Académique Documents
Professionnel Documents
Culture Documents
11- RISK
MANAGEMENT
page 1
RISK
An uncertain event or condition
that, if it occurs, has a positive or
negative effect on a project's
objectives.
page 2
RISK
Threat Opportunity
page 3
Threat
A condition or situation
unfavorable to the project, a
negative set of circumstances, a
negative set of events, a risk that
will have a negative impact on a
project objective if it occurs, or a
possibility for negative changes.
Contrast with opportunity.
page 4
Opportunity
A condition or situation favorable
to the project, a positive set of
circumstances, a positive set of
events, a risk that will have a
positive impact on project
page 5
RISK MANAGEMENT PROCESS
Analyze
How?
Identify
Qualitative
Quantitative
page 6
RISK MANAGEMENT PROCESS
page 7
11 - Project Risk Management
The processes concerned with
conducting risk management
planning, identification, analysis,
responses, and monitoring & control
on a project to
increase the probability and impact of
positive events,
and
decrease those adverse to the project.
page 9
SWOT ANALYSIS
INTERNAL STRENGTH WEAKNESS
EXTERNAL
~~~~~~~~ ~~~~~~~~
OPPORTUNITY ~~~~~~~~ ~~~~~~~~
~~~~~~~~ ~~~~~~~~
~~~~~~~~ ~~~~~~~~
THREAT ~~~~~~~~ ~~~~~~~~
~~~~~~~~ ~~~~~~~~
page 10
Reserve
A provision in the project
management plan to mitigate cost
and/or schedule risk. Often used
with a modifier (e.g., management
reserve, contingency reserve) to
provide further detail on what types
of risk are meant to be mitigated.
The specific meaning of the
modified term varies by application
area.
page 11
Reserve Analysis
An analytical technique to determine
the essential features and
relationships of components in the
project management plan to
establish a reserve for the schedule
duration, budget, estimated cost, or
funds for a project
page 12
RESERVE
page 13
Project Risk Management
page 14
Risk Management Plan
page 15
Contents of The Risk Management Plan
1. Methodology
2. Roles and responsibilities
3. Budgeting
4. Timing
5. Risk categories
6. Definitions of risk probability and impact
7. Probability and impact matrix
8. Revised stakeholders’ tolerances
9. Reporting formats
10.Tracking
page 16
page 17
page 18
page 19
Project Risk Management
Identify Risks
page 21
Project Risk Management
Perform Qualitative Risk
Analysis
Prioritizing risks for
subsequent further analysis or
action by assessing and
combining their probability of
occurrence and impact
page 22
Project Risk Management
Perform Quantitative Risk
Analysis
page 23
Expected Monetary Value
Calculate the EMV for the following risks:
• Opportunity of probability = 30% and
Impact of $10,000.
• Threat of probability = 10% and Impact of
$5,000.
• Threat of probability = 5% and Impact of
$100,000.
EMV = 30% x 10,000 – 10% x 5,000 – 5% x 100,000
page 25
ANSWER – Example 1
Initial Failure EMV
Cost Cost
200 35% x 242
k$ 120 k$ k$
- 70% x 315
450 k$ k$
page 27
PMBOK Example
• It will cost you 120 M$ to build a new plant
• It will cost you 50 M$ to upgrade the
existing one
• Given the following Decision Tree, what is
your decision and what is the monetary
value of it?
page 28
Cost
Revenue
page 29
Monte Carlo Analysis
A simulation uses a project model that
translates the uncertainties specified at a
detailed level into their potential impact
on objectives that are expressed at the
level of the total project . Project
simulations use computer models and
estimates of risk , usually expressed as a
probability distribution of possible costs
or durations at a detailed work level, and
are typically performed using Monte
Carlo
page 30 analysis .
Monte Carlo Analysis
page 32
Project Risk Management
Plan Risk Response
Developing
options and
actions to
enhance
opportunities, and
to reduce threats
to project
objectives.
page 33
Importing Material
• The risk is that material may sink
• Avoidance : Decide to deliver locally
• Transfer : Insurance
• Mitigate : Use more reliable shipping
company
• Active Acceptance : Import and prepare a
contingency plan such as local delivery
• Passive Acceptance : Do nothing , just
import the material
slide # 34
Risk Response Strategies
THREATS OPPORTUNITIES
Avoid Exploit
Mitigate Enhance
Transfer Share
A C C E P T
page 35
Risk Acceptance
A risk response planning technique
that indicates that the project team
has decided not to change the
project management plan to deal
with a risk , or is unable to identify
any other suitable response strategy
.
page 36
Threshold
• A cost, time, quality, technical, or resource
value used as a parameter, and which
may be included in product specifications.
Crossing the threshold should trigger
some action, such as generating an
exception report
page 37
Triggers
• Indications that a risk has occurred or is
about to occur. Triggers may be
discovered in the risk identification
process and watched in the risk monitoring
and control process. Triggers are
sometimes called risk symptoms or
warning signs
page 38
Workaround
• A response to a negative risk that has
occurred. Distinguished from contingency
plan in that a workaround is not planned in
advance of the occurrence of the risk
event
page 39
Residual Risk
Secondary Risk
A risk that arises as a direct result of
implementing a risk response.
page 40
Project Risk Management
Monitor & Control Risk
Tracking identified risks,
monitoring residual risks,
identifying new risks,
executing risk response plans,
and evaluating their
effectiveness throughout the
project life cycle
page 41
Assess Risk Workaround is a
Identify response to a
Risks Risk Rating (Qualitative Risk Analysis)
(Rating matrix) negative risk that
has occurred
at any time
Accept
Quantitative Risk Analysis
Response Planning
Watch List
Opportunity Threat
Secondary Fail
Risks Fallback plan
page 42
PERT EXAMPLE
What is the chance of finishing the following project within 24 days?
i j Act O M P
5 10 A 5 7 10
5 15 B 4 6 8
10 20 C 4 6 7
10 25 E 3 5 10
15 25 d1 0 0 0
15 30 F 5 6 8
20 35 G 2 4 6
25 35 L 2 3 5
30 35 d2 0 0 0
30 40 M 4 5 7
35 45 N 5 6 10
40 45 P 4 7 9
slide # 43
Calculate mean and standard deviation for each activity.
i j Act O M P te sd var
5 10 A 5 7 10 7.17 0.83 0.69
5 15 B 4 6 8 6.00 0.67 0.45
10 20 C 4 6 7 5.83 0.50 0.25
10 25 E 3 5 10 5.50 1.17 1.37
15 25 d1 0 0 0 0.00 0.00 0
15 30 F 5 6 8 6.17 0.50 0.25
20 35 G 2 4 6 4.00 0.67 0.45
25 35 L 2 3 5 3.17 0.50 0.25
30 35 d2 0 0 0 0.00 0.00 0
30 40 M 4 5 7 5.17 0.50 0.25
35 45 N 5 6 10 6.50 0.83 0.69
40 45 P 4 7 9 6.83 0.83 0.69
slide # 44
Calculate forward pass and identify critical path.
slide # 45
Calculate mean and standard deviation for the critical path.
i j Act O M P te sd var
5 15 B 4 6 8 6.00 0.67 0.45
15 30 F 5 6 8 6.17 0.50 0.25
30 40 M 4 5 7 5.17 0.50 0.25
40 45 P 4 7 9 6.83 0.83 0.69
slide # 46
Calculate Z = (T - TE) / SD and get the probability from the normal distribution table.
You may use Excel NORMDIST (T , TE , SD , TRUE)
exit
T %
19 0%
20 0%
21 1%
22 5%
23 18%
24 45%
25 74%
26 92%
27 99%
28 100%
29 100%
The chance of finishing this project within 24 days is 45%.
Note: The chance of finishing the project later than 24 days is 100-45 = 55%.
slide # 47