 1.00 3.35 2.60 8.33 435.33
ESCALERA 1.00 1.00 4.20 2.30 8.33 80.47

2DO PISO
aula 6.00 1.00 6.80 3.35 8.33 1,138.54
corredor 6.00 1.00 3.35 2.30 8.33 385.10
ESCALERA 1.00 1.00 6.80 4.20 8.33 237.90
1.00 1.00 4.20 1.35 8.33 47.23
1.00 1.00 4.20 2.30 8.33 80.47
volado 6.00 1.00 3.76 1.35 8.33 253.70

05.08.04 ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA ALIGERADA kg 3,198.76


1ER PISO Traslape long. Coef.
AULAS 1/2" 22.00 1.00 1.20 24.00 1.00 633.60
3/8" 22.00 1.00 1.00 0.56 12.32
1/2" 22.00 1.00 2.70 1.00 59.40
1/2" 22.00 1.00 2.00 1.00 44.00
CORREDOR 3/8" 4.00 1.00 3.00 0.56 6.72

2DO PISO Traslape long. Coef.


AULAS 1/2" 27.00 1.00 1.20 24.00 1.00 777.60
3/8" 27.00 1.00 1.00 0.56 15.12
1/2" 27.00 1.00 2.70 1.00 72.90
1/2" 27.00 1.00 2.00 1.00 54.00
CORREDOR 3/8" 4.00 1.00 3.00 0.56 6.72
TEMPERATURA 1/4" 1.00 80.00 10.00 0.25 200.00

POSTERIOR 1/2" 27.00 1.00 24.00 1.00 648.00


3/8" 27.00 1.00 1.00 0.56 15.12
1/2" 27.00 1.00 2.70 1.00 72.90
1/2" 27.00 1.00 2.00 1.00 54.00
3/8" 4.00 1.00 3.00 0.56 6.72
TEMPERATURA 1/4" 1.00 80.00 10.00 0.25 200.00

ESCALERA 1/2" 27.00 1.00 4.90 1.00 132.30


3/8" 27.00 1.00 4.90 0.56 74.09
3/8" 27.00 1.00 4.90 0.56 74.09
TEMPERATURA 1/4" 1.00 33.33 4.70 0.25 39.17

05.11 ESCALERAS
05.11.01 ACERO CORRUGADO FY=4200 KG/CM2 EN ESCALERA kg 428.80
Traslape Long. Coef.
acero 1° tramo 1/2" 1.00 1.00 4.00 1.00 4.00
1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

acero 2° tramo 1/2" 1.00 1.00 4.00 1.00 4.00


1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

acero 3° tramo 1/2" 1.00 1.00 4.00 1.00 4.00


1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

acero 3° tramo 1/2" 1.00 1.00 4.00 1.00 4.00


1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 63.70


fondo 2.00 2.00 3.00 2.10 25.20
descanzo 2.00 1.00 4.20 2.50 21.00
contrapasos 2.00 20.00 2.50 0.18 17.50

CONCRETO EN ESCALERA CON f'c=210 kg/cm2 m3 23.25


area
pasos 2.00 20.00 0.15 2.50 15.00
descanzo 2.00 1.00 4.20 2.50 0.25 5.25
cimiento 2.00 1.00 2.50 0.50 1.20 3.00