CORPORATE ENGINEERING DEPARTMENT

Project: HOTEL SOGO SANTOLAN


Subject: Awarded Cost Breakdown for Additional 15 Rooms @ (Structural Works,Wet Works,
Dry Works Finishing, Hallway,Exterior Painting and Trade Works)
Ref: Purchase Order 7230 dated February 19,2018
Date: February 28, 2018

Unit
Item No. Description Unit Qty
Material

A. GENERAL REQUIREMENTS
1.00 Mobilization & Demobilization lot 1.00
2.00 Temporary Facilities (Barracks Rental)/Board Up lot 1.00
3.00 Cleaning & Disposal (daily) lot 1.00
4.00 Security Services lot 1.00
5.00 Safety Requirement lot 1.00
6.00 Power and Water Consumption lot 1.00
7.00 As-Built lot 1.00

B. ARCHITECTURAL WET WORKS

Interior Partition Wall (4" CHB-300psi) w/ Rebars 12mm


1.00 sq.m 560.32 480.00
Ø - 0.6 Bothways

Interior Partition Wall (5" CHB-300psi) w/ Rebars 12mm


2.00 sq.m 96.00 580.00
Ø - 0.6 Bothways
Exterior Wall (6" CHB-300psi) w/ Rebars 12mm Ø - 0.6
3.00 sq.m
Bothways
4.00 Plastering Works
a.Exposed Columns /Beams sq.m 64.00 125.00
b.Interior Wall Partition, Both Sides sq.m 1,312.00 125.00
c.Existing interior wall,one side only sq.m 165.50 125.00
d. Exterior Wall, Both Side Only sq.m
5.00 Concrete Collar, T & B lm 90.00 150.00
6.00 Stiffener Column, (including formworks) lm 192.00 300.00
Lintel Beam @ 2.10 m w/ Rebars 12mm Ø (including
7.00 lm 190.00 300.00
formworks)
8.00 Structural Epoxy - pioneer lot 1.00 3,500.00
Floor Topping 2",(Rooms,T &b & Smooth Finish @
9.00 sq.m 237.80 200.00
Hallway)
10.00 Aircon ledge (conreter) set/s 2.00 1,200.00
11.00 ACU opening (finish) set/s 7.00 450.00
13.00 Aircon housing set/s 2.00 2,500.00
Unit
Item No. Description Unit Qty
Material

C. ARCHITECTURAL DRY WORKS (NEW DESIGN)


I. ECONO ROOMS 5
1.00 Ceiling Works
Gypsum Board on Metal Frame (Main Room + Ante
1.01 m² 42.35 468.00
Room)
1.02 1/4" thk Hardiflex on Metal Frame (T&B) m² 9.00 488.00
Drop Ceiling -Paint Finish w/ 2" x 2" Good Lumber for
1.03 set/s 5.00 3,000.00
Ceiling Design
1.04 Lighting Fixture - Drop light, 7W set/s 5.00 3,000.00
Pinlights ( Mainroom-2pcs ) and ( Foyer-1pc ) - 3watts,
1.05 set/s 15.00 650.00
with Frosted Glass diffuser

1.06 Pinlights ( T&B-1pc.) - 7watts, with Clear Glass diffuser set/s 5.00 750.00

2.00 Door and Jamb Works


Federal Moulded Doors HDF (40mm x 800mmx
2.01 set/s 5.00 3,880.00
2100mm) & Door Jamb
PVC Door white w/ louver incl accessories,incl SUS
2.02 set/s 5.00 1,650.00
Hinges (Upson)

3.00 Hardwares (as per standard)

RF Electronic Key Card Lockset (Main Rm) OSM-Labor


3.01 pc/s 5.00
Only

3.02 Lockset Keyless (T&B) pc/s 5.00 450.00


3.03 Butterfly Hinges (3pcs/Door) pc/s 15.00 150.00
3.04 Door Stopper pc/s 5.00 120.00
3.05 Barrel Bolt pc/s 5.00 188.00
3.06 Clothes Hanger, 2pcs. per room pc/s 10.00 150.00
3.07 Robe Hook (w/Rubber tip) pc/s 5.00 88.00
3.08 Door viewer pc/s 5.00 120.00

4.00 Wood Mouldings & Sash Works


4.01 Cornice - Mattwood Colonial 1x3x12 lm. 63.00 168.00
4.02 Baseboards - Mattwood TRTD Mcasing 1x4x12 lm. 37.50 228.00
4.03 ACU moulding - Mattwood Colonial(1" x 2") lm. 9.00 128.00

5.00 Floor Finishes


5.01 Ceramic Tiles (400mmx400mm), Granito Bone m² 42.35 680.00
Unit
Item No. Description Unit Qty
Material
5.02 Floor tiles 300mmx300mm MASCARA (T & B) m² 9.00 550.00

6.00 Wall Finishes


6.01 Wall tiles 300mmx 600mm YINGSHING WHITE (T & B) m² 44.70 880.00

Wall Accent 300mmx300mm ARTE AURORA CAFE (T &


6.02 m² 16.20 680.00
B)
6.03 Corner Ledge in paint finish in 3/4 thk plywood set/s 5.00 3,000.00

7.00 Painting
7.01 Doors and Jambs - Spray finished (lacquer type) set/s 5.00 850.00
7.02 Ceilings m² 51.35 140.00
7.03 Cornice lm 63.00 88.00
7.04 Baseboard lm 37.50 88.00
7.05 ACU Moulding lm 9.00 88.00
7.06 Wall Painting (Non Accent)-Premix m² 140.00 140.00

8.00 Amenities
Bedbox (60" x 75") w/ side table on top Laminate, w/
8.01 1/2" Phenolic Board,incl angular support - Plain Paint set/s 5.00 8,500.00
Finish
8.02 Dresser Mirror & Frame set/s 5.00 1,800.00
8.03 Dresser Counter set/s 5.00 2,000.00
8.04 Dresser Chair (OSM) set/s 5.00
Headboard w/ fabric (Using Uratex Foam & German
8.05 set/s 5.00 3,500.00
Leatherette incl. canvass image)
8.06 Push Cart (OSM) set/s 5.00

9.00 T & B
9.01 Water Closet incl Accessories (OSM-Labor Only) set/s 5.00
9.02 Lavatory incl accessories (OSM-Labor Only) set/s 5.00
9.03 Bidet (OSM-Labor Only) sets 5.00
9.04 Shower Head LED w/ mixer (OSM-Labor Only) sets 5.00
9.05 Tissue Holder (OSM) Labor Only pc/s 5.00
9.06 6mm thk Mirror @ T & B sets 5.00 1,550.00
9.07 Waterproofing works, elastomeric (6 coats) sq.m 14.60 350.00
9.08 Ceiling exhaust (OSM-Labor Only) rm 5.00
9.09 Lavatory Faucet (OSM-Labor Only) set 5.00
9.10 S/S floor drain (OSM-Labor Only) set 5.00
9.11 Grab Bar ( OSM ) (Labor Only) pc 5.00
Unit
Item No. Description Unit Qty
Material
I. PREMIUM ROOMS 7
1.00 Ceiling Works
Gypsum Board on Metal Frame (Main Room + Ante
1.01 m² 69.65 468.00
Room)
1.02 1/4" thk Hardiflex on Metal Frame (T&B) m² 12.60 488.00
Drop Ceiling -Paint Finish w/ 2" x 2" Good Lumber for
1.03 set/s 7.00 5,000.00
Ceiling Design
1.04 Lighting Fixture - Drop light, 7W set/s 7.00 3,000.00
Pinlights ( Mainroom-2pcs ) and ( Foyer-1pc ) - 3watts,
1.05 set/s 7.00 650.00
with Frosted Glass diffuser

1.06 Pinlights ( T&B-1pc.) - 7watts, with Clear Glass diffuser set/s 7.00 750.00

2.00 Door and Jamb Works


Federal Moulded Doors HDF (40mm x 800mmx
2.01 set/s 7.00 3,880.00
2100mm) & Door Jamb
PVC Door white w/ louver incl accessories,incl SUS
2.02 set/s 7.00 1,650.00
Hinges (Upson)

3.00 Hardwares (as per standard)


RF Electronic Key Card Lockset (Main Rm) OSM-Labor
3.01 pc/s 7.00
Only
3.02 Lockset Keyless (T&B) pc/s 7.00 450.00
3.03 Butterfly Hinges (3pcs/Door) pc/s 21.00 150.00
3.04 Door Stopper pc/s 7.00 120.00
3.05 Barrel Bolt pc/s 7.00 188.00
3.06 Clothes Hanger, 2pcs. per room pc/s 14.00 150.00
3.07 Robe Hook (w/Rubber tip) pc/s 7.00 88.00
3.08 Door viewer pc/s 7.00 120.00

4.00 Wood Mouldings & Sash Works


4.01 Cornice - Mattwood Colonial 1x3x12 lm. 93.80 168.00

4.02 Baseboards - Mattwood TRTD Mcasing 1x4x12 lm. 58.10 228.00

4.03 ACU moulding - Mattwood Colonial(1" x 2") lm. 12.60 128.00

5.00 Floor Finishes


5.01 Ceramic Tiles (400mmx400mm), Granito Bone m² 69.65 680.00
Unit
Item No. Description Unit Qty
Material
5.02 Floor tiles 300mmx300mm MASCARA (T & B) m² 12.60 580.00

6.00 Wall Finishes


6.01 Wall tiles 300mmx 600mm YINGSHING WHITE (T & B) m² 62.58 880.00

Wall Accent 300mmx300mm ARTE AURORA CAFE (T &


6.02 m² 22.68 680.00
B)
6.03 Corner Ledge in paint finish in 3/4 thk plywood set/s 7.00 3,000.00

7.00 Painting
7.01 Doors and Jambs - Spray finished (lacquer type) set/s 7.00 850.00
7.02 Ceilings m² 69.65 140.00
7.03 Cornice lm 93.80 88.00
7.04 Baseboard lm 58.10 88.00
7.05 ACU Moulding lm 12.60 88.00
7.06 Wall Painting (Non Accent)-Premix m² 225.12 140.00

8.00 Amenities
Bedbox (60" x 75") w/ side table on top Laminate, w/
8.01 1/2" Phenolic Board,incl angular support - Plain Paint set/s 7.00 8,500.00
Finish
8.02 Dresser Mirror & Frame set/s 7.00 1,800.00
8.03 Dresser Counter set/s 7.00 2,000.00
8.04 Dresser Chair (OSM) set/s 7.00
Headboard w/ fabric (Using Uratex Foam & German
8.05 set/s 7.00 3,500.00
Leatherette incl. canvass image)
8.06 Push Cart (OSM) set/s

9.00 T & B
9.01 Water Closet incl Accessories (OSM-Labor Only) set/s 7.00
9.02 Lavatory incl accessories (OSM-Labor Only) set/s 7.00
9.03 Bidet (OSM-Labor Only) sets 7.00
9.04 Shower Head LED w/ mixer (OSM-Labor Only) sets 7.00
9.05 Tissue Holder (OSM) Labor Only pc/s 7.00
9.06 6mm thk Mirror @ T & B sets 7.00 1,550.00
9.07 Waterproofing works, elastomeric (6 coats) sq.m 20.44 350.00
9.08 Ceiling exhaust (OSM-Labor Only) rm 7.00
9.09 Lavatory Faucet (OSM-Labor Only) set 7.00
9.10 S/S floor drain (OSM-Labor Only) set 7.00
9.11 Grab Bar ( OSM ) (Labor Only) pc 7.00
Unit
Item No. Description Unit Qty
Material
II. Deluxe Rooms 3
1.00 Ceiling Works
Gypsum Board on Metal Frame (Main Room + Ante
1.01 m² 37.98 468.00
Room)
1.02 1/4" thk Hardiflex on Metal Frame (T&B) m² 6.48 488.00
Drop Ceiling -Paint Finish w/ 2" x 2" Good Lumber for
1.03 set/s 3.00 5,000.00
Ceiling Design
1.04 Lighting Fixture - Drop light, 7W set/s 3.00 3,000.00
Pinlights ( Mainroom-2pcs ) and ( Ante room-1pc ) -
1.05 set/s 9.00 650.00
3watts, with Frosted Glass diffuser

1.06 Pinlights ( T&B-1pc.) - 7watts, with Clear Glass diffuser set/s 3.00 750.00

2.00 Door and Jamb Works


Federal Moulded Doors HDF (40mm x 800mmx
2.01 set/s 6.00 3,880.00
2100mm) & Door Jamb
PVC Door white w/ louver incl accessories, incl. SUS
2.02 set/s 3.00 1,650.00
Hinges (Upson)

3.00 Hardwares (as per standard)


RF Electronic Key Card Lockset (Main Rm) OSM-Labor
3.01 pc/s 3.00
Only
3.02 Lockset Keyless (Ante Room & T&B) pc/s 6.00 450.00
3.03 Butterfly Hinges (3pcs/Door) pc/s 18.00 150.00
3.04 Door Stopper pc/s 6.00 120.00
3.05 Barrel Bolt pc/s 3.00 188.00
3.06 Clothes Hanger, 2pcs. per room pc/s 6.00 150.00
3.07 Robe Hook (w/Rubber tip) pc/s 3.00 88.00
3.08 Door viewer pc/s 3.00 120.00

4.00 Wood Mouldings & Sash Works


4.01 Baseboards - Mattwood TRTD Mcasing 1x4x12 lm. 39.60 228.00
4.02 ACU moulding - Mattwood Colonial(1" x 2") lm. 5.40 128.00

5.00 Floor Finishes


5.01 Ceramic Tiles (400mmx400mm), Granito Bone m² 37.98 750.00
5.02 Floor tiles 300mmx300mm MASCARA (T & B) m² 6.48 580.00

6.00 Wall Finishes


6.01 Wall tiles 300mmx 600mm YINGSHING WHITE (T & B) m² 29.70 880.00
Unit
Item No. Description Unit Qty
Material
Wall Accent 300mmx300mm ARTE AURORA CAFE (T &
6.02 m² 9.72 680.00
B)
Shelves in paint finish in 3/4 thk plywood w/ 2x2 solid
6.03 set/s 3.00 4,500.00
wood & canvass sticker & Backing 1/2 plywood
3/4" thk plywood for Accent Framing of Mirror in Paint
6.04 set/s 3.00 3,000.00
Finish w/ 4mm thk Mirror
6.05 Corner Ledge in paint finish in 3/4 thk plywood set/s 3.00 3,000.00

7.00 Painting
7.01 Doors and Jambs - Spray finished (lacquer type) set/s 6.00 850.00
7.02 Ceilings m² 39.60 140.00
7.03 Cabinet set/s 3.00 1,500.00
7.04 Baseboard lm 39.60 88.00
7.05 ACU Moulding lm 5.40 88.00
7.06 Wall Painting (Non Accent)-Premix m² 95.04 140.00

8.00 Amenities
Bedbox (60" x 75") w/ side table on top Laminate, w/
8.01 1/2" Phenolic Board,incl angular support - Plain Paint set/s 3.00 8,500.00
Finish
8.02 Dresser Mirror & Frame set/s 3.00 1,800.00
8.03 Dresser Counter set/s 3.00 2,000.00
8.04 Dresser Chair (OSM) set/s 3.00
8.05 Closet Cabinet set/s 3.00 3,500.00
Headboard,incl canvass image wall & Ceiling,LED strip
8.06 set/s 3.00 15,000.00
light
8.07 Ledge set/s 3.00 650.00
8.09 Push Cart (OSM) set/s

9.00 T & B
9.01 Water Closet incl Accessories (OSM-Labor Only) set/s 3.00
9.02 Lavatory incl accessories (OSM-Labor Only) set/s 3.00
9.03 Bidet (OSM-Labor Only) sets 3.00
9.04 Shower Head LED w/ mixer (OSM-Labor Only) sets 3.00
9.05 Tissue Holder (OSM) Labor Only pc/s 3.00
9.06 6mm thk Mirror @ T & B sets 3.00 1,550.00
9.07 Waterproofing works, elastomeric (6 coats) sq.m 10.08 350.00
9.08 Ceiling exhaust (OSM-Labor Only) rm 3.00
9.09 Lavatory Faucet (OSM-Labor Only) set 3.00
9.10 S/S floor drain (OSM-Labor Only) set 3.00
9.11 Grab Bar ( OSM ) (Labor Only) pc 3.00
Unit
Item No. Description Unit Qty
Material

D. HALLWAY
Ceiling Works
1.0 Gypsum Ceiling w/ metal studs sq.m 67.20 468.00

3/4" x 2" plywood on wood stain finish - ceiling accent


2.0 lm 78.40 128.00
paint finish, 2.0 mts distance O.C

3.0 Ultra Slim Square Pinlight (LED) 4"- 6 Watts Warmwhite pcs 28.00 850.00

Wood Mouldings & Sash Works


1.0 Cornice - Mattwood Colonial 1x4x12 lm 103.40 168.00

2.0 Center Moulding - Mattwood Colonial Casing 1x2x10 lm 206.80 128.00

3.0 Baseboards - Mattwood TRTD Mcasing 9x16x4x14 lm 89.90 228.00

Floor Finishes
1.0 500 x 500 Carpet Tiles (OSM) sq.m

Wall Finishes
1.0 Wall Paper (OSM) sq.m
2.0 1 x 1 solid wood door accent paint finish lm 90.00 128.00
3.0 Room Signage (OSM) rms

Painting works
1.0 Ceilings sq.m 67.20 140.00
2.0 Walls sq.m 248.16 140.00
3.0 Cornice lm 103.40 88.00
4.0 Center Moulding lm 206.80 88.00
5.0 Baseboard lm 89.90 88.00

E. TRADEWORKS
Plumbing & Sanitary Works, Incl Tapping Point
(Plumbing and Sanitary, Hot & Cold Water Line - PPR,
1.0 Installation of all fixtures, conrete coring, Bracket and room 15.00 20,000.00
supports, valves and accessories, Aircon Drain for 9 Split
Type Unit Aircons, etc.)
Unit
Item No. Description Unit Qty
Material
Electrical Works, Incl. Tapping Point (wires, cables,
conduit, outlets, switches, sub-feeder lines, installation
2.0 of RCP, USB Port w/ plates & speaker surround with room 15.00 30,000.00
platform), 2 - Fire Alarm (tap to nearest existing), wirings
for hallway pinlights , etc.

3.0 Mechanical Works (All ductworks and installation of


exhaust fan, Bracket and supports, valves and
accessories, installation of fresh air diffuser @ hallway room 15.00 8,000.00
and for split type units aircons, etc.)

4.0 Auxiliary Works, incl. wiring & installation of speaker


surround using UTP CAT 5e, Blank plate cover w/ 6 pins
push button switch, and wiring & installation of room 15.00 15,000.00
Electronic Door Lockset, Enercon system, relays, wiring
for WIFI (from hallway to Admin office)

Fire Protection Works (complete sprinkler system


5.0 works incl. piping and topping, Bracket and supports, room 15.00 20,000.00
valves and accessories, including fire house cabinet, etc.)

F. Others
Elevator façade
1.00 Granite red alphi (See actual specs installed) sq.m 9.80 6,800.00
Restoration of ceiling (if needed) @ kitchen & Rentable
2.00 sq.m 43.20 680.00
space

Cladding works @ level 2 of existing ducting (Using


3.00 sq.m 6.00 1,200.00
gypsum board w/ furring including painting)

Fire exit steel door w/ panic device w/ deadbolt


4.00 set/s 1.00 15,000.00
mechanism @ main stair

Additional Breaker (for 15 rooms) to be connected to


5.00 set/s 1.00 35,000.00
MDP (incl. feeder lines)
6.00 Emergency Lights with outlet set/s 4.00 2,500.00
Federal Moulded Doors HDF (40mm x 800mmx
7.00 set/s 2.00 4,500.00
2100mm) & Door Jamb
8.00 Lockset Key set/s 2.00 650.00
9.00 Butterfly Hinges (3pcs/Door) set/s 6.00 150.00

10.00 Doors and Jambs - Spray finished (lacquer type) set/s 2.00 2,000.00
Unit
Item No. Description Unit Qty
Material
DIRECT COST
Profit
Admin
General Requirements
TOTAL AMOUNT VAT INCLUSIVE
Cost per room 15

Note: Painting in Wood was Ducco Finish

Prepared By:

Company Name: G.B. CAMAYRA CONSTRUC

Date: 1/25/2017
ural Works,Wet Works,

Unit Labor Total Material Total Labor Total Amount

- 275,000.00 275,000.00
120,000.00 - 120,000.00 120,000.00
60,000.00 - 60,000.00 60,000.00
30,000.00 - 30,000.00 30,000.00
10,000.00 - 10,000.00 10,000.00
25,000.00 - 25,000.00 25,000.00
20,000.00 - 20,000.00 20,000.00
10,000.00 - 10,000.00 10,000.00

707,031.10 391,807.60 1,098,838.70

180.00 268,953.60 100,857.60 369,811.20

180.00 55,680.00 17,280.00 72,960.00

- - -

125.00 8,000.00 8,000.00 16,000.00


120.00 164,000.00 157,440.00 321,440.00
120.00 20,687.50 19,860.00 40,547.50
- - -
100.00 13,500.00 9,000.00 22,500.00
120.00 57,600.00 23,040.00 80,640.00
120.00 57,000.00 22,800.00 79,800.00

500.00 3,500.00 500.00 4,000.00

100.00 47,560.00 23,780.00 71,340.00


850.00 2,400.00 1,700.00 4,100.00
650.00 3,150.00 4,550.00 7,700.00
1,500.00 5,000.00 3,000.00 8,000.00
Unit Labor Total Material Total Labor Total Amount

1,208,829.88 590,752.32 1,799,582.20


355,862.80 175,231.70 531,094.50

150.00 19,819.80 6,352.50 26,172.30


150.00 4,392.00 1,350.00 5,742.00
2,500.00 15,000.00 12,500.00 27,500.00
150.00 15,000.00 750.00 15,750.00
150.00 9,750.00 2,250.00 12,000.00

150.00 3,750.00 750.00 4,500.00

1,500.00 19,400.00 7,500.00 26,900.00

650.00 8,250.00 3,250.00 11,500.00

250.00 - 1,250.00 1,250.00

120.00 2,250.00 600.00 2,850.00


55.00 2,250.00 825.00 3,075.00
55.00 600.00 275.00 875.00
55.00 940.00 275.00 1,215.00
55.00 1,500.00 550.00 2,050.00
55.00 440.00 275.00 715.00
55.00 600.00 275.00 875.00

80.00 10,584.00 5,040.00 15,624.00


80.00 8,550.00 3,000.00 11,550.00
80.00 1,152.00 720.00 1,872.00

200.00 28,798.00 8,470.00 37,268.00


Unit Labor Total Material Total Labor Total Amount

200.00 4,950.00 1,800.00 6,750.00

200.00 39,336.00 8,940.00 48,276.00

200.00 11,016.00 3,240.00 14,256.00


1,500.00 15,000.00 7,500.00 22,500.00

850.00 4,250.00 4,250.00 8,500.00


132.00 7,189.00 6,778.20 13,967.20
68.00 5,544.00 4,284.00 9,828.00
68.00 3,300.00 2,550.00 5,850.00
68.00 792.00 612.00 1,404.00
132.00 19,600.00 18,480.00 38,080.00

3,500.00 42,500.00 17,500.00 60,000.00

1,050.00 9,000.00 5,250.00 14,250.00


1,050.00 10,000.00 5,250.00 15,250.00
- - -
3,000.00 17,500.00 15,000.00 32,500.00
- - -

650.00 - 3,250.00 3,250.00


550.00 - 2,750.00 2,750.00
150.00 - 750.00 750.00
550.00 - 2,750.00 2,750.00
150.00 - 750.00 750.00
120.00 7,750.00 600.00 8,350.00
150.00 5,110.00 2,190.00 7,300.00
450.00 - 2,250.00 2,250.00
150.00 - 750.00 750.00
150.00 - 750.00 750.00
150.00 - 750.00 750.00
Unit Labor Total Material Total Labor Total Amount

522,345.60 262,556.14 784,901.74

150.00 32,596.20 10,447.50 43,043.70


150.00 6,148.80 1,890.00 8,038.80
4,000.00 35,000.00 28,000.00 63,000.00
150.00 21,000.00 1,050.00 22,050.00
150.00 4,550.00 1,050.00 5,600.00

150.00 5,250.00 1,050.00 6,300.00

1,500.00 27,160.00 10,500.00 37,660.00

650.00 11,550.00 4,550.00 16,100.00

250.00 - 1,750.00 1,750.00


120.00 3,150.00 840.00 3,990.00
55.00 3,150.00 1,155.00 4,305.00
55.00 840.00 385.00 1,225.00
55.00 1,316.00 385.00 1,701.00
55.00 2,100.00 770.00 2,870.00
55.00 616.00 385.00 1,001.00
55.00 840.00 385.00 1,225.00

80.00 15,758.40 7,504.00 23,262.40

80.00 13,246.80 4,648.00 17,894.80

80.00 1,612.80 1,008.00 2,620.80

200.00 47,362.00 13,930.00 61,292.00


Unit Labor Total Material Total Labor Total Amount

200.00 7,308.00 2,520.00 9,828.00

200.00 55,070.40 12,516.00 67,586.40

200.00 15,422.40 4,536.00 19,958.40


1,500.00 21,000.00 10,500.00 31,500.00

850.00 5,950.00 5,950.00 11,900.00


132.00 9,751.00 9,193.80 18,944.80
68.00 8,254.40 6,378.40 14,632.80
68.00 5,112.80 3,950.80 9,063.60
68.00 1,108.80 856.80 1,965.60
132.00 31,516.80 29,715.84 61,232.64

3,500.00 59,500.00 24,500.00 84,000.00

1,050.00 12,600.00 7,350.00 19,950.00


1,050.00 14,000.00 7,350.00 21,350.00
- - -
3,000.00 24,500.00 21,000.00 45,500.00
- - -

650.00 - 4,550.00 4,550.00


550.00 - 3,850.00 3,850.00
150.00 - 1,050.00 1,050.00
550.00 - 3,850.00 3,850.00
150.00 - 1,050.00 1,050.00
120.00 10,850.00 840.00 11,690.00
150.00 7,154.00 3,066.00 10,220.00
450.00 - 3,150.00 3,150.00
150.00 - 1,050.00 1,050.00
150.00 - 1,050.00 1,050.00
150.00 - 1,050.00 1,050.00
-
Unit Labor Total Material Total Labor Total Amount

330,621.48 152,964.48 483,585.96

150.00 17,774.64 5,697.00 23,471.64


150.00 3,162.24 972.00 4,134.24
4,000.00 15,000.00 12,000.00 27,000.00
150.00 9,000.00 450.00 9,450.00
150.00 5,850.00 1,350.00 7,200.00

150.00 2,250.00 450.00 2,700.00

1,500.00 23,280.00 9,000.00 32,280.00

650.00 4,950.00 1,950.00 6,900.00

250.00 - 750.00 750.00


120.00 2,700.00 720.00 3,420.00
55.00 2,700.00 990.00 3,690.00
55.00 720.00 330.00 1,050.00
55.00 564.00 165.00 729.00
55.00 900.00 330.00 1,230.00
55.00 264.00 165.00 429.00
55.00 360.00 165.00 525.00

80.00 9,028.80 3,168.00 12,196.80


80.00 691.20 432.00 1,123.20

200.00 28,485.00 7,596.00 36,081.00


200.00 3,758.40 1,296.00 5,054.40

200.00 26,136.00 5,940.00 32,076.00


Unit Labor Total Material Total Labor Total Amount

200.00 6,609.60 1,944.00 8,553.60

2,500.00 13,500.00 7,500.00 21,000.00

1,500.00 9,000.00 4,500.00 13,500.00


1,500.00 9,000.00 4,500.00 13,500.00

850.00 5,100.00 5,100.00 10,200.00


132.00 5,544.00 5,227.20 10,771.20
1,200.00 4,500.00 3,600.00 8,100.00
68.00 3,484.80 2,692.80 6,177.60
68.00 475.20 367.20 842.40
132.00 13,305.60 12,545.28 25,850.88

3,500.00 25,500.00 10,500.00 36,000.00

1,050.00 5,400.00 3,150.00 8,550.00


1,050.00 6,000.00 3,150.00 9,150.00
- - -
2,500.00 10,500.00 7,500.00 18,000.00
5,000.00 45,000.00 15,000.00 60,000.00
350.00 1,950.00 1,050.00 3,000.00

650.00 - 1,950.00 1,950.00


550.00 - 1,650.00 1,650.00
150.00 - 450.00 450.00
550.00 - 1,650.00 1,650.00
150.00 - 450.00 450.00
120.00 4,650.00 360.00 5,010.00
150.00 3,528.00 1,512.00 5,040.00
450.00 - 1,350.00 1,350.00
150.00 - 450.00 450.00
150.00 - 450.00 450.00
150.00 - 450.00 450.00
Unit Labor Total Material Total Labor Total Amount

220,502.80 131,625.52 352,128.32

150.00 31,449.60 10,080.00 41,529.60

98.00 10,035.20 7,683.20 17,718.40

150.00 23,800.00 4,200.00 28,000.00

- - -
80.00 17,371.20 8,272.00 25,643.20

80.00 26,470.40 16,544.00 43,014.40

80.00 20,497.20 7,192.00 27,689.20

- - -
- - -

- - -
- - -
98.00 11,520.00 8,820.00 20,340.00
- - -

- - -
132.00 9,408.00 8,870.40 18,278.40
132.00 34,742.40 32,757.12 67,499.52
68.00 9,099.20 7,031.20 16,130.40
68.00 18,198.40 14,062.40 32,260.80
68.00 7,911.20 6,113.20 14,024.40

1,395,000.00 765,000.00 2,160,000.00

12,000.00 300,000.00 180,000.00 480,000.00


Unit Labor Total Material Total Labor Total Amount

15,000.00 450,000.00 225,000.00 675,000.00

4,000.00 120,000.00 60,000.00 180,000.00

5,000.00 225,000.00 75,000.00 300,000.00

15,000.00 300,000.00 225,000.00 525,000.00

178,416.00 82,092.40 260,508.40


- - -
4,800.00 66,640.00 47,040.00 113,680.00

282.00 29,376.00 12,182.40 41,558.40

750.00 7,200.00 4,500.00 11,700.00

1,500.00 15,000.00 1,500.00 16,500.00

10,000.00 35,000.00 10,000.00 45,000.00

500.00 10,000.00 2,000.00 12,000.00

1,500.00 9,000.00 3,000.00 12,000.00

120.00 1,300.00 240.00 1,540.00


55.00 900.00 330.00 1,230.00

650.00 4,000.00 1,300.00 5,300.00


Unit Labor Total Material Total Labor Total Amount

3,709,779.78 1,961,277.84 5,671,057.62


850,658.64
212,212.31
275,000.00
7,850,000.00
523,333.33

G.B. CAMAYRA CONSTRUCTION

1/25/2017