1.00 EARTH WORK EXCAVATION

Output Per Day(8


Sl.No Description of item Unit Skilled Unskilled
Hours)

Earth Work Excavation in all soils upto a depth of 3Mtr from


the natural ground level using excavator and carting away the
1.1 Cum
excavatred earth outside the site or dumping the excavated
earth as directed by the Engineer in Charge.

Earth work Excavation Manually for Foundation Pits , and


1.2 trenches in all soils up to a depth of 1.5M from the Ground
level including a lift of 1.5M and lead of 30Mtrs

1.2.1 In ordinary Soil Cum 1.00 2.50

Trimming the pits excavated by excavator to required level in


1.2.4 Nos 1.00 1.00
ordinary soil

1.5 Sand & jelly filling Cum 1.00 4.00

Page 1 of 11
Mfar Constructions Pvt. Ltd. ITTINA ABBY
118839204.xlsx.ms_office JOB # 030

2. CONCRETE WORKS

Output Per
Sl.No Description of item Unit Skilled Unskilled
Day(8 Hours)

Laying cast- in situ P.C.C. of specified thickness wherever


specified using river sand, 40mm and down size aggregate,
manually using concrete mixer and chute including feeding to the
2.1
mixer, transportation, placement including cleaning, sub grade
preparation, leveling, all leads and lifts, compacting, rough finishing
at the top surface etc., at all heights and depths as instructed.

2.1.1 Foundation , Footing bases of Coluimns , Plinth beams Cum 1.00 15.00 9.00

2.1.2 Damp proof Course in specfied thicknesss Cum 1.00 12.00 8.00

Flooring ,Flagging concrete, Surkhi concrete and Screeding


2.1.3 Sqm 1.00 12.00 150.00
Concrete up to 100mm thickness

Laying cast-in -situ Reinforced Cement concreting of any mix


using concrete mixer and chute including feeding to the mixer,
2.2 transportation, placement, vibrating and finsihing of the concrete as
per the directions including all lead and lift.(rate includes all labours
and masons for finishing)

2.2.1 Footing , Plinth Beams , and column pededtrals Cum. 1.00 10.00 7.50

2.2.2 Columns in all Shapes and all Levels Cum. 1.00 6.00 5.00
2.2.3 Roof Beams at all levels Cum. 1.00 9.00 7.50
2.2.4 Roof slabs at all levels and heights in any shapes Cum. 1.00 9.00 7.50
2.2.5 Sloped Chajja , Pardi Gutter Beam Concrete Cum.
2.2.6 Lintel at all levels Cum.
2.2.7 Cill Concrete at all levels Cum. 1.00 1.00 1.00
2.2.8 Staircase in all levels Cum. 1.00 9.00 7.00

2.2.9 Retaining wall , Drops , lift wall , Ribs upto 150mm thick Cum. 1.00 9.00 5.00

RCC Chajja / Lofts / Kitchen Platform / Counter slabs of 75mm


2.2.10 Cum. 1.00 10.00 1.14
thick

2.2.11 Starter concrete No 1.00 1.00 8.00

2.2.13 Starter concreting for water tank Rmt 1.00 1.00 20.00

Laying Ready-mix concrete/concrete supplied by batching plant of


any grade using concrete pump including placement, vibrating
2.3
and finsihing of the concrete as per the directions including all lead
and lift.(rate includes all labours and masons for finishing)

2.3.1 Footing , Plinth Beams , and column pededtrals Cum. 1.00 4.00 30.00

2.3.2 Columns in all Shapes and all Levels Cum.

2.3.3 Roof Beams at all levels Cum. 1.00 4.00 25.00

2.3.4 Roof slabs at all levels and heights in any shapes Cum. 1.00 4.00 30.00

Page 2 of 11
Mfar Constructions Pvt. Ltd. ITTINA ABBY
118839204.xlsx.ms_office JOB # 030

74.39
7.44
1.49

Page 3 of 11
Mfar Constructions Pvt. Ltd. ITTINA ABBY
118839204.xlsx.ms_office JOB # 024

3. REINFORCEMENT WORKS
Output Per
Sl.No Description of item Unit Skilled Unskilled Day(8
Hours)

Fabricating and placing reinforcement steel of high yield


strength ribbed bars of various diameters and grade
conforming to IS 1786 for reinforced concrete work. The work
includes cutting, bending, fabricating, and placing in position
3.1
according to drawings. Cost to include supply and use of 18G
black annealed binding wire double fold to tie the bars in
position As per IS 786 for each 100kg of reinforcing bars of
100kg of rebar, 1kg. of binding wires should be used.

3.1.1 Up to 12mm Dia Bar ( For Residential Buildings ) MT 1.00 2.00 0.28

3.1.2 Above 12mm Dia Bar ( For Residential Buildings ) MT 1.00 2.00 0.30

Unloading of steel receiving from suppliers at site and


3.1.3 MT 4.00 20.00
stacking at specified places
Mfar Constructions Pvt. Ltd. ITTINA ABBY
118839204.xlsx.ms_office JOB # 030

4. SHUTTERING / FORM WORKS

Output Per
Sl.No Description of item Unit Skilled Unskilled Day(8
Hours)

Erecting form work at all levels and places wherever


needed/specified as per drawing including striking with 12mm
Plastic coated, marine resistant waterproof ply or M.S.steel form
4.1 work with adjustable steel props of acceptable Staging system
and with sufficient bracing as approved by site engineer.
Deshuttering as the duration as approved by the site engineer
etc., complete at all levels, heights and profiles for

4.1.1 Footing , Plinth Beams , and column pedestrals Sqm. 1.00 2.00 14.00

4.1.2 Columns in all Shapes and all Levels Sqm. 1.00 2.00 15.00

4.1.3.1 Roof Beams at all levels - shuttering Sqm. 1.00 2.00 20.00

4.1.3.2 - deshuttering Sqm.

4.1.4.1 Roof slabs at all levels and heights in any shapes - shuttering Sqm. 1.00 2.00 20.00
-
4.1.4.2 Sqm.
deshuttering
4.1.5 Sloped Chajja , Pardi Gutter Beam Concrete Sqm. 1.00 1.00 5.00

4.1.6 Lintel at all levels Sqm. 1.00 1.00 15.00

4.1.7 Cill Concrete at all levels Sqm. 1.00 1.00 5.00

4.1.8 Staircase in all levels Sqm. 1.00 1.00 4.00

4.1.9 Retaining wall , Drops , lift wall , Ribs upto 150mm thick Sqm. 1.00 1.00 10.00

4.1.10 RCC Chajja / Lofts / Kitchen Platform / Counter slabs of 75mm thickSqm. 1.00 1.00 5.00

4.1.11 Column Starter No 1.00 1.00 10.00

4.1.12 Staging for Columns Ist lift Sqm. 1.00 1.00 15.00

4.1.13 Staging for Columns II nd lift Sqm. 1.00 1.00 10.00

4.1.14 Casurina Poles Scaffolding Sqm.

4.1.15 Scaffolding using horizontals and verticals pipes Sqm. 1.00 1.00 50.00

4.2 Making of Form Work as per the Design and Drawing

4.2.2 Columns in all Shapes and all Levels Sqm. 1.00 1.00 5.00

4.2.3 Roof Beams at all levels Sqm. 1.00 1.00 10.00

4.2.8 Staircase in all levels Sqm. 1.00 1.00 4.00

4.2.9 Retaining wall , Drops , lift wall , Ribs upto 150mm thick Sqm. 1.00 1.00 20.00

4.2.11 Column Starter No 1.00 1.00 8.00


Mfar Constructions Pvt. Ltd. ITTINA ABBY
118839204.xlsx.ms_office JOB # 030

683.84

56.99

3.80

1053.20

52.66

26.33

2.63
Mfar Constructions Pvt. Ltd. Project : Ittina Abby
118839204.xlsx.ms_office Job No. 30

5. MASONRY WORKS

Output Per
Description of item Unit Skilled Unskilled Day(8
Hours)

Providing and constructing OF PCC block work at all


5.2 levels in specfied Mix including curing, scaffolding,
staging, leads and lifts.

5.2.1 Granite / Size Stone Masonry in foundation Cum 1.00 1.00 2.00

5.2.2 Granite / Size Stone Masonry for plinth Cum 1.00 1.00 2.00

5.2.3 Laterite Stone Masonry Cum

5.2.4 9" thick Burnt Brick Masonry Cum

5.2.5 4 1/2" thick Burnt Brick Msonry Sqm

5.2.6 200mm thick Solid Block Masonry Cum 1.00 1.00 1.70

5.2.7 100mm thick Solid Block Masonry Sqm 1.00 1.00 8.50

5.2.8 150mm thick Solid Block Masonry Sqm 1.00 1.00 8.50

5.2.9 Size stone Masonry with Pointing Sqm 1.00 1.00 1.50

5.2.10 Brick Tile Masonry (for Managlore zone only) Cum

5.2.11 200mm thick Hollow Block Masonry Cum 1.00 1.00 1.90

5.2.12 100mm thick Hollow Block Masonry Sqm 1.00 1.00 9.50

5.2.13 150mm thick Hollow Block Masonry Sqm 1.00 1.00 9.50

5.2.14 Extra over 5.2.1 for rough dressing in one side No 1.00 30.00

5.2.16 Extra over 5.2.1 for rough dressing in both sides No 1.00 20.00

Manually Mixing and placing Concrete approx.0.1m thick in


5.2.18 Rmt 1.00 1.00 15.00
every fifth coarse of Block work

5.2.19 Design Work in 4" /6" Block for Elevation Treatment Sqm 1.00 1.00 5.00

5.2.20 Shifting Blocks From Storage Area to Upper floors Per No. 1.00 40.00

Cement 1;6 8"


Cement 1;4 6"
Cement 1;4 4"
Ceiling 1;5 Full fine sand
Wall 1;6 Full fine sand
Ext wall

Page 7 of 11
Mfar Constructions Pvt. Ltd. Project : Ittina Abby
118839204.xlsx.ms_office Job No. 30

6. Plastering Works

Output Per
Sl.No Description of item Unit Skilled Unskilled Day(8
Hours)

Plastering to ceilings, in specfied cement mortar mix up to


15mm thick, finishing to line and level with lime rendering at all
6.1 levels & lifts, including lead and lift of materials, hydrating the lime Sqm. 1.00 1.00 15.00
24 hours before starting of work, scaffolding, curing, etc.,
complete.

Plastering to Internal Walls, RCC exposed Areas including


Beams etc in Specfied cement mortar Mix up to 15mm thick,
6.2 finishing to line and level with lime rendering at all levels & lifts, Sqm. 1.00 1.00 12.00
including lead and lift of materials, hydrating the lime 24 hours
before starting of work, scaffolding, curing, etc., complete.
Plastering to External Walls Double Coat, RCC exposed
Areas including Beams etc in Specfied cement mortar Mix up to
6.3 Sqm. 1.00 1.00 7.50
25mm thick, finishing to line and level including lead and lift of
materials, scaffolding, curing, etc., complete.
Plastering to External Walls Single Coat, RCC exposed Areas
including Beams etc in Specfied cement mortar Mix up to 18mm
6.4 Sqm. 1.00 1.00 9.50
thick, finishing to line and level including lead and lift of materials,
scaffolding, curing, etc., complete.
Rough plastering in specfied Mixes as an undercoat (backing
plaster 15mm) on walls for fixing tiles, at all levels & lifts, including
6.5 Sqm. 1.00 1.00 10.00
rough finishing to line and plumb, the cost of scaffolding, curing,
leads and lifts etc., complete.
Providing Plastering Bands / Grooves / Window Fins to the
line and level on External walls at all levels for a maximum width
6.6
of 150mm including finishing to line and plumb, the cost of
scaffolding, curing, leads and lifts etc., complete.
6.6.1 Up to 12mm thick RM 1.00 1.00 35.00

6.6.2 Above 12mm thick RM 1.00 1.00 25.00

Fixing in position galvanised chicken/plaster mesh 24


guage/Expanded GI mesh at junctions of concrete and masonry
6.7 RM 1.00 1.00 35.00
and other locations as called for including fixing using adhesives/
cement paste/ nails as instructed by the project manager.
Providing and laying Lath plaster at required places using 6mm
dia MS rods with approved quality double layer 24 guage chicken
mesh/Expanded GI mesh, CM 1:4 plastering, either sand faced
6.8 finish/ neeru finish as per requirement, curing, staging, Sqm. 1.00 1.00 3.00
scaffolding, work at all heights, welding to the main rods if
required as per site conditions, etc., complete as per the
instructions of the Project Manager.
Finishing of triangular shaped parapet coping with plastering
6.12 Rmt 1.00 1.00 7.00

Page 8 of 11
Mfar Constructions Pvt. Ltd. Project : Ittina Abby
118839204.xlsx.ms_office Job No.: 30

8. Flooring & Finishing Works


Output Per
Sl.No Description of item Unit Skilled Unskilled Day(8
Hours)

A Cement Concrete Flooring

Providing & laying 40mm thick granolithic flooring


laid in panels consisting of consolidating, curing etc.
8.1 complete. The rate also to include floor hardener of sqm 1.00 1.00 10.00
approved make as per specifications and
instructions.

B Ceramic / Vitrified Flooring

Providing and laying Ceramic tile / Vitrified Tile /


Glazed Tiles of Various Sizes with approved shade
8.2 over minimum 20mm thick cement mortar bed of
1:4 mix including pointing with the matching colour
pigment cement, washing with dilute acid, etc.

8.2.1 For Flooring sqm 1.00 1.00 20.00

8.2.2 Skirting RM 1.00 1.00 20.00

8.2.3 Wall Dadooing Sqm 1.00 1.00 10.00

Page 9 of 11
Mfar Constructions Pvt.Ltd 118839204.xlsx.ms_office ITTINA ABBY
JOB#030

9. PAINTING WORKS

Output Per Day(8


Sl.No Description of item Unit Skilled Unskilled
Hours)

Prepare the surface of ceiling, internal walls, beams, column, fins


etc., and apply two coats acryllic distemper of approved make and
9.1 Sqm. 1.00 30.00
shade over one coat of wall primer painting including necessary
sand papering, fully putty work, scaffolding etc., complete.

Applying three coats of water proof cement base paint of approved


make and colour (snowcem or equivalent). The surface should be
9.2 Sqm. 1.00 20.00
thoroughly cleaned and wetted before painting. The painting and
curing should be done as per the manufacturer's specification.

Providing two or more coats of synthetic enamel paint of approved


make and shade over one coat of primer for doors, windows,
9.3
gates, railings, grills, and structural steel work at all levels to give a
uniform finish as approved.

9.3.1 Wooden Surfaces Sqm. 1.00 20.32

9.3.2 steel Surfaces Sqm. 1.00 36.60

Providing three or more coats of white washing to walls, ceiling,


9.4 etc.in all areas as called for, applied with brushes and brought to Sqm. 1.00 15.00
approved uniform finish.

Prepare the surface of ceiling, internal walls, beams, column, fins


etc., and apply two coats of Plastic Emulsion Paint of approved
9.5 make and shade over one coat of wall primer painting including Sqm. 1.00 30.00
necessary sand papering, fully putty work, scaffolding etc.,
complete.
Mfar Constructions Pvt. Ltd. Project : Ittina Abby
118839204.xlsx.ms_office Job No: 30

10. MISCELLANEOUS WORKS

Output Per
Sl.No Description of item Unit Skilled Unskilled
Day(8 Hours)

10.1 Joinery Fixing

10.1.1 Door Frame Fixing No 1.00 1.00 4.00

10.1.2 Single Panel Window Frame Fixing No 1.00 1.00 4.00

10.1.6 Door Shutter Fixing Sqm 1.00 1.00 14.00

10.1.7 Window Shutter Fixing Sqm

10.1.8 Grill Fixing for windows Sqm 1.00 1.00 9.15

10.1.9 Lock Fixing for Doors No 1.00 1.00 5.00

10.1.15 Fixing of Door Bush No 1.00 15.00

10.1.16 Fixing of Curtain Rod No 1.00 20.00

10.1.17 Fixing of Door Stopper No 1.00 20.00

10.1.18 Fixing of Door Handle No 1.00 18.00

10.1.19 Fixing of wooden beading on shutters Rmt 1.00 1.00 75.00

10.4 Hacking Works

With Tools

10.4.1 Column Hacking Sqm 1.00 50.00

10.4.2 Ceiling Hacking Sqm 1.00 30.00

10.4.3 Beam Hacking Sqm 1.00 30.00

Page 11 of 11