PROYECTO : REHABILITACIÓN Y MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD EN EL TRAMO DE LA CARRETERA DOS AGUAS – CASHUNAYO ALTA, DISTRITO DE CHINCHAO, HUÁNUCO - HUÁNUCO
REHABILITACION Y
I MEJORAMIENTO DEL SERVICIO 1,494,197.85 1,494,197.85
DE TRANSITABILIDAD
25.00% 25.00% 25.00% 25.00%
01 OBRAS PROVISIONALES 2,800.00 2,800.00
700.00 700.00 700.00 700.00
5.00% 10.00% 10.00% 10.00% 10.00% 15.00% 20.00% 20.00%
02 TRABAJOS PRELIMINARES 12,809.63
1,280.96 1,280.96 1,280.96 1,280.96 1,921.44 2,561.93 2,561.93
12,809.63
640.48
7.00% 7.00% 7.00% 7.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 7.00% 5.00%
03 MOVIMIENTO DE TIERRAS 913,461.86
63,942.33 63,942.33 63,942.33 63,942.33 91,346.19 91,346.19 91,346.19 91,346.19 91,346.19 91,346.19 63,942.33 45,673.09
913,461.86
5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00%
04 PAVIMENTOS 189,626.58
9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 18,962.66 18,962.66 18,962.66 18,962.66 18,962.66 18,962.66
189,626.58
7.00% 7.00% 7.00% 7.00% 7.00% 8.00% 8.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00%
05 OBRAS DE ARTE Y DRENAJE 368,165.78
25,771.60 25,771.60 25,771.60 25,771.60 25,771.60 29,453.26 29,453.26 25,771.60 25,771.60 25,771.60 25,771.60 25,771.60 25,771.60 25,771.60
368,165.78
10.00% 15.00% 15.00% 15.00% 15.00% 10.00% 10.00% 5.00% 5.00%
06 SEÑALIZACION 6,060.00
606.00 909.00 909.00 909.00 909.00 606.00 606.00 303.00 303.00
6,060.00
5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
07 HITOS KILOMETRICOS 1,274.00
63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70
1,274.00
COSTO DIRECTO 1,508,270.73 133,887.07 318,748.16 378,617.53 148,921.37 127,227.92 189,975.74 128,754.45 82,138.49 1,508,270.73
GASTOS GENERALES 10.0% 150,827.07 13,388.71 31,874.82 37,861.75 14,892.14 12,722.79 18,997.57 12,875.45 8,213.85 150,827.07
UTILIDADES 10.0% 150,827.07 13,388.71 31,874.82 37,861.75 14,892.14 12,722.79 18,997.57 12,875.45 8,213.85 150,827.07
PRESUPUESTO DE OBRA 1,809,924.88 160,664.48 382,497.79 454,341.04 178,705.64 152,673.50 227,970.89 154,505.34 98,566.19 1,809,924.88
IGV 18.0% 325,786.48 28,919.61 68,849.60 81,781.39 32,167.02 27,481.23 41,034.76 27,810.96 17,741.91 325,786.48
SUB TOTAL PRESUPUESTO 2,135,711.35 189,584.09 451,347.39 536,122.42 210,872.66 180,154.73 269,005.65 182,316.30 116,308.10 2,135,711.35
EXPEDIENTE TECNICO 50,648.12 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 50,648.12
GASTOS DE SUPERVISION 70,013.54 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 70,013.54
PRESUPUESTO DE OBRA 2,256,373.01 204,666.80 466,430.10 551,205.13 225,955.37 195,237.44 284,088.36 197,399.01 131,390.81 2,256,373.01
% DE INCIDENCIA 9.07% 20.67% 24.43% 10.01% 8.65% 12.59% 8.75% 5.82% 100%