Académique Documents
Professionnel Documents
Culture Documents
Introduction In the case of a kicking well, the flow rate taking place at the
It is a well-known fact that the during drilling, the influx of sandface is unknown and there is no method to measure the
formation fluid into wellbore is extremely dangerous. If timely sandface flowrate during kick. Using total mud pit gain
actions are not taken to shut-in and kill the well using proper
procedure, blowout or other complications may result.
N and the inflow time t , measured between the time of
p p
time(4,9) is used. With the equivalent flow rate and flow time, continued with actual field data obtained during kicks
shut-in drill pipe pressure is given by provided by Mobil Drilling Data Center.
Rq tp B t The following simple procedure is given as a guideline to
SIDPP p i 0.052 m L 162.6 ln . (2) estimate the formation thickness of the kicking zone.
khh St p t
where the coefficients are(2,3) Procedure:
R=1.35 and S=0.83,
t in Eq. 2 is called a plotting time. Step 1
the ratio
The recorded shut-in time is converted to plotting
St p t
time using plotting time equation.
When a well is closed, the early pressure response is localized
Step 2
at the wellbore with fluid flow confined to the nearby
Plot shut-in drillpipe pressure versus logarithm of
wellbore. As time progresses the pressure transient starts
plotting time using S = 0.83.
moving into the deep bulk formation. The SIDPP, plotted
Establish the two straight lines and estimate their
against logarithm of plotting time, yields a straight line
slopes m1 & m2 using R = 1.35.
segment of slope m1 showing an early response localized near
Step 3
the wellbore and a second straight line segment of slope m2, Calculate the ratio of the penetration from Eq. 3
indicating the response from the bulk formation. and Eq. 4 for liquid kick and Eq. 6 and Eq. 7 for
From Eq. 2 the slopes are given as gas kick.
Rq tp B Step 4
m1 162.6 (3)
k h Calculate the equivalent flowrate and the flow time
Rq tp B 24 N p
m 2 162.6 (4) using q tp for oil kick and
khh t p
where q tp is calculated in bbls/day using the following 24 5.61 N p
q tp for gas kick.
equation 1000 t p
24 N p
q tp . (5) Step 5
tp Calculate horizontal permeability and the formation
The early slope (m1) yields the flow capacity of k h of the thickness h, using the initial penetration into the
open interval while m2 gives the flow capacity of the entire kicking formation.
formation k h h .
Illustration:
From Eqs. 2 & 3, the ratio of the slopes, m2 is equal to ,
m1 h
Example - 1
which is further used to estimate the formation thickness, h. This example pertains to a synthetic kick data with the
The procedures for the estimation of the formation thickness following information:
are common for both liquid and gas kicks, except for gas kick Vertical depth of the well = 7000 ft.
the pressure is replaced with real gas pseudopressure. The Mud density at the time of kick = 10 ppg.
slopes of the semilog lines for gas kicks are given by the Pit gain observed = 15 bbl.
following equations Inflow time = 15 min.
Rq tp Tp sc
m1 57910 (6)
k h Tsc Calculation Procedure:
and
Rq tp Tp sc Step 1
m 2 57910 (7)
The shut-in drill pipe pressures (simulated) and
k h hTsc
shut-in time converted to the plotting time are
where q tp is calculated in mcf/day using the following shown in Table 1.
equation
24 5.61 N p
q tp . (8)
1000 t p
Case Studies
A few examples are presented along with the step by step
calculation procedure. Initially the model is verified by using
numerically simulated kick data and further validation is
Robello, Engler, Miska
Table 1 5
17 ft.
h 0.3
Shut-in time SIDPP in Plotting time Using qtp from Step 4 and Eq. 4,
in hours psi k h h 219.5 1440
283
0.05 50 0.26 = 1,117 md-ft/cp
0.08 175 0.35 Assuming a reasonable value for the formation
fluid viscosity, e.g. =2 cp, the corresponding in-
0.10 235 0.41
situ horizontal permeability can be estimated as
0.12 290 0.47
1117 2
0.15 335 0.52 kh = 131 md.
17
0.17 365 0.55 Example - 2
0.20 380 0.59 The following are the actual field cases provided to TUDRP
0.22 390 0.61 (Tulsa University Drilling Research Projects), by Mobil
0.25 400 0.64 Drilling Data Center.
0.27 410 0.66 This example is from a well drilled in an offshore lease area.
After the intermediate casing string of 9 5 8 ” at a depth of
Step 2 11,358 ft. (measured depth)/10,498 ft. (vertical depth), the
A graph of SIDPP versus plotting time is shown in production hole with a diameter of 8 1 2 ” was in progress with a
Fig. 2. The plot clearly exhibits two regions that mud weight of 16.5 ppg. As the drilling progressed, a kick was
can be approximated by straight lines with the encountered at a depth of 12,267 ft. Drilling was stopped and
slopes m2=956 psi/cycle and m2 = 283 psi/cycle. BOP was closed. From the Geolograph, a total of 27 bbls of
mud pit gain was recorded in about 50 minutes. Also it was
observed that the mud pit gain started slowly when a drill
600 break was encountered at a depth of 12,262 ft.
400 Step 1
SIDPP(PSI)
400
350 m2
300
SIDPP
250
m1
200
150
100
50
0
1 Plotting Time 0.1
Step 4
Equivalent formation fluid flow rate q tp ,
24 N p
q tp = 24 27
tp 50
60
Figure 3: SP/GR plot - Example - 2
= 777 bbls/day.
Robello, Engler, Miska
Example - 3 It seems that only the late radial region is observed
This example is from the data file of Well-B. After setting in this illustration. The line is drawn and the slope
11 7 8 ” inches casing at 11,620 ft, a pilot hole was drilled first is measured to be m2 12 psi/cycle.
and later a 12 ¼"” phase of under reaming was continued with Step 4
1,014 ft bottom hole assembly. It appears that this is a case of The equivalent formation fluid flow rate,
an attempt of only slight overbalance drilling to avoid 24 N p 24 150
(minimize) payzone damage. The well was under normal q tp = =3,927 bbls/day.
tp 55
operation with a mud weight of 17 ppg. Operation was stopped
60
for pipe connection at 12,918 ft. The well of mud started
flowing during pipe connection and a gain of 80 bbls was Step 5
recorded. The BOP was closed, and shut in drillpipe and Hence, the horizontal transmissibility of the
casing pressures were noted. The SIDPP of zero psi and wellbore from Eq. 11 is
SICPP of 800 psi was observed. After bleeding off the k h h = 219.539271/12
pressure through annulus, the well was opened and found to be
dead. When reaming resumed, the well flowed back = 71,831md-ft/cp.
vigorously. The total pit gain was found to be 150 bbls in 55 This is a case of a completely penetrated condition. Figure 5
minutes. shows the SP/GR and induction log deflections. As seen in the
log there is no change in formation from 12080 ft.
Calculation Procedure:
Step 1
The recorded shut-in drill pipe pressures given in
psi and shut-in time in hours are given in Table 3.
The shut-in time converted to plotting time is
given in the third column.
Table 3
Step 2
The semilog plot of SIDPP is shown in Fig. 4.
90
80
70
m2
60
SIDPP (psi)
50
40
30
Example - 4
1
0
0.1 0.01 This example is from an offshore well. The well was under
Plotting Time
normal drilling with a mud weight of 13.8 ppg when a drilling
break at a depth of 11,332 ft was reported. Mild flow of mud
Figure 4: SIDPP vs Plotting Time - Example - 3 was observed with a strong background of gas recorded by the
chromotograph. Due to the trickling nature of the mud flow the
mud weight was arbitrarily increased to 14.5 ppg and the
A Practical Technique to Estimate the Formation Thickness in a Kicking Well.
drilling was continued. At 11,338 ft, the well started flowing. The ratio of the slopes (penetration ratio)
A total of 18 bbls of mud gain was observed in 14 minutes. m2 . 108
105
h 014
.
m1 7.2 108
Calculation Procedure: Step 4
The equivalent formation fluid flow rate,
Step 1 24 5.61 N p
The recorded shut-in pressures and shut-in time are q tp
1000 t p
shown in Table 4. The SIDPP converted to
psuedopressure(6) and shut-in time converted to 24 561
. 18
= =10.39 Mcf/day.
plotting time are shown in third and fourth column 14
1000
respectively. 60
Step 5
Table 4 The horizontal flow capacity of the formation is
Rq tpTpsc
Shut-in SIDPP Pseudopressure Plotting time k h h 57910 .
m2Tsc
Time hour (psi) (psia 2 /cp) Substituting the respective values, the horizontal
flow capacity is calculated to be
0.017 0231 493.5E04 0.079
k h h =579101.3510.3956014.7/5201.05108
0.033 0833 618.7E05 0.146
0.050 1131 1130E05 0.204 =0.122md-ft.
0.067 1294 1468E05 0.255 The formation penetrated, =6ft.
0.083 1381 1677E05 0.300 Total thickness of the payzone h= 6
h 014
.
0.100 1407 1741E05 0.339 = 42 ft.
Analysis
The following properties are assumed for the calculation: Figure 7 shows the portion of the electrical logs recorded after
= 0.2, c = 2.35 104 psi1 , completion of the phase. From the deflection of the
T = 560deg.R g = 0.7. Spontaneous Potential (SP) and Gamma Ray (GR) logs, it can
be clearly seen that the total thickness of the sand section
= 0.03cp. above the shale streak at 11400 ft. is approximately 50 ft.
Step 2
A plot of SIDPP(psuedopressure) versus plotting
time is shown in Fig. 6.The slopes are calculated to
be:
m1 = 7.2 108 (psi2/cp)/cycle and
. 108 (psi2/cp)/cycle.
m2 = 105
2.50E+08
2.00E+08
m2
1.50E+08
Pseudopressure(psi2/cp)
1.00E+08
m1
5.00E+07
0.00E+00
1 0.1 0.01
Plotting TIme
References