Vous êtes sur la page 1sur 11

This article has been accepted for publication in a future issue of this journal, but has not been

fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
1

Optimal Allocation of PV Generation and


Battery Storage for Enhanced Resilience
Bei Zhang, Student Member, IEEE, Payman Dehghanian, Student Member, IEEE,
and Mladen Kezunovic, Life Fellow, IEEE

 Sk,t the energy remained in the batteries on bus k at


Abstract—This paper proposes an optimal sizing and siting time t.
scheme for the battery storage and photovoltaic (PV) generation T Total time duration.
aiming at improving power system resilience. The concept of Qg Prioritization factor of the NB-S generating unit g.
capacity accessibility for both electricity demand and non-black- Pjstart Cranking power needed by NB-S generating unit j.
start (NB-S) generating units is proposed to evaluate the Tjcmax Critical maximum time for unit j to start up.
reachability to the power and energy capacity during extreme
Tjcmin Critical minimum time for unit j to start up.
events. Priority of the NB-S generating units, characterized by
their different importance during the black start (B-S) process, is
Rri Ramp rate of generating unit i.
also taken into account. The unknowable nature of the extreme Tbl_start Total time of the B-S process.
events is captured and modeled through a multi-objective Tlctp Cranking time for generating unit l.
optimization formulation to balance three main objectives: 1) the Pjrob Probability of scenario j.
investment and operation costs; 2) the capacity accessibility for r Interest rate.
electricity demand; and 3) the capacity accessibility for NB-S Lp Capital longevity.
generating units. The proposed approach is validated through CenergyB_in Unit investment cost of the battery energy.
numerical experiments, which illustrate how the new planning CpowerB_in Unit investment cost of the battery power.
approach can help enhance the grid resilience.
Cpv_in Unit investment cost of the PV generation.
Index Terms—battery storage, capacity accessibility, extreme CGi Marginal cost of power generation for unit i.
event, photovoltaic (PV) generation, resilience. CFRUi Marginal cost of ramp-up service for unit i.
CFRDi Marginal cost of ramp-down service for unit i.
I. NOMENCLATURE CBG,k Discharging cost of the battery storage at bus k.
A. Sets CBFRU,k Ramp-up cost of the battery storage at bus k.
K Set of buses in the system. CBFRD,k Ramp-down cost of the battery storage at bus k.
L Set of load points in the system. ξB,k Cost coefficient for battery degradation.
NBSG Set of all NB-S generating units. Djl,t Demand at load point l at time t in scenario j.
BSG Set of all B-S generating units. pGimin Minimum power generation of generating unit i.
ALL Set of all generating units. pGimax Maximum power generation of generating unit i.
Ω Set of different scenarios. ∆t Unit time interval.
G Set of all conventional generating units. DjFRU,t System ramp-up and ramp-down requirement at
DjFRD,t time t in scenario j.
B. Parameters
η-, η+ Battery charging and discharging efficiency.
Asi Availability index of the element i during an Sj0,k Initial state of charge (SOC) of the battery at bus k
extreme event of level s. in scenario j.
Aevent,s Designated system availability under an extreme Skmin Minimum battery SOC allowed at bus k.
event of level s. Skmax Maximum battery SOC allowed at bus k.
ζi Adjusting coefficient for the element i. Fmin Vector of transmission line minimum capacity.
Rsi-j Reachability between bus i and j under Aevent,s. Fmax Vector of transmission line maximum capacity.
PkGmax Power capacity of the conventional generating
units at bus k. C. Variables
Dl average load at load point l. Bkpow Power capacity of the battery storage at bus k.
θpow Capacity availability factor of the battery power. BkPV Power capacity of the PV generation at bus k.
θpv Capacity availability factor of the PV power. Bken Energy capacity of the battery storage at bus k.
θG Capacity availability factor of the conventional tjstart Starting time of NB-S generating unit j.
generating unit. ttj1 Time segment before the generating unit j starts.
ttj3 Time segment after the generating unit j reaches
This publication was made possible by the NPRP 8-241-2-095 award from its maximum generation capacity.
the Qatar National Research Fund (a member of the Qatar Foundation). The ttj4 Time segment before the cranking power is
statements made herein are solely the responsibility of the authors. needed for generating unit j.
The authors are with the Department of Electrical and Computer
Engineering, Texas A&M University, College Station, TX 77843 USA (e- wtj1 Status variable to denote the generating unit j
mails: adele.zhang@tamu.edu; payman.dehghanian@ieee.org; kezunov@ece. starts to generate power.
tamu.edu).

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
2

wtj2 Status variable to denote the generating unit j and thus leading to a potentially higher accessibility during
reaches its maximum generation capacity. extreme events. Despite some disadvantages of the battery
wtj3 Status variable to denote the cranking power is storage (e.g., limited energy capacity) and the PV generation
needed by generating unit j. (e.g., variable power output), their advantages still exhibit
uit Status variable to denote the unit i is started. promising features during extreme events. References [10],
pjGi,t Power generation of unit i at time t in scenario j. [11] investigate the energy not supplied (ENS) reduction
FRUji,t Ramp-up service of unit i at time t in scenario j. through batteries. How the B-S process can be expedited by
FRDji,t Ramp-down service of unit i at time t in scenario j. the additional battery capacity is investigated in [12]. Hence,
pjBdis,kt Discharging power of the battery at bus k at time t optimal allocation of the battery storage and PV generation
in scenario j.
aiming at improving the system resilience in face of extreme
pjBch,kt Charging power of the battery at bus k at time t in
events is an emerging planning problem to be solved.
scenario j.
Quite a few researchers have been studying the sizing and
FRUjB,kt Ramp-up service of the battery at bus k at time t in
scenario j. siting problem of the battery storage and the renewable
FRDjB,kt Ramp-down service of the battery at bus k at time t resources [13]-[25], among which [13]-[16] investigate the
in scenario j. problem in distribution systems and [17]-[24] focus on the
xjBdis,kt Status variables denoting whether the battery on transmission grid. The placement schemes in both distribution
bus k is discharging at time t in scenario j. and transmission systems are discussed in [25]. Facilitating
xjBch,kt Status variables denoting whether the battery on the grid operation is the main goal of the aforementioned
bus k is charging at time t in scenario j. research: [13] focuses on the risk-based operation of
pjpv,kt PV Power at bus k at time t in scenario j. distribution companies; [14] reduces the real power loss; [15]
Ftj Vector of the line flow at time t in scenario j enhances the system reliability; [18] and [19] improve the
grid-scale integration of renewables; [21] alleviates the
II. INTRODUCTION transmission congestion; and [17], [20], [22]-[25] minimize
the total operation cost. Ref [16] exceptionally optimizes some
P OWER grids are traditionally designed and planned to
operate reliably under normal operating conditions and
withstand the expected contingencies. Due to the recent years’
mobile resources in distribution systems in preparation for a
particular hurricane. The impact of such resources on
severe events in power industry (e.g., 2011 Fukushima Daiichi enhancing the grid resilience still requires further research.
nuclear disaster, 2012 Superstorm Sandy, and 2016 Hurricane In this paper, an optimal sizing and siting scheme for the
Hermine with approximately 8.5 million customer power battery storage and the PV generation in the transmission
outages and direct damage amounted to $71.4 billion in network is proposed. The suggested allocation scheme extends
United States [1]), it has become more apparent that further the conventional sizing and siting paradigm [17]-[24] for
considerations beyond the traditional system reliability accommodating battery storage and renewable resources to
analysis is needed for keeping the lights on at all times. New further improve the grid resilience in face of unknowable
NERC power system planning performance standard TPL- extreme events.
0014/0040a enforced in 2016 states that “studies shall be This paper is organized as follows: Section III models the
performed to assess the impact of the extreme events [2].” The capacity accessibility, with the concept of reachability during
resilience is becoming an emerging topic since how the extreme events proposed. A new method for prioritizing the
electricity grid can withstand and react to unexpected extreme NB-S generating units is also presented in Section III. Section
events has rendered more and more criticality to people’s lives IV proposes a multi-objective optimization model to allocate
and every aspect of our economy. the battery storage and PV generation aiming at improving
Recent research on power system resilience is elaborated in both the capacity accessibility and grid operation
references [3] and [4]. In [5], the grid resilience is quantified performance. Numerical experiments are conducted and
by assessing the vulnerability of transmission lines under analyzed in Section V. Section VI concludes the paper and
different loading and weather conditions. Power system lists the contributions.
resilience is a quite complicated concept with many driving
III. MODELING OF CAPACITY ACCESSIBILITY
factors such as generator governor actions [6], transient
stability [7], physical degradation [8], etc. Resource adequacy, A. Proposed Concepts
as another important factor influencing the grid resilience, is Capacity adequacy is one of the key factors playing a
discussed in [9] where a deterministic approach based on the critical role on system resilience [9]. Higher capacity
extent of the resource adequacy is adopted to examine the adequacy during the extreme events leads to a higher
system resilience in face of an extreme event similar to the accessibility to the capacity (conventional generation, PV
2014 Polar Vortex Event [9]. generation, battery energy, etc.), which renders a reduced
As an evolving and promising resource, the PV generation energy not supplied (ENS), expedited B-S process, etc. during
and battery storage are rapidly being deployed in the grid. the extreme events. With rapid advancements in the control of
Compared with conventional generators, batteries are able to power electronics, battery storages and PV generation are also
store the energy for use during emergencies. Besides, both the able to provide the required reactive power [26], [27].
PV generation and battery storage devices can be distributed, Coordinated with the conventional generators, their

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
3

effectiveness in speeding up the system restoration is studied 1 2 i j M


and proved in the past research [12], [28]. R s
11 R s
1 2 R s
1i R s
1 j R1s M  1
 s s s 
In this paper, a new metric of capacity accessibility during  R22 R 2 i R 2 j R2s M  2
extreme events is proposed to describe the capacity adequacy  
 
 Ri  M 
s
status during extreme events. The capacity accessibility Risi Ris j i (2)
 
determines the extent of power and energy the grid would be  
able to utilize during the extreme events. The difficulty in  R sj  j R j M 
s
j
 
assessing the capacity accessibility lies in the unknowable  
nature of the extreme events [29], i.e., those with low  RMs  M  M
occurrence probability but high impact [3], [4]. It is almost
C. Capacity Accessibility for Electricity Demand
impossible and not realistic to enumerate all the possible cases
and scenarios of different extreme events. Besides, referring The capacity accessibility for electricity demand reflects
the extreme event to several particular kinds of contingencies the extent of capacity that can be accessible to support the
may cause an inappropriate disregard of others. Differentiated load demand during the extreme event. Two types of capacity
from the conventional “N-m” contingency principle, we are considered: (a) power capacity and (b) energy capacity, the
propose to emulate the extreme event based on its common latter of which is specifically designed to quantify the energy
impact, which is the sharp decrease in the availability of stored in the battery storage, and implies how long the battery
system elements, instead of specifically defining the storage power can last.
contingency set. Extreme events under various severity levels Besides, there are different types of electricity demand in
are considered to take into account their unknowable nature. different load points (e.g., industrial, commercial, residential,
Generally, the capacity accessibility depends on: (1) the hospitals, etc.) with various loss of load consequences. The
size of available capacity, and (2) the reachability to the magnitude of the load is used in this paper as the priority
capacity during extreme events. index, while it can be modified adaptively to account for other
practical considerations. The system-wide power and energy
B. Reachability during Extreme Events capacity accessibility indices for electricity demand under an
We quantify the reachability based on the common impact extreme event of level s are defined in (3) and (4), denoted as
of the extreme events, i.e., the sharp decrease in the PCA_loads and ECA_loads, respectively.
 
availability of system elements. An availability index is first
assigned to each element during an extreme event, as in (1).   pow
k
Bpow   pv Bpv
k
 G pGk max   Rlsk  Dl
PCA_load  s kK lL
(3)
Ais  Aevent ,s   i (1) D
lL
l

 tn   
Aevent,s reflects the general availability of all system
elements under an extreme event of level s, i.e. the more
ECA_load s   Sk ,t  Rlsk  Dl   T   Dl    (4)
 t t0 kK lL   lL 
severe the extreme event is, the less likely that the device
would “survive” the extreme event. In this way, extreme In (3), the capacity availability factors θpow, θpv and θG are
events can be naturally grouped into different levels introduced to consider the uncertainty associated with the
characterized by different Aevent,s. The lower Aevent,s, the higher availability of the battery power, PV power and the power
destructive impact the event could result in. Meanwhile, the from the conventional generators, respectively. Due to the
availability of an element in face of the extreme event, Ais, is dependence on the solar irradiance, PV generation may not be
also affected by its own characteristic, denoted by ζi, which is able to always generate at its rated maximum capability. Such
statistically correlated to the factors such as the equipment capacity availability factor can be calculated as the ratio of the
reliability status, its length or size/capacity, its vulnerability in potential maximum generation, which is constrained by the
some extreme conditions, etc. In other words, the availability weather conditions (PV generation), available energy (battery
of different elements in face of the extreme events of the same storage) and equipment reliability (conventional generator), to
level is differentiated by ζi. the rated maximum generation within a period of time.
The reachability Rsi-j between node i and j under Aevent,s is The demand reachability of bus k, under an extreme event
defined as the probability that node i and j are within the same of level s, representing the total reachability of the unit
island and, therefore, reachable to each other. In a complex capacity on bus k to the entire distributed load, is defined in
system, this probability can be obtained through Monte Carlo (5). Therefore, the PCA_loads and ECA_loads can be re-
simulations. The probability is calculated as the number of expressed in (6) and (7), respectively.
scenarios where bus i and bus j are reachable to each other,  
divided by the total number of simulated scenarios. The
k ,s
Reachload   Rls k  Dl 
 lL 
  D lL
l (5)
reachability between each set of two nodes should be
calculated to evaluate the system reachability under an PCA_load s    pow Bpow
k
  pv Bpv
k
 G pGk max   Reachload
k ,s
(6)
kK
extreme event of level s, as denoted in (2), where M is the
total number of nodes. Note that different values of Aevent,s can  tn 
be assumed to simulate the extreme events of different levels. ECA_load s    Sk ,t  Reachload
k ,s
 T (7)
 t t0 kK 

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
4

D. Capacity Accessibility for NB-S Generating Units wit2  PGimax Rri  t  tit1  tit3  wit1  PGimax Rri
(13.g)
Other than reducing the ENS at load points, expediting the , t  1, 2,..., Tbl _ start , i  ALL, i  g
tlt3  wlt2 T  Tlctp  PGlmax Rrl  , t  1,2,...Tbl _ start , l  BSG
system B-S process can also help improving the system
(13.h)
resilience. Conventional generating units can be categorized Tbl _ start
into B-S and NB-S units. For those NB-S units, cranking t tj 3   u  T jt jctp  PGjmax Rrj  1 wtj 2
(13.i)
power is needed to initiate the first start, while a B-S unit (e.g. t 1

hydro unit, combustion turbine) can start on its own. At the , t  1, 2,..., Tbl _ start , j  NBSG , j  g
very beginning of the B-S process, the cranking power can be t tj 3  wtj 2Tbl _ start , t  1,2,..., Tbl _ start , j  NBSG , j  g (13.j)
supplied from the B-S units, the energy stored in the battery Tbl _ start

storage, and possibly the power from the installed PV wtj 3Tbl _ start  u
t 1
jt  t tj 4  t jstart  1, t  1, 2,..., Tbl _ start
(13.k)
generation. Previous research demonstrated that increasing the
j  NBSG , j  g
system capability to provide the required cranking power can
t tj 4  0 , t  1, 2,..., Tbl _ start , j  NBSG , j  g (13.l)
rapidly speed up the B-S process [12].
Tbl _ start
The system-wide capacity accessibility for NB-S units
during an extreme event of level s is defined in (8) and (9).
wtj 3  t  t tj 4  t 1
u jt , t  1, 2,..., Tbl _ start , j  NBSG , j  g (13.m)

   pow B pow
k
  pv Bpv
k
   Rgs k  Qg  t  t tj 4  wtj 3Tbl _ start , t  1,2,..., Tbl _ start , j  NBSG , j  g (13.n)
 kK

gNBSG
PCA_Gen   s
 Qg (8)
   G pG max   Rg  h  Qg 
h s
 gNBSG wtjh  wtjh1 , h  1,2,3, t  1,2,..., Tbl _ start  1, j  NBSG , j  g (13.o)
 hBSG gNBSG 
wit2  wit1 , t  1,2,..., Tbl _ start , i  ALL, i  g (13.p)
 tn   
ECA_Gen s   Sk ,t   Rgs k  Qg   T   Qg  (9) t tj1  t tj11 , t  1,2,..., Tbl _ start  1, j  NBSG , j  g (13.q)
 t t0 kK gNBSG   gNBSG 
t 1
Similarly, the generating unit reachability of bus k, under t  t , t  1,2,..., Tbl _ start  1, j  NBSG , j  g
t
j3 j3
(13.r)
an extreme event of level s, is defined in (10) to reflect the The objective (12) aims at maximizing the total generation
reachability of the unit capacity at bus k to all the NB-S units. capacity during the B-S process. Note that the generation
  capacity of the B-S unit within Tbl_start is constant, while the
k ,s
Reachgen     Rgs  k  Qg   Qg (10) generation capacity of the NB-S unit can be expressed as the
 g NBSG  gNBSG
difference of the shaded area in the left and right charts in
In this paper, the priority of an NB-S unit is coupled to its Fig.1, which is Sdeqh–Ssuzw=Sdkh+Sdeqk–Ssuzw=Sdkh+Saeqf–Sbdkg–
importance in the B-S process, i.e. how much less the pick-up Sabgf–(Sruzv–Srswv). Since some of these areas are constant and
energy would be, if a given NB-S unit does not participate in independent of tjstart, maximizing the area of Sdeqh–Ssuzw can be
the B-S process, and is defined in (11). transformed to minimizing the area of Sabgf–Srswv, which leads
Qg  Ebl0  start  Eblg start to (12). Meanwhile, tjstart is assumed to be zero for all B-S
(11)
units. The detailed definition of ttj1, ttj3, ttj4, wtj1, wtj2, wtj3, uit is
0
where E bl-start is the pick-up energy in the B-S process with shown in Fig. 1 [30], where the generator output Pgen and the
the participation of all generating units; Egbl-start is the pick-up cranking power Pstart during the start-up process are depicted.
energy with no participation of generating unit g. The Equations (13.a) and (13.b) limit the unit starting within the
evaluation of E0bl-start and Egbl-start depends on the sequence of max and min critical time. The power requirement during the
the units to be turned on during the B-S process, which is B-S process is described in (13.c), enforcing the generated
reflected via variable tjstart. The model presented in [30] is power be greater than the cranking power needed. Equations
utilized, with some modifications, to further improve the (13.d)–(13.f) set the boundaries on the time tti1, and correlate it
calculation performance. The order of the unit start-up is with wti1, which indicates that wti1 becomes 1 after Tlctp (for B-
evaluated through (12)-(13): S units) or tjstart+Tlctp (for NB-S units). The limits on the
duration tti2=t-tti1-tti3 and its correlation with wti1 and wti2 are
obj. min  P
jNBSG , j  g
j max  Pjstart   t jstart (12) presented in (13.g), which denotes that tti2 should be 0 before
wti1 becomes 1 and reaches it maximum after wti2 gets to 1.
s.t. t jstart  Tjc max , j  NBSG , j  g (13.a)
Equations (13.h)–(13.j) set the limits on tti3 and its correlation
t jstart  Tjc min , j  NBSG , j  g (13.b) with wti2, indicating that wti2 becomes 1 and tti3 starts to be
non-zero after the unit reaches its maximum generation
 Rr  t  t
iALL
i
t
i1  tit3   
jNBSG
wtj 3 Pjstart  0 , t  1, 2,..., Tbl _ start (13.c) capacity. Equations (13.k) and (13.l) limit ttj4 with wtj3 for NB-
,i  g , jg
S units, reflecting that ttj4 reaches its maximum after wtj3 turns
wlt1Tlctp  tlt1  Tlctp , t  1,2,...,Tbl _ start , l  BSG (13.d) to 1. The correlation of ttj5=t-ttj4 with wtj3 is described in
Tbl _ start (13.m) and (13.n), indicating that ttj5 will be non-zero after wtj3
T bl _ start  1  T jctp  wtj1  u jt  t tj1  t jstart  T jctp
(13.e)
turns to 1, and should be within Tbl_start. And (13.o)–(13.r) list
t 1 the constraints on the status variables corresponding to the
, t  1,2,..., Tbl _ start , j  NBSG , j  g physical operation status. The energy that is picked up during
t tj1  0, t  1,2,..., Tbl _ start , j  NBSG , j  g (13.f) the B-S process with no participation of unit g can be
eventually calculated in (14).

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
5

the capacity adequacy during an extreme event, which is one


of the many factors that contribute to the system resilience.
Therefore, enhancing the capacity accessibility when planning
a system-wide allocation of battery storage and PV generation
is critical for improving the system resilience.
A. Objective Functions
In order to optimally allocate the PV generation and
battery storages, multi-objective optimization is adopted to
Fig. 1. Illustration of some defined variables in formulation set (13) [30]. simultaneously consider: (a) the investment and operation
costs; (b) the capacity accessibility for the electricity demand;
(c) the capacity accessibility for the NB-S units; and (d) other
factors. The planning problem is to determine the power and
energy capacity of the battery storage as well as the power
capacity of the PV generation at each bus, denoted by Bpow,
Ben, and Bpv, respectively. We assume that both the
conventional units and the battery storages are bidding into the
ramp market, which is newly proposed to accommodate the
increasing net load variations and uncertainties [31].
The first objective (15.a), includes the investment cost of
the battery storage and the PV generation, as well as the
operation cost of the entire system, where fcr is the capital
recovery factor, calculated in (15.b), which converts the total
investment into a stream of annual payments; t0 and tn are the
starting and ending time of the simulations; The marginal cost
of PV generation is assumed to be 0. Stochastic programming
is adopted in (15) to handle the uncertainties of PV generation
intermittency, where various scenarios regarding to different
PV generation patterns and load profiles are considered.
obj1. Min   f
kK
cr
power k k

_ in Ben  f cr C B _ in B pow  f cr C pv _ in B pv 
CBenergy k

  CGi pGij ,t  CFRUi FRU i ,jt  CFRDi FRDi ,jt  


 iG  (15.a)
 
tn
  Prob
j
  CBG ,k pBdis
j
 C FRU j
 
t  t0  

, kt BFRU , k B , kt
j  
 kK  CBFRD ,k FRDB ,kt   B ,k  pBdis ,kt  pBch ,kt   
j j j
 

f cr  r 1  r  1  r  Lp  1
Lp
  (15.b)
Fig. 2. Illustration of system availability, reachability, capacity accessibility.
The second objective is related to the contribution of the

,i  g  PGimax  2Rri  PGimax Tbl _ start  Tictp  PGimax Rri   battery storage and the PV generation on the system-wide
2

iALL
  capacity accessibility for the demand, as described in (16).
Eblg  start    (14)
  PjstartTbl _ start    PGi tistart   PGj t jstart  
 iALL ,i  g
max max
 obj2. max PCA_load s  Tlasting   Prob
j
 ECA_load s , j (16)
 jNBSG ,  jNBSG , j  g  j
 jg 
The power capacity of the conventional units is neglected
Fig. 2 illustratively summarizes the concepts proposed so from (16) as the focus is solely on the battery storage and the
far: system availability, (generating unit/demand) reachability PV generation. Moreover, in order to combine the PCA_load
(node-based, illustratively for node i), and the capacity and ECA_load together, a coefficient approximately denoting
accessibility (system-wide). Three illustrative scenarios in
how long the battery power and the PV generation can last
terms of the extreme events of different severity levels
(Tlasting), is added to convert the power into energy.
(reflected by different system availability indices Aevent,s) are
Following the same principle, the third objective (17),
presented. In a more severe extreme event (scenarios 2 and 3),
the availability of the elements tends to be lower and the models the contribution of the battery storage and PV on the
reachability indices also decline. However, the reachability system-wide capacity accessibility for the NB-S units.
and accessibility indices are higher (reflected by longer-dotted obj3. max PCA_Gen s  Tlasting   Prob
j
 ECA_Gen s , j
j
(17)
lines) in a less severe extreme event (scenario 1).
The fourth objective (18) targets at improving the system
IV. OPTIMIZATION SCHEME FOR SIZING AND SITING OF reliability and represents the extensibility of modeling and
BATTERY STORAGE AND PV GENERATION incorporating additional factors in such a planning study. The
The capacity accessibility for both the electricity demand expected energy not supplied (EENS), as an example, is
and the NB-S units (Section III.B & III.C) can help evaluating selected here to reflect the system reliability performance.

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
6

obj4. min EENS    ILzk  z  Prob


z
 (18) Equations (19.a)–(19.d) set the limits reflecting the fact that
z kK
the battery cannot charge and discharge simultaneously. The
where ILkz is the interrupted load at bus k in contingency z; power balance considering the possible curtailment of PV
Pzrob denotes the occurrence probability of the contingency z; generation is modeled in (19.e) and (19.f). Coefficient β in
Λ is the set of all contingencies. The model is generic and this (19.g) is to ensure that the battery generation can last for a
objective can be also adjusted to consider other factors such as period of time. Equations (19.h)–(19.n) set the operation
risk, congestion management, etc. [32], [33]. conditions for the conventional units: (19.h) regulates the unit
generation within its upper and lower limits; (19.i) and (19.j)
B. Constraints
set limits on the ramp service provided by the unit; (19.k) and
The constraints of the proposed problem are as follows: (19.l) constrain the sum of the generation and the ramp service
0  pBdis
j
, kt  xBdis , kt Bpow ,
j k
j , k  K , t  t0 , t1 ,..., tn (19.a) within the generation capacity limits; (19.m) and (19.n)
models the ramping limits. The system ramp-up and ramp-
0 p j
Bch , kt x j
Bch , kt B k
pow , j , k  K , t  t0 , t1 ,..., tn (19.b) down requirements are set in (19.o) and (19.p). Equation
(19.q) is the battery dynamic equation, and (19.r), (19.s) set
, kt  xBch , kt  1, j , k  K , t  t0 , t1 ,..., tn
j j
xBdis (19.c)
the limitation on the battery energy. Battery operational limits
, kt , xBch, kt  0 or 1, j , k  K , t  t0 , t1 ,..., tn
j j
xBdis (19.d) are described in (19.t)–(19.w): (19.t) and (19.u) set the
charging/discharging power of the battery storage as well as
0  p pvj ,kt  Bpv
k
 pvj ,kt , j , k  K , t  t0 , t1 ,..., tn (19.e) its ramp service within its charging/discharging limits; (19.v)
p j
Gi ,t   p j
Bdis , kt  p pvj ,kt    j
pBch , kt  D j
l ,t
and (19.w) regulate the battery ramp service within its
i{G} k{ K } k{ K } l{ L} (19.f) capacity limits. Equation set (19.x) models the power flow
, j , t  t0 , t1 ,..., tn equations and the transmission line flow limits. The extended
k
Bpow  Benk  , k  K (19.g) distribution factor matrix H represents the algebraic
relationship between the branch flows and nodal power
min
pGi  pGij ,t  pGimax , j , k  K , t  t0 , t1 ,..., tn (19.h) injections. It includes not only the regular transmission
0  FRU  Rri  t , j , k  K , t  t0 , t1 ,..., tn
j constraints but also N-1 contingencies and security constraints.
i ,t (19.i)
C. Considerations of the Unknowable Nature of the Extreme
0  FRD  Rri  t , j , k  K , t  t0 , t1 ,..., tn
j
(19.j)
i ,t
Events in the Proposed Formulations
pGij ,t  FRUi ,jt  pGimax , j , k  K , t  t0 , t1 ,..., tn (19.k) In the proposed optimization model, the demand
reachability (Reachk,sload) and generating unit reachability
pGij ,t  FRDi ,jt  pGimin , j , k  K , t  t0 , t1 ,..., tn (19.l) (Reachk,sgen) of each bus, especially their sequence, play an
pGij ,t  pGij ,t 1  Rri  t , j , k  K , t  t0 , t1 ,..., tn (19.m) important role in maximizing the second and third objectives.
The reason lies in the fact that the same amount of available
pGij ,t 1  pGij ,t  Rri  t , j , k  K , t  t0 , t1 ,..., tn (19.n) capacity can achieve larger capacity accessibility if it is placed
 FRU j
  FRU j
D j
, j , t  t0 , t1 ,..., tn on a bus with higher reachability. However, the reachability
i ,t B , kt FRU ,t (19.o)
iG kK
of each bus can be quite different during the extreme events of
 FRD
iG
j
i ,t   FRDBj ,kt  DFRD
kK
j
,t , j , t  t0 , t1 ,..., tn (19.p) different levels, resulting in different allocation strategies.
Considering the unknowable nature of extreme events, the
Skj,t 1  Skj,t   pBdis
j
, kt    pBch , kt   t
  j
idea is to: (1) calculate Reachk,sload and Reachk,sgen of each bus
(19.q) under extreme events of different levels, which can be
, j , k  K , t  t0 , t1 ,..., tn
simulated by altering Aevent,s within a certain range; (2) obtain
Skj t  tn  S0,j k Benk , j , k  K (19.r) the optimal sizing and siting scheme under each set of
Reachk,sload and Reachk,sgen; (3) average the attained optimal
Skmin Benk  Skj,t  Skmax Benk , j , k  K , t  t0 , t1 ,..., tn (19.s) schemes to find the final allocation plan, as in (20).
 
Benk / pow/ pv    Benk / pow / pv  Aevent ,s   N S
p j
Bdis .kt p j
Bch , kt  FRU j
B , kt B k
pow
(19.t) (20)
, j , k  K , t  t0 , t1 ,..., tn  sS 
where S is the set of all different levels of extreme events
.kt  pBch , kt  FRDB , kt   B pow
j j j k
pBdis
(19.u) simulated; Ns is the number of extreme event levels in the set
, j , k  K , t  t0 , t1 ,..., tn S; Bken/pow/pv (Aevent,s) is the allocation scheme (battery energy,
0  FRU Bj ,kt  Bpow
k
, j , k  K , t  t0 , t1 ,..., tn (19.v) battery power or PV generation, respectively) at bus k under
Aevent,s; and Benk / pow/ pv is the final allocation scheme at bus k.
0  FRD j
B , kt B k
pow , j , k  K , t  t0 , t1 ,..., tn (19.w)
Fmin  Ft  HP  Fmax , j , t  t0 , t1 ,..., tn
j
(19.x) V. NUMERICAL EXPERIMENTS AND ANALYSIS
A modified IEEE-RTS 24-bus test system is employed to
where αjpv,kt is the PV prediction coefficient (the percentage of
illustrate the performance of the proposed framework.
the maximum output) on bus k at time t in scenario j. Further
Detailed system configuration, including the bus connectivity
details on physical modeling of the PVs can be found in [34].
and the unit parameters, is in [35]. Load profile and solar data

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
7

are collected from the ERCOT system [36] and the California
Irrigation Management Information System [37], respectively.
A. Prioritizing the NB-S Generating Units
During the B-S process, the hydro units located on bus 22
are treated as the B-S units, while the others are regarded as
NB-S units. Table I lists the start-up parameters of the units.
Fig. 3 demonstrates the starting time of the NB-S units during
the B-S process with participation of all generating units.
Also, the priority of each NB-S unit characterized by (11) is
illustrated. One can observe, from Fig. 3, that the importance
of the NB-S units during the B-S process does not solely
depend on their power capacity, but also affected by other Fig. 3. The priority and starting time of the generating units.
factors such as: (a) starting time: early start-up results in
higher priority (No. 21 vs. 22); (b) the value of Tctp: the longer
Tctp causes lower priority (No.1, 2 vs. No. 5, 6, and No. 3, 4
vs. No. 7, 8); (c) the value of Pstart: larger Pstart leads to lower
priority; and (d) ramp rates: higher ramp rate results in higher
priority. The reason behind (c) and (d) is that the NB-S units
with higher ramp rate and lower Pstart tend to start earlier than
the others, with the constraints on Tcmin and Tcmax satisfied.
B. Demand/Generating Unit Reachability under Extreme Events
Having recognized the priority of each NB-S unit,
Reachkload (5) and Reachkgen (10) can be calculated for each
bus under events of different levels, as illustrated in Fig. 4 and Fig. 4. Demand reachability (Reachkload) of each bus under events of different
Fig. 5, respectively. To illustrate the events of different levels intensity levels.
(from light to extremely severe), Aevent,s is varied from 0.01 to
0.9, with the interval of 0.05. To simplify the problem, the
adjusting coefficient ζ is assumed to be 1. One can see that the
reachability decreases as Aevent,s decreases (more severe). The
reachability of all buses is 1 (no island) when Aevent,s exceeds
0.9 and higher (that is why the upper limit for Aevent,s is
selected to be 0.9). The white stars in the aforementioned two
figures denote the bus with the highest reachability in each
case. Those stars connected with lines reflect the fact that the
highest reachability is achieved on the same bus. The results
demonstrate that: (1) the bus with the highest reachability
varies among the events of different levels. Therefore, various
events of different levels need to be considered when Fig. 5. Generating unit reachability (Reachkgen) of each bus under events of
determining the optimal sizing and siting scheme; (2) the bus different intensity levels.
with the highest demand reachability may not be the one with
the highest generating unit reachability. It confirms the need for a multi-objective optimization approach; (3) buses with the
highest reachability levels remain the same when Aevent,s
TABLE I changes within a certain range, and therefore, the selection of
LIST OF THE GENERATING UNITS’ START-UP PARAMETERS the 0.05 interval for Aevent,s would not miss any important
Gen Bus Unit Tctp Tcmin Tcmax Rr Pstart
ID ID Type (hr) (hr) (hr) (MW/min) (MW) buses. The lower bound of Aevent,s is determined to be 0.01, as
1, 2 1 U20 0 0:15 N/A 3 0 the important buses remain the same when Aevent,s is lower.
3, 4 1 U76 0 0:15 N/A 2 0
5, 6 2 U20 0:30 0 4:00 3 0.7 C. Optimal Sizing and Siting Scheme
7, 8 2 U76 0:30 0 4:00 2 2.6
9-11 7 U100 2:00 0 3:30 7 3 The proposed optimization is conducted considering the
12-14 13 U197 2:40 0:20 N/A 3 0.9 events with Aevent,s ranging from 0.01 to 0.85. The costs related
15 14 SC* 2:40 0:20 N/A 30 9
16-20 15 U12 2:00 0 N/A 1 0.7
to the generators are listed in Table II, in which the generation
21 15 U155 2:00 0 N/A 3 9 cost is calculated from [35]. r and Lp in (15.b) are assumed to
22 16 U155 1:40 0 N/A 3 3.1 be 0.25 and 10, respectively. CBG is selected to be 50; CBFRU
23 18 U400 0:30 0 N/A 20 8
24 21 U400 0:30 0 N/A 20 8.8 and CBFRD are considered to be 5.44 [31]. CenergyB_in, CpowerB_in
25-30 22 U50 0 0 N/A 5 0 and Cpv_in are calculated from [38]. The proposed formulation
31-32 23 U155 1:40 0 2:50 3 3.1
33 23 U350 1:40 0 2:50 4 7
is a mixed-integer linear optimization model and is solved by
* Synchronous Condenser CPLEX V12.5 in MATLAB (R2011a) environment on an

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
8

TABLE II accessibility metric is different from the concept of reliability;


LIST OF GENERATION COST AND RAMP COST
and (2) the improvement in system reliability cannot guarantee
Unit Type CG ($/MWh) CFRU, CFRD ($/MWh)
U12 85 15 the improvement on the capacity accessibility and system-
U20 90 15 wide resilience in face of extreme events.
U50 7 20
U76 31 15
The detailed placement solutions for the result denoted in
U100 75 15 the red dot in Fig. 6 are illustrated in Fig. 8, together with the
U155 27 20 case with a conventional placement scheme that just considers
U197 70 17
U350 25 15 the cost in obj.1 (15.a). One can observe that the proposed
U400 15 16 placement solution tends more to place the resources on the
buses with the highest Reachkload or Reachkgen, compared with
Intel i5 1.6-GHz processor (8 GB of memory), with the the other case (obj.1). The resource on bus 11 is an exception,
computation time of about 23 mins per case. Fig. 6 illustrates which also considers the operation requirements.
the Pareto Front resulted from the proposed scheme. The value In order to evaluate the impact of the placement of the
of lost load, assumed to be $3500/MWh [39], is utilized to battery storage and the PV generation on system resilience,
convert the second and third objectives into monetary values. especially on the load pick-up process, several contingencies
Besides, these two objectives are transformed into are simulated and the reaction of the system is studied. The
minimization problems through their additive inverse, and contingencies are assumed to occur on a certain day at hour 11
therefore, are in negative numbers. This figure illustrates the and last for 2 hours. The detailed information of the studied
trade-off between the economic cost and resilience, and contingencies is illustrated in Table III, in the order from light
provides a reference for the planning decision. to severe. The ENS associated with the proposed placement
Meanwhile, we conduct the N-1 and N-2 reliability analysis solution and the one with neither battery nor PV generation
(failure of any one or two elements in the system) on some of available are illustrated in Fig. 9 under different contingency
the optimal solutions in Fig. 6. The index of Loss of Load scenarios. In addition, Fig. 10 shows: (1) the differences in
Probability (LOLP) is utilized to evaluate the system ENS of all other placement cases under each contingency
reliability performance by reflecting the probability that the scenario, compared with that of the proposed case; and (2) the
load interruption occurs in the system. It is calculated in (21), Mean Absolute Error (MAE) of the differences in ENS under
where Π is the set of single-order and second-order each contingency scenario. Other than the placement solution
contingencies; yz is a binary variable indicating whether the obtained through obj.1 alone (see Fig. 8), additional sizing and
system experiences any load interruption (0: no load siting cases are compared. Case i denotes that the resources
interruption; 1: load interruption); the contingency probability obtained by the proposed method are all placed on the bus i.
Pzrob is calculated using the equipment failure probabilities.
LOLP   yz  Prob
z
(21)
z

Accordingly, Fig. 7 illustrates the result of LOLP indices as


well as the system-wide capacity accessibility for both
electricity demand and NB-S generating units (i.e., values of
obj. 2 & obj. 3). The system LOLP in the base case scenario is
0.82. From Fig. 7, one can observe that the installation of PV
and the battery storage does improve the system reliability, as
the updated LOLP is lower. However, no distinct correlation
between the LOLP and the capacity accessibility can be
observed. This highlights that (1) the proposed capacity
Fig. 7. Illustration of the LOLP and capacity availability.

-1.45
Obj2:generation reachabiltuy cost (1e9, $)

-1.5

-1.55

-1.6
-1.65

-1.7
-1.4
-1.75
-1.5
-1.8
-1.6
-1.85
-1.7
-1.9
-1.8
2.095
2.0955 2.096 2.0965 Obj3: load reachability
2.097 cost (1e9, $)
Obj1: Investment cost plus operation cost (1e9, $)

Fig. 6. Pareto front of the optimal sizing and siting scheme. Fig. 8. Detailed illustration of the optimal sizing and siting solutions.

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
9

TABLE III TABLE IV


DETAILED INFORMATION ON THE STUDIED CONTINGENCIES DETAILED RESULTS OF THE ENS UNDER VARIOUS ALLOCATION SCHEMES
ID Gen. in fault Lines in fault Gen. start-up Obj1 No PV generation
ID
1 U23, U24 None U13 ENS(MWh) Difference(MWh) ENS(MWh) Difference(MWh)
2 U23, U24 None None 1 2.54 1.32 4.92 3.71
3 U23, U24, U33 2, 3, 6 None 2 19.77 5.14 33.68 19.04
4 U23, U24, U33 2,3,6,10 None 3 595.71 42.94 683.33 130.55
5 U3, U4, U23, U24, U33 2, 3, 6, 10, 15, 16 None 4 595.71 42.94 683.33 130.55
6 U3, U4, U23, U24, U33 2,3,6,10,15,16,18,19,25,26,31 None 5 1088.62 63.31 1196.76 171.45
6 1463.37 77.26 1578.28 192.16
* Note: the ENS under the proposed case is set as the reference to generate the
“Difference” in Table IV.

Fig. 9. ENS of the system under difference contingencies.


Fig. 11. Energy pick-up during the black-start process.
the B-S process; (2) more energy can be picked up under the
proposed placement solution compared with the one that just
considers the investment and operational cost (obj.1); and (3)
the pick-up energy under the proposed scheme, although not
the highest, is higher than most of the other allocation cases.

VI. CONCLUSION
This paper investigates an optimal placement scheme for
battery storage and PV generation to be more accessible for
both the load and NB-S units in face of extreme events,
aiming at enhancing the system resilience. We introduced the
concepts of reachability and index of capacity accessibility to
help identifying some critical buses and framing the objectives
Fig. 10. Differences in ENS corresponding to different placement schemes.
in a multi-objective sizing and siting optimization paradigm. It
From Fig. 9 and Fig. 10, one can see that: (1) installation of is found in the numerical experiments that some buses are
the PV and the battery storage does help reducing the ENS quite more critical than others, since resources placed on those
during contingencies; and (2) the proposed placement solution buses can be more reachable by the loads or NB-S units
gradually shows its obvious advantage over the other during extreme events of different intensity levels. Following
placement schemes where the contingency tends to be more the proposed optimal sizing and siting scheme, the system has
extreme (the variations and the MAEs in Fig. 10 increase better performance in terms of load pick-up and the B-S
when the contingency is more severe). In order to more clearly process expedition during extreme events, compared with
demonstrate the difference in the ENS between the two cases other placement schemes. The difference becomes more
shown in Fig. 8, and to highlight the role of the PV generation, obvious when the contingency tends to be more extreme.
additional results are tabulated in Table IV*. In the case of The main contributions of the paper are:
“No PV generation”, the solar generation is removed from the 1) A new concept of reachability is proposed enabling the
proposed placement solution. The results demonstrate that the simulation of the impact of extreme events of different
PV generation, although not installed in a large capacity, is intensity levels on power systems;
also playing an important role in helping recovering the load, 2) Metrics of capacity accessibility for both demand and
especially when the contingency tends to be more extreme. NB-S generating unit are proposed which allows the
Last but not the least, the impact of different placement evaluation of the capacity adequacy during extreme
schemes on the B-S process, which is another critical aspect of events, considering the priority of the NB-S generating
system resilience, is evaluated in terms of the pick-up energy units in terms of their criticality in the B-S process;
in Fig. 11. One can observe that: (1) the integration of battery 3) A new multi-objective optimization model is
storage and PV generation helps restore more energy during formulated to find the optimal sizing and siting scheme

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
10

for the battery storage and PV generation, aiming at [17] M. Ghofrani, et al, “A framework for optimal placement of energy
storage units within a power system with high wind penetration”, IEEE
improving the system resilience through increasing the Trans. Sustainable Energy, vol. 4, no. 2, pp. 434-442, Apr. 2013.
system-wide capacity accessibility, taking into account [18] M. Ghofrani, et al, “Energy storage application for performance
the unknowable nature of the extreme events and costs; enhancement of wind integration”, IEEE Trans. Power Syst., vol. 28, no.
4, pp. 4803-4811, Nov. 2013.
4) Numerical experiments are conducted to verify the
[19] L. Zheng, et al, “Optimal energy storage system allocation and operation
effectiveness of the proposed approach in improving for improving wind power penetration”, IET Generation, Trans. &
the system resilience. Dist., vol. 9, no. 16, pp. 2672-2678, Dec. 2015.
Future research may include a detailed physical modeling [20] C. Thrampoulidis, S. Bose, & B. Hassibi, “Optimal placement of
distributed energy storage in power networks”, IEEE Trans. Automatic
of PV and storage units to be incorporated in the proposed Control, vol. 61, no. 2, pp. 416-429. Feb. 2016.
optimization framework. Other aspects of system [21] H. Pandžić, Y. Wang, T. Qiu, Y. Dvorkin, and D. S. Kirschen, “Near-
resilience, e.g., transmission line energization, load pickup, optimal method for siting and sizing of distributed storage in a
transmission network”, IEEE Trans. Power Syst., vol. 30, no. 5, pp.
and system stability, should be also further studied and 2288-2300, Sep. 2015.
efficiently embedded in the suggested optimization scheme. [22] S. Wogrin, & D. F. Gayme, “Optimizing storage siting, sizing, and
technology portfolios in transmission-constrained networks”, IEEE
Trans. Power Syst., vol. 30, no. 6, pp. 3304-3313. Nov. 2015.
REFERENCES [23] V. Krishnan, & T. Das, “Optimal allocation of energy storage in a co-
[1] S. Frueh, “Improving power system resilience in the 21st century,” Resilie optimized electricity market: Benefits assessment and deriving
nt America Roundtable. Jul. 24-25, 2014. [Online]. Available: http://sites. indicators for economic storage ventures”, Energy, vol. 81, pp. 175-188,
nationalacademies.org/cs/groups/pgasite/documents/webpage/pga_15342 Mar. 2015.
0.pdf. [Accessed: Jan, 21st, 2017]. [24] R. Fernández-Blanco, Y. Dvorkin, B. Xu, Y. Wang, and D. S. Kirschen.
[2] NERC, “2015 Risk element: extreme physical events,” Industrial Webina “Energy storage siting and sizing in the WECC area and the CAISO
r, Oct. 15, 2015. [Online]. Available: http://www.nerc.com/pa/comp/Doc system” Jun, 2016. [Online]. Available: https://www2.ee.washington.
uments/2015%20Extreme%20Physical%20Events%20v1.08.pdf. [Access edu/research/real/Library/Reports/storage_siting_and_sizing.pdf.
ed: Jan, 21st, 2017]. [25] M. Motalleb, E. Reihani, & R. Ghorbani, “Optimal placement and sizing
[3] M. Panteli, and P. Mancarella, “The grid: stronger, bigger, smarter?: of the storage supporting transmission and distribution networks”,
Presenting a conceptual framework of power system resilience”, IEEE Renewable Energy, vol. 94, pp. 651-659, Aug. 2016.
Power and Energy Magazine, vol. 13, no. 3, pp. 58-66, May./Jun. 2015. [26] H. Yu, J. Pan, & A. Xiang, “A multi-function grid-connected PV system
[4] M. Panteli and P. Mancarella, “Modeling and evaluating the resilience with reactive power compensation for the grid,” Solar Energy, vol. 79,
of critical electrical power infrastructure to extreme weather events”, no. 1, pp. 101-106, 2005.
IEEE System Journal, Feb. 2015. [Online]. Available: [27] S. Adhikari & F. Li, “Coordinated Vf and PQ control of solar
http://ieeexplore.ieee.org/stamp/stamp.jsp?arnumber=7036086. photovoltaic generators with MPPT and battery storage in
[5] M. Panteli and P. Mancarella, “Operational resilience assessment of microgrids”, IEEE Trans. Smart Grid, no.5, vol.3, pp.1270-1281, 2014.
power systems under extreme weather and loading conditions”, in Proc. [28] L. Jiang, & Q. Yang, “Intelligent power supply restoration in power
IEEE PES General Meeting, pp. 1-5, 2015, Denver, Colorado, USA. distribution networks with distributed generation,” IEEE 2016 China Int.
[6] D. Barus, “Implementation of free governor action in power plant to Conf. on Electricity Distribution (CICED), pp. 1-6, Aug. 2016.
increase system resilience of Jawa Bali power system network”, in [29] C. Velásquez, et al, “A framework for transmission expansion planning:
Proc. 46th International Universities' Power Engineering Conference A complex problem clouded by uncertainty,” IEEE Power and Energy
(UPEC), pp. 1-5, 2011. Magazine, vol. 14, no. 4, pp. 20-29, Jul-Aug 2016.
[7] Y. Liu, Q. H. Wu, and X. X. Zhou, “Co-ordinated multiloop switching [30] W. Sun, C. C. Liu, and L. Zhang, “Optimal generator start-up strategy
control of DFIG for resilience enhancement of wind power penetrated for bulk power system restoration”, IEEE Trans. Power Syst., vol. 26,
power systems”, IEEE Trans. Sustainable Energy, vol. 7, no. 3, pp. no. 3, pp. 1357-1366, Aug. 2011.
1089-1099, Jul. 2016. [31] B. Zhang, and M. Kezunovic, “Impact on power system flexibility by
[8] K. Eshghi, B. K. Johnson, and C. G. Rieger, “Power system protection electric vehicle participation in ramp market”, IEEE Trans. Smart
and resilient metrics”, in Proc. IEEE Resilience Week, pp. 1-8, 2015. Grid, vol. 7, no. 3, pp. 1285-1294, May. 2016.
[9] T. C. Ly, J. N. Moura, and G. Velummylum, “Assessing the bulk power [32] M. Moeini-Aghtaie, A. Abbaspour, & M. Fotuhi-Firuzabad,
system's resource resilience to future extreme winter weather events”, “Incorporating large-scale distant wind farms in probabilistic
in IEEE Power & Energy Society General Meeting, pp. 1-4, 2015, transmission expansion planning—Part I: Theory and algorithm,” IEEE
Denver, Colorado, USA. Trans. Power Syst., vol. 27, no. 3, pp. 1585-1593, Aug. 2012.
[10] Y. Sun, Z. Li, M. Shahidehpour, et al., “Battery-based energy storage [33] A. Arabali, M. Ghofrani, M. Etezadi-Amoli, et al., “A multi-objective
transportation for enhancing power system economics and security”, transmission expansion planning framework in deregulated power
IEEE Trans. Smart Grid, vol. 6, no. 5, pp. 2395-2402, Sept. 2015. systems with wind generation,” IEEE Trans. Power Syst., vol. 29, no. 6,
[11] N. Kadel, W. Sun, and Q. Zhou, “On battery storage system for load pp. 3003-3011, Nov. 2014.
pickup in power system restoration”, in IEEE Power and Energy Society [34] Y. M. Atwa, E. F. El-Saadany, M. M. A. Salama, & R. Seethapathy,
General Meeting, pp. 1-5, 2014, Washington DC, USA. “Optimal renewable resources mix for distribution system energy loss
[12] W. Liu, L. Sun, Z. Lin, et al., “Multi-objective restoration optimisation minimization,” IEEE Trans. Power Syst., vol. 25, no. 1, pp. 360-370,
of power systems with battery energy storage systems,” IET Generation, Feb. 2010.
Transmission & Distribution, vol. 10, no. 7, pp. 1749-1757, Feb. 2016. [35] C. Grigget al., “The IEEE reliability test system-1996. A report prepared
[13] Y. Zheng, Z. Y. Dong, F. J. Luo, et al, “Optimal allocation of energy by the reliability test system task force of the application of probability
storage system for risk mitigation of DISCOs with high renewable methods subcommittee,” IEEE Trans. Power Syst., vol. 14, no. 3, pp.
penetrations”, IEEE Trans. Power Syst., vol.29, no.1, pp.212-220, 2014. 1010–1020, Aug. 1999.
[14] M. A. Darfoun, M. E. El-Hawary, “Multi-objective optimization [36] ERCOT Balancing Energy Services Daily Reports Archives. 2008
approach for optimal distributed generation sizing and balancing energy services daily reports. [Online]. Available: http:
placement”, Electric Power Components and Systems, vol.43, no.7, pp. //www.ercot.com/mktinfo/services/bal/2008/index
828-836, Apr. 2015. [37] California Irrigation Management Information System (CIMIS),
[15] A. S. Awad, T. H. El-Fouly, & M. M. Salama, “Optimal ESS allocation [Online]. Available: http://www.cimis.water.ca.gov/
and load shedding for improving distribution system reliability”, IEEE [38] L. Xu, X. Ruan, C. Mao, B. Zhang, & Y. Luo, “An improved optimal
Trans. Smart Grid, vol. 5, no. 5, pp. 2339-2349, Sep. 2014. sizing method for wind-solar-battery hybrid power system,” IEEE
[16] H. Gao, Y. Chen, S. Mei, S, et al., “Resilience-oriented pre-hurricane Trans. Sustainable Energy, vol. 4, no.3, pp. 774-785, Jul. 2013.
resource allocation in distribution systems considering electric buses,” [39] A. A. Thatte, X. A. Sun, and X. Le, “Robust optimization based
Proceedings of the IEEE, Feb. 2017. [Online]. Available: economic dispatch for managing system ramp requirement,” in Proc.
http://ieeexplore.ieee.org/stamp/stamp.jsp?arnumber=7879853 Hawaii Int. Conf. Syst. Sci., pp. 2344–2352, 2014, Waikoloa, HI, USA.

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TSG.2017.2747136, IEEE
Transactions on Smart Grid
11

BIOGRAPHY

Bei Zhang (S’12) received the B.S. and M.S.


degrees from Shanghai Jiao Tong University,
Shanghai, China, in 2009 and 2012,
respectively, both in electrical engineering.
She is currently pursuing the Ph.D. degree in
electrical engineering from Texas A&M
University, College Station, TX, USA.
Her research interests include power system
reliability, electric vehicle, and electricity
market.

Payman Dehghanian (S’11) received the


B.Sc. and M.Sc. degrees both in Electrical
Engineering respectively from University of
Tehran, Tehran, Iran, in 2009, and Sharif
University of Technology, Tehran, Iran, in
2011. He is currently a research assistant at
the Department of Electrical and Computer
Engineering, Texas A&M University, where
he is pursuing his PhD degree. His research
interests include power system protection and control, power system
reliability and resiliency, asset management, and smart electricity grid
applications.
Mr. Dehghanian is the recipient of the 2013 IEEE Iran Section Best M.Sc.
Thesis Award in Electrical Engineering, the 2014 and 2015 IEEE Region 5
Outstanding Professional Achievement Awards, and the 2015 IEEE-HKN
Outstanding Young Professional Award.

Mladen Kezunovic (S’77-M’80–SM’85–F’99),


received the Dipl. Ing., M.S., and Ph.D. degrees
in electrical engineering in 1974, 1977, and
1980, respectively. He has been with Texas
A&M University for 31 years.
Currently, he is Regents Professor and Eugene
E. Webb Professor, Director of the Smart Grid
Center, Site Director of NSF I/UCRC "Power
Engineering Research Center, PSerc". His
expertise is in Protective Relaying, Automated
Power System Disturbance Analysis,
Computational Intelligence, Data Analytics, and Smart Grids. He has
published over 550 papers, given over 120 seminars, invited lectures and short
courses, and consulted for over 50 companies worldwide. He is the Principal
of XpertPower™ Associates, a consulting firm specializing in power systems
data analytics.
Dr. Kezunovic is an IEEE Life Fellow, a CIGRE Fellow and Honorary
Member, and a Registered Professional Engineer in Texas.

1949-3053 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.

Vous aimerez peut-être aussi