WEEKLY PLAN

Week 28 | 09-15 Juli’18

Satui Coal Project

“Do Everithing Without Accidents”


Contents Weekly Plan STC

Forecast PA
Plan EWH
Plan Production
Haul Distance
Sequence
Dewatering
Forecast PA Weekly Plan STC

PA WEEK 28 - 2018
UNIT POPULASI UNIT PLAN UNIT READY AVERAGE PA UNIT RFU
DIGGER OB 13 8 82% 7
DIGGER COAL 3 2 73% 1
DIGGER SUPPORT 10 7 77% 5
HAUL TRUCK (785C) 34 21 75% 16
HAUL TRUCK (777D) 33 29 79% 23
HAUL TRUCK (TOP SOIL) 8 6 78% 5
HAUL TRUCK (COAL) 12 12 78% 9
LOADER 7 5 75% 4
COAL HAULING TRUCK 23 6 67% 4
DOZER 28 10 76% 8
GRADER 15 3 78% 2
WATER TRUCK 50KL 3 1 67% 1
WATER TRUCK 40KL 5 3 80% 2
DRILLING 3 3 81% 2
COMPACTOR 2 1 71% 1
DEWATERING PUMP 17 7 78% 5
WATERFILL PUMP 3 2 78% 2
Average Plan PA 76,1%
PA DIGGER RAMA
PA - EX3203 83%
PA - EX1767 83%
PA - EX1650 83%
PA DIGGER HSPE
PA - EX3144 83%
PA - EX3051 71%
PA - EX3183 81%
PA - EX3181 83%
PA DIGGER BIMA
PA - EX3179 83%
Plan EWH Weekly Plan STC
WEEKLY PLAN - WEEK 28
09 s.d 15 Juli 2018

SATUI COAL PROJECT


PLAN EWH
TOTAL WORKING HOURS 09 10 11 12 13 14 15
TOTAL
Jul Jul Jul Jul Jul Jul Jul
Hour per day 24 24 24 24 24 24 24 168,0
Rain Fall mm 9,15 9,15 9,15 9,15 9,15 9,15 9,15 64,0
Rain Delay hrs 2,25 2,25 2,25 2,25 2,25 2,25 2,25 15,7
Slippery (OB) hrs 1,00 1,00 1,00 1,00 1,00 1,00 1,00 7,0
Slippery (Coal) hrs 1,00 1,00 1,00 1,00 1,00 1,00 1,00 7,0
Friday Pray hrs 0,52 0,5
Washing Eq. Coal hrs 0,50 0,50 0,50 0,50 0,50 0,50 0,50 3,5
Traveling Front hrs 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,2
Shift Change hrs 0,33 0,33 0,33 0,33 0,33 0,33 0,33 2,3
Blasting hrs 0,06 0,06 0,06 0,06 0,06 0,06 0,06 0,4
Safety Talk hrs 0,50 0,5
Public Holiday hrs 0,00 0,00 0,00 0,00 0,00 0,00 0,0
Meal Break/Rest hrs 2,00 2,00 2,00 2,00 2,00 2,00 2,00 14,0
Daily Prayers hrs 0,50 0,50 0,50 0,50 0,50 0,50 0,50 3,5
Fasting Month hrs 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,0
EWH (OB)/day exclude maintenance hrs 17,83 17,83 17,83 17,83 16,81 17,83 17,83 123,8
EWH (COAL MINE)/day exclude maintenance hrs 17,33 17,33 17,33 17,33 16,31 17,33 17,33 120,3
EWH (HAULING)/day exclude maintenance hrs 20,67 20,67 20,67 20,67 20,15 20,67 20,67 144,2

7/9/2018 4
Plan Production Weekly Plan STC

SATUI COAL PROJECT


OB REMOVAL
10
ELEVATION WEEK 28
COAL UNIT DTs
BLOCKNAME PIT DUMP DIST
NUMBER ACT TARGET NUMBER TOTAL
SEAM INTERVAL
2 R 3 4
B40-41 SU2,SM1,SM2,SL1, SL2,SL3 EX3203 -35 -45 3 IPD RLM 0 / IPD RL M 10 1.500 97.042
B42-B43 RAMA SR3 EX1767 -25 -30 3 IPD RLM 0 / IPD RL M 10 1.600 86.220
B42-B43 SR5 EX1650 -15 -20 4 IPD RLM 0 / IPD RL M 10 2.000 67.695
B67-B68 SR2, SR3, SM1 EX3144 0 -10 4 IPD HSPE 40 1.500 60.057
B67-B68 SR2, SR3, SM1 EX3051 -5 -10 4 IPD HSPE 40 1.750 90.166
HSPE
B67-B68 SR5, SR7 EX3183 -5 -15 5 OPD HSPE 125 1.900 49.995
B67-B68 SR5, SR7 EX3181 -5 -15 5 OPD HSPE 126 1.900 17.875
B123 - B124 BIMA SU2,SM1,SM2,SL1, SL2,SL3 EX3179 5 0 5 OPD BIMA RL+20 2.100 67.060
TOTAL 33 536.109
Avg
COAL MINING

B41- B43 RAMA SR3, SR5, SU2, SM1, SM2, SL1, SL2, SL3 EX1731 -83 -90 3 ROM RAMA 2.700 13.901
B66 - B67 HSPE SM1, SR3, SR2, SL1, SL23 EX1937 -56 -60 2 ROM A1, A2 2.500 6.028
B123 - B124 BIMA SM1,SM2,SL2,SL23 EX1733 7 5 2 ROM BIMA F & G 1.323 14.985
TOTAL 7 34.913

RAMA 13,18
HSPE 33,22
SR
BIMA 4,48
TOTAL 15,36

COAL HAULING
RAMA, HSP, BIMA SR,SU2,SM1,SM2,SL1,SL2,SL3 FH16C 47 Base 6 X FH16 ROM RAMA TO PORT 29K 12.512
SR 42,85

Note : 5
*. FH 16 by actual daily progress akan di running optimal.
Haul Distance Weekly Plan STC
OB DISTANCE WK-28/2018
PIT EXCAVATOR DISTANCE (m) PRODUCTION (bcm) WASTE DUMP
EX3203 1.500 97.042 IPD RLM 0 / IPD RL M 10
RAMA EX1767 1.600 86.220 IPD RLM 0 / IPD RL M 10
EX1650 2.000 67.695 IPD RLM 0 / IPD RL M 10
EX3144 1.500 60.057 IPD HSPE 40
EX3051 1.750 90.166 IPD HSPE 40
HSP-EAST
EX3183 1.900 49.995 OPD HSPE 125
EX3181 1.900 17.875 OPD HSPE 126
BIMA EX3179 2.100 67.060 OPD BIMA RL+20
HSP 1.712,47 250.956,18
RAMA 1.669,23 150.222,87
BIMA 2.100,00 67.059,72
Total 1.746,95 468.238,77

COAL MINING DISTANCE


PIT EXCAVATOR DISTANCE (m) PRODUCTION (Ton) COAL DUMP
RAMA EX1731 2.700 13.901 ROM RAMA
HSPE EX1937 2.500 6.028 ROM HSPE
BIMKRES EX1733 1.323 14.985 ROM BIMA
RAMA 2.700,00 13.900,72
HSPE 2.500,00 6.027,54
7/9/2018 BIMKRES 1.323,00 14.984,62
Total 2.074,46 34.912,89
Sequence Pit Rama
Weekly Plan STC

EX. 1731
Cut RL -40
Vol. CO : 13 KMT

EX. 3203
Cut RL -40
Vol. OB : 97 KBcm

EX.1650
Cut RL -20
Vol. OB : 67 KBcm
EX. 1767
Cut RL -15 (OB Blasting)
Vol. OB : 86 KBcm

7/9/2018 7
Sequence Pit HSPE
Weekly Plan STC

EX. 3181
Cut RL -5
Vol. OB : 17 KBcm

EX. 3144
Cut RL -15
Vol. OB : 60 KBcm EX. 3183
Cut RL -5
Vol. OB 45 KBcm

EX. 3051
EX. 1937 Cut RL -15
Coal getting RL -15 Vol. OB 90 KBcm
(SM1,SR2, SR3 & SR7)
Budget: 6 KMT

7/9/2018 8
Sequence BIMKRES
Weekly Plan STC

EX. 1733
EX.3179
OPD
Coal getting RL0 & RL5
(SM1,SM2,SL1)
Vol.Coal : 14 KMT Cut RL +5
Vol. OB : 67 KBcm

9
7/9/2018 10
10
7/9/2018 11
11
7/9/2018 12
12
Dewatering Weekly Plan STC

ELEVASI SUMP RAMA : Update elv 25 Juni 2018 RL : - 85.656

POMPA STC -PIT RAMA 2018


30 31

DEWATERING
Bulan JUN JUL
Jumlah Hari 5 18

PIT
Air Sump 240,927 189,807
Hujan mm 287 284
Cathment Area ha 98.0 98.0
Volume Hujan m3 46,864 161,349
Volume Ground Water50 lt/s 21,600 77,760
Total Volume Air m3 309,391 428,916
Kemampuan Pompa

RAMA
UA 80% 80%
PA 79% 79%
Jam Kerja Pompa/Hari jam 15 15
PU1600 (FBP300) 219 ltr/dtk 59,792 215,252
PU1601 (FBP 300) 219 ltr/dtk 59,792 215,252
Kemampuan Pompa 119,585 430,504
7/9/2018
Sisa Air m3 189,807 (1,589)
13
Dewatering Weekly Plan STC
POMPA STC - PIT BIMA 2018
30 31
Bulan JUN JUL
Jumlah Hari 6 31
Air Sump 1,564,627 1,399,351
Hujan mm 287 284
Cathment Area ha 72.2 72.2
Volume Hujan m3 41,420 204,666
Volume Ground Water50 lt/s 25,920 133,920
Total Volume Air m3 1,631,968 1,737,938
Kemampuan Pompa
UA 80% 80%
PA 79% 79%
Jam Kerja Pompa/Hari jam 15 15

PU1548 (HH 220i) 136 ltr/dtk 44,558 230,214


PU1608 (FBP300) 219 ltr/dtk 71,751 370,712
PU1673 (HH 220i) 136 ltr/dtk 44,558 230,214
ELEVASI SUMP
PU1607 Barat
(FBP 300) : Update 27 Mei
219 2018
ltr/dtk RL : - 87 .809
71,751 370,712
Kemampuan Pompa 232,616 1,201,852

Sisa Air m3 1,399,351 536,086


DEWATERING

PIT
BIMA
ELEVASI SUMP BIMA : Update elv 24 Juni 2018 RL : -47.883
14
7/9/2018
Dewatering Weekly Plan STC

POMPA STC -PIT KRESNA 2018


30 31
Bulan Jun-18 Jul-18
Jumlah Hari 6 31
Air Sump 3,582,232 3,528,196
Hujan mm 287 284
Cathment Area ha 87.7 87.7
Volume Hujan m3 50,332 248,702
Volume Ground Water 50 lt/s 25,920 133,920
Total Volume Air m3 3,658,484 3,910,817
Kemampuan Pompa
UA 80% 80%
PA 77% 77%
Jam Kerja Pompa/Hari jam 15 15
PU1548 (HH 220i) 136 ltr/dtk
PU1723 (HH 220i) 136 ltr/dtk 43,429 224,386
PU1677 (HH 220i) 136 ltr/dtk 43,429 224,386
PU1607 (FBP 300) 219 ltr/dtk
PU3013 (HH 220i) 136 ltr/dtk 43,429 224,386
PU1673 (HH 220i) 136 ltr/dtk
Kemampuan Pompa 130,288 673,157

DEWATERING
Sisa Air m3 3,528,196 3,237,661

PIT
KRESNA
ELEVASI SUMP KRESNA: Update 24 Juni 2018 RL : - 18.44
SEKIAN
TERIMA KASIH
Prepared by:
PT DarmaHenwa – STC Project

“Do Everithing Without Accidents”