CRONOGRAMA VALORIZADO DE OBRA

PROYECTO : REHABILITACIÓN Y MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD EN EL TRAMO DE LA CARRETERA DOS AGUAS – CASHUNAYO ALTA, DISTRITO DE CHINCHAO, HUÁNUCO - HUÁNUCO

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8


ITEM PARTIDAS PARCIAL SUB TOTAL
1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM 1 SEM 2 SEM 3 SEM 4 SEM

REHABILITACION Y
I MEJORAMIENTO DEL SERVICIO 1,494,197.85 1,494,197.85
DE TRANSITABILIDAD
25.00% 25.00% 25.00% 25.00%
01 OBRAS PROVISIONALES 2,800.00 2,800.00
700.00 700.00 700.00 700.00
5.00% 10.00% 10.00% 10.00% 10.00% 15.00% 20.00% 20.00%
02 TRABAJOS PRELIMINARES 12,809.63
1,280.96 1,280.96 1,280.96 1,280.96 1,921.44 2,561.93 2,561.93
12,809.63
640.48
7.00% 7.00% 7.00% 7.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00% 7.00% 5.00%
03 MOVIMIENTO DE TIERRAS 913,461.86
63,942.33 63,942.33 63,942.33 63,942.33 91,346.19 91,346.19 91,346.19 91,346.19 91,346.19 91,346.19 63,942.33 45,673.09
913,461.86
5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 10.00% 10.00%
04 PAVIMENTOS 189,626.58
9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 9,481.33 18,962.66 18,962.66 18,962.66 18,962.66 18,962.66 18,962.66
189,626.58
7.00% 7.00% 7.00% 7.00% 7.00% 8.00% 8.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00% 7.00%
05 OBRAS DE ARTE Y DRENAJE 368,165.78
25,771.60 25,771.60 25,771.60 25,771.60 25,771.60 29,453.26 29,453.26 25,771.60 25,771.60 25,771.60 25,771.60 25,771.60 25,771.60 25,771.60
368,165.78
10.00% 15.00% 15.00% 15.00% 15.00% 10.00% 10.00% 5.00% 5.00%
06 SEÑALIZACION 6,060.00
606.00 909.00 909.00 909.00 909.00 606.00 606.00 303.00 303.00
6,060.00
5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
07 HITOS KILOMETRICOS 1,274.00
63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70 63.70
1,274.00

II PLAN DE MANEJO AMBIENTAL 14,072.88 14,072.88


2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 7.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
01 PLAN DE MANEJO AMBIENTAL 14,072.88
281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 281.46 985.10 703.64 703.64 703.64 703.64 703.64 703.64 703.64 703.64 703.64 703.64 703.64 703.64 703.64
14,072.88

COSTO DIRECTO 1,508,270.73 133,887.07 318,748.16 378,617.53 148,921.37 127,227.92 189,975.74 128,754.45 82,138.49 1,508,270.73
GASTOS GENERALES 10.0% 150,827.07 13,388.71 31,874.82 37,861.75 14,892.14 12,722.79 18,997.57 12,875.45 8,213.85 150,827.07
UTILIDADES 10.0% 150,827.07 13,388.71 31,874.82 37,861.75 14,892.14 12,722.79 18,997.57 12,875.45 8,213.85 150,827.07
PRESUPUESTO DE OBRA 1,809,924.88 160,664.48 382,497.79 454,341.04 178,705.64 152,673.50 227,970.89 154,505.34 98,566.19 1,809,924.88
IGV 18.0% 325,786.48 28,919.61 68,849.60 81,781.39 32,167.02 27,481.23 41,034.76 27,810.96 17,741.91 325,786.48
SUB TOTAL PRESUPUESTO 2,135,711.35 189,584.09 451,347.39 536,122.42 210,872.66 180,154.73 269,005.65 182,316.30 116,308.10 2,135,711.35
EXPEDIENTE TECNICO 50,648.12 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 6,331.02 50,648.12
GASTOS DE SUPERVISION 70,013.54 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 8,751.69 70,013.54
PRESUPUESTO DE OBRA 2,256,373.01 204,666.80 466,430.10 551,205.13 225,955.37 195,237.44 284,088.36 197,399.01 131,390.81 2,256,373.01
% DE INCIDENCIA 9.07% 20.67% 24.43% 10.01% 8.65% 12.59% 8.75% 5.82% 100%