Vous êtes sur la page 1sur 11

Engineering Geology 85 (2006) 302 – 312

www.elsevier.com/locate/enggeo

Prediction of tunnel lining loads using correction factors


H.J. Kim a,⁎, Z. Eisenstein b
a
Department of Geological Engineering, Daejeon University, 96-3 Yongwoon Dong, Dong-gu, Daejeon, 300-716, South Korea
b
Department of Civil and Environmental Engineering, University of Alberta, Edmonton, Alberta, Canada
Received 26 August 2004; received in revised form 28 September 2005; accepted 10 March 2006
Available online 21 April 2006

Abstract

A design method for the prediction of lining loads should include the decrease of lining loads due to the stress release before
lining installation and the increase of lining loads due to development of ground yielding. Schwartz and Einstein included both
factors in their original closed form solutions in the form of a support delay factor λd and a yield factor λy respectively. The validity
of the design method is reviewed by comparing the loads calculated using the methods with the field measurements obtained from
several tunnels. The possible causes of the load discrepancy between measurements and predictions are presented.
Schwartz and Einstein's proposed method gives reasonable results for tunnels with short delay lengths. However, the method
could not be used reliably for tunnels either with long delay lengths or with voids between the soil and TBM due to the difficulties
finding the pre-support ground movements and therefore λd.
© 2006 Elsevier B.V. All rights reserved.

Keywords: Tunnel lining loads; Support delay factor; Yield factor; Prediction of lining loads; Field measurements

1. Introduction by a number of authors (Craig and Muir Wood, 1978;


O'Rourke, 1984; Duddeck and Erdmann, 1985; Negro,
Prediction of lining loads is one of the major issues to be 1988; Whittaker and Frith, 1990; Kim and Eisenstein,
addressed in the design of a tunnel. However, the problem 1998) and will not be repeated here again.
is not easily solved due to uncertainties of the ground There are several basic requirements of a good design
conditions, the redistribution of the in situ stresses related method. First, the design method should be simple to use.
to the ground deformation before and after lining in- Duddeck and Erdmann (1985) reviewed the progress of the
stallation, and the differences in construction procedures. development of design models. They concluded that the
Therefore, most tunnels are often built too conservatively. available design methods are simple enough for practical
The lining loads can be calculated using many existing applications. In other words, if a design method is very
lining design methods which may be divided into four complex or time consuming to apply, the method will not
groups: empirical and semi-empirical methods, ring and be widely used by practical engineers. Second, the design
plate models, ring and spring models, and numerical mo- method should consider the stress release occurring before
dels. Most of these methods have been reviewed in detail the installation of a liner in some way. Muir Wood (1975)
presented a closed form solution, recommending a 50%
⁎ Corresponding author. Tel.: +82 42 280 2574; fax: +82 42 280 570. reduction of the full overburden pressures to account for
E-mail address: hakkim@dju.ac.kr (H.J. Kim). support delay. The 50% stress reduction is an arbitrary
0013-7952/$ - see front matter © 2006 Elsevier B.V. All rights reserved.
doi:10.1016/j.enggeo.2006.03.001
H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312 303

value, and various suggestions have been given by others, replotted in the form of the ground and the liner
e.g. about a 33% stress reduction as suggested by Panet characteristic curves. Ui is the ground displacement
(1973). Einstein and Schwartz (1980) also suggested that that occurs before the liner installation, whereas Uf is
the stress reduction factor could be between 15% and the final ground displacement that would have occur-
100% according to simple analytical and numerical tech- red if no liner had been applied. If the lining is
niques and case study data. Third, the method should take installed in contact with the ground at point B, the
into account the plastic behaviour of the ground as well as lining will resist only Ua. The displacement of liner,
that of elastic ground. However, most of the existing Ul, is usually smaller than Ua due to the greater stiff-
methods were not satisfactory for the estimation of lining ness of the liner than that of the ground. Uoe is the final
loads because they could not consider all the factors elastic displacement for an unlined circular opening at
mentioned above. infinity behind the face. The support delay factor was
Schwartz and Einstein (1980a,b) suggested using obtained from finite element analyses. The support de-
correction factors to take into account the decrease of lay length Ld is defined as the distance between the
lining loads due to the stress release before lining tunnel face and the midpoint of the leading support
installation and the increase of lining loads due to section as shown in Fig. 2 (A). Fig. 3 shows the rela-
development of ground yielding. The method is reviewed tionship between λd and the normalized support delay
in detail in this paper with the emphasis on the delay factor length determined from the results of the axisymme-
λd. The main purpose of this study is to verify the tric finite element analyses using values for Ld / R of
applicability of the method for actual tunnel design. 0.25, 0.75, and 1.25 (Schwartz and Einstein, 1980a,b).
The relationship can be expressed as follows:
2. Effect of delay in liner placement
kd ¼ 0:98−0:57ðLd =RÞ ð2Þ
Einstein and Schwartz (1979) presented closed form
solutions for the estimation of loads on the liner, solutions where R is the tunnel radius. Schwartz and Einstein
which depend mainly on the relative support stiffness and suggested not using Eq. (2) for cases in which Ld / R is
in situ stress ratio. Einstein and Schwartz's method has less than 0.15 or more than about 1.5.
been widely used by practical engineers due to its sim- The equilibrium support pressure in a yielding gro-
plicity. However, the original Einstein and Schwartz und should satisfy the equation:
method generally overestimates the lining loads because
fg ðPs Þ−fs ðPs Þ−fd ðkd Þ ¼ 0 ð3Þ
the method is calculated based on the full overburden
pressure without consideration of the stress reduction
occurring prior to lining installation. This has been cor- The terms in the equation are shown in Fig. 1. The
rected by Schwartz and Einstein (1980a,b). ground characteristic curve, fg(Ps), can be obtained from
Schwartz and Einstein (1980a,b) included the any of the standard axisymmetric plasticity solutions for
decrease of support loads with the delay of the the tunnelling problem (e.g., Deere et al., 1969). Schwartz
support construction behind the face and the increase and Einstein (1980a,b) found the value using a Mohr–
of support loads due to development of ground Coulomb yield criterion with zero total volume change in
yielding with the original closed form solutions in the yield zone. fs(Ps) is the support characteristic curve,
the form of a support delay factor λd and a yield factor which is expressed as follows for a linearly elastic support:
λy respectively. The support delay factor can be
Ps R2 ð1−m2s Þ
expressed as: fs ðPs Þ ¼ ð4Þ
Es As
PsV Uoe −Ui
¼ ¼ kd : ð1Þ
Ps Uoe where νs is the Poisson's ratio of the support, Es is the
Young's modulus of the support and As is the cross-
Ps is the support load obtained from the plane strain sectional area of the support.
relative stiffness solution as suggested by Einstein and fd(λd) is the offset of the support characteristic curve
Schwartz (1979) and Ps′ is the reduced support load equivalent to the support delay, which can be expressed
due to the effect of support delay as shown in Fig. 1. as:
Fig. 1 (A) shows the longitudinal distribution of the PRð1 þ mÞ
radial displacements that have occurred when the fd ðkd Þ ¼ ð1−kd Þ: ð5Þ
E
tunnel face was advanced to point A. In Fig. 1 (B), the
ground response of excavation shown in Fig. 1 (A) is If there is no support delay, λd is 1 and fd(λd) equals 0.
304 H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312

Fig. 1. Effect of support delay on support loads and characteristic curves for yielding ground.

The yield factor λy is mainly a function of the strength 3. Comparison with case study data
of the ground and is indirectly dependent on the support
delay and the relative support stiffness. To calculate λy, Schwartz and Einstein (1980a) applied the procedure
Eq. (3) must be solved twice. First, Ps⁎ is calculated for to five tunnel projects in order to verify the accuracy of
the yielding ground case using the correct ground the proposed method. These case histories are summa-
strength properties. Second, Ps′ is obtained for the elastic rized in Table 1. The normalized lining loads, (T /
case using artificially high ground strength properties. PR)predic, calculated using the method were compared
The ground yield factor λy is then equal to the ratio Ps⁎/Ps′. with field measurements of the case histories and gave
The final thrust T can be expressed as: errors in the predicted support loads that ranged between
the extremes of − 68% (underestimated) and 62%
T ¼ k d ky T 1 ð6Þ
(conservative), with an average error of 32%, as
in which T1 is the thrust calculated from the original shown in Table 2. Predicted lining loads using closed
closed form solutions of Einstein and Schwartz (1979). form solutions of Einstein and Schwartz (1979) without
H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312 305

Fig. 2. Support delay length for the simulated and actual tunnelling sequences.

the consideration of correction factors, (T / PR)basic, give The support delay length Ld for the Kielder Ex-
errors between − 42% and 242%, with an average error perimental tunnel was 4.0 m. Since the tunnel radi-
of 97%. us was 1.65 m, the normalized delay length Ld / R of
Schwartz and Einstein (1980a) reported several 2.4 exceeded the upper limits of about 1.5. The
problems when applying the method suggested above. authors found the upper bound support load from the

Fig. 3. Support delay correction factor.


306 H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312

Table 1
Case studies used for the application of Schwartz and Einstein's method
Tunnel Method Geology Depth (m) Diameter (m) References
Garrison Drill and blast Clay shale 30–55 7.9–10.7 Lane (1960), Burke (1960)
Kielder Exp. Road header Mudstone 75–100 3.3 Ward et al. (1976), Ward (1978)
Thunder Bay Shielded TBM Silty clay 10.5 2.38 Belshaw and Palmer (1978)
Tyne Hand Exca. Clay 12.1 3.2 Attewell and El-Naga (1977)
Victoria, PCL Digger shield London clay 27.9 4.28 Ward and Thomas (1965)
Victoria, cast iron 26.1 4.0

equilibrium point between the convergence and con- element analysis even though the excavation and
finement curves assuming that the support curve support construction do not take place simultaneously
offset is Uoe . The support load was calculated from in the actual tunnelling sequence. Therefore, the authors
the combination of the relative stiffness solution and considered a delay length Ld for actual tunnelling
Eq. (3). sequences as the delay length Ld in the finite element
Another problem was to calculate the support analyses. This is true if the liner is installed before
delay length Ld for the tunnel constructed by a TBM excavation in the finite element sequence.
with a shield such as that of the Thunder Bay Sewer Hutchinson (1982) observed that Ld′, the distance
tunnel. The support delay length was taken from the from the old face before excavation to the center of the
tail of the rigid TBM rather than from the face of the closest liner segment, should be considered as the delay
tunnel to the midpoint of the second ring behind the length for the actual tunnelling sequences based on the
TBM because the tail void could be grouted after axisymmetric finite element analyses and case histories.
clearing the TBM tailpiece. However, the measured Hutchinson suggested that the line for Eq. (2) in Fig. 3
settlements indicated that the grouting procedure was should be translated as shown with the new equation as
not effectively filling the tail void between the follows:
support and the ground. Therefore, the pre-support
ground movements, Uo′, were added to the calculation kd ¼ 0:70−0:57ðLV=RÞ:
d ð8Þ
of support delay. Eq. (2) for the support delay
correction factor could be modified as: Hutchinson suggested using Eq. (8) with a delay
length Ld′ based on the assumption that the excavation
kd ¼ 0:98−0:57ðLd =RÞ−UoV=Uoe 0Vkd V1 ð7Þ and lining installation might not be done at the same
time in the finite element analyses of Schwartz and
Einstein. However, if Hutchinson's assumption is valid,
4. Discussion of results Eq. (2) should have been used with Ld′.
There is an actual reason that Eq. (8) should be
Schwartz and Einstein (1980a,b) compared the actual used with Ld′ rather than applying Eq. (2) with Ld,
and simulated tunnelling sequences as shown in Fig. 2. which was not recognized by Hutchinson. Hutch-
Excavation and support occur at one step in a finite inson performed axisymmetric finite element analyses

Table 2
Comparisons of predicted and measured average thrust coefficients
Case (T / PR)basic Ld / R Uo′ (cm) λd λy (T / PR)predic (T / PR)mea. Error (%)
Garrison, 4A 0.41 1 0 0.41 1.24 0.208 0.132 58
Garrison, 4B1 0.03 1 0 0.41 4.95 0.061 0.052 17
Garrison, 4B2 0.033 1 0 0.41 4.66 0.063 0.039 62
Garrison, 2B, F 0.106 1.33 0 0.22 4.33 0.101 0.078 29
Garrison, 2E 0.123 1.17 0 0.31 2.95 0.112 0.132 −15
Garrison, 5A–E 0.14 1 0 0.41 2.21 0.127 0.115 10
Kielder Exp. 0.464 2.4 0 0 – 0.227 0.162 40
Thunder Bay 0.714 1.26 0–4.5 0.011 43.8 0.482 0.422 14
Tyne, site 1 and 2 0.724 0.57 0 0.66 1 0.478 0.387 24
Victoria, concrete 1.23 0.43 0.79–1.11 0.24 1.18 0.324 0.359 −10
Victoria, cast iron 1.2 0.46 0.95–1.27 0.07 2.29 0.16 0.49 −68
H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312 307

and compared the results with those from the analyses and Einstein's for the case compared with a Ld such
of Schwartz and Einstein as shown in Fig. 3. The as LC1′ as shown in Fig. 3. In other words, a dif-
results are plotted as LC1 and LC1′. However, the ferent λd can be obtained for the same delay length of
comparison was not done correctly for the point, LC1′, Ld depending on the round length if Eq. (2) is applied
obtained from the delay length of Ld because the round with a Ld as suggested by Schwartz and Einstein.
length and the length of support that Hutchinson λd calculated from Eqs. (2) and (8) using Ld and Ld′
adopted for the analyses were 1R. respectively are the same only if a round length of 0.5R
The differences in two tunnelling sequences is used for a certain tunnelling sequence because the
applied for the finite element analyses are presented round length or the length of the support ring used for
in Fig. 4. It is a well-known fact that the load distri- the finite element analyses of Schwartz and Einstein was
bution along one segment of lining is not uniform. 0.5R. This is the reason that Eq. (8) can be obtained if
Therefore, the load should be taken at the center of (L′d + 0.5R) is substituted for Ld in Eq. (2). The problem
the liner segment to get the average value. A Ld of can be eliminated if Eq. (8) is used with Ld′ because the
1.5R was used by Hutchinson for the point of LC1′ in distance actually determines the load on the lining in the
the finite element analyses as shown in Fig. 4(B). finite element analyses and in the actual tunnelling
Even though Schwartz and Einstein did not perform sequence. In other words, the same lining loads can
finite element analyses with a Ld of 1.5R, the tun- always be obtained for the same delay length of Ld′
nelling sequence used by them was drawn as shown regardless of the round length. Therefore, Eq. (8), which
in Fig. 4(A) for comparison with the Hutchinson's is obtained from finite element analyses using the
case. The figure is drawn based on the finite element distance Ld′, should be applied with the delay length Ld′
mesh that Schwartz and Einstein (1980a,b) used for from the actual tunnelling sequence as shown in Fig. 2.
the analyses. The comparison can be done because This is the reason that LC1 matches well with the line
Schwartz and Einstein's result shows a linear rela- from Eq. (8) along with a Ld′ of 0.5R, while LC1′ does
tionship between λd and Ld / R as shown in Eq. (2). not agree with the line from Eq. (2) combined with Ld of
However, the distance Ld′, which is from the old face 1.5R. Eq. (8) is not applicable for values of Ld′ / R greater
before excavation to the center of the liner segment than about 1.
to be installed in the next round, as shown in Fig. 4,
actually determines the amount of stress release 5. Recalculation of the lining loads
before liner installation. After one round of simulta-
neous excavation and support for both cases, the Lining loads of case histories calculated by Schwartz
distance Ld′ for Hutchinson's case is 0.5R, which is and Einstein were recalculated using Eq. (8) and delay
shorter than the 1R of Schwartz and Einstein's case. length Ld′ as shown in Table 3. The yield factor λy was
This is the reason that the load from Hutchinson's obtained following the procedure suggested by Schwartz
analyses gave a higher value than that of Schwartz and Einstein because the derivation of λy was very

Fig. 4. Tunnelling sequences used in the finite element analyses.


308 H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312

Table 3
Comparisons of predicted and measured average thrust coefficients using delay length Ld′
Case (T / PR)basic Ld′ / R Uo′ (cm) λd λy (T / PR)predic (T / PR)mea. Error (%)
Garrison, 4A 0.41 0.67 0 0.32 1.49 0.195 0.132 48
Garrison, 4B1 0.03 0.67 0 0.32 6.23 0.060 0.052 15
Garrison, 4B2 0.033 0.67 0 0.32 5.86 0.062 0.039 59
Garrison, 2B, F 0.106 0.88 0 0.2 4.74 0.100 0.078 28
Garrison, 2E 0.123 0.77 0 0.26 3.48 0.111 0.132 −16
Garrison, 5A–E 0.14 0.67 0 0.32 2.7 0.121 0.115 5
Kielder Exp. 0.464 0.79 0 0.25 1.47 0.171 0.162 6
Thunder Bay 0.714 0.42 4.5 0.2 3.22 0.460 0.422 9
Tyne, site 1 and 2 0.724 0.19 0 0.59 1 0.427 0.387 10
Victoria, concrete 1.23 0.14 0.72 0.24 1.07 0.316 0.359 −12
Victoria, cast iron 1.2 0.16 0.72 0.17 1.14 0.233 0.49 −52

reasonable. There is an another advantage to using Ld′ over bead at the leading edge of the digger shield considering
Ld. The method suggested by Schwartz and Einstein could the expansion of the liner. Table 3 shows that the results
not be used for the Kielder Experimental tunnel because give errors in the predicted support loads ranging between
the delay length Ld was 4 m with the normalized delay the extremes of − 52% (underestimated) and 59%
length Ld / R of 2.4, which exceeded the upper limits of (conservative), with an average error of 24%, which is
Ld / R of about 1.5. The long delay length Ld / R was caused better approximation than that of Schwartz and Einstein.
by the long round length of 1.64R. However, the method
could be applied without any problem if Ld′ is used since 6. Application of the method to tunnels in
L′d was 1.3 m with a Ld′ / R of 0.79, which is less than the Edmonton
upper limits of Ld′ / R of about 1.
Another modification is applied during the recalcula- Schwartz and Einstein's method was applied to
tion of the lining loads due to the existence of the pre- tunnels in Edmonton using Eq. (8) and delay length Ld′
support ground movements, Uo′. Eq. (7) should be used to to verify the accuracy and applicability of the proposed
calculate λd for the Thunder Bay tunnel because of U′o. method. Tunnels in Edmonton used for this study are
However, a Uo′ of 4.5 cm exceeded the elastic radial summarized in Table 4 and described briefly in this
displacement of the unlined tunnel, which is about section. The City of Edmonton has been developing a
2.4 cm. Schwartz and Einstein suggested finding an Light Rail Transit (LRT) system since the early
upper bound support load from the equilibrium point seventies. The development of the system has been in
between the convergence and confinement curves stages, the first of which is termed the Northeast Line,
assuming that the support curve offset is Uoe. The support connecting the city center with northeast suburbs. The
load was calculated from the combination of the relative tunnels are located within a dense, jointed till sequence.
stiffness solution and Eq. (3). However, the predicted The tunnels were advanced using a shielded mechanical
load gave only an upper bound support load. Therefore, mole manufactured by Lovat Tunnelling Equipment
λd of 0.2 is arbitrarily assumed for the calculation of the Inc., Toronto. The primary support system is composed
load based on the finite element analyses of Hutchinson of steel ribs at 1.22 m centers and timber laggings while
(1982), which showed that some thrust would be obtained the permanent lining was cast-in-place reinforced
even at large values of support delay in an elastic analysis. concrete. The project is described in detail by Eisenstein
An additional difficulty occurred using the method due and Thomson (1978).
to the consideration of negative displacement caused by The second stage is termed the LRT-South Extension
the expansion of the lining during erection for the case of tunnel and connects the Central station with the Canadian
the Victoria Line tunnels. The authors presented equations Pacific Railway right-of-way. The two stages have a total
for the negative displacement due to jacking pressure length of 10.3 km, with eight stations. The tunnel was
assuming that the liner was fully in contact with the soil excavated with a tunnel boring machine (TBM) built by
before the liner was expanded. However, many field Lovat Tunnel Equipment Inc., Ontario. The tunnel is
measurements in other tunnels showed that the liner might located within till and described in detail by Eisenstein
not be fully contacted even after the expansion of the liner et al. (1982). The initial support system for the tunnel is
(e.g. Eisenstein et al., 1979). Therefore, Uo′ is assumed to composed of steel ribs at 1.22 m centers and wooden
be one half of the void between the soil and the cutting laggings placed between the webs of successive ribs. The
H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312 309

Table 4
Tunnels in Edmonton used for the application of Schwartz and Einstein's method
Tunnel Method Geology Depth (m) Diameter (m)
Northeast Line TBM Till 10.2 6.1
LRT-South Exten. TBM Till 11.8 6.2
SLRT–Phase II (Section B2) TBM Till 15.8 6.3
SLRT–Phase II (Section C2) NATM Till 9.7 6.3
SLRT–Phase II (Section A1) TBM Sand 17.2 6.3
Whitemud Creek TBM Shale 47.2 6.05
170th street TBM Till 20 2.56
Experimental tunnel (Section 1) TBM Till 27 2.56
Experimental tunnel (Section 2) TBM Till 27 2.56
Experimental tunnel (Section 3) TBM Till 24 2.56
North Saska. River (Section 1) TBM Till 13.7 3.2
North Saska. River (Section 2) TBM Till 13.7 3.2
North Saska. River (Section 4) TBM Sand 16.7 3.2

permanent lining consists of 0.30 to 0.38 m thick rein- mented lining (Sections 2 and 3) were used in two separate
forced concrete. The third stage, which is 1.8 km long, is parts of the tunnel. The primary lining in the conventional
termed the South Light Rail Transit (SLRT)–Phase II lining system is composed of steel ribs at 1.5 m centers and
tunnels and connects the North Saskatchewan River bank timber lagging. The secondary lining is plain concrete,
to Corona station. The tunnels in Sections B2 and C2 are 20 cm thick. Each meter of the precast concrete lining
located within a thick layer of glacial till while Section A1 consists of four segments 11 cm thick. These segments
is located in postglacial sand (Tweedie et al., 1989). The were assembled in the shield behind the mole and were
primary support system for the NATM tunnel (Section expanded radially to the excavated surface of the soil as
C2) is composed of 15 cm of shotcrete and steel ribs at soon as the shield advanced beyond them. The tunnel is
1.0 m centers. The initial support system for the TBM described in detail by Eisenstein et al. (1979).
tunnel (Sections B2 and A1) is composed of steel ribs and The tunnel on the banks of North Saskatchewan River
wooden lagging. The permanent support was formed by is 1670 m long with an excavated diameter of 3.2 m. The
0.25 m thick cast-in-place concrete. tunnel is used to convey storm water to the North
The Whitemud Creek Tunnel is an extension of a storm Saskatchewan River. The tunnel was bored through till
system to an outfall in the North Saskatchewan River. The (Sections 1 and 2) and sand (Section 4) by a TBM
tunnel was bored through Upper Cretaceous clay shale by (Corbett, 1984). The primary lining consists of segmented
two moles. The primary lining consisted of segmented steel ribs at 1.22 m centers and timber lagging. The three
steel ribs at 1.5 m centers and spruce laggings. The plain steel segments required to make the complete circle were
concrete secondary lining was placed about 4 months after erected within the shield. Steel sets were expanded using
completion of the moling operation (Thomson and El- radially positioned rams.
Nahhas, 1980). Most of the soil and lining parameters used for the
The 170th Street tunnel was constructed to connect the application of the Schwartz and Einstein method were
sewer network under a new city subdivision to the obtained from the references presented by Thomson
existing main sewer interceptor. The mole used was fully et al. (1982), Thurber (1986), EBA (1988), and Mont-
shielded and similar to that used in the Northeast Line. gomery and Eisenstein (1995) which are summarized in
The initial lining consisted of steel ribs at 1.5 m centers Table 5.
with timber lagging. The plain concrete permanent lining One major problem arose when applying the
was placed 10 days after completion of the moling of the method to tunnels in Edmonton. If support delay
tunnel. When the mole had advanced sufficiently that the lengths are taken from the face of the tunnels, all of
rib emerged from the tailpiece, it was expanded outwards the normalized delay lengths, Ld / R or Ld′ / R, exceeded
using hydraulic jacks (Thomson and El-Nahhas, 1980). the upper limits of 1.5 or 1. On the other hand, if
In Edmonton, a new tunnel construction method was support delay lengths are taken from the tail of the
introduced on an experimental basis using a precast seg- TBM with consideration of Uo′ due to the existence of
mented concrete lining in 1978. The tunnel is used as a voids between the soil and the mole, the normalized
main storm sewer for a freeway. The conventional two- delay lengths are within the limits. However, the voids
phase support system (Section 1) and the precast seg- often exceeded Uoe , which made λd meaningless
310 H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312

Table 5
Input parameters for the application of Schwartz and Einstein's method
Tunnel Ground Support In situ stress
E (MPa) ν ϕ (°) c (kPa) Es (GPa) νs 2
As (m /m) P (kPa) K
Northeast Line 150 0.4 40 0 200 0.2 0.0039 214 0.8
LRT-South Exten. 150 0.4 40 0 200 0.2 0.0039 248 0.8

SLRT–Phase II
(Section B2) 150 0.4 40 0 200 0.2 0.0047 332 0.8
(Section C2) 150 0.4 40 0 10 0.25 0.19 204 0.8
(Section A1) 100 0.3 30 0 200 0.2 0.0047 361 1.0
Whitemud Creek 250 0.4 16 50 200 0.2 0.0032 991 1.0
170th street 150 0.4 40 0 200 0.2 0.0017 420 0.8

Experimental tunnel
(Section 1) 150 0.4 40 0 200 0.2 0.0017 567 0.8
(Section 2) 150 0.4 40 0 25.1 0.25 0.11 567 0.8
(Section 3) 150 0.4 40 0 25.1 0.25 0.11 504 0.8

North Saska. River


(Section 1) 150 0.4 40 0 200 0.2 0.002 288 0.8
(Section 2) 150 0.4 40 0 200 0.2 0.002 288 0.8
(Section 4) 100 0.3 30 0 200 0.2 0.002 351 0.8

according to Eq. (7). Therefore, upper bound lining average error of 75%. The method give better results
loads were calculated for Edmonton tunnels using than those from solutions of Einstein and Schwartz
the procedure suggested by Schwartz and Einstein (1979) without consideration of correction factors,
(1980a). which give errors between − 19% and 1198%, with an
The upper bound lining loads are calculated and average error of 277%. However, most of lining loads
compared with field measurements for tunnels in were underestimated even though the method was
Edmonton as shown in Table 6. The results give errors supposed to give upper bound lining loads. A possible
in the predicted support loads ranging between − 83% cause of the underestimation of lining loads may be
(underestimated) and 174% (conservative), with an related to the fact that the actual ground displacements

Table 6
Comparisons of predicted and measured average thrust coefficients for tunnels in Edmonton
Tunnel (T / PR)basic (T / PR)predic (T / PR)mea. Method of measurements Error (%) for basic Error (%) for predic.
Northeast Line 0.641 0.135 0.789 Strain gauge − 19 − 83
LRT-South Exten. 0.638 0.135 0.234 Load cell 173 − 42

SLRT–Phase II
(Section B2) 0.671 0.135 0.316 Load cell 112 − 57
(Section C2) 0.772 0.144 0.439 Flat jack 76 − 67
(Section A1) 0.803 0.24 0.127 Load cell 531 88
Whitemud Creek 0.549 0.33 0.141 Deformation 289 134
170th street 0.644 0.135 0.448 Lagging deflec. 44 − 70

Experimental tunnel
(Section 1) 0.644 0.135 0.182 Strain gauge 254 − 26
(Section 2) 0.860 0.144 0.387 Strain gauge 122 − 63
(Section 3) 0.860 0.144 0.289 Load cell 198 − 50

North Saska. River


(Section 1) 0.641 0.135 0.094 Load cell 585 44
(Section 2) 0.641 0.135 0.049 Load cell 1198 174
(Section 4) 0.697 0.216 0.741 Load cell −6 − 71
H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312 311

can be smaller than U oe even though there is a bigger Belshaw, D.J., Palmer, J.H.L., 1978. Results of a program of
gap between the soil and TBM than U oe. In other instrumentation involving a precast segmented concrete-lined
tunnel in clay. Canadian Geotechnical Journal 15, 573–583.
words, the method may not give reliable results due to Burke, H.H., 1960. Garrison dam test tunnel, investigation and
the difficulties for estimating Uo′. construction. Transactions of the American Society of Civil
In conclusion, the proposed method of Schwartz Engineers 125, 230–267.
and Einstein gave reasonable results for tunnels with Corbett, I., 1984. Load and displacement variations along a soft
ground tunnel. MSc. thesis, Department of Civil Engineering,
short delay lengths, i.e., Ld′ / R less than about 1.
University of Alberta, Edmonton, Canada, p. 246.
However, the method cannot be used reliably for Craig, R.N., Muir Wood, A.M., 1978. A review of tunnel lining
tunnels either with long delay lengths or with voids practice in the United Kingdom. Supplementary Report - Transport
between the soil and TBM due to the difficulties in and Road Research Laboratory 335, p. 211.
finding Uo′ and therefore λd. Since most of the tunnels Deere, D.U., Peck, R.B., Monsees, J.E., Schmidt, B., 1969. Design of
in Edmonton were built using TBM with the clearance tunnel liners and support systems. Report for U. S. Department of
Transportation, Office of High Speed Ground Transportation,
voids, Schwartz and Einstein's method is not Contract no. 3-0152, pp. 287.
recommended for estimating lining loads for these Duddeck, H., Erdmann, J., 1985. On structural design models for
tunnels. tunnels in soft soil. Underground Space 9, 246–259.
EBA Engineering Consultants Ltd., 1988. Preliminary engineering
7. Conclusions report-South tunnel, SLRT Phase II. City of Edmonton and Stanley
Associates Engineering Ltd.
Einstein, H.H., Schwartz, C.W., 1979. Simplified analysis for tunnel
Schwartz and Einstein included correction factors supports. Journal of the Geotechnical Engineering Division,
considering non-linear ground behaviour and stress American Society of Civil Engineers 105 (GT4), pp. 499–518.
reduction occurring prior to lining installation in their Einstein, H.H., Schwartz, C., 1980. Discussion on simplified analysis
original closed form solutions. The proposed method for tunnel supports. Journal of the Geotechnical Engineering
Division, ASCE GT7, pp. 835–838.
of Schwartz and Einstein is reviewed in detail. From Eisenstein, Z., Thomson, S., 1978. Geotechnical performance of a
the review of the method, it was concluded that a tunnel in till. Canadian Geotechnical Journal 15, 332–345.
different λd could be obtained for the same delay Eisenstein, Z., El-Nahhas, F., Thomson, S., 1979. Pressure–displace-
length of Ld depending on the round length if Ld is ment relations in two systems of tunnel lining. Proceedings, 6th
used as suggested by Schwartz and Einstein. There- Pan-American Conference on Soil Mechanics, Lima, pp. 85–94.
Eisenstein, Z., Thomson, S., Branco, P., 1982. South LRT extension
fore, it was suggested using the delay length of Ld′ Jasper Avenue twin tunnel—instrumentation test section at 102nd
instead of Ld to predict the lining loads reliably street. Part I : Southbound tunnel. City of Edmonton, Alberta,
regardless of the round length. Lining loads of case Canada, p. 330.
histories given by Schwartz and Einstein were better Hutchinson, D.E., 1982. Effects of construction procedure on shaft and
tunnel performance. MSc. thesis, Department of Civil Engineering,
approximated when Eq. (8) was used with delay length
University of Alberta, Edmonton, Canada, p. 267.
Ld′. The yield factor λy was used for this study as Kim, H.J., Eisenstein, Z., 1998. Prediction of lining loads from case
suggested by Schwartz and Einstein because the histories. World Tunnel Congress '98, Sao Paulo, Brazil, pp. 299–304.
derivation of λy was very reasonable. Lane, K.S., 1960. Garrison dam test tunnel, evaluation of test results.
The proposed method gave reasonable results for Transactions of the American Society of Civil Engineers 125,
tunnels with short delay lengths, i.e., Ld′ / R less than 268–306.
Montgomery, C.J., Eisenstein, Z., 1995. Soft ground tunnel design in
about 1. However, the method cannot be used reliably Edmonton. City of Edmonton, Alberta, Canada, p. 198.
for tunnels either with long delay lengths or with voids Muir Wood, A.M., 1975. The circular tunnel in elastic ground.
between the soil and TBM due to the difficulties finding Geotechnique 25 (1), 115–127.
Uo′ and therefore λd. Negro Jr., A., 1988. Design of shallow tunnels in soft ground. Ph.D.
thesis, Department of Civil Engineering, University of Alberta,
Edmonton, Canada, p. 1480.
Acknowledgements O'Rourke, T.D., 1984. Guidelines for Tunnel Lining Design. American
Society of Civil Engineers, p. 82.
The authors wish to acknowledge the support Panet, H., 1973. La stabilite des ouvrages souterrains-soutenement et
provided by the City of Edmonton. revetement. Rapport de recherche, vol. 28. Laboratoires des Ponts et
Chaussees, Paris.
Schwartz, C.W., Einstein, H.H., 1980a. Improved design of tunnel
References supports: vol. 1 — simplified analysis for ground–structure inter-
action in tunneling. Report No. UMTA-MA-06-0100-80-4. U.S.
Attewell, P.B., El-Naga, N.M.A., 1977. Ground-lining pressure Department of Transportation, p. 427.
distribution and lining distortion in two tunnels driven through Schwartz, C.W., Einstein, H.H., 1980b. Simplified analysis for ground–
stiff, stony/laminated clay. Ground Engineering 10 (3), 28–35. structure interaction in tunneling. The state of the art in rock
312 H.J. Kim, Z. Eisenstein / Engineering Geology 85 (2006) 302–312

mechanics. Proceedings of the 21st U.S. Symposium on Rock Ward, W.H., 1978. Ground supports for tunnels in weak rocks.
Mechanics, Rolla, pp. 787–796. Geotechnique 28 (2), 133–171.
Thomson, S., El-Nahhas, F., 1980. Field measurements in two tunnels Ward, W.H., Thomas, H.S.H., 1965. The development of earth loading
in Edmonton, Alberta. Canadian Geotechnical Journal 17, 20–33. and deformation in tunnel linings in London clay. Proceedings,
Thomson, S., Martin, R.L., Eisenstein, Z., 1982. Soft zones in the glacial Sixth International Conference on Soil Mechanics and Foundation
till in downtown Edmonton. Canadian Geotechnical Journal 19, Engineering, vol. 2, pp. 432–436.
175–180. Ward, W.H., Coats, D.J., Tedd, P., 1976. Performance of tunnel support
Thurber Consultants Ltd., 1986. SLRT extension–Phase II, in situ systems in the Four Fathom mudstone. Tunneling '76, London,
testing at the proposed university station site. Geotechnical Report pp. 329–340, disc. pp. 348–367.
No. 3, City of Edmonton. Whittaker, B.N., Frith, R.C., 1990. Tunnelling—Design, Stability and
Tweedie, R.W., Harris, M.C., Gerber, G.E., Eisenstein, Z., 1989. Construction. The Institution of Mining and Metallurgy, London,
Ground and structure monitoring for the Edmonton SLRT–Phase p. 460.
II tunnels. Canadian Tunnelling, pp. 61–72.

Vous aimerez peut-être aussi