Vous êtes sur la page 1sur 18

1/16/2008

Definition
Dams - Temples of modern India-Nehru
According to the International Commission on
Large Dams (ICOLD), a dam is classified large
Debate on Small vrs Big when:
 — It is higher than 15 m
dams  — It is between 10 and 15 m high and:
 a) has a crest length exceeding 500 m, OR
 b) its spillway capacity is in excess of 2,000
cubic meters per second, OR
By  c) its reservoir capacity exceeds 1,000,000 cubic

Dr.S.S.Rao meters, OR
 d) has unusual characteristics

Purpose of Dams
Another Classification Most (48% approx.) dams with single purpose are for
irrigation
 (15%) of those dams serve for domestic and industrial water
Sr.No Categor Storage in Height Command supply.
y HaM (m) Area (ha)  Nearly 20% of dams generate electricity..
1 Minor 6- 125 8-12 <2000  Other purposes include flood control (8%), recreation
(4%) and to a lesser degree, inland navigation and fish
farming.
2 Medium 125 -6250 12 -30 2000-10000  Multi--purpose dams account for a large proportion of the
Multi
total – 7400 out of the 25,400 reported (nearly 30% of
the total).
3 Major >6250 >30 >10000  Irrigation comes first in this category also, followed by
flood control, hydro power, domestic and industrial water
supply and recreation, with fish farming and navigation.

1
1/16/2008

Men have built dams for thousands of


years for Conversion of available water Major investments … 6 000
Number Of Dams

to useable water.
 Reducing variability in seasons of low flow in 4 000

rivers  45,000 large dams worldwide


 Water storage to provide insurance against  2 dams commissioned 2 000

uncertainty in natural water availability due to per day in1970s


climatic variability. 0
 total investment exceeds 1900 1990s
 Regulating release of water to various users. $2 trillion
 Safety from social and economic upheavals due
 $40 billion expenditure
to flood and drought conditions
per year at peak
 Sustainable energy generation

The role of dams  The oldest dams about which there is


documented evidence were located in Jordan
 19 percent of electricity around 3000 BC
from hydropower  Several hundred dams, more than 10 m high,
– more than 50% in 63 countries were built before 1800 in about ten Asian
countries, around the Mediterranean and in
 dams support 30-
30-40% of Central America.
irrigated area & 12
12--16% of  Many ancient dams have disappeared, but some
global food production are still operational 500 or 1000 years after
being built.
 12% of all dams have a water
supply function
 By 1930, more than 2000 large dams had been
built around the world. 75% of them were in
 75 countries have dams for Japan, Great Britain and USA.
flood control
Dams and Development - Report of the World Commiss
ommission on Dams

2
1/16/2008

Funding Scenario
World bank share as of March 1999

 World Bank US$800,000  WWF US$ 10,000


 Norway US$750,000  Mott Foun. US$ 25,000
 Japan US$500,000  UK US$675,000
 Sweden US$490,000  Alsthom US$ 50,000
 ABB US$200,000  Enron US$100,000
 Switzerland US$650,000  Atlas Copco US$ 50,000
 Germany US$850,000  Rockefeller BF US$ 50,000
 NWF/USA US$ 2,000  Harza US$ 10,000
 Skanska US$ 50,000  Tractebel US$ 5,000
 China US$ 20,000  Coyne&Bellier US$ 5,000
 South Africa US$ 10,000  Denmark US$ 50,000
 Siemens US$ 65,000  Canada US$ 65,000
 US B R US$ 50,000  Hydro Quebec U S$ 135,000

World Commission on Dams

3
1/16/2008

India
 since 1951, 246 big surface irrigation projects have
been initiated. Only 65 out of these have been
completed. One hundred and eighty-
eighty-one are still
under construction.
 no benefit has come to the people from these
projects.
 According to the 7th Plan document, the additional
potential created by the M& M sector in the 35
years between 1950 to 1990 was 25.1 million
hectares (mh
(mh).
).
 an outlay of INR 11,207 crore had been utilised by
the sector during these years.

Design, Construction and Operations


Procedure of Large Dams Reconnaissance Stage II
Reconnaissance Stage I
 Topographical survey.

 1. Preliminary reconnaissance survey of the project area and collection
of field data. • Geological and foundation investigation
2. Hydrological investigations, collection of flow data of the river

flows, peak flood details, dependability of water yield over a period of • Hydrological and meteorological studies
time. • Pre-
Pre-irrigation soil survey and drainage.
 3. Area to be benefited by the dam with the water availability,
nature of crops to be cultivated, additional food • Special survey for hydroelectric projects
production/cultivation aspects like stabilisation of existing irrigated
area, increase in irrigation utility, crop yields and so on. • Construction material investigation
 4. Material survey, its availability and cost with lead particulars. • Communication investigation
5. Details of submergence of land due to storage created and

the cost of lands to be acquired both for the canal and storage and • Collection of relevant data for drawing up
the quantum of compensation to be paid. programme for construction including coffer
 6. Displacement of human habitats and displaced persons due to the dam construction.
reservoir and the rehabilitation and re- re-settlement aspects.
 7. Environmental impact of losing rich forestlands like plantations, • Hydraulic model studies for setting up important
affected flora and fauna, rare wild species of animals and birds etc, features

4
1/16/2008

Project Clearance Stage II :


1. (a) The State Proposal will be taken up for technical
Stage I : examination by the Technical Advisory Committee (TAC)
1. The Feasibility Study Report will be scrutinised in the and by the Project Preparation Cell of the Central Water
Chief Engineer.s Office by the Technical cell for its Commission (CWC) for according technical clearance for
Technical Competence in all aspects concerned. the Proposal.
2. Similarly the proposals will be examined for their (b) Technical clearance of the Proposal by the CWC
economic viability aspects by the Commissioner of Land paves the way for administrative clearance by the
Revenue (Formerly The Board of Revenue) and the Central Planning Commission.
comments will be forwarded to the Chief Engineer. 2. Clearance of the Project by the Central Planning
3. Re-
Re-formulate the proposal based on the comments of Commission is subjected to various considerations
Items 1 and 2 above. other than the technical such as socio-
socio-economical,
Inter--State, Regional and other aspects. Clearance of
Inter
4. The Proposal will then be cleared by the the Proposal by the Planning Commission qualifies for
Government after consulting the State Planning funding.
Commission and its Finance Wing.
3. Inclusion of the Project Proposal under Plan
5. Forward the proposal to the Government of India schemes for funding by the Central Planning
for Scrutiny, Approval and Allotment of Funds. Commission.

Construction
Most of the projects suffer from inordinate delays during 6. Delay in manufacture of spillway gates.
construction. Projects are seldom completed in time as 7. Time delay in erection of spillways and sluice gates due
programmed. This is an indication of cost and time to lack of skilled labour and technical expertise.
overruns over successive plan periods in the completion 8. Inadequate funding by the Government and delay in
of Irrigation Projects in India. allotting funds which makes the Project Managers unable to
Factors contributory to delay as experienced : act with vision and conviction.
1. Delay in land acquisition and handing over site for taking 9. Wilful suppression of the Project cost for getting Project
up construction activity. clearance throwing the project out of gear because funds have
to be obtained during execution.
2. Delay in construction of coffer dams and diversion of
10. Awarding work to incompetent contractors who lack
river flows. financial strength and technical competence for extraneous
3. Delay in tackling foundations owing to lack of reasons.
equipment, design finalisations for treatment of 11. Unforeseen natural calamities like unprecedented flood
foundation rocks due to rock characteristics. damage, break out of epidemic in the Project site during the
4. Delay in getting HT Power supply at construction site. construction period.
5. Delay due to lack of co-
co-ordination between various 12. Though trivial, a few more items may also be contributory for
the delay other than the above, such as pump repairs, power
Departments and agencies associated with the Project failures, labour unrest, non-
non-availability of adequate
construction materials in time.

5
1/16/2008

Narmada-
Narmada- Narmada, India
Management Good
Rules of regulation, generally, address the following  The creation of the reservoir will allow water to be
aspects: diverted north through a vast system of canals
 The period or duration the reservoir will be thrown open
which will provide drinking and irrigation water to
for irrigation.
40 million people in three Indian States.
 The mode of impounding river flows in the reservoir
during normal and monsoon seasons  It will supply drinking and irrigation water to more
 considering the riparian rights prior to the construction than 3.5 thousand villages and 1.9 million hectare
of the dam. Minimum storage to be maintained to of agricultural land. Put quite simply, it's massive.
safeguard the riparian interests, to protect the fish life in  When completed in 2005 it will produce 1450
the reservoir and soon. megawatts of electrical power - that's about 1.5
 Rules for operating the spillway gates to modulate the
percent of India's total electrical power
flood flows and to dispose the floods so as to maintain
flood peaks downstream of the reservoir on production. The reservoir behind it stretches back
manageable levels to ensure safety standards already more than 200 kilometres.
kilometres.
set forth.

TEHRI HYDRO-
HYDRO-ELECTRIC
Narmada--bad
Narmada
PROJECT
 So far 245 villages have been submerged and  Displacement / resettlement / rehabilitation
more than a million people displaced. And now work is unsatisfactory; 15 years after
the plan is to raise the dam even higher, which displacement, the original PAPs still not properly
rehabilitated and are living in very difficult
will displace yet more communities. conditions.
 Those displaced by the dam were mainly small  Widespread and persistent complaints of
farmers. Now for most of them, the only work corruption
available is on the dam itself – at least until it is  Study of impacts on flora and fauna inadequate
completed in three years time  Water quality, rim stability, etc., need more
study
 On seismicity aspect, continuing differences
among experts
 'Compensatory' afforestation done far away, in a
different zone

6
1/16/2008

EXPERIENCE OF NARMADA /
China
TEHRI REVIEWS
 Non-compliance / delayed compliance with conditions
Non-  China is the world's most 'dammed'
laid down at the time of conditional clearance of project.
country with around 19,000 large dams.
 Despite claims of extensive studies, there are many
gaps; for instance, impacts of reduced flows The United States comes second with
downstream of dam (fisheries, boatmen, agriculture, around 5,500 large dams, followed by the
industry, estuarine conditions) not fully known former USSR, Japan and India. Most large
Inadequate preparatory work on reducing distress to

wildlife.
dams have been built since 1950, during
 Seismicity aspect may have to be re-
re-studied in the light the post-
post-war development era when large
large--
of changed perceptions following the Latur earthquake. scale infrastructure such as dams were
seen as symbols of patriotic pride and
technological progress.

 The dam will control flooding, produce vast


amounts of electricity - equivalent to18 nuclear
Three Gorges, China power stations - and allow a five
shipping.
five--fold increase in

 But to do all this, the dam's reservoir will


1. The dam takes it's name from the three submerge many towns and even whole cities,
spectacular gorges, which occur roughly two-
two- displacing more than a million people. Allegations
thirds of the way down the Yangzte's journey of corruption have also plagued construction, not
to the sea. an uncommon occurrence in big dam projects.
2. It will be the biggest hydroelectric dam in the  In this case officials from the Three Gorges
world, stretching almost two kilometres across Resettlement Bureau were caught embezzling 58
the river and towering 185 metres above the million dollars of resettlement money in January
waters. 2000.
 Even sophisticated resettlement policies run the
3. Its reservoir will extend back more than 600 risk of improper implementation.
kilometres upstream.
 But in spite of the problems the Chinese
Government is pressing ahead with the dam and
plans to finish it in 2009.

7
1/16/2008

Supporters of large-
large-dam projects Opponents of large dams
 Benefits of large dams overstated, costs understated
 They do far more harm than good
 Large dams confer many benefits
 Their impacts and consequences cannot be fully foreseen,
 They do more good than harm much less remedied; many adverse impacts irremediable
 The harm they do can be remedied  They do more harm than good, they simply have to be
 In any case, we do need large dams - without them ruled out, and needs managed through alternative means
growing needs of food, water and energy cannot  Projecting ever-
ever-higher demands of various kinds and using
science and technology to raid nature to meet them is the
be met road to disaster - to humanity, to planet earth itself - this
 In particular, they are needed for hydro-
hydro-electric is totally unsustainable: 'development' needs to be re-re-
power (crucial for peaking needs and for balancing defined
system; 'clean' power)  Future needs can be met through a combination of
demand management, economy in water use,
 Needs of big metropolitan centres cannot be met 
 increased efficiency in all uses, resource conservation and
without water from large projects  extensive local water harvesting and watershed development
 Opposition to large dams is opposition to  There are several striking instances of local watershed
development development and management, and social transformation
these need to be replicated in thousands

 Rejoinder by supporters of dams Effect of dams


 No quarrel with these ideas; they are not 'alternatives' to
large dams; there is no conflict between the two 1. Responses of river 3. The impacts of a dam may occur a
approaches - both are needed ecosystems to dams great distance from where it is
are multiple, varied and built.
 Local watershed development, water harvesting, etc can complex.
only be a small part of overall planning - they cannot 4. it is in many cases impossible to
2. Dams cause changes in predict, even with site specific
make a significant contribution to water availability - they a biotic steering studies, what the precise impacts
are not substitutes for large projects variables related to of a dam will be.
hydrology, 5. There is a need for fundamental
 Answer by opponents geomorphology and research linking abiotic processes
 In any case, large dams do so much harm that they have water quality. These to changes in ecology, particularly
changes impact on the in tropical environments,
to be ruled out - we simply have to manage without biotic components 6. There is a need for long term
them (including people) of datasets from around the around
 Not true that 'alternatives' can only make a small river ecosystems. the world . Such studies must
collect pre and post dam data
contribution -this is an a-
a-priori statement not based on
examination

8
1/16/2008

7 There is a need for more comprehensive


methods of economic analysis which
incorporate a measure of all costs and
benefits, including all positive and negative
externalities from non marketed ecological
services.
8 For sustainability to be achieved in its
fullest sense, social impacts should be
given the same weighting as economic and
environmental impacts, subject to the
maintenance of ecosystem integrity.
9. There is a need for more equitable
distribution of the benefits gained from a
dam. It is essential that those people
directly affected by its construction benefit

Engineer’s view _water Engineer’s view-


view- Power
 Reliable grid supply to consumers all over the
 Premise 1: Variability of water availability country at the least cost. To achieve this, Large
 Over space: areas of heavy, moderate or Hydro projects are required.
poor rainfall, and arid or drought-
drought-prone areas
 Large hydro are said to be advantageous for
 Over time: concentration of rainfall during a
few months or weeks of the year following reasons. They are:
 Premise 2: Precipitation runs off in rivers to  Clean (low social and environmental costs),
sea; this has to be used; whatever goes to the
sea is 'wasted'  Renewable source of energy,
 Conclusion: Store river waters in large  Having high untapped potential (estimated at 60
reservoirs behind dams, and use this storage to GW in the country) and cheap.
transfer water from water-
water-surplus to deficit
areas, and from wet to dry seasons

9
1/16/2008

Anti--project movements in several


Anti REASONS FOR
countries Examples: DISENCHANTMENT
 India - Sardar Sarovar (Narmada) Project in DIVERSE CONCERNS:

Gujarat
Tehri Hydro-
Hydro-Electric Project in the Himalaya 1. Financial / Economic
Both stalled by anti-
anti-project movements: Cases  Massive time and cost over-
over-runs
pending in the Supreme Court of India  Insatiable demand for resources - imposing
Northeast of India: Dihang,
Dihang, Subansiri,
Subansiri, and severe strains on government budget; crowding
Tipaimukh -projects making no headway: facing out other necessary activities
opposition  Increasingly unaffordable capital cost per
 Pakistan - Controversy surrounding the Kalabagh hectare of irrigation
Project  Failure to achieve projected benefits fully
 Nepal -Arun III-
III- World Bank's withdrawal  Failure to generate revenues for reinvestment or
 China - Some muted dissidence on the Three even for proper maintenance
Gorges Project

2.'Political Economy' Aspects 3. ENVIRONMENTAL AND


RELATED IMPACTS
 Widespread prevalence of corruption I. Project construction in remote 3. Stilling of flowing water
and pristine areas  Changes in morphology
 collusions in some cases between politicians / Tremendous upheaval in the lives and water quality:
of local communities, often temperature stratification,
bureaucrats and consultants / contractors tribal settlements.
variations in nutrient
2. Submergence / acquisition of content and dissolved
 Serious inequities in incidence of costs and land for reservoir, canals,
oxygen at different levels
construction colonies
benefits Loss of agricultural land and  Grave consequences for
forests; submergence of aquatic and riparian life
 -hardship inflicted on people (mostly poor or towns and villages  Emission of greenhouse
disadvantaged) in the submergence area, benefits going Displacement of people and their gases from decaying
livestock, loss of occupations organic matter
to people in the command area (primary, secondary)
4. Impact on fish
Possible submergence of places /
 -benefits mostly going to the richer people
people-- structures of religious,  Movement impeded, spawning
historical or cultural hindered
 -canal water going mostly to head
head--reach importance - loss of heritage
 -farmers; tail
tail--enders put to hardship

10
1/16/2008

5. Impact on flora, fauna


 Danger to wildlife through 9. Downstream impacts Why is there so much opposition to
possibilities of drowning or  Reduced flows, silt load and
marooning; habitats and nutrient content downstream large dams?
movement routes disrupted; of dam - river regime affected,
inter--related species split;
inter also aquatic and riparian life;  Large dams have provoked opposition for
food--chains broken; some
food adverse impact on lives and
species could disappear occupations downstream numerous social, environmental, economic and
6. Public health aspects (fisheries, boat-
boat-plying,
 Reservoir and canals: possible agriculture, industries ) safety reasons. The main reason for opposition
spread of disease vectors –  Decline in groundwater worldwide is the huge number of people that
malaria, filaria,
filaria, recharge
7. Climate 10. Impacts of canals have been evicted from their lands and homes
 Large water-
water-body -  Disruption of natural drainage; to make way for reservoirs..
possible climatological possible drainage congestion
changes  Canal irrigation-
irrigation- possibilities of  Dam reservoirs can also become breeding
8. Seismic aspects water--logging and salinity
water
 Possible reactivation of old conditions in command area, grounds for waterborne diseases such as
and dormant faults leading to loss of valuable malaria, leishmaniasis and schistosomiasis.
schistosomiasis.
 Possibilities of reservoir-
reservoir- agricultural land
induced seismicity

How many people have been  How much land has been flooded under
reservoirs?
displaced by dams?  More than 400,000 square kilometres -
representing have been inundated by reservoirs
 Between 30 and 60 million people - the majority worldwide.
of them in China and India - have been displaced  Have many people been killed in dam
by large dams. At present, perhaps 2 million collapses?
people are displaced every year by large dams.
 More than 13,500 people have been swept to
 Where compensation is given, cash payments are their deaths by the roughly 200 dams outside
very rarely enough to compensate for the loss of China which have collapsed or been overtopped
land, homes, jobs and businesses. Where during the 20th century.
compensation is in the form of land, it is usually
 People have also died in earthquakes caused by
of poorer quality and smaller than the original
the great weight of water in large reservoirs. A
holdings.
magnitude 6.3 earthquake caused by Koyna
Dam in India in 1967 killed around 180 people.

11
1/16/2008

World commission on dams

12
1/16/2008

13
1/16/2008

14
1/16/2008

A Change in Paradigm and Practice


 Design Team Era
 Engineers Pre-
Pre-WWII
 Engineers + Economists Post--WWII
Post
 Engineers + Economists + EIS at end Late 1970s
 Engineers + Economists + Environ & Sociologists Late 1980s
 Eng. + Econ.. + Evt & Soc. + Affected People Early 1990s
 Eng. + Econ. + Evt & Soc. + AP + NGOs Mid 1990s
 Eng. + Econ. + Evt & Soc. + AP + NGOs + Public Acceptance
Early 2000s?

World Commission on Dams

15
1/16/2008

Alternatives A NEW APPROACH


 A process for dialogue  Insist on Environmental
established by all stakeholders Impact Assessment (EIA)
and interest groups studies
 Open, fair and transparent  Quantify direct and indirect
 Inclusive of public sector, costs and benefits (financial,
private sector and civil society economic, environmental,
 A Commission composed of social and human), and base
individuals reflecting different project decision on a
perspectives thorough--going cost-
thorough cost-benefit
analysis
 For all adverse impacts, take
appropriate counter-
counter-measures
- remedial, mitigatory or
compensatory

Solutions 7. Ensure imaginative humane implementation


approach through appropriate training,
4. Examine carefully if adequate
1. Treat mega-
mega-projects as a last
financial resources will be orientation and monitoring. Establish a
resort only after considering
other possibilities such as local forthcoming for the timely credible responsive and effective grievance
water conservation, watershed completion of the project,
development, small projects without imposing crippling redressal machinery.
etc., after making a careful burdens on the State budget.
evaluation of all options. 5. Insist that the necessary
2. Move from isolated planning to studies and surveys, action 8 Keep equity and social justice in all facets of
integrated and holistic planning plans on environmental and
re-
re- settlement aspects be the project, say from Planning to implementation.
for a basin or sub-
sub-basin.
completed before project
3. Subject "mega" projects to the approval.
most rigorous scrutiny and 9. Keep the Project under constant review
clear them only after fully 6. Ensure and institutionalise
fullest consultation and and institute corrective actions and remedial
establishing techno-
techno-economic
viability, environmental and collaboration between people measures wherever necessary
social acceptability. Reject a and NGO organisations
project if it fails to qualify representing them from the
according to these norms. earlier stages of planning till
its completion and operation

16
1/16/2008

Communities do have an answer Drought Proofing


 The strategy for drought-
drought-proofing should
 Barmer district in Rajasthan, one of India’s be to ensure that every village captures all
driest places, receives 100 mm of water in the the runoff resulting from the rain falling
year. If this rain falls on one hectare of land, over its entire land and storing it in tanks
the total rainwater received is as much as one
or ponds or using it to recharge the
million litres - enough to meet drinking and
cooking water needs of 182 people at a liberal
depleting groundwater.
15 litres per day.  It would then have enough water in its
 Cherrapunji which gets 11,000 mm annual tanks or in its wells to cultivate substantial
rainfall, still suffers from serious drinking water lands with water-
water-saving crops like millets
shortage. and maize.

 While a 1 hectare (ha) of watershed in the


Negev yielded as much as 95 cubic metres
(cum) of water per ha per year, a 345 ha
watershed yielded only 24 cum/ha/year. In
other words, as much as 75 per cent of the
water that could be collected was lost
 in a drought-
drought-prone area where water is scarce,
10 tiny dams with a catchment of 1 ha each will
collect much more water than one larger dam
with a catchment of 10 ha.

17
1/16/2008

End

18

Vous aimerez peut-être aussi