Académique Documents
Professionnel Documents
Culture Documents
Definition
Dams - Temples of modern India-Nehru
According to the International Commission on
Large Dams (ICOLD), a dam is classified large
Debate on Small vrs Big when:
It is higher than 15 m
dams It is between 10 and 15 m high and:
a) has a crest length exceeding 500 m, OR
b) its spillway capacity is in excess of 2,000
cubic meters per second, OR
By c) its reservoir capacity exceeds 1,000,000 cubic
Dr.S.S.Rao meters, OR
d) has unusual characteristics
Purpose of Dams
Another Classification Most (48% approx.) dams with single purpose are for
irrigation
(15%) of those dams serve for domestic and industrial water
Sr.No Categor Storage in Height Command supply.
y HaM (m) Area (ha) Nearly 20% of dams generate electricity..
1 Minor 6- 125 8-12 <2000 Other purposes include flood control (8%), recreation
(4%) and to a lesser degree, inland navigation and fish
farming.
2 Medium 125 -6250 12 -30 2000-10000 Multi--purpose dams account for a large proportion of the
Multi
total – 7400 out of the 25,400 reported (nearly 30% of
the total).
3 Major >6250 >30 >10000 Irrigation comes first in this category also, followed by
flood control, hydro power, domestic and industrial water
supply and recreation, with fish farming and navigation.
1
1/16/2008
to useable water.
Reducing variability in seasons of low flow in 4 000
2
1/16/2008
Funding Scenario
World bank share as of March 1999
3
1/16/2008
India
since 1951, 246 big surface irrigation projects have
been initiated. Only 65 out of these have been
completed. One hundred and eighty-
eighty-one are still
under construction.
no benefit has come to the people from these
projects.
According to the 7th Plan document, the additional
potential created by the M& M sector in the 35
years between 1950 to 1990 was 25.1 million
hectares (mh
(mh).
).
an outlay of INR 11,207 crore had been utilised by
the sector during these years.
4
1/16/2008
Construction
Most of the projects suffer from inordinate delays during 6. Delay in manufacture of spillway gates.
construction. Projects are seldom completed in time as 7. Time delay in erection of spillways and sluice gates due
programmed. This is an indication of cost and time to lack of skilled labour and technical expertise.
overruns over successive plan periods in the completion 8. Inadequate funding by the Government and delay in
of Irrigation Projects in India. allotting funds which makes the Project Managers unable to
Factors contributory to delay as experienced : act with vision and conviction.
1. Delay in land acquisition and handing over site for taking 9. Wilful suppression of the Project cost for getting Project
up construction activity. clearance throwing the project out of gear because funds have
to be obtained during execution.
2. Delay in construction of coffer dams and diversion of
10. Awarding work to incompetent contractors who lack
river flows. financial strength and technical competence for extraneous
3. Delay in tackling foundations owing to lack of reasons.
equipment, design finalisations for treatment of 11. Unforeseen natural calamities like unprecedented flood
foundation rocks due to rock characteristics. damage, break out of epidemic in the Project site during the
4. Delay in getting HT Power supply at construction site. construction period.
5. Delay due to lack of co-
co-ordination between various 12. Though trivial, a few more items may also be contributory for
the delay other than the above, such as pump repairs, power
Departments and agencies associated with the Project failures, labour unrest, non-
non-availability of adequate
construction materials in time.
5
1/16/2008
Narmada-
Narmada- Narmada, India
Management Good
Rules of regulation, generally, address the following The creation of the reservoir will allow water to be
aspects: diverted north through a vast system of canals
The period or duration the reservoir will be thrown open
which will provide drinking and irrigation water to
for irrigation.
40 million people in three Indian States.
The mode of impounding river flows in the reservoir
during normal and monsoon seasons It will supply drinking and irrigation water to more
considering the riparian rights prior to the construction than 3.5 thousand villages and 1.9 million hectare
of the dam. Minimum storage to be maintained to of agricultural land. Put quite simply, it's massive.
safeguard the riparian interests, to protect the fish life in When completed in 2005 it will produce 1450
the reservoir and soon. megawatts of electrical power - that's about 1.5
Rules for operating the spillway gates to modulate the
percent of India's total electrical power
flood flows and to dispose the floods so as to maintain
flood peaks downstream of the reservoir on production. The reservoir behind it stretches back
manageable levels to ensure safety standards already more than 200 kilometres.
kilometres.
set forth.
TEHRI HYDRO-
HYDRO-ELECTRIC
Narmada--bad
Narmada
PROJECT
So far 245 villages have been submerged and Displacement / resettlement / rehabilitation
more than a million people displaced. And now work is unsatisfactory; 15 years after
the plan is to raise the dam even higher, which displacement, the original PAPs still not properly
rehabilitated and are living in very difficult
will displace yet more communities. conditions.
Those displaced by the dam were mainly small Widespread and persistent complaints of
farmers. Now for most of them, the only work corruption
available is on the dam itself – at least until it is Study of impacts on flora and fauna inadequate
completed in three years time Water quality, rim stability, etc., need more
study
On seismicity aspect, continuing differences
among experts
'Compensatory' afforestation done far away, in a
different zone
6
1/16/2008
EXPERIENCE OF NARMADA /
China
TEHRI REVIEWS
Non-compliance / delayed compliance with conditions
Non- China is the world's most 'dammed'
laid down at the time of conditional clearance of project.
country with around 19,000 large dams.
Despite claims of extensive studies, there are many
gaps; for instance, impacts of reduced flows The United States comes second with
downstream of dam (fisheries, boatmen, agriculture, around 5,500 large dams, followed by the
industry, estuarine conditions) not fully known former USSR, Japan and India. Most large
Inadequate preparatory work on reducing distress to
wildlife.
dams have been built since 1950, during
Seismicity aspect may have to be re-
re-studied in the light the post-
post-war development era when large
large--
of changed perceptions following the Latur earthquake. scale infrastructure such as dams were
seen as symbols of patriotic pride and
technological progress.
7
1/16/2008
Supporters of large-
large-dam projects Opponents of large dams
Benefits of large dams overstated, costs understated
They do far more harm than good
Large dams confer many benefits
Their impacts and consequences cannot be fully foreseen,
They do more good than harm much less remedied; many adverse impacts irremediable
The harm they do can be remedied They do more harm than good, they simply have to be
In any case, we do need large dams - without them ruled out, and needs managed through alternative means
growing needs of food, water and energy cannot Projecting ever-
ever-higher demands of various kinds and using
science and technology to raid nature to meet them is the
be met road to disaster - to humanity, to planet earth itself - this
In particular, they are needed for hydro-
hydro-electric is totally unsustainable: 'development' needs to be re-re-
power (crucial for peaking needs and for balancing defined
system; 'clean' power) Future needs can be met through a combination of
demand management, economy in water use,
Needs of big metropolitan centres cannot be met
increased efficiency in all uses, resource conservation and
without water from large projects extensive local water harvesting and watershed development
Opposition to large dams is opposition to There are several striking instances of local watershed
development development and management, and social transformation
these need to be replicated in thousands
8
1/16/2008
9
1/16/2008
Gujarat
Tehri Hydro-
Hydro-Electric Project in the Himalaya 1. Financial / Economic
Both stalled by anti-
anti-project movements: Cases Massive time and cost over-
over-runs
pending in the Supreme Court of India Insatiable demand for resources - imposing
Northeast of India: Dihang,
Dihang, Subansiri,
Subansiri, and severe strains on government budget; crowding
Tipaimukh -projects making no headway: facing out other necessary activities
opposition Increasingly unaffordable capital cost per
Pakistan - Controversy surrounding the Kalabagh hectare of irrigation
Project Failure to achieve projected benefits fully
Nepal -Arun III-
III- World Bank's withdrawal Failure to generate revenues for reinvestment or
China - Some muted dissidence on the Three even for proper maintenance
Gorges Project
10
1/16/2008
How many people have been How much land has been flooded under
reservoirs?
displaced by dams? More than 400,000 square kilometres -
representing have been inundated by reservoirs
Between 30 and 60 million people - the majority worldwide.
of them in China and India - have been displaced Have many people been killed in dam
by large dams. At present, perhaps 2 million collapses?
people are displaced every year by large dams.
More than 13,500 people have been swept to
Where compensation is given, cash payments are their deaths by the roughly 200 dams outside
very rarely enough to compensate for the loss of China which have collapsed or been overtopped
land, homes, jobs and businesses. Where during the 20th century.
compensation is in the form of land, it is usually
People have also died in earthquakes caused by
of poorer quality and smaller than the original
the great weight of water in large reservoirs. A
holdings.
magnitude 6.3 earthquake caused by Koyna
Dam in India in 1967 killed around 180 people.
11
1/16/2008
12
1/16/2008
13
1/16/2008
14
1/16/2008
15
1/16/2008
16
1/16/2008
17
1/16/2008
End
18