Albanian Road Construction Standards – ARCS 7 – List of Works

Albanian Road Design and Construction Standards

Table of Contents

1 PREPARATORY WORK................................................................................................................ 4

1.1 SURVEYING .............................................................................................................................. 4


1.2 TERRAIN CLEARANCE ................................................................................................................ 4

2 EARTHWORKS ............................................................................................................................. 5

2.1 EXCAVATION ............................................................................................................................. 5


2.2 SUBSOIL SUBGRADE ............................................................................................................... 10
2.3 DRAINAGE AND FILTER LAYERS ............................................................................................... 10
2.4 EMBANKMENTS, BACKFILLS, BARRIER LAYER AGGREGATE, ROAD BED, AND RAMMED LOAM
CONSTRUCTION ...................................................................................................................... 11
2.5 SLOPES AND GREEN AREAS .................................................................................................... 15
2.6 SOIL REINFORCEMENT ............................................................................................................ 16
2.7 PILES AND DROP SHAFTS ........................................................................................................ 17
2.8 SHEET PILING ......................................................................................................................... 24
2.9 SPREADING SURPLUS MATERIALS............................................................................................ 24

3 ROAD CONSTRUCTION ............................................................................................................. 25

3.1 ROADBASES ........................................................................................................................... 25


3.1.1 UNSTABILISED ROADBASES ................................................................................................. 25
3.1.2 CEMENT BOUND BASES ....................................................................................................... 26
3.1.3 BASE COURSES AND BASE-WEARING COURSES BOUND BY BITUMINOUS BINDERS .................. 29
3.1.4 NATURAL ASPHALT BITUMEN (ASHPALT) MODIFIED BITUMEN BINDERS .................................. 33
3.2 POLYMER MODIFIED BITUMEN BINDERS ................................................................................... 34
3.3 WEARING AND SEALING COURSES ........................................................................................... 34
3.3.1 UNSTABILISED WEARING COURSES ...................................................................................... 34
3.3.2 STABILISED WEARING AND SEALING COURSES – BITUMINOUS CONCRETES ........................... 35
3.3.3 STABILISED WEARING AND SEALING COURSES – POURED ASPHALTS .................................... 38
3.3.4 STABILISED WEARING AND SEALING COURSES – SURFACE DRESSINGS ................................. 39
3.3.5 STABILISED WEARING COURSE – DRAINAGE – ASPHALT ....................................................... 44
3.3.6 BOUND WEARING AND SEAL COURSES – SPLIT MASTIC ASPHALT .......................................... 45
3.3.7 STABILISED ROADBASES AND WEARING COURSES – CEMENT CONCRETES ............................ 47
3.3.8 PAVED WEARING COURSES ................................................................................................. 49
3.4 EDGE ELEMENTS OF CARRIAGEWAYS ...................................................................................... 51
3.4.1 EXTRA WIDTH ..................................................................................................................... 51
3.4.2 KERBS ................................................................................................................................ 52
3.4.3 BORDERS ........................................................................................................................... 54
3.4.4 GUARD RAILS...................................................................................................................... 54
3.5 SHOULDERS ........................................................................................................................... 55

4 DRAINAGE................................................................................................................................... 57

4.1 SURFACE DRAINAGE ............................................................................................................... 57


4.2 DEEP DRAINAGE SYSTEMS – DRAINAGES ................................................................................. 61
4.2.1 FLEXIBLE PLASTIC PIPES ..................................................................................................... 66

Draft of Version 1 – March 2008 Page ii


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

4.2.2 HARD PLASTIC PIPES .......................................................................................................... 67


4.2.3 PERFORATED PIPES ............................................................................................................ 68
4.3 DEEP DRAINAGE SYSTEMS – STORM SEWERAGE SYSTEM ........................................................ 80
4.4 MANHOLES ............................................................................................................................. 89
4.5 CULVERTS .............................................................................................................................. 98
4.6 SOURCES, WELLS, SINK HOLES, FUNNEL-SHAPED HOLES ...................................................... 101

5 CONSTRUCTION AND SPECIALIST WORK ........................................................................... 104

5.1 CARPENTRY WORK ............................................................................................................... 104


5.2 WORK WITH STEEL FOR REINFORCEMENT .............................................................................. 106
5.3 WORK WITH CEMENT CONCRETE ........................................................................................... 109
5.4 MASONRY AND STONEMASONRY WORK ................................................................................. 114
5.4.1 ANCHORING ...................................................................................................................... 119
5.4.2 GROUTING ........................................................................................................................ 122
5.4.3 WATERPROOFING .............................................................................................................. 127
5.5 METALWORK ......................................................................................................................... 130
5.6 PROTECTION OF METAL AGAINST CORROSION ....................................................................... 134

6 ROAD EQUIPMENT................................................................................................................... 137

6.1 ROADSIDE AND OVERHEAD ROAD EQUIPMENT ....................................................................... 137


6.2 ROAD MARKINGS .................................................................................................................. 156
6.3 TRAFFIC GUIDING EQUIPMENT ............................................................................................... 173
6.4 TRAFFIC SAFETY EQUIPMENT ................................................................................................ 179
6.5 ROAD EQUIPMENT FOR SNOW REMOVAL AND ICE CONTROL ................................................... 182
6.6 OTHER ROAD EQUIPMENT ..................................................................................................... 183

Draft of Version 1 – March 2008 Page iii


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

1 Preparatory Work

1.1 Surveying

Unit
Code Description of work
measure

11 111 km Renewal and protection of the staked out alignment

11 121 Piece Placing and protection of cross sections

1.2 Terrain Clearance

Unit
Code Description of work
measure
Felling and removal of bushes and trees with trunks 15 cm in diameter and
12 111 m²
removal of branches
Felling and removal of trees with trunks 15–50 cm in diameter and removal
12 122 Piece
of branches
Felling and removal of trees with trunks over 50 cm in diameter and
12 113 Piece
removal of branches
12 121 Hour Removal of branches from previously felled trees
12 131 Piece Removal of tree stumps 15–50 cm in diameter
12 132 Piece Removal of tree stumps over 50 cm in diameter
12 211 Piece Disassembly of traffic signs
12 212 m Disassembly of guard rails
12 221 m² Demolition of all types of carriageways
12 222 m Demolition of all types of kerbs
12 223 m Demolition of all types of fences
12 224 m Demolition of all types of slope paving
12 225 m² Demolition of all types of structures
12 226 m³ Demolition of all types of walls

Draft of Version 1 – March 2008 Page 4


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

2 Earthworks

2.1 Excavation

Unit
Code Description of work
measure
21 111 m³ Stripping of fertile soil (topsoil)
21 211 m³ Bulk excavation of the soil of low bearing capacity
21 212 m³ Bulk excavation of the soil of light soil
21 213 m³ Bulk excavation of the soil of heavy soil
21 214 m³ Bulk excavation of the soil of soft rock
21 215 m³ Bulk excavation of the soil of hard rock
21 216 m Addition for safe blasting
Excavation of foundations, service ditches, culverts, and drainage up to
21 311 m³
1.0 m wide and 1.0 m deep in the soil of low bearing capacity
Excavation of foundations, service ditches, culverts, and drainage up to
21 312 m³
1.0 m wide and 1.0 m deep in light soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 313 m³
1.0 m wide and 1.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 314 m³
1.0 m wide and 1.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 315 m³
1.0 m wide and 1.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 321 m³
1.0 m wide and 1.0–2.0 m deep in the soil of low bearing capacity
Excavation of foundations, service ditches, culverts, and drainage up to
21 322 m³
1.0 m wide and 1.0–2.0 m deep in light soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 323 m³
1.0 m wide and 1.0–2.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 324 m³
1.0 m wide and 1.0–2.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 325 m³
1.0 m wide and 1.0–2.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 331 m³
1.0 m wide and 1.0–4.0 m deep in the soil of low bearing capacity
Excavation of foundations, service ditches, culverts, and drainage up to
21 332 m³
1.0 m wide and 1.0–4.0 m deep in light soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 333 m³
1.0 m wide and 1.0–4.0 m deep in heavy soil

Draft of Version 1 – March 2008 Page 5


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Excavation of foundations, service ditches, culverts, and drainage up to
21 334 m³
1.0 m wide and 1.0–4.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 335 m³
1.0 m wide and 1.0–4.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 341 m³
1.0 m wide and over 4.0 m deep in the soil of low bearing capacity
Excavation of foundations, service ditches, culverts, and drainage up to
21 342 m³
1.0 m wide and over 4.0 m deep in light soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 343 m³
1.0 m wide and over 4.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 344 m³
1.0 m wide and over 4.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 345 m³
1.0 m wide and over 4.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 351 m³ 1.0 m wide and not more than 4.0 m deep in the soil of low bearing
capacity
Excavation of foundations, service ditches, culverts, and drainage up to
21 352 m³
1.0 m wide and not more than 4.0 m deep in light soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 353 m³
1.0 m wide and not more than 4.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, and drainage up to
21 354 m³
1.0 m wide and not more than 4.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, and drainage up to
21 355 m³
1.0 m wide and not more than 4.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, shafts and drainage
21 361 m³
up to 1.0 m wide and 1.0–2.0 m deep in soil of low bearing capacity
Excavation of foundations, service ditches, culverts, shafts and drainage
21 362 m³
1.0–2.0 m wide and 1.0–2.0 m deep in light soil
Excavation of foundations, service ditches, culverts, shafts and drainage
21 363 m³
1.0–2.0 m wide and 1.0–2.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, shafts and drainage
21 364 m³
1.0–2.0 m wide and 1.0–2.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, shafts and drainage
21 365 m³
1.0–2.0 m wide and 1.0–2.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, shafts and drainage
21 371 m³
up to 1.0 m wide and 2.0–4.0 m deep in soil of low bearing capacity

Draft of Version 1 – March 2008 Page 6


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Excavation of foundations, service ditches, culverts, shafts and drainage
21 372 m³
1.0–2.0 m wide and 2.0–4.0 m deep in light soil
Excavation of foundations, service ditches, culverts, shafts and drainage
21 373 m³
1.0–2.0 m wide and 2.0–4.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, shafts and drainage
21 374 m³
1.0–2.0 m wide and 2.0–4.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, shafts and drainage
21 375 m³
1.0–2.0 m wide and 2.0–4.0 m deep in hard rock
Excavation of foundations, service ditches, culverts, shafts and drainage
21 381 m³
1.0–2.0 m wide and over 4.0 m deep in soil of low bearing capacity
Excavation of foundations, service ditches, culverts, shafts and drainage
21 382 m³
1.0–2.0 m wide and over 4.0 m deep in light soil
Excavation of foundations, service ditches, culverts, shafts and drainage
21 383 m³
1.0–2.0 m wide and over 4.0 m deep in heavy soil
Excavation of foundations, service ditches, culverts, shafts and drainage
21 384 m³
1.0–2.0 m wide and over 4.0 m deep in soft rock
Excavation of foundations, service ditches, culverts, shafts and drainage
21 385 m³
1.0–2.0 m wide and over 4.0 m deep in hard rock
Excavation of building pits for structures not more than 1.0 m deep in soil
21 411 m³
of low bearing capacity
Excavation of building pits for structures not more than 1.0 m deep in light
21 412 m³
soil
Excavation of building pits for structures not more than 1.0 m deep in
21 413 m³
heavy soil
Excavation of building pits for structures not more than 1.0 m deep in soft
21 414 m³
rock
Excavation of building pits for structures not more than 1.0 m deep in hard
21 415 m³
rock
Excavation of building pits for structures between 1.0 and 2.0 m deep in
21 421 m³
the soil of low bearing capacity
Excavation of building pits for structures between 1.0 and 2.0 m deep in
21 422 m³
light soil
Excavation of building pits for structures between 1.0 and 2.0 m deep in
21 423 m³
heavy soil
Excavation of building pits for structures between 1.0 and 2.0 m deep in
21 424 m³
soft rock
Excavation of building pits for structures between 1.0 and 2.0 m deep in
21 425 m³
hard rock

Draft of Version 1 – March 2008 Page 7


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Excavation of building pits for structures between 2.0–4.0 m deep in the
21 431 m³
soil of low bearing capacity
Excavation of building pits for structures between 2.0–4.0 m deep in light
21 432 m³
soil
Excavation of building pits for structures between 2.0–4.0 m deep in heavy
21 433 m³
soil
Excavation of building pits for structures between 2.0–4.0 m deep in soft
21 434 m³
rock
Excavation of building pits for structures between 2.0–4.0 m deep in hard
21 435 m³
rock
Excavation of building pits for structures over 4.0 m deep in the soil of low
21 441 m³
bearing capacity
21 442 m³ Excavation of building pits for structures over 4.0 m deep in light soil
21 443 m³ Excavation of building pits for structures over 4.0 m deep in heavy soil
21 444 m³ Excavation of building pits for structures over 4.0 m deep in soft rock
21 445 m³ Excavation of building pits for structures over 4.0 m deep in hard rock
Excavation of land reclamation channels and sewer trenches not more
21 511 m³
than 1.0 m deep in the soil of low bearing capacity
Excavation of land reclamation channels and sewer trenches not more
21 512 m³
than 1.0 m deep in light soil
Excavation of land reclamation channels and sewer trenches not more
21 513 m³
than 1.0 m deep in heavy soil
Excavation of land reclamation channels and sewer trenches not more
21 514 m³
than 1.0 m deep in soft rock
Excavation of land reclamation channels and sewer trenches not more
21 515 m³
than 1.0 m deep in hard rock
Excavation of land reclamation channels and sewer trenches between
21 521 m³
1.0–2.0 m deep in the soil of low bearing capacity
Excavation of land reclamation channels and sewer trenches between
21 522 m³
1.0–2.0 m deep in light soil
Excavation of land reclamation channels and sewer trenches between
21 523 m³
1.0–2.0 m deep in heavy soil
Excavation of land reclamation channels and sewer trenches between
21 524 m³
1.0–2.0 m deep in soft rock
Excavation of land reclamation channels and sewer trenches between
21 525 m³
1.0–2.0 m deep in hard rock
Excavation of land reclamation channels and sewer trenches between
21 531 m³
2.0–4.0 m deep in the soil of low bearing capacity

Draft of Version 1 – March 2008 Page 8


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Excavation of land reclamation channels and sewer trenches between
21 532 m³
2.0–4.0 m deep in light soil
Excavation of land reclamation channels and sewer trenches between
21 533 m³
2.0–4.0 m deep in heavy soil
Excavation of land reclamation channels and sewer trenches between
21 534 m³
2.0–4.0 m deep in soft rock
Excavation of land reclamation channels and sewer trenches between
21 535 m³
2.0–4.0 m deep in hard rock
Excavation of land reclamation channels and sewer trenches not more
21 541 m³
than 4.0 m deep in the soil of low bearing capacity
Excavation of land reclamation channels and sewer trenches not more
21 542 m³
than 4.0 m deep in light soil
Excavation of land reclamation channels and sewer trenches not more
21 543 m³
than 4.0 m deep in heavy soil
Excavation of land reclamation channels and sewer trenches not more
21 544 m³
than 4.0 m deep in soft rock
Excavation of land reclamation channels and sewer trenches not more
21 545 m³
than 4.0 m deep in hard rock
Excavation of drainage ditches and flumes in the soil of low bearing
21 611 m³
capacity
21 612 m³ Excavation of drainage ditches and flumes in light soil
21 613 m³ Excavation of drainage ditches and flumes in heavy soil
21 614 m³ Excavation of drainage ditches and flumes in soft rock
21 615 m³ Excavation of drainage ditches and flumes in hard rock
21 711 m³ Excavation for paving and revetment in the soil of low bearing capacity
21 712 m³ Excavation for paving and revetment in light soil
21 713 m³ Excavation for paving and revetment in heavy soil
21 714 m³ Excavation for paving and revetment in soft rock
21 715 m³ Excavation for paving and revetment in hard rock

Draft of Version 1 – March 2008 Page 9


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

2.2 Subsoil Subgrade

Unit
Code Description of work
measure
22 111 m2 Sub grade of the original subsoil in light soil
2
22 112 m Sub grade of the original subsoil in light soil
2
22 113 m Sub grade of the original subsoil in heavy soil
2
22 114 m Sub grade of the original subsoil in soft rock
2
22 115 m Sub grade of the original subsoil in hard rock
2
22 211 m Improvement of subsoil by adding 3% m/m of lime
2
22 212 m Improvement of subsoil by adding 4% m/m of lime
2
22 213 m Improvement of subsoil by adding 5% m/m of lime
2
22 221 m Improvement of subsoil by adding 6% m/m of fly ash
2
22 222 m Improvement of subsoil by adding 8% m/m of fly ash
2
22 223 m Improvement of subsoil by adding 10% m/m of fly ash
2
22 311 m Chemical stabilisation of subsoil by adding 4% m/m of lime
2
22 312 m Chemical stabilisation of subsoil by adding 5% m/m of lime
2
22 313 m Chemical stabilisation of subsoil by adding 6% m/m of lime
2
22 321 m Chemical stabilisation of subsoil by adding 3% m/m of cement
2
22 322 m Chemical stabilisation of subsoil by adding 4% m/m of cement
2
22 323 m Chemical stabilisation of subsoil by adding 5% m/m of cement
22 331 m2 Chemical stabilisation of subsoil by adding 10% m/m of fly ash
2
22 332 m Chemical stabilisation of subsoil by adding 12% m/m of fly ash
22 333 m2 Chemical stabilisation of subsoil by adding 14% m/m of fly ash

2.3 Drainage and Filter Layers

Unit
Code Description of work
measure
23 111 m³ Drainage layers of stony material, thickness of not more than 50 cm
23 112 m³ Drainage layers of stony material, thickness of more than 50 cm
23 211 m³ Filter layers of stony material, thickness of not more than 20 cm
23 212 m³ Filter layers of stony material, thickness between 20 to 40 cm
23 213 m³ Filter layers of stony material, thickness more than 40 cm
23 311 m² Drainage layers of polypropylene felt – 200 g

Draft of Version 1 – March 2008 Page 10


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
23 312 m² Drainage layers of polypropylene felt – 300 g
23 313 m² Drainage layers of polypropylene felt – 400 g
23 314 m² Drainage layers of polypropylene felt – 500 g
23 411 m³ Placing the quarry waste for the site, to the thickness of 30 cm
23 412 m³ Placing the quarry waste for the site, to the thickness of 40 cm
23 413 m³ Placing the quarry waste for the site, to the thickness of 50 cm
23 414 m³ Placing the quarry waste for the site, to the thickness of 60 cm
23 421 m³ Placing the gravel for the site, to the thickness of 30 cm
23 422 m³ Placing the gravel for the site, to the thickness of 40 cm
23 423 m³ Placing the gravel for the site, to the thickness of 50 cm
23 424 m³ Placing the gravel for the site, to the thickness of 60 cm
23 431 m³ Placing crushed stone for the site, to the thickness of 30 cm
23 432 m³ Placing crushed stone for the site, to the thickness of 40 cm
23 433 m³ Placing crushed stone for the site, to the thickness of 50 cm
23 434 m³ Placing crushed stone for the site, to the thickness of 60 cm

2.4 Embankments, Backfills, Barrier Layer Aggregate, Road Bed, and


Rammed Loam Construction

Unit
Code Description of work
measure
24 111 m³ Construction of embankments of natural light soil
24 112 m³ Construction of embankments of natural heavy soil
24 113 m³ Construction of embankments of natural soft rock
24 114 m³ Construction of embankments of natural hard rock
24 121 m³ Construction of embankments of fly ash
24 122 m³ Construction of embankments of fly ash sandwich 20 + 10 cm
24 123 m³ Construction of embankments of fly ash sandwich 30 + 10 cm
24 124 m³ Construction of embankments of fly ash sandwich 40 + 10 cm
Construction of embankments of improved types of soil by adding
24 131 m³
3% m/m of lime
Construction of embankments of improved types of soil by adding
24 132 m³
4% m/m of lime

Draft of Version 1 – March 2008 Page 11


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of embankments of improved types of soil by adding
24 133 m³
5% m/m of lime
Construction of embankments of improved types of soil by adding
24 141 m³
6% m/m of fly ash
Construction of embankments of improved types of soil by adding
24 142 m³
8% m/m of fly ash
Construction of embankments of improved types of soil by adding
24 143 m³
10% m/m of fly ash
Construction of embankments of chemically stabilised natural materials by
24 151 m³
adding 4% m/m of lime
Construction of embankments of chemically stabilised natural materials by
24 152 m³
adding 5% m/m of lime
Construction of embankments of chemically stabilised natural materials by
24 153 m³
adding 6% m/m of lime
Construction of embankments of chemically stabilised natural materials by
24 161 m³
adding 3% m/m of cement
Construction of embankments of chemically stabilised natural materials by
24 162 m³
adding 4% m/m of cement
Construction of embankments of chemically stabilised natural materials by
24 163 m³
adding 5% m/m of cement
Construction of embankments of chemically stabilised natural materials by
24 171 m³
adding 10% m/m of fly ash
Construction of embankments of chemically stabilised natural materials by
24 172 m³
adding 12% m/m of fly ash
Construction of embankments of chemically stabilised natural materials by
24 173 m³
adding 14% m/m of fly ash
24 211 m³ Backfilling with natural light soil
24 212 m³ Backfilling with natural heavy soil
24 213 m³ Backfilling with natural soft rock
24 214 m³ Backfilling with natural hard rock
24 221 m³ Backfilling with fly ash
24 231 m³ Backfilling with improved types of natural soil by adding 3% m/m of lime
24 232 m³ Backfilling with improved types of natural soil by adding 4% m/m of lime
24 233 m³ Backfilling with improved types of natural soil by adding 5% m/m of lime
24 241 m³ Backfilling with improved types of natural soil by adding 6% m/m of fly ash
24 242 m³ Backfilling with improved types of natural soil by adding 8% m/m of fly ash

Draft of Version 1 – March 2008 Page 12


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Backfilling with improved types of natural soil by adding 10% m/m of fly
24 243 m³
ash
Backfilling with chemically stabilised natural materials by adding 4% m/m
24 251 m³
of lime
Backfilling with chemically stabilised natural materials by adding 5% m/m
24 252 m³
of lime
Backfilling with chemically stabilised natural materials by adding 6% m/m
24 253 m³
of lime
Backfilling with chemically stabilised natural materials by adding 3% m/m
24 261 m³
of cement
Backfilling with chemically stabilised natural materials by adding 4% m/m
24 262 m³
of cement
Backfilling with chemically stabilised natural materials by adding 5% m/m
24 263 m³
of cement
Backfilling with chemically stabilised natural materials by adding 10% m/m
24 271 m³
of fly ash
Backfilling with chemically stabilised natural materials by adding 12% m/m
24 272 m³
of fly ash
Backfilling with chemically stabilised natural materials by adding 14% m/m
24 273 m³
of fly ash
24 311 m³ Placing the choke aggregate of natural light soil
24 312 m³ Placing the choke aggregate of natural heavy soil
24 313 m³ Placing the choke aggregate of natural stony material
24 321 m³ Placing the choke aggregate of fly ash
Placing the choke aggregate of chemically stabilised natural materials by
24 331 m³
adding 4% of lime
Placing the choke aggregate of chemically stabilised natural materials by
24 332 m³
adding 5% of lime
Placing the choke aggregate of chemically stabilised natural materials by
24 333 m³
adding 6% of lime
Placing the choke aggregate of chemically stabilised natural materials by
24 341 m³
adding 3% of cement
Placing the choke aggregate of chemically stabilised natural materials by
24 342 m³
adding 4% of cement
Placing the choke aggregate of chemically stabilised natural materials by
24 343 m³
adding 5% of cement
Placing the choke aggregate of chemically stabilised natural materials by
24 351 m³
adding 10% of fly ash

Draft of Version 1 – March 2008 Page 13


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Placing the choke aggregate of chemically stabilised natural materials by
24 352 m³
adding 12% of fly ash
Placing the choke aggregate of chemically stabilised natural materials by
24 353 m³
adding 14% of fly ash
24 411 m³ Construction of road bed, 30 cm thick of soil
24 412 m³ Construction of road bed, 30 cm thick of improved natural materials
Construction of road bed, 30 cm thick of chemically stabilised natural
24 413 m³
materials
24 414 m³ Construction of road bed, 30 cm thick of rock
24 415 m³ Construction of road bed, 30 cm thick of fly ash
24 421 m³ Construction of road bed, 40 cm thick of soil
24 422 m³ Construction of road bed, 40 cm thick of improved natural materials
Construction of road bed, 40 cm thick of chemically stabilised natural
24 423 m³
materials
24 424 m³ Construction of road bed, 40 cm thick of rock
24 425 m³ Construction of road bed, 40 cm thick of fly ash
24 431 m³ Construction of road bed, 50 cm thick of soil
24 432 m³ Construction of road bed, 50 cm thick of improved natural materials
Construction of road bed, 50 cm thick of chemically stabilised natural
24 433 m³
materials
24 434 m³ Construction of road bed, 50 cm thick of rock
24 435 m³ Construction of road bed, 50 cm thick of fly ash
24 511 m³ Rammed loam construction, thickness of not more than 15 cm
24 512 m³ Rammed loam construction, thickness between 16 and 30 cm
24 513 m³ Rammed loam construction, thickness over 30 cm

Draft of Version 1 – March 2008 Page 14


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

2.5 Slopes and Green Areas

Unit
Code Description of work
measure
25 111 m² Placing top soil and applying grass seed on the slopes without rolling
Placing top soil and applying grass seed on the slopes of green areas
25 112 m²
without rolling
25 121 m² Placing top soil and applying grass seed on the slopes and rolling
25 122 m² Placing top soil on green areas and rolling
25 131 m² Bio-guniting of slopes with mulch
25 132 m² Wattle work on slopes
25 151 Piece Planting of slopes with various types of trees and shrubs
25 152 Piece Planting of green areas with various types of trees and shrubs
25 211 m² Slope protection by netting
25 221 m² Slope protection by penning
25 231 m² Slope protection by guniting without reinforcement
25 232 m² Slope protection by guniting and reinforcement
Slope protection by precast cement concrete elements of cribwork type,
25 241 m²
filled with crushed stone
Slope protection by precast cement concrete elements of cribwork type
25 242 m²
with quarry stone
Slope protection by precast cement concrete elements type, filled with
25 251 m²
topsoil
Slope protection by precast cement concrete elements type, filled with
25 252 m²
sand
Slope protection by precast cement concrete elements type, filled with
25 253 m²
gravel
Slope protection by precast cement concrete elements type, filled with
25 254 m²
crushed stone
25 261 m² Slope protection by other precast elements filled with topsoil
25 262 m² Slope protection by other precast elements filled with sand
25 263 m² Slope protection by other precast elements filled with other material

Draft of Version 1 – March 2008 Page 15


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

2.6 Soil Reinforcement

Unit
Code Description of work
measure
Piece Soil reinforcement by elements of cement concrete type A (with dowels
26 111
and anchors)
Piece Soil reinforcement by elements of cement concrete type B (with dowels
26 112
and anchors)
Piece Soil reinforcement by elements of cement concrete type C (with dowels
26 113
and anchors)
Piece Soil reinforcement by elements of cement concrete type D (with dowels
26 114
and anchors)
Piece Soil reinforcement by elements of cement concrete type E (with dowels
26 115
and anchors)
Piece Soil reinforcement by elements of cement concrete with other units
26 116
(complete with all additional materials)
26 121 m Strips for soil reinforcement, made of laminated polyester
26 122 m Strips for soil reinforcement, made of galvanised steel
26 123 m Strips for soil reinforcement, made of steel protected by some other means
26 124 m Strips for soil reinforcement, made of some other material
26 131 m Extra payment for placing in the fill around the strips of heavy soil
26 132 m Extra payment for placing in the fill around the strips of soft rock
26 133 m Extra payment for placing in the fill around the strips of hard rock
26 134 m Extra payment for placing in the fill around the strips of fly ash
26 211 m Soil reinforcement by 300 g polypropylene felt in fill layer 20 cm thick
26 212 m Soil reinforcement by 300 g polypropylene felt in fill layer 30 cm thick
26 213 m Soil reinforcement by 300 g polypropylene felt in fill layer 40 cm thick
26 221 m Soil reinforcement by 400 g polypropylene felt in fill layer 20 cm thick
26 222 m Soil reinforcement by 400 g polypropylene felt in fill layer 30 cm thick
26 223 m Soil reinforcement by 400 g polypropylene felt in fill layer 40 cm thick
26 231 m Soil reinforcement by 500 g polypropylene felt in fill layer 20 cm thick
26 232 m Soil reinforcement by 500 g polypropylene felt in fill layer 30 cm thick
26 233 m Soil reinforcement by 500 g polypropylene felt in fill layer 40 cm thick

Draft of Version 1 – March 2008 Page 16


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

2.7 Piles and Drop Shafts

Unit
Code Description of work
measure
Placing of drilled, vertical piles of reinforced cement concrete, system
27 111 m
Benotto, dia. 60 cm
Placing of drilled, vertical piles of reinforced cement concrete, system
27 112 m
Benotto, dia. 80 cm
Placing of drilled, vertical piles of reinforced cement concrete, system
27 113 m
Benotto, dia. 100 cm
Placing of drilled, vertical piles of reinforced cement concrete, system
27 114 m
Benotto, dia. 125 cm
Placing of drilled, vertical piles of reinforced cement concrete, system
27 115 m
Benotto, dia. 150 cm
Placing of drilled, vertical piles of reinforced cement concrete, system
27 116 m
Benotto, dia. 200 cm
Placing of drilled, batter piles of reinforced cement concrete, system
24 121 m
Benotto, dia. 60 cm
Placing of drilled, batter piles of reinforced cement concrete, system
27 122 m
Benotto, dia. 80 cm
Placing of drilled, batter piles of reinforced cement concrete, system
27 123 m
Benotto, dia. 100 cm
Placing of drilled, batter piles of reinforced cement concrete, system
27 124 m
Benotto, dia. 125 cm
Placing of drilled, batter piles of reinforced cement concrete, system
27 125 m
Benotto, dia. 150cm
Placing of drilled, batter piles of reinforced cement concrete, system
27 126 m
Benotto, dia. 200cm
Placing of drilled, injected vertical piles of reinforced cement concrete,
27 131 m
dia. 60 cm
Placing of drilled, injected vertical piles of reinforced cement concrete,
27 132 m
dia. 80 cm
Placing of drilled, injected vertical piles of reinforced cement concrete,
27 133 m
dia. 100 cm
Placing of drilled, injected vertical piles of reinforced cement concrete,
27 134 m
dia. 125 cm
Placing of drilled, injected vertical piles of reinforced cement concrete,
27 135 m
dia. 150 cm

Draft of Version 1 – March 2008 Page 17


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Placing of drilled, injected vertical piles of reinforced cement concrete,
27 136 m
dia. 200 cm
Placing of drilled, injected batter piles of reinforced cement concrete,
27 141 m
dia. 60 cm
Placing of drilled, injected batter piles of reinforced cement concrete,
27 142 m
dia. 80 cm
Placing of drilled, injected batter piles of reinforced cement concrete,
27 143 m
dia. 100 cm
Placing of drilled, injected batter piles of reinforced cement concrete,
27 144 m
dia. 125 cm
Placing of drilled, injected batter piles of reinforced cement concrete,
27 145 m
dia. 150 cm
Placing of drilled, injected batter piles of reinforced cement concrete,
27 146 m
dia. 200 cm
Extending of drilled piles of reinforced cement concrete, above the level of
27 151 m
excavation bottom, dia. 60 cm
Extending of drilled piles of reinforced cement concrete, above the level of
27 152 m
excavation bottom, dia. 80 cm
Extending of drilled piles of reinforced cement concrete, above the level of
27 153 m
excavation bottom, dia. 100 cm
Extending of drilled piles of reinforced cement concrete, above the level of
27 154 m
excavation bottom, dia. 125 cm
Extending of drilled piles of reinforced cement concrete, above the level of
27 155 m
excavation bottom, dia. 150 cm
Extending of drilled piles of reinforced cement concrete, above the level of
27 156 m
excavation bottom, dia. 200 cm
27 161 Piece Dressing of drilled piles of reinforced cement concrete, dia. 60 cm
27 162 Piece Dressing of drilled piles of reinforced cement concrete, dia. 80 cm
27 163 Piece Dressing of drilled piles of reinforced cement concrete, dia. 100 cm
27 164 Piece Dressing of drilled piles of reinforced cement concrete, dia. 125 cm
27 165 Piece Dressing of drilled piles of reinforced cement concrete, dia. 150 cm
27 166 Piece Dressing of drilled piles of reinforced cement concrete, dia. 200 cm
27 211 m Driving of vertical piles of reinforced cement concrete, section 36/36 cm
27 212 m Driving of vertical piles of reinforced cement concrete, section … cm
27 216 m Driving of batter piles of reinforced cement concrete, section 36/36 cm
27 217 m Driving of batter piles of reinforced cement concrete, section … cm
27 221 m Extending of driven piles of reinforced cement concrete, section 36/36 cm

Draft of Version 1 – March 2008 Page 18


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
27 222 m Extending of driven piles of reinforced cement concrete, section … cm
27 226 Piece Dressing of driven piles of reinforced cement concrete, section 36/36 cm
27 227 Piece Dressing of driven piles of reinforced cement concrete, section … cm
Driving of pre-stressed vertical piles of reinforced cement concrete,
27 231 m
dia. 60 cm
Driving of pre-stressed vertical piles of reinforced cement concrete,
27 232 m
dia. 70 cm
Driving of pre-stressed vertical piles of reinforced cement concrete,
27 233 m
dia. 80 cm
Driving of pre-stressed vertical piles of reinforced cement concrete,
27 234 m
dia. … cm
Driving of pre-stressed batter piles of reinforced cement concrete,
27 236 m
dia. 60 cm
Driving of pre-stressed batter piles of reinforced cement concrete,
27 237 m
dia. 70 cm
Driving of pre-stressed batter piles of reinforced cement concrete,
27 238 m
dia. 80 cm
Driving of pre-stressed batter piles of reinforced cement concrete,
27 239 m
dia. … cm
Extending of pre- stressed driven piles of reinforced cement concrete, dia.
27 241 m
60 cm
Extending of pre- stressed driven piles of reinforced cement concrete, dia.
27 242 m
70 cm
Extending of pre- stressed driven piles of reinforced cement concrete, dia.
27 243 m
80 cm
Extending of pre- stressed driven piles of reinforced cement concrete,
27 244 m
dia. … cm
Dressing of pre-stressed driven piles of reinforced cement concrete,
27 246 Piece
dia. 60 cm
Dressing of pre-stressed driven piles of reinforced cement concrete,
27 247 Piece
dia. 70 cm
Dressing of pre-stressed driven piles of reinforced cement concrete,
27 248 Piece
dia. 80 cm
Dressing of pre-stressed driven piles of reinforced cement concrete,
27 249 Piece
dia. … cm
27 251 m Driving of vertical steel piles dia. 300 mm
27 252 m Driving of vertical steel piles dia. 400 mm

Draft of Version 1 – March 2008 Page 19


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
27 253 m Driving of vertical steel piles dia. 500 mm
27 254 m Driving of vertical steel piles dia. 600 mm
27 255 m Driving of vertical steel piles dia. 700 mm
27 261 m Driving of batter steel piles dia. 300 mm
27 262 m Driving of batter steel piles dia. 400 mm
27 263 m Driving of batter steel piles dia. 500 mm
27 264 m Driving of batter steel piles dia. 600 mm
27 265 m Driving of batter steel piles dia. 700 mm
27 271 m Extending of driven vertical steel piles dia. 300 mm
27 272 m Extending of driven vertical steel piles dia. 400 mm
27 273 m Extending of driven vertical steel piles dia. 500 mm
27 274 m Extending of driven vertical steel piles dia. 600 mm
27 275 m Extending of driven vertical steel piles dia. 700 mm
27 281 Piece Cutting off of driven vertical steel piles dia. 300 mm
27 282 Piece Cutting off of driven vertical steel piles dia. 400 mm
27 283 Piece Cutting off of driven vertical steel piles dia. 500 mm
27 284 Piece Cutting off of driven vertical steel piles dia. 600 mm
27 285 Piece Cutting off of driven vertical steel piles dia. 700 mm
Sinking vertical piles of reinforced cement concrete with casing–drop
27 311 m
shafts, dia. 100 cm
Sinking vertical piles of reinforced cement concrete with casing–drop
27 312 m
shafts, dia. 120 cm
Sinking vertical piles of reinforced cement concrete with casing–drop
27 313 m
shafts, dia. 140 cm
Sinking vertical piles of reinforced cement concrete with casing–drop
27 314 m
shafts, dia. 160 cm
Sinking vertical piles of reinforced cement concrete with casing–drop
27 315 m
shafts, dia. 180 cm
Sinking vertical piles of reinforced cement concrete with casing–drop
27 316 m
shafts, dia. 200 cm
Sinking of batter piles of reinforced cement concrete with casing–drop
27 321 m
shafts, dia. 100 cm
Sinking of batter piles of reinforced cement concrete with casing–drop
27 322 m
shafts, dia. 120 cm
Sinking of batter piles of reinforced cement concrete with casing–drop
27 323 m
shafts, dia. 140 cm

Draft of Version 1 – March 2008 Page 20


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Sinking of batter piles of reinforced cement concrete with casing–drop
27 324 m
shafts, dia. 160 cm
Sinking of batter piles of reinforced cement concrete with casing–drop
27 325 m
shafts, dia. 180 cm
Sinking of batter piles of reinforced cement concrete with casing–drop
27 326 m
shafts, dia. 200 cm
Extending sunk piles of reinf. cement concrete with casing–drop shafts,
27 331 m
dia. 100 cm
Extending sunk piles of reinf. cement concrete with casing–drop shafts,
27 332 m
dia. 120 cm
Extending sunk piles of reinf. cement concrete with casing–drop shafts,
27 333 m
dia. 140 cm
Extending sunk piles of reinf. cement concrete with casing–drop shafts,
27 334 m
dia. 160 cm
Extending sunk piles of reinf. cement concrete with casing–drop shafts,
27 335 m
dia. 180 cm
Extending sunk piles of reinf. cement concrete with casing–drop shafts,
27 336 m
dia. 200 cm
Dressing of sunk piles of reinforced cement concrete with casing–drop
27 341 Piece
shafts, dia. 100 cm
Dressing of sunk piles of reinforced cement concrete with casing–drop
27 342 Piece
shafts, dia. 100 cm
Dressing of sunk piles of reinforced cement concrete with casing–drop
27 343 Piece
shafts, dia. 100 cm
Dressing of sunk piles of reinforced cement concrete with casing–drop
27 344 Piece
shafts, dia. 100 cm
Dressing of sunk piles of reinforced cement concrete with casing–drop
27 345 Piece
shafts, dia. 100 cm
Dressing of sunk piles of reinforced cement concrete with casing–drop
27 346 Piece
shafts, dia. 100 cm
27 351 m Sinking of vertical steel piles–drop shafts, dia. 1000 mm
27 352 m Sinking of vertical steel piles–drop shafts, dia. 1250 mm
27 353 m Sinking of vertical steel piles–drop shafts, dia. 1500 mm
27 354 m Sinking of vertical steel piles–drop shafts, dia. 1750 mm
27 355 m Sinking of vertical steel piles–drop shafts, dia. 2000 mm
27 361 m Sinking of batter steel piles–drop shafts, dia. 1000 mm
27 362 m Sinking of batter steel piles–drop shafts, dia. 1250 mm

Draft of Version 1 – March 2008 Page 21


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
27 363 m Sinking of batter steel piles–drop shafts, dia. 1500 mm
27 364 m Sinking of batter steel piles–drop shafts, dia. 1750 mm
27 365 m Sinking of batter steel piles–drop shafts, dia. 2000 mm
27 371 m Extending of sunk steel piles–drop shafts, dia. 1000 mm
27 372 m Extending of sunk steel piles–drop shafts, dia. 1250 mm
27 373 m Extending of sunk steel piles–drop shafts, dia. 1500 mm
27 374 m Extending of sunk steel piles–drop shafts, dia. 1750 mm
27 375 m Extending of sunk steel piles–drop shafts, dia. 2000 mm
27 381 Piece Cutting off of sunk steel piles–drop shafts, dia. 1000 mm
27 382 Piece Cutting off of sunk steel piles–drop shafts, dia. 1250 mm
27 383 Piece Cutting off of sunk steel piles–drop shafts, dia. 1500 mm
27 384 Piece Cutting off of sunk steel piles–drop shafts, dia. 1750 mm
27 385 Piece Cutting off of sunk steel piles–drop shafts, dia. 2000 mm
27 411 m Placing of vertical wood piles dia. 25 cm
27 412 m Placing of vertical wood piles dia. 30 cm
27 413 m Placing of vertical wood piles dia. 35 cm
27 414 m Placing of vertical wood piles dia. 40 cm
27 421 m Placing of batter wood piles dia. 25 cm
27 422 m Placing of batter wood piles dia. 30 cm
27 423 m Placing of batter wood piles dia. 35 cm
27 424 m Placing of batter wood piles dia. 40 cm
27 431 Piece Cutting off of wood piles dia. 25 cm
27 432 Piece Cutting off of wood piles dia. 30 cm
27 433 Piece Cutting off of wood piles dia. 35 cm
27 434 Piece Cutting off of wood piles dia. 40 cm
27 511 m Placing of piles of stabilised soils, dia. 50 cm, by adding 8% m/m of lime
27 512 m Placing of piles of stabilised soils, dia. 50 cm, by adding 10% m/m of lime
27 513 m Placing of piles of stabilised soils, dia. 50 cm, by adding 12% m/m of lime
27 514 m Placing of piles of stabilised soils, dia. 50 cm, by adding 15% m/m of lime
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 8%
27 521 m
m/m of fly ash
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 10%
27 522 m
m/m of fly ash
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 12%
27 523 m
m/m of fly ash

Draft of Version 1 – March 2008 Page 22


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 15%
27 524 m
m/m of fly ash
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 5%
27 531 m
m/m of gypsum
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 6%
27 532 m
m/m of gypsum
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 8%
27 533 m
m/m of gypsum
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 10%
27 534 m
m/m of gypsum
Placing of piles of chemically stabilised soils, dia. 50 cm, by adding 15%
27 535 m
m/m of gypsum
27 611 m Placing of piles of granular stone mixture dia. 40 cm
27 612 m Placing of piles of granular stone mixture dia. 50 cm
27 613 m Placing of piles of granular stone mixture dia. 60 cm
27 614 m Placing of piles of granular stone mixture dia. 70 cm

Draft of Version 1 – March 2008 Page 23


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

2.8 Sheet Piling

Unit
Code Description of work
measure
28 111 m2 Construction and maintenance of steel sheet piling
2
28 112 m Construction and maintenance of wood sheet piling
2
28 113 m Construction and maintenance of anchored sheet pile
2
28 114 m Construction and maintenance of sheet piling of grooved boards
2
28 121 m Removal of steel sheet piling, including complete disassembly
2
28 122 m Removal of wood sheet piling, including complete disassembly
2
28 123 m Removal of anchored sheet piling, including complete disassembly
2
28 124 m Removal of sheet piling made of grooved boards

2.9 Spreading Surplus Materials

Unit
Code Description of work
measure
29 111 m2 Spreading surplus fertile soil
29 112 m2 Spreading surplus soil of low bearing capacity
2
29 113 m Spreading surplus light soil
29 114 m2 Spreading surplus heavy soil
2
29 115 m Spreading surplus rock
2
29 116 m Spreading other surplus material
Loading, transport and unloading of excavated material; transport distance
29 121 m
up to 100 m
Loading, transport and unloading of excavated material; transport distance
29 122 m
100–250 m
Loading, transport and unloading of excavated material; transport distance
29 123 m
250–500 m
Loading, transport and unloading of excavated material; transport distance
29 124 m
500–1000 m
Loading, transport and unloading of excavated material; transport distance
29 125 m
1000–2000 m
Loading, transport and unloading of excavated material; transport distance
29 126 m
2000–5000 m
Loading, transport and unloading of excavated material; transport distance
29 127 m
above 5000 m

Draft of Version 1 – March 2008 Page 24


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3 Road Construction

3.1 Roadbases

3.1.1 Unstabilised Roadbases

Unit
Code Description of work
measure
31 111 m3 Construction of unstabilised roadbase of gravel, thickness to 20 cm
31 112 m3 Construction of unstabilised roadbase of gravel, thickness to 21–30 cm
3
31 113 m Construction of unstabilised roadbase of gravel, thickness to 31–40 cm
31 114 m3 Construction of unstabilised roadbase of gravel, thickness to 41–50 cm
3
31 121 m Construction of unstabilised roadbase of gravel, thickness to 20 cm
31 122 m3 Construction of unstabilised roadbase of gravel, thickness to 21–30 cm
3
31 123 m Construction of unstabilised roadbase of gravel, thickness to 31–40 cm
31 124 m3 Construction of unstabilised roadbase of gravel, thickness to 41–50 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 131 m3
thickness to 20 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 132 m3
thickness to 21–30 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 133 m3
thickness to 31–40 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 134 m3
thickness to 41–50 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 141 m3
thickness to 20 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 142 m3
thickness to 21–30 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 143 m3
thickness to 31–40 cm
Construction of unstabilised roadbase of single graded crushed stone,
31 144 m3
thickness to 41–50 cm
Construction of unstabilised roadbase of equally graded crushed stone
31 151 m3
made of slag, thickness to 20 cm
Construction of unstabilised roadbase of equally graded crushed stone
31 152 m3
made of slag, thickness to 21–30 cm
Construction of unstabilised roadbase of equally graded crushed stone
31 153 m3
made of slag, thickness to 31–40 cm

Draft of Version 1 – March 2008 Page 25


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of unstabilised roadbase of equally graded crushed stone
31 154 m3
made of slag, thickness to 41–50 cm
Construction of unstabilised roadbase of single graded crushed stone from
31 161 m3
slag, thickness to 20 cm
Construction of unstabilised roadbase of single graded crushed stone from
31 162 m3
slag, thickness to 21–30 cm
Construction of unstabilised roadbase of single graded crushed stone from
31 163 m3
slag, thickness to 31–40 cm
Construction of unstabilised roadbase of single graded crushed stone from
31 164 m3
slag, thickness to 41–50 cm

3.1.2 Cement Bound Bases

Unit
Code Description of work
measure
Construction of cement bound (stabilised) natural gravel subbase,
31 211 m2
thickness 12 cm
Construction of cement bound (stabilised) natural gravel subbase,
31 212 m2
thickness 15 cm
Construction of cement bound (stabilised) natural gravel subbase,
31 213 m2
thickness 18 cm
Construction of cement bound (stabilised) natural gravel subbase,
31 214 m2
thickness 20 cm
Construction of cement bound (stabilised) natural gravel subbase,
31 215 m2
thickness 22 cm
Construction of cement bound (stabilised) subbase of naturally crushed
31 221 m2
stone material, thickness 12 cm
Construction of cement bound (stabilised) subbase of naturally crushed
31 222 m2
stone material, thickness 15 cm
Construction of cement bound (stabilised) subbase of naturally crushed
31 223 m2
stone material, thickness 18 cm
Construction of cement bound (stabilised) subbase of naturally crushed
31 224 m2
stone material, thickness 20 cm
Construction of cement bound (stabilised) subbase of naturally crushed
31 225 m2
stone material, thickness 22 cm

Draft of Version 1 – March 2008 Page 26


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of cement bound (stabilised) sand gravel subbase, thickness
31 231 m2
12 cm
Construction of cement bound (stabilised) sand gravel subbase, thickness
31 232 m2
15 cm
Construction of cement bound (stabilised) sand gravel subbase, thickness
31 233 m2
18 cm
Construction of cement bound (stabilised) sand gravel subbase, thickness
31 234 m2
20 cm
Construction of cement bound (stabilised) sand gravel subbase, thickness
31 235 m2
22 cm
Construction of cement bound (stabilised) sand gravel subbase, thickness
31 236 m2
25 cm
Construction of cement bound (stabilised) crushed stone subbase,
31 241 m2
thickness 12 cm
Construction of cement bound (stabilised) crushed stone subbase,
31 242 m2
thickness 15 cm
Construction of cement bound (stabilised) crushed stone subbase,
31 243 m2
thickness 18 cm
Construction of cement bound (stabilised) crushed stone subbase,
31 244 m2
thickness 20 cm
Construction of cement bound (stabilised) crushed stone subbase,
31 245 m2
thickness 22 cm
Construction of cement bound (stabilised) crushed stone subbase,
31 246 m2
thickness 25 cm
Construction of cement bound (stabilised) recycled material subbase,
31 251 m2
thickness 10 cm
Construction of cement bound (stabilised) recycled material subbase,
31 252 m2
thickness 12 cm
Construction of cement bound (stabilised) recycled material subbase,
31 253 m2
thickness 15 cm
Construction of cement bound (stabilised) recycled material subbase,
31 254 m2
thickness 18 cm
Construction of cement bound (stabilised) recycled material subbase,
31 255 m2
thickness 20 cm
Construction of cement bound (stabilised) subbase of mixed stone
31 261 m2
material, thickness 10 cm
Construction of cement bound (stabilised) subbase of mixed stone
31 262 m2
material, thickness 12 cm

Draft of Version 1 – March 2008 Page 27


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of cement bound (stabilised) subbase of mixed stone
31 263 m2
material, thickness 15 cm
Construction of cement bound (stabilised) subbase of mixed stone
31 264 m2
material, thickness 18 cm
Construction of cement bound (stabilised) subbase of mixed stone
31 265 m2
material, thickness 20 cm
Construction of subbase of natural gravel or naturally crushed stone
31 271 m2
material, bound (stabilised) by composite binder, thickness 15 cm
Construction of subbase of natural gravel or naturally crushed stone
31 272 m2
material, bound (stabilised) by composite binder, thickness 18 cm
Construction of subbase of natural gravel or naturally crushed stone
31 273 m2
material, bound (stabilised) by composite binder, thickness 20 cm
Construction of subbase of natural gravel or naturally crushed stone
31 274 m2
material, bound (stabilised) by composite binder, thickness 25 cm
Construction of sand gravel subbase, bound (stabilised) by composite
31 281 m2
binder, thickness 15 cm
Construction of sand gravel subbase, bound (stabilised) by composite
31 282 m2
binder, thickness 18 cm
Construction of sand gravel subbase, bound (stabilised) by composite
31 283 m2
binder, thickness 20 cm
Construction of sand gravel subbase, bound (stabilised) by composite
31 284 m2
binder, thickness 25 cm
Construction of crushed stone subbase, bound (stabilised) by composite
31 291 m2
binder, thickness 15 cm
Construction of crushed stone subbase, bound (stabilised) by composite
31 292 m2
binder, thickness 18 cm
Construction of crushed stone subbase, bound (stabilised) by composite
31 293 m2
binder, thickness 20 cm
Construction of crushed stone subbase, bound (stabilised) by composite
31 294 m2
binder, thickness 25 cm

Draft of Version 1 – March 2008 Page 28


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3.1.3 Base Courses and Base-wearing Courses Bound by Bituminous Binders

Unit
Code Description of work
measure
Construction of road base made of asphalt mixture with bituminous sand
31 311 m2
gravel of grading 0/16 or 0/22 mm, thickness 4 cm
Construction of road base made of asphalt mixture with bituminous sand
31 312 m2
gravel of grading 0/16 or 0/22 mm, thickness 5 cm
Construction of road base made of asphalt mixture with bituminous sand
31 313 m2
gravel of grading 0/16 or 0/22 mm, thickness 6 cm
Construction of road base made of asphalt mixture with bituminous sand
31 314 m2
gravel of grading 0/16 or 0/22 mm, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous sand
31 315 m2
gravel of grading 0/16 or 0/22 mm, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous sand
31 316 m2
gravel of grading 0/16 or 0/22 mm, thickness 9 cm
Construction of road base made of asphalt mixture with bituminous sand
31 317 m2
gravel of grading 0/16 or 0/22 mm, thickness 10 cm
Construction of road base made of asphalt mixture with bituminous sand
31 318 m2
gravel of grading 0/16 or 0/22 mm, thickness 11 cm
Construction of road base made of asphalt mixture with bituminous sand
31 321 m2
gravel of grading 0/32 mm, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous sand
31 322 m2
gravel of grading 0/32 mm, thickness 9 cm
Construction of road base made of asphalt mixture with bituminous sand
31 323 m2
gravel of grading 0/32 mm, thickness 10 cm
Construction of road base made of asphalt mixture with bituminous sand
31 324 m2
gravel of grading 0/32 mm, thickness 11 cm
Construction of road base made of asphalt mixture with bituminous sand
31 325 m2
gravel of grading 0/32 mm, thickness 12 cm
Construction of road base made of asphalt mixture with bituminous sand
31 326 m2
gravel of grading 0/32 mm, thickness 14 cm
Construction of road base made of asphalt mixture with bituminous
31 331 m2
crushed stone of grading 0/16 or 0/16S mm, thickness 4 cm
Construction of road base made of asphalt mixture with bituminous
31 332 m2
crushed stone of grading 0/16 or 0/16S mm, thickness 5 cm
Construction of road base made of asphalt mixture with bituminous
31 333 m2
crushed stone of grading 0/16 or 0/16S mm, thickness 6 cm

Draft of Version 1 – March 2008 Page 29


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of road base made of asphalt mixture with bituminous
31 334 m2
crushed stone of grading 0/16 or 0/16S mm, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous
31 335 m2
crushed stone of grading 0/16 or 0/16S mm, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous
31 341 m2
crushed stone of grading 0/22 or 0/32 mm, thickness 6 cm
Construction of road base made of asphalt mixture with bituminous
31 342 m2
crushed stone of grading 0/22 or 0/32 mm, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous
31 343 m2
crushed stone of grading 0/22 or 0/32 mm, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous
31 344 m2
crushed stone of grading 0/22 or 0/32 mm, thickness 9 cm
Construction of road base made of asphalt mixture with bituminous
31 345 m2
crushed stone of grading 0/22 or 0/32 mm, thickness10 cm
Construction of road base made of asphalt mixture with bituminous
31 346 m2
crushed stone of grading 0/22 or 0/32 mm, thickness11 cm
Construction of road base made of asphalt mixture with bituminous
31 347 m2
crushed stone of grading 0/22 or 0/32 mm, thickness12 cm
Construction of road base made of asphalt mixture with bituminous
31 348 m2
crushed stone of grading 0/22 or 0/32 mm, thickness13 cm
Construction of road base made of asphalt mixture with bituminous
31 349 m2
crushed stone of grading 0/22 or 0/32 mm, thickness14 cm
Construction of road base made of asphalt mixture with bituminous
2
31 351 m crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 6 cm
Construction of road base made of asphalt mixture with bituminous
2
31 352 m crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous
31 353 m2 crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous
31 354 m2 crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 9 cm
Construction of road base made of asphalt mixture with bituminous
31 355 m2 crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 10 cm

Draft of Version 1 – March 2008 Page 30


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of road base made of asphalt mixture with bituminous
2
31 356 m crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 11 cm
Construction of road base made of asphalt mixture with bituminous
2
31 357 m crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 12 cm
Construction of road base made of asphalt mixture with bituminous
2
31 358 m crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 13 cm
Construction of road base made of asphalt mixture with bituminous
2
31 359 m crushed stone of grading 0/22S or 0/32S mm, containing road construction
bitumen, thickness 14 cm
Construction of road base made of asphalt mixture with bituminous
2
31 361 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 6 cm
Construction of road base made of asphalt mixture with bituminous
2
31 362 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous
2
31 363 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous
2
31 364 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 9 cm
Construction of road base made of asphalt mixture with bituminous
2
31 365 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 10 cm
Construction of road base made of asphalt mixture with bituminous
2
31 366 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 11 cm
Construction of road base made of asphalt mixture with bituminous
2
31 367 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 12 cm
Construction of road base made of asphalt mixture with bituminous
2
31 368 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 13 cm
Construction of road base made of asphalt mixture with bituminous
2
31 369 m crushed stone of grading 0/22S or 0/32S mm, containing composite
bitumen binder, thickness 14 cm

Draft of Version 1 – March 2008 Page 31


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of road base made of asphalt mixture with bituminous
2
31 371 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 6 cm
Construction of road base made of asphalt mixture with bituminous
2
31 372 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous
2
31 373 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous
2
31 374 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 9 cm
Construction of road base made of asphalt mixture with bituminous
2
31 375 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 10 cm
Construction of road base made of asphalt mixture with bituminous
2
31 376 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 11 cm
Construction of road base made of asphalt mixture with bituminous
2
31 377 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 12 cm
Construction of road base made of asphalt mixture with bituminous
2
31 378 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 13 cm
Construction of road base made of asphalt mixture with bituminous
2
31 379 m crushed stone of grading 0/22S or 0/32S mm, containing polymer modified
bitumen binder, thickness 14 cm
Construction of road base made of asphalt mixture with bituminous gravel
31 381 m2
chippings of grading 0/16 or 0/22 mm, thickness 4 cm
Construction of road base made of asphalt mixture with bituminous gravel
31 382 m2
chippings of grading 0/16 or 0/22 mm, thickness 5 cm
Construction of road base made of asphalt mixture with bituminous gravel
31 383 m2
chippings of grading 0/16 or 0/22 mm, thickness 6 cm
Construction of road base made of asphalt mixture with bituminous gravel
31 384 m2
chippings of grading 0/16 or 0/22 mm, thickness 7 cm
Construction of road base made of asphalt mixture with bituminous gravel
31 385 m2
chippings of grading 0/16 or 0/22 mm, thickness 8 cm
Construction of road base made of asphalt mixture with bituminous gravel
31 386 m2
chippings of grading 0/16 or 0/22 mm, thickness 9 cm

Draft of Version 1 – March 2008 Page 32


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of road base made of asphalt mixture with bituminous gravel
31 387 m2
chippings of grading 0/16 or 0/22 mm, thickness 10 cm
Construction of base wearing course with bituminous crushed stone of
31 391 m2
grading 0/16 mm, thickness 4 cm
Construction of base wearing course with bituminous crushed stone of
31 392 m2
grading 0/16 mm, thickness 5 cm
Construction of base wearing course with bituminous crushed stone of
31 393 m2
grading 0/16 mm, thickness 6 cm
Construction of base wearing course with bituminous crushed stone of
31 394 m2
grading 0/16 mm, thickness 7 cm
Construction of base wearing course with bituminous crushed stone of
31 395 m2
grading 0/16 mm, thickness 8 cm

3.1.4 Natural Asphalt Bitumen (Ashpalt) Modified Bitumen Binders

Unit
Code Description of work
measure
Supply and application of bitumen for subbase asphalt mixture containing
31 911 t
natural asphalt Trinidad modified bituminous binder (requirements for PmB II)
Supply and application of bitumen for subbase asphalt mixture containing
31 912 t
natural asphalt Selenica modified bituminous binder (requirements for PmB II)
Supply and application of bitumen for subbase asphalt mixture containing
31 913 t
natural asphalt Uintate modified bituminous binder (requirements for PmB II)
Supply and application of bitumen for subbase asphalt mixture containing
31 914 t
natural bitumen .......... modified bituminous binder (requirements for PmB II)
Supply and application of bitumen for subbase asphalt mixture containing
31 915 t
natural asphalt ........... modified bituminous binder (requirements for PmB II)

Draft of Version 1 – March 2008 Page 33


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3.2 Polymer Modified Bitumen Binders

Unit
Code Description of work
measure
Supply and application of bitumen for wearing course asphalt mixture
31 921 t
containing modified bituminous binder PmB I
Supply and application of bitumen for wearing course asphalt mixture
31 922 t
containing modified bituminous binder PmB II
Supply and application of bitumen for wearing course asphalt mixture
31 923 t
containing modified bituminous binder PmB III
Supply and application of bitumen for wearing course asphalt mixture
31 924 t
containing modified bituminous binder PmB IV

3.3 Wearing and Sealing Courses

3.3.1 Unstabilised Wearing Courses

Unit
Code Description of work
measure
Construction of unstabilised (mechanically stabilised) wearing course
32 111 m3
made of mixture of crushed stone, thickness 15 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 112 m3
made of mixture of crushed stone, thickness 16–20 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 113 m3
made of mixture of crushed stone, thickness 21–25 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 114 m3
made of mixture of crushed stone, thickness 26–30 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 115 m3
made of mixture of crushed stone, thickness above 30 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 121 m3
made of mixture of pit-run gravel, thickness 15 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 122 m3
made of mixture of pit-run gravel, 16–20 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 123 m3
made of mixture of pit-run gravel, 21–25 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 124 m3
made of mixture of pit-run gravel, 26–30 cm
32 125 m3 Construction of unstabilised (mechanically stabilised) wearing course

Draft of Version 1 – March 2008 Page 34


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
made of mixture of pit-run gravel, above 30 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 131 m3
made of mixture of gravel granules, thickness 15 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 132 m3
made of mixture of gravel granules, thickness 16–20 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 133 m3
made of mixture of gravel granules, thickness 21–25 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 134 m3
made of mixture of gravel granules, thickness 26–30 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 135 m3
made of mixture of gravel granules, thickness above 30 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 141 m3
made of mixture of various size granules, thickness 15 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 142 m3
made of mixture of various size granules, thickness 16–20 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 143 m3
made of mixture of various size granules, thickness 21–25 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 144 m3
made of mixture of various size granules, thickness 26–30 cm
Construction of unstabilised (mechanically stabilised) wearing course
32 145 m3
made of mixture of various size granules, thickness above 30 cm

3.3.2 Stabilised Wearing and Sealing Courses – Bituminous Concretes

Unit
Code Description of work
measure
Construction of wearing–sealing courses of bituminous concrete from
32 211 m2
mixture of granules 0/8 mm made of silicate stone, thickness 2.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 212 m2
mixture of granules 0/8 mm made of silicate stone, thickness 3.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 213 m2
mixture of granules 0/8 mm made of silicate stone, thickness 3.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 214 m2
mixture of granules 0/8 mm made of silicate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 221 m2
mixture of granules 0/11 mm made of silicate stone, thickness 3.5 cm

Draft of Version 1 – March 2008 Page 35


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing–sealing courses of bituminous concrete from
32 222 m2
mixture of granules 0/11 mm made of silicate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 223 m2
mixture of granules 0/11 mm made of silicate stone, thickness 4.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 224 m2
mixture of granules 0/11 mm made of silicate stone, thickness 5.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 225 m2
mixture of granules 0/11 mm made of silicate stone, thickness 6.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 231 m2
mixture of granules 0/16 mm made of silicate stone, thickness 3.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 232 m2
mixture of granules 0/16 mm made of silicate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 233 m2
mixture of granules 0/16 mm made of silicate stone, thickness 4.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 234 m2
mixture of granules 0/16 mm made of silicate stone, thickness 5.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 235 m2
mixture of granules 0/16 mm made of silicate stone, thickness 6.0 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 241 m size 0/8 mm, from mixture of granules of sand of carbonate stone and
granules of chippings of silicate stone, thickness 2.5 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 242 m size 0/8 mm, from mixture of granules of sand of carbonate stone and
granules of chippings of silicate stone, thickness 3.0 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 243 m size 0/8 mm, from mixture of granules of sand of carbonate stone and
granules of chippings of silicate stone, thickness 3.5 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 244 m size 0/8 mm, from mixture of granules of sand of carbonate stone and
granules of chippings of silicate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 251 m size 0/11 mm, from mixture of granules of sand of carbonate stone and of
chippings of silicate stone, thickness 3.0 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 252 m size 0/11 mm, from mixture of granules of sand of carbonate stone and of
chippings of silicate stone, thickness 3.5 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 253 m size 0/11 mm, from mixture of granules of sand of carbonate stone and of
chippings of silicate stone, thickness 4.0 cm

Draft of Version 1 – March 2008 Page 36


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 254 m size 0/11 mm, from mixture of granules of sand of carbonate stone and of
chippings of silicate stone, thickness 4.5 cm
Construction of wearing–sealing courses of bituminous concrete, grade-
2
32 255 m size 0/11 mm, from mixture of granules of sand of carbonate stone and of
chippings of silicate stone, thickness 5.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 261 m2
mixture of granules 0/4 mm made of carbonate stone, thickness 2.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 262 m2
mixture of granules 0/4 mm made of carbonate stone, thickness 2.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 263 m2
mixture of granules 0/4 mm made of carbonate stone, thickness 3.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 271 m2
mixture of granules 0/8 mm made of carbonate stone, thickness 2.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 272 m2
mixture of granules 0/8 mm made of carbonate stone, thickness 3.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 273 m2
mixture of granules 0/8 mm made of carbonate stone, thickness 3.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 274 m2
mixture of granules 0/8 mm made of carbonate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 281 m2
mixture of granules 0/11 mm made of carbonate stone, thickness 3.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 282 m2
mixture of granules 0/11 mm made of carbonate stone, thickness 3.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 283 m2
mixture of granules 0/11 mm made of carbonate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 284 m2
mixture of granules 0/11 mm made of carbonate stone, thickness 4.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 285 m2
mixture of granules 0/11 mm made of carbonate stone, thickness 5.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 291 m2
mixture of granules 0/16 mm made of carbonate stone, thickness 4.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 292 m2
mixture of granules 0/16 mm made of carbonate stone in thickness 4.5 cm
Construction of wearing–sealing courses of bituminous concrete from
32 293 m2
mixture of granules 0/16 mm made of carbonate stone in thickness 5.0 cm
Construction of wearing–sealing courses of bituminous concrete from
32 294 m2
mixture of granules 0/16 mm made of carbonate stone in thickness 5.5 cm

Draft of Version 1 – March 2008 Page 37


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing–sealing courses of bituminous concrete from
32 295 m2
mixture of granules 0/16 mm made of carbonate stone in thickness 6.0 cm

3.3.3 Stabilised Wearing and Sealing Courses – Poured Asphalts

Unit
Code Description of work
measure
Construction of wearing–sealing courses of poured asphalt from mixture of
32 311 m2
granules 0/8 mm made of silicate stone, thickness 2.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 312 m2
granules 0/8 mm made of silicate stone, thickness 3.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 313 m2
granules 0/8 mm made of silicate stone, thickness 3.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 321 m2
granules 0/8 mm made of carbonate stone, thickness 2.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 322 m2
granules 0/8 mm made of carbonate stone, thickness 3.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 323 m2
granules 0/8 mm made of carbonate stone, thickness 3.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 331 m2 granules 0/8 mm made of carbonate stone and with silicate stone
chippings, thickness 2.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 332 m2 granules 0/8 mm made of carbonate stone and with silicate stone
chippings, thickness 3.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 334 m2 granules 0/8 mm made of carbonate stone and with silicate stone
chippings, thickness 3.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 341 m2
granules 0/11 mm made of silicate stone, thickness 3.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 342 m2
granules 0/11 mm made of silicate stone, thickness 3.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 343 m2
granules 0/11 mm made of silicate stone, thickness 4.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 351 m2
granules 0/11 mm made of carbonate stone, thickness 3.0 cm

Draft of Version 1 – March 2008 Page 38


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing–sealing courses of poured asphalt from mixture of
32 352 m2
granules 0/11 mm made of carbonate stone, thickness 3.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 353 m2
granules 0/11 mm made of carbonate stone, thickness 4.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
2
32 361 m granules 0/11 mm made of carbonate stone and gritting of silicate stone,
thickness 3.0 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
2
32 362 m granules 0/11 mm made of carbonate stone and gritting of silicate stone,
thickness 3.5 cm
Construction of wearing–sealing courses of poured asphalt from mixture of
32 363 m2 granules 0/11 mm made of carbonate stone and gritting of silicate stone,
thickness 4.0 cm

3.3.4 Stabilised Wearing and Sealing Courses – Surface Dressings

Unit
Code Description of work
measure
Construction of single layer carriageway surface dressing with single
32 411 m2
spread of crushed aggregate of 2/4 mm and with road construction bitumen
Construction of single layer carriageway surface dressing with single
32 412 m2
spread of crushed aggregate of 2/4 mm and with polymer modified bitumen
Construction of single layer carriageway surface dressing with single
2
32 413 m spread of crushed aggregate of 2/4 mm and with polymer modified bitumen
emulsion
Construction of single layer carriageway surface dressing with single
32 414 m2
spread of crushed aggregate of 4/8 mm and with road construction bitumen
Construction of single layer carriageway surface dressing with single
32 415 m2
spread of crushed aggregate of 4/8 mm and with polymer modified bitumen
Construction of single layer carriageway surface dressing with single
2
32 416 m spread of crushed aggregate of 4/8 mm and with polymer modified bitumen
emulsion
Construction of single layer carriageway surface dressing with single
2
32 417 m spread of crushed aggregate of 8/11 mm and with road construction
bitumen

Draft of Version 1 – March 2008 Page 39


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of single layer carriageway surface dressing with single
2
32 418 m spread of crushed aggregate of 8/11 mm and with polymer modified
bitumen
Construction of single layer carriageway surface dressing with single
2
32 419 m spread of crushed aggregate of 8/11 mm and with polymer modified
bitumen emulsion
Construction of single layer carriageway surface dressing with single
2
32 421 m spread of coated crushed aggregate of 2/4 mm and with road construction
bitumen
Construction of single layer carriageway surface dressing with single
2
32 422 m spread of coated crushed aggregate of 2/4 mm and with polymer modified
bitumen
Construction of single layer carriageway surface dressing with single
2
32 423 m spread of coated crushed aggregate of 2/4 mm and with polymer modified
bitumen emulsion
Construction of single layer carriageway surface dressing with single
2
32 424 m spread of coated crushed aggregate of 4/8 mm and with road construction
bitumen
Construction of single layer carriageway surface dressing with single
2
32 425 m spread of coated crushed aggregate of 4/8 mm and with polymer modified
bitumen
Construction of single layer carriageway surface dressing with single
2
32 426 m spread of coated crushed aggregate of 4/8 mm and with polymer modified
bitumen emulsion
Construction of single layer carriageway surface dressing with single
2
32 427 m spread of coated crushed aggregate of 8/11 mm and with road construction
bitumen
Construction of single layer carriageway surface dressing with single
2
32 428 m spread of coated crushed aggregate of 8/11 mm and with polymer modified
bitumen
Construction of single layer carriageway surface dressing with single
2
32 429 m spread of coated crushed aggregate of 8/11 mm and with polymer modified
bitumen emulsion
Construction of single layer carriageway surface dressing with double
2
32 431 m spread of crushed aggregate of 8/11 and 2/4 mm and with road
construction bitumen
Construction of single layer carriageway surface dressing with double
2
32 432 m spread of crushed aggregate of 8/11 and 2/4 mm and with polymer
modified bitumen

Draft of Version 1 – March 2008 Page 40


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of single layer carriageway surface dressing with double
2
32 433 m spread of crushed aggregate of 8/11 and 2/4 mm and with polymer
modified bitumen emulsion
Construction of single layer carriageway surface dressing with double
2
32 435 m spread of crushed aggregate of 11/16 and 4/8 mm and with road
construction bitumen
Construction of single layer carriageway surface dressing with double
2
32 436 m spread of crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen
Construction of single layer carriageway surface dressing with double
2
32 437 m spread of crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen emulsion
Construction of single layer carriageway surface dressing with double
2
32 441 m spread of coated crushed aggregate of 8/11 and 2/4 mm and with road
construction bitumen
Construction of single layer carriageway surface dressing with double
2
32 442 m spread of coated crushed aggregate of 8/11 and 2/4 mm and with polymer
modified bitumen
Construction of single layer carriageway surface dressing with double
2
32 443 m spread of coated crushed aggregate of 8/11 and 2/4 mm and with polymer
modified bitumen emulsion
Construction of single layer carriageway surface dressing with double
2
32 445 m spread of coated crushed aggregate of 11/16 and 4/8 mm and with road
construction bitumen
Construction of single layer carriageway surface dressing with double
2
32 441 m spread of coated crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen
Construction of single layer carriageway surface dressing with double
2
32 447 m spread of coated crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen emulsion
Construction of double layer carriageway surface dressing with single
2
32 451 m spread of crushed aggregate of 8/11 and 4/8 mm and with road
construction bitumen
Construction of double layer carriageway surface dressing with single
2
32 452 m spread of crushed aggregate of 8/11 and 4/8 mm and with polymer
modified bitumen
Construction of double layer carriageway surface dressing with single
2
32 453 m spread of crushed aggregate of 8/11 and 4/8 mm and with polymer
modified bitumen emulsion

Draft of Version 1 – March 2008 Page 41


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of double layer carriageway surface dressing with single
2
32 455 m spread of crushed aggregate of 11/16 and 4/8 mm and with road
construction bitumen
Construction of double layer carriageway surface dressing with single
2
32 456 m spread of crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen
Construction of double layer carriageway surface dressing with single
2
32 457 m spread of crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen emulsion
Construction of double layer carriageway surface dressing with single
2
32 461 m spread of coated crushed aggregate of 8/11 and 4/8 mm and with road
construction bitumen
Construction of double layer carriageway surface dressing with single
2
32 462 m spread of coated crushed aggregate of 8/11 and 4/8 mm and with polymer
modified bitumen
Construction of double layer carriageway surface dressing with single
2
32 463 m spread of coated crushed aggregate of 8/11 and 4/8 mm and with polymer
modified bitumen emulsion
Construction of double layer carriageway surface dressing with single
2
32 465 m spread of coated crushed aggregate of 11/16 and 4/8 mm and with road
construction bitumen
Construction of double layer carriageway surface dressing with single
2
32 466 m spread of coated crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen
Construction of double layer carriageway surface dressing with single
2
32 467 m spread of coated crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen emulsion
Construction of inverted double layer carriageway surface dressing with
2
32 471 m single spread of crushed aggregate of 2/4 and 8/11 mm and with road
construction bitumen
Construction of inverted double layer carriageway surface dressing with
2
32 472 m single spread of crushed aggregate of 2/4 and 8/11 mm and with polymer
modified bitumen
Construction of inverted double layer carriageway surface dressing with
2
32 473 m single spread of crushed aggregate of 2/4 and 8/11 mm and with polymer
modified bitumen emulsion
Construction of inverted double layer carriageway surface dressing with
2
32 475 m single spread of crushed aggregate of 4/8 and 11/16 mm and with road
construction bitumen

Draft of Version 1 – March 2008 Page 42


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of inverted double layer carriageway surface dressing with
2
32 476 m single spread of crushed aggregate of 4/8 and 11/16 mm and with polymer
modified bitumen
Construction of inverted double layer carriageway surface dressing with
2
32 477 m single spread of crushed aggregate of 4/8 and 11/16 mm and with polymer
modified bitumen emulsion
Construction of sandwich carriageway surface dressing system with single
2
32 481 m spread of crushed aggregate of 8/11 and 2/4 mm and with road
construction bitumen
Construction of sandwich carriageway surface dressing system with single
2
32 482 m spread of crushed aggregate of 8/11 and 2/4 mm and with polymer
modified bitumen
Construction of sandwich carriageway surface dressing system with single
2
32 483 m spread of crushed aggregate of 8/11 and 2/4 mm and with polymer
modified bitumen emulsion
Construction of sandwich carriageway surface dressing system with single
2
32 484 m spread of crushed aggregate of 8/11 and 4/8 mm and with road
construction bitumen
Construction of sandwich carriageway surface dressing system with single
2
32 485 m spread of crushed aggregate of 8/11 and 4/8 mm and with polymer
modified bitumen
Construction of sandwich carriageway surface dressing system with single
2
32 486 m spread of crushed aggregate of 8/11 and 4/8 mm and with polymer
modified bitumen emulsion
Construction of sandwich carriageway surface dressing system with single
2
32 487 m spread of crushed aggregate of 11/16 and 4/8 mm and with road
construction bitumen
Construction of sandwich carriageway surface dressing system with single
2
32 488 m spread of crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen
Construction of sandwich carriageway surface dressing system with single
2
32 489 m spread of crushed aggregate of 11/16 and 4/8 mm and with polymer
modified bitumen emulsion
32 491 m2 Construction of surface dressing with bituminous slurry seal up to 3 kg/m2
32 492 m2 Construction of surface dressing with bituminous slurry seal 3–5 kg/m2
32 493 m2 Construction of surface dressing with bituminous slurry seal 5–8 kg/m2
32 494 m2 Construction of surface dressing with bituminous slurry seal 8–12 kg/m2

Draft of Version 1 – March 2008 Page 43


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3.3.5 Stabilised Wearing Course – Drainage – Asphalt

Unit
Code Description of work
measure
Construction of wearing course of drainage–asphalt from mixture of
32 511 m2
granules 0/8 mm of silicate stone, thickness 2.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 512 m2
granules 0/8 mm of silicate stone, thickness 3.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 513 m2
granules 0/8 mm of silicate stone, thickness 3.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 521 m2
granules 0/8 mm of carbonate stone, thickness 2.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 522 m2
granules 0/8 mm of carbonate stone, thickness 3.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 523 m2
granules 0/8 mm of carbonate stone, thickness 3.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 531 m2
granules 0/11 mm of silicate stone, thickness 2.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 532 m2
granules 0/11 mm of silicate stone, thickness 3.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 533 m2
granules 0/11 mm of silicate stone, thickness 3.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 541 m2
granules 0/11 mm of carbonate stone, thickness 3.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 542 m2
granules 0/11 mm of carbonate stone, thickness 3.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 543 m2
granules 0/11 mm of carbonate stone, thickness 4.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 551 m2
granules 0/16 mm of silicate stone, thickness 4.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 552 m2
granules 0/16 mm of silicate stone, thickness 4.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 553 m2
granules 0/16 mm of silicate stone, thickness 5.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 561 m2
granules 0/16 mm of carbonate stone, thickness 4.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 562 m2
granules 0/16 mm of carbonate stone, thickness 4.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 563 m2
granules 0/16 mm of carbonate stone, thickness 5.0 cm

Draft of Version 1 – March 2008 Page 44


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing course of drainage–asphalt from mixture of
32 571 m2
granules 0/22 mm of silicate stone in thickness 5.0 cm
Construction of wearing course of drainage–asphalt from mixture of
32 572 m2
granules 0/22 mm of silicate stone in thickness 5.5 cm
Construction of wearing course of drainage–asphalt from mixture of
32 573 m2
granules 0/22 mm of silicate stone in thickness 6.0 cm

3.3.6 Bound Wearing and Seal Courses – Split Mastic Asphalt

Unit
Code Description of work
measure
Construction of wearing-seal courses made of split mastic asphalt with
2
32 611 m silicate rock aggregate of grading 0/8 mm and road construction bitumen,
thickness 2.0 cm
32 612 m2 As above, thickness 2.5 cm
2
32 613 m As above, thickness 3.0 cm
32 614 m2 As above, thickness 3.5 cm
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 616 m silicate rock aggregate of grading 0/8 mm and modified bitumen, thickness
2.0 cm
32 617 m2 As above, thickness 2.5 cm
2
32 618 m As above, thickness 3.0 cm
2
32 619 m As above, thickness 3.5 cm
Construction of wearing-seal courses made of splittmastixasphalt with
32 621 m2 silicate rock aggregate of grading 0/11 mm and road construction bitumen,
thickness 2.5 cm
32 622 m2 As above, thickness 3.0 cm
2
32 623 m As above, thickness 3.5 cm
2
32 624 m As above, thickness 4.0 cm
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 626 m silicate rock aggregate of grading 0/11 mm and modified bitumen,
thickness 2.5 cm
32 627 m2 As above, thickness 3.0 cm
2
32 628 m As above, thickness 3.5 cm
2
32 629 m As above, thickness 4.0 cm

Draft of Version 1 – March 2008 Page 45


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 631 m carbonate rock sand and silicate rock aggregate of grading 0/8 mm and
road construction bitumen, thickness 2.0 cm
32 632 m2 As above, thickness 2.5 cm
32 633 m2 As above, thickness 3.0 cm
2
32 634 m As above, thickness 3.5 cm
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 636 m carbonate rock sand and silicate rock aggregate of grading 0/8 mm and
modified bitumen, thickness 2.0 cm
32 637 m2 As above, thickness 2.5 cm
2
32 638 m As above, thickness 3.0 cm
Construction of wearing-seal courses made of splittmastixasphalt with
32 639 m2 carbonate rock sand and silicate rock aggregate of grading 0/8 mm and
modified bitumen, thickness 3.5 cm
Construction of wearing-seal courses made of splittmastixasphalt with
32 641 m2 carbonate rock sand and silicate rock aggregate of grading 0/11 mm and
road construction bitumen, thickness 2.5 cm
32 642 m2 As above, thickness 3.0 cm
2
32 643 m As above, thickness 3.5 cm
2
32 644 m As above, thickness 4.0 cm
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 646 m carbonate rock sand and silicate rock aggregate of grading 0/11 mm and
modified bitumen, thickness 2.5 cm
32 647 m2 As above, thickness 3.0 cm
2
32 648 m As above, thickness 3.5 cm
2
32 649 m As above, thickness 4.0 cm
Construction of wearing-seal courses made of splittmastixasphalt with
32 651 m2 carbonate rock aggregate of grading 0/4 mm and road construction
bitumen, thickness 1.5 cm
32 652 m2 As above, thickness 2.0 cm
32 655 m2 As above, thickness 2.5 cm
2
32 656 m As above, thickness 3.0 cm
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 661 m carbonate rock aggregate of grading 0/8 mm and road construction
bitumen, thickness 2.0 cm
32 662 m2 As above, thickness 2.5 cm
2
32 663 m As above, thickness 3.0 cm

Draft of Version 1 – March 2008 Page 46


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing-seal courses made of splittmastixasphalt with
2
32 666 m carbonate rock aggregate of grading 0/8 mm and modified bitumen,
thickness 2.0 cm
32 667 m2 As above, thickness 2.5 cm
32 668 m2 As above, thickness 3.0 cm

3.3.7 Stabilised Roadbases and Wearing Courses – Cement Concretes

Unit
Code Description of work
measure
Construction of roadbase from mass cement concrete MB ……. made of
33 111 m2
mixture of carbonate stone granules, thickness 10 cm
Construction of roadbase from mass cement concrete MB ……. made of
33 112 m2
mixture of carbonate stone granules, thickness 12 cm
Construction of roadbase from mass cement concrete MB ……. made of
33 113 m2
mixture of carbonate stone granules, thickness 14 cm
Construction of roadbase from mass cement concrete MB ……. made of
33 114 m2
mixture of carbonate stone granules, thickness 16 cm
Construction of roadbase from mass cement concrete MB ……. made of
33 115 m2
mixture of carbonate stone granules, thickness 18 cm
Construction of roadbase from reinforced cement concrete MB ……. made
33 121 m2
of mixture of carbonate stone granules, thickness 10 cm
Construction of roadbase from reinforced cement concrete MB ……. made
33 122 m2
of mixture of carbonate stone granules, thickness 12 cm
Construction of roadbase from reinforced cement concrete MB ……. made
33 123 m2
of mixture of carbonate stone granules, thickness 14 cm
Construction of roadbase from reinforced cement concrete MB ……. made
33 124 m2
of mixture of carbonate stone granules, thickness 16 cm
Construction of roadbase from reinforced cement concrete MB ……. made
33 125 m2
of mixture of carbonate stone granules, thickness 18 cm
Construction of wearing–sealing course cement concrete MB ……. made
33 211 m2
of mixture of granules of silicate stone, thickness 5 cm
Construction of wearing–sealing course cement concrete MB ……. made
33 212 m2
of mixture of granules of silicate stone, thickness 6 cm
Construction of wearing–sealing course cement concrete MB ……. made
33 213 m2
of mixture of granules of silicate stone, thickness 7 cm

Draft of Version 1 – March 2008 Page 47


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of wearing–sealing course cement concrete MB ……. made
33 221 m2
of mixture of carbonate granules of stone, thickness 5 cm
Construction of wearing–sealing course cement concrete MB ……. made
33 222 m2
of mixture of carbonate granules of stone, thickness 6 cm
Construction of wearing–sealing course cement concrete MB ……. made
33 223 m2
of mixture of carbonate granules of stone, thickness 7 cm
Construction of roadbase and wearing courses of cement concrete MB
33 311 m2
……. made of mixture of granules of silicate stone, thickness 14 cm
Construction of roadbase and wearing courses of cement concrete MB
33 312 m2
……. made of mixture of granules of silicate stone, thickness 16 cm
Construction of roadbase and wearing courses of cement concrete MB
33 313 m2
……. made of mixture of granules of silicate stone, thickness 18 cm
Construction of roadbase and wearing courses of cement concrete MB
33 314 m2
……. made of mixture of granules of silicate stone, thickness 20 cm
Construction of roadbase and wearing courses of cement concrete MB
33 315 m2
……. made of mixture of granules of silicate stone, thickness 22 cm
Construction of roadbase and wearing courses of cement concrete MB
33 316 m2
……. made of mixture of granules of silicate stone, thickness 24 cm
Construction of roadbase and wearing courses of cement concrete MB
33 321 m2
……. made of mixture of carbonate stone granules, in thickness 14 cm
Construction of roadbase and wearing courses of cement concrete MB
33 322 m2
……. made of mixture of carbonate stone granules, thickness 14 cm
Construction of roadbase and wearing courses of cement concrete MB
33 323 m2
……. made of mixture of carbonate stone granules, thickness 14 cm
Construction of roadbase and wearing courses of cement concrete MB
33 324 m2
……. made of mixture of carbonate stone granules, thickness 14 cm
Construction of roadbase and wearing courses of cement concrete MB
33 325 m2
……. made of mixture of carbonate stone granules, thickness 14 cm
Construction of roadbase and wearing courses of cement concrete MB
33 326 m2
……. made of mixture of carbonate stone granules, thickness 14 cm

Draft of Version 1 – March 2008 Page 48


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3.3.8 Paved Wearing Courses

Unit
Code Description of work
measure
Construction of paved wearing courses–mosaic of silicate stone cubes,
34 111 m2
size … mm/ …mm/ …mm, joints sealed with sand
Construction of paved wearing courses–mosaic of silicate stone cubes,
34 112 m2
size … mm/ …mm/ …mm, joint sealed with cement mortar
Construction of paved wearing courses–mosaic of silicate stone cubes,
34 113 m2
size … mm/ …mm/ …mm, joint sealed with bituminous mixture
Construction of paved wearing courses–mosaic of silicate stone cubes,
34 114 m2
size … mm/ …mm/ …mm, joint sealed with elastic mixture
Construction of paved wearing courses–mosaic of carbonate stone cubes,
34 121 m2
size … mm/ …mm/ …mm, joints sealed with sand
Construction of paved wearing courses–mosaic of carbonate stone cubes,
34 122 m2
size … mm/ …mm/ …mm, joint sealed with cement mortar
Construction of paved wearing courses–mosaic of carbonate stone cubes,
34 123 m2
size … mm/ …mm/ …mm, joint sealed with bituminous mixture
Construction of paved wearing courses–mosaic of carbonate stone cubes,
34 124 m2
size … mm/ …mm/ …mm, joint sealed with elastic mixture
Construction of paved wearing courses made of small silicate stone cubes,
34 211 m2
size … mm/ …mm/ …mm, joints sealed with sand
Construction of paved wearing courses made of small silicate stone cubes,
34 212 m2
size … mm/ …mm/ …mm, joint sealed with cement mortar
Construction of paved wearing courses made of small silicate stone cubes,
34 213 m2
size … mm/ …mm/ …mm, joint sealed with bituminous mixture
Construction of paved wearing courses made of small silicate stone cubes,
34 214 m2
size … mm/ …mm/ …mm, joint sealed with elastic mixture
Construction of paved wearing courses made of small carbonate stone
34 321 m2
cubes, size … mm/ …mm/ …mm, joints sealed with sand
Construction of paved wearing courses made of small carbonate stone
34 322 m2
cubes, size … mm/ …mm/ …mm, joint sealed with cement mortar
Construction of paved wearing courses made of small carbonate stone
34 323 m2
cubes, size … mm/ …mm/ …mm, joint sealed with bituminous mixture
Construction of paved wearing courses made of small carbonate stone
34 324 m2
cubes, size … mm/ …mm/ …mm, joint sealed with elastic mixture
Construction of paved wearing courses made of large silicate stone cubes,
34 311 m2
size … mm/ …mm/ …mm, joints sealed with sand

Draft of Version 1 – March 2008 Page 49


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of paved wearing courses made of large silicate stone cubes,
34 312 m2
size … mm/ …mm/ …mm, joint sealed with cement mortar
Construction of paved wearing courses made of large silicate stone cubes,
34 313 m2
size … mm/ …mm/ …mm, joint sealed with bituminous mixture
Construction of paved wearing courses made of large silicate stone cubes,
34 314 m2
size … mm/ …mm/ …mm, joint sealed with elastic mixture
Construction of paved wearing courses made of cement concrete cubes,
34 411 m2
size … mm/ …mm/ …mm, joints sealed with sand
Construction of paved wearing courses made of cement concrete cubes,
34 412 m2
size … mm/ …mm/ …mm, joint sealed with cement mortar
Construction of paved wearing courses made of cement concrete cubes,
34 413 m2
size … mm/ …mm/ …mm, joint sealed with bituminous mixture
Construction of paved wearing courses made of cement concrete cubes,
34 414 m2
size … mm/ …mm/ …mm, joint sealed with elastic mixture
Construction of paved wearing courses made of grass slabs made of
34 511 m2
cement concrete size … mm/ …mm/ …mm, joints sealed with sand
Construction of paved wearing courses made of grass slabs made of
2
34 512 m cement concrete size … mm/ …mm/ …mm, joint sealed with cement
mortar
Construction of paved wearing courses made of grass slabs made of
2
34 513 m cement concrete size … mm/ …mm/ …mm, joint sealed with bituminous
mixture
Construction of paved wearing courses made of grass slabs made of
2
34 514 m cement concrete size … mm/ …mm/ …mm, joint sealed with elastic
mixture
Construction of paved wearing courses made of slabs size … mm/ …mm/
2
34 611 m …mm placed on support layer of unstabilised mixture of granules, joints
sealed with sand
Construction of paved wearing courses made of slabs size … mm/ …mm/
2
34 612 m …mm placed on support layer of unstabilised mixture of granules, joint
sealed with cement mortar
Construction of paved wearing courses made of slabs size … mm/ …mm/
2
34 613 m …mm placed on support layer of unstabilised mixture of granules, joint
sealed with bituminous mixture
Construction of paved wearing courses made of slabs size … mm/ …mm/
2
34 614 m …mm placed on support layer of unstabilised mixture of granules, joint
sealed with elastic mixture

Draft of Version 1 – March 2008 Page 50


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Production of paved wearing courses made of slabs size … mm/ …mm/
2
34 621 m …mm, placed on support layer of limestone mortar, joints sealed with
cement mortar
Production of paved wearing courses made of slabs size … mm/ …mm/
2
34 622 m …mm, placed on support layer of limestone mortar, j joint sealed with
bituminous mixture
Production of paved wearing courses made of slabs size … mm/ …mm/
2
34 623 m …mm, placed on support layer of limestone mortar, jo joint sealed with
elastic mixture

3.4 Edge Elements of Carriageways

3.4.1 Extra Width

Unit
Code Description of work
measure
Construction of double-layered mass concrete 50 cm wide extra width
35 111 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 10 cm
Construction of double-layered mass concrete 50 cm wide extra width
35 112 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 12 cm
Construction of double-layered mass concrete 50 cm wide extra width
35 113 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 14 cm
Construction of double-layered mass concrete 50 cm wide extra width
35 114 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 16 cm
Construction of double-layered mass concrete 50 cm wide extra width
35 115 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 18 cm
Construction of double-layered mass concrete 50 cm wide extra width
35 121 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 16 cm
Construction of double-layered mass concrete 50 cm wide extra width
35 122 m made of cement concrete made of 6 cm thick surfacing from a silicate
stone mixture and a base of carbonate stone mixture, thickness 18 cm

Draft of Version 1 – March 2008 Page 51


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of single-layer mass concrete 50 cm wide extra width made
35 123 m of cement concrete made of 6 cm thick surfacing from a carbonate stone
mixture, in thickness 20 cm
Construction of single-layer mass concrete 50 cm wide extra width made
35 124 m of cement concrete made of 6 cm thick surfacing from a carbonate stone
mixture, thickness 22 cm
Construction of single-layer mass concrete 50 cm wide extra width made
35 125 m of cement concrete made of 6 cm thick surfacing from a carbonate stone
mixture, thickness 24 cm
Construction of single–layer reinforced concrete 50 cm wide extra width
35 131 m made of cement concrete made of carbonate stone mixture, thickness
8 cm
Construction of single–layer reinforced concrete 50 cm wide extra width
35 132 m made of cement concrete made of carbonate stone mixture, thickness
10 cm
Construction of single–layer reinforced concrete 50 cm wide extra width
35 133 m made of cement concrete made of carbonate stone mixture, thickness
12 cm
Construction of single–layer reinforced concrete 50 cm wide extra width
35 134 m made of cement concrete made of carbonate stone mixture, thickness
14 cm
Construction of single–layer reinforced concrete 50 cm wide extra width
35 135 m made of cement concrete made of carbonate stone mixture, thickness
16 cm

3.4.2 Kerbs

Unit
Code Description of work
measure
Placing of prefabricated elevated kerbs from cement concrete, with cross
35 211 m
section 15/25 cm
Placing of prefabricated elevated kerbs from cement concrete, with cross
35 212 m
section 15/30 cm
Placing of prefabricated elevated kerbs from cement concrete, with cross
35 213 m
section 18/30 cm
Placing of prefabricated elevated kerbs from cement concrete, with cross
35 214 m
section …./… cm

Draft of Version 1 – March 2008 Page 52


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of elevated kerbs made of cement concrete, with cross
35 221 m
section 15/25 cm
Construction of elevated kerbs made of cement concrete, with cross
35 222 m
section 15/30 cm
Construction of elevated kerbs made of cement concrete, with cross
35 223 m
section 18/30 cm
Construction of elevated kerbs made of cement concrete, with cross
35 224 m
section … /….cm
Placing of prefabricated sunken kerbs made of cement concrete, with
35 231 m
cross section 10/20 cm
Placing of prefabricated sunken kerbs made of cement concrete, with
35 232 m
cross section 12/20 cm
Placing of prefabricated sunken kerbs made of cement concrete, with
35 233 m
cross section 12/25 cm
Placing of prefabricated sunken kerbs made of cement concrete, with
35 234 m
cross section 15/25 cm
Placing of prefabricated sunken kerbs made of cement concrete, with
35 235 m
cross section …/… cm
Construction of flush kerbs made of cement concrete, with cross section
35 241 m
10/20 cm
Construction of flush kerbs made of cement concrete, with cross section
35 242 m
12/20 cm
Construction of flush kerbs made of cement concrete, with cross section
35 243 m
12/25 cm
Construction of flush kerbs made of cement concrete, with cross section
35 244 m
15/25 cm
Construction of flush kerbs made of cement concrete, with cross section
35 245 m
…/ … cm
Placing of elevated kerbs made of natural stone, with cross section …/ …
35 251 m
cm
Placing of elevated kerbs made of natural stone, with cross section …/ …
35 252 m
cm
35 261 m Placing of flush kerbs made of natural stone, with cross section …/ … cm
35 262 m Placing of flush kerbs made of natural stone, with cross section …/ … cm
Construction of kerbs made from bituminous mixture, with cross section
35 271 m
…/ … cm
Construction of kerbs made from bituminous mixture, with cross section
35 272 m
…/ … cm

Draft of Version 1 – March 2008 Page 53


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3.4.3 Borders

Unit
Code Description of work
measure
Placing of borders made of small cubes from natural stone, size
35 311 m
8 / 8 / 8 cm
Placing of borders made of small cubes from natural stone, size
35 312 m
9 / 9 / 9 cm
Placing of borders made of small cubes from natural stone, size
35 313 m
10 / 10 / 10 cm
Placing of borders made of small cubes from natural stone, size
35 314 m
.../ .../.... cm
Placing of borders made of small cubes from cement concrete, size
35 321 m
8 / 8 / 8 cm
Placing of borders made of small cubes from cement concrete, size
35 322 m
9 / 9 / 9 cm
Placing of borders made of small cubes from cement concrete, size
35 323 m
10 / 10 / 10 cm
Placing of borders made of small cubes from cement concrete, size
35 324 m
.../ .../.... cm

3.4.4 Guard Rails

Unit
Code Description of work
measure
Construction of guard rails, type New Jersey made of cement concrete of
35 411 m
mixture of carbonate stone granules, height ….. cm
Construction of guard rails, type New Jersey, made of prefabricated
35 412 m elements of cement concrete made from carbonate stone mixtures, height
…. cm

Draft of Version 1 – March 2008 Page 54


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

3.5 Shoulders

Unit
Code Description of work
measure
36 111 m2 Construction of shoulders with gravel or pit-run gravel, width to 0.5 m
2
36 112 m Construction of shoulders with gravel or pit-run gravel, width 0.5–1.0 m
2
36 113 m Construction of shoulders with gravel or pit-run gravel, width over 1.0 m
2
36 121 m Construction of shoulders with gravel, width to 0.5 m
2
36 122 m Construction of shoulders with gravel, width 0.5–1.0 m
2
36 123 m Construction of shoulders with gravel, width over 1.0 m
2
36 211 m Construction of top soil shoulders, width to 0.5 m
2
36 212 m Construction of top soil shoulders, width 0.5–1.0 m
2
36 213 m Construction of top soil shoulders, width over 1.0 m
Construction of shoulders, stabilised with grass covered slabs,
36 311 m2
width to 0.5 m
Construction of shoulders, stabilised with grass covered slabs,
36 312 m2
width 0.5–1.0 m
Construction of shoulders, stabilised with grass covered slabs,
36 313 m2
width over 1.0 m
Construction of shoulders, stabilised with crushed stone, filled with topsoil,
36 411 m2
width to 0.5 m
Construction of shoulders, stabilised with crushed stone, filled with topsoil,
36 412 m2
width 0.5–1.0 m
Construction of shoulders, stabilised with crushed stone, filled with topsoil,
36 413 m2
width over 1.0 m
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 511 m² composition of bituminous crush stone mixture BCSM 16, thickness 40
mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 512 m² composition of bituminous crush stone mixture BCSM 16, thickness 50
mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 513 m² composition of bituminous crush stone mixture BCSM 16, thickness 60
mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 521 m² composition of bituminous concrete BC 8 or BC 11, measuring in
thickness 25 mm

Draft of Version 1 – March 2008 Page 55


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 522 m² composition of bituminous concrete BC 8 or BC 11, measuring in
thickness 30 mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 523 m² composition of bituminous concrete BC 8 or BC 11, measuring in
thickness 35 mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 524 m² composition of bituminous concrete BC 8 or BC 11, measuring in
thickness 40 mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 531 m² composition of split mastic asphalt SMA 8s or SMA 11s, measuring in
thickness 25 mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 532 m² composition of split mastic asphalt SMA 8s or SMA 11s, measuring in
thickness 30 mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 533 m² composition of split mastic asphalt SMA 8s or SMA 11s, measuring in
thickness 35 mm
Construction of shoulder, not more than 0.5 m wide, of asphalt-based
36 534 m² composition of split mastic asphalt SMA 8s or SMA 11s, measuring in
thickness 40 mm

Draft of Version 1 – March 2008 Page 56


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

4 Drainage

4.1 Surface Drainage

Unit
Code Description of work
measure
Paving of ditches with broken stone of thickness 20 cm, joints filled with
2
41 111 m crushed rock, on under laid course of mixtures of crushed rock granules of
thickness 10 cm
Paving of ditches with broken stone of thickness 20 cm, joints filled with
2
41 112 m crushed rock, on under laid course of mixtures of crushed rock granules of
thickness 15 cm
Paving of ditches with broken stone of thickness 20 cm, joints filled with
2
41 113 m crushed rock, on under laid course of mixtures of crushed rock granules of
thickness 20 cm
Paving of ditches with broken stone of thickness 20 cm, joints filled with
2
41 121 m cement mortar, on under laid course of mixtures of crushed rock granules
of thickness 10 cm
Paving of ditches with broken stone of thickness 20 cm, joints filled with
2
41 122 m cement mortar, on under laid course of mixtures of crushed rock granules
of thickness 15 cm
Paving of ditches with broken stone of thickness 20 cm, joints filled with
41 123 m2 cement mortar, on under laid course of mixtures of crushed rock granules
of thickness 20 cm
Strengthening of ditches according to “Colcrete “ procedure in course of
41 131 m2
thickness 10 cm
Strengthening of ditches according to “Colcrete “ procedure in course of
41 132 m2
thickness 15 cm
Strengthening of ditches according to “Colcrete “ procedure in course of
41 133 m2
thickness 20 cm
Strengthening of ditches according to “Colcrete “ procedure in course of
41 134 m2
thickness 25 cm
Strengthening of ditches according to “Colcrete “ procedure in course of
41 135 m2
thickness 30 cm
Strengthening of ditches according to “Colcrete “ procedure in course of
41 136 m2
thickness 40 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 141 m filled with crushed rock, on under laid course of mixtures of crushed rock
granules of thickness 10 cm

Draft of Version 1 – March 2008 Page 57


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 142 m filled with crushed rock, on under laid course of mixtures of crushed rock
granules of thickness 15 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 143 m filled with crushed rock, on under laid course of mixtures of crushed rock
granules of thickness 20 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 146 m filled with cement mortar, on under laid course of mixtures of crushed rock
granules of thickness 10 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 147 m filled with cement mortar, on under laid course of mixtures of crushed rock
granules of thickness 15 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 148 m filled with cement mortar, on under laid course of mixtures of crushed rock
granules of thickness 20 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 151 m filled with cement mortar, on under laid course of cement concrete of
thickness 10 cm
Paving of ditches with slabs of cement concrete of thickness 10 cm, joints
2
41 152 m filled with cement mortar, on under laid course of cement concrete of
thickness 15 cm
Paving of ditches with filled of cement concrete, joints filled with crushed
2
41 161 m rock, on under laid course of mixtures of crushed rock granules of
thickness 10 cm
Paving of ditches with filled of cement concrete, joints filled with crushed
2
41 162 m rock, on under laid course of mixtures of crushed rock granules of
thickness 15 cm
Paving of ditches with filled of cement concrete, joints filled with crushed
2
41 163 m rock, on under laid course of mixtures of crushed rock granules of
thickness 20 cm
Paving of ditches with tiles of cement concrete, joints filled with cement
2
41 166 m mortar, on under laid course of mixtures of crushed rock granules of
thickness 10 cm
Paving of ditches with tiles of cement concrete, joints filled with cement
2
41 167 m mortar, on under laid course of mixtures of crushed rock granules of
thickness 15 cm
Paving of ditches with tiles of cement concrete, joints filled with cement
2
41 168 m mortar, on under laid course of mixtures of crushed rock granules of
thickness 20 cm

Draft of Version 1 – March 2008 Page 58


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Paving of ditches with tiles of cement concrete, joints filled with cement
41 171 m2
mortar, on under laid course of cement concrete of thickness 10 cm
Paving of ditches with tiles of cement concrete, joints filled with cement
41 172 m2
mortar, on under laid course of cement concrete of thickness 15 cm
Strengthening of ditches with segments of cement concrete, of width
2
41 181 m 80 cm, diameter 120 cm on under laid course of mixture of crushed rock
granules of thickness 10 cm
Strengthening of ditches with segments of cement concrete, of width
2
41 182 m 80 cm, diameter 120 cm on under laid course of mixture of crushed rock
granules of thickness 15 cm
Strengthening of ditches with segments of cement concrete, of width
41 183 m2 80 cm, diameter 120 cm on under laid course of mixture of crushed rock
granules of thickness 20 cm
Strengthening of ditches with segments of cement concrete, of width
41 186 m 100 cm, diameter 150 cm on under laid course of mixture of crushed rock
granules of thickness 10 cm
Strengthening of ditches with segments of cement concrete, of width
41 187 m 100 cm, diameter 150 cm on under laid course of mixture of crushed rock
granules of thickness 15 cm
Strengthening of ditches with segments of cement concrete, of width
41 188 m 100 cm, diameter 150 cm on under laid course of mixture of crushed rock
granules of thickness 20 cm
Strengthening of ditches with kerbs of cement concrete, 110/40 cm on
41 191 m
under laid course of mixture of crushed rock granules of thickness 10 cm
Strengthening of ditches with kerbs of cement concrete, 110/40 cm on
41 192 m
under laid course of mixture of crushed rock granules of thickness 10 cm
Strengthening of ditches with kerbs of cement concrete, 110/40 cm on
41 193 m
under laid course of mixture of crushed rock granules of thickness 10 cm
Execution of gutters of cement concrete MB 30, of thickness 10 cm on
41 211 m under laid course of mixtures of crushed rock of thickness 15 cm, near the
already built kerb of width 50 cm
Execution of gutters of cement concrete MB 30, of thickness 10 cm on
41 212 m under laid course of mixtures of crushed rock of thickness 15 cm, near the
already built kerb of width 75 cm
Execution of gutters of cement concrete MB 30, of thickness 10 cm on
41 216 m under laid course of mixture of crushed rock granules of thickness 15 cm
and with kerb of width 50 cm

Draft of Version 1 – March 2008 Page 59


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of gutters of cement concrete MB 30, of thickness 10 cm on
41 217 m under laid course of mixture of crushed rock granules of thickness 15 cm
and with kerb of width 75 cm
Execution of gutters of bituminous concrete thickness 5 cm on under laid
41 221 m course of mixture of crushed rock granules of thickness 20 cm, near the
already built kerb of cement concrete, width 50 cm
Execution of gutters of bituminous concrete thickness 5 cm on under laid
41 222 m course of mixture of crushed rock granules of thickness 20 cm, near the
already built kerb of cement concrete, width 75 cm
Execution of gutters of bituminous concrete thickness 5 cm on under laid
41 226 m course of mixture of crushed rock granules of thickness 20 cm, to serve as
a base for kerb of bituminous, width 75 cm
Execution of gutters of bituminous concrete thickness 5 cm on under laid
41 227 m course of mixture of crushed rock granules of thickness 20 cm, to serve as
a base for kerb of bituminous, width 100 cm
Execution of gutters with sett paving of broken stone of thickness 15 cm,
41 231 m joints are filled with cement mortar, on the course of the mixture of crushed
rock granules of thickness 10 cm, width 50 cm
Execution of gutters with sett paving of broken stone of thickness 15 cm,
41 232 m joints are filled with cement mortar, on the course of the mixture of crushed
rock granules of thickness 10 cm, width 75 cm
Execution of gutters with sett paving of broken stone of thickness 10 cm,
41 236 m joints are filed with cement mortar, on under laid course of cement
concrete of thickness 15 cm, width 50 cm
Execution of gutters with sett paving of broken stone of thickness 10 cm,
41 237 m joints are filed with cement mortar, on under laid course of cement
concrete of thickness 15 cm, width 75 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 311 m
of thickness 4 cm, width 50 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 312 m
of thickness 4 cm, width 60 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 313 m
of thickness 4 cm, width 70 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 314 m
of thickness 4 cm, width 80 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 321 m
of thickness 6 cm, width 50 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 322 m
of thickness 6 cm, width 60 cm

Draft of Version 1 – March 2008 Page 60


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Protection of curved trough bottoms with a course of bituminous concrete
41 323 m
of thickness 6 cm, width 70 cm
Protection of curved trough bottoms with a course of bituminous concrete
41 324 m
of thickness 6 cm, width 80 cm
Protection of curved trough bottoms with small stone tiles (sett paving) on
41 331 m
under laid course of cement concrete of thickness 10 cm, width 50 cm
Protection of curved trough bottoms with small stone tiles (sett paving) on
41 332 m
under laid course of cement concrete of thickness 10 cm, width 60 cm
Protection of curved trough bottoms with small stone tiles (sett paving) on
41 333 m
under laid course of cement concrete of thickness 10 cm, width 70 cm
Protection of curved trough bottoms with small stone tiles (sett paving) on
41 334 m
under laid course of cement concrete of thickness 10 cm, width 80 cm

3 Protection of ditch slope foot with broken stone of size larger than 0.1 m3 /
41 411 m
Piece
41 421 m3 Protection of ditch slope foot with steel wire baskets
3
41 431 m Protection of ditch slope foot with baskets of plastic nets

4.2 Deep Drainage Systems – Drainages

Unit
Code Description of work
measure
Execution of longitudinal and transverse shallow drainage of depth up to
42 111 m 1.0 m on the excavation formation level, with flexible plastic pipes of
diameter Ø 5 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 112 m 1.0 m on the excavation formation level, with flexible plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 113 m 1.0 m on the excavation formation level, with flexible plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 114 m 1.0 m on the excavation formation level, with flexible plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 121 m
1.0 m on clayey charge with flexible plastic pipes of diameter Ø 5 cm

Draft of Version 1 – March 2008 Page 61


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse shallow drainage of depth up to
42 122 m
1.0 m on clayey charge with flexible plastic pipes of diameter Ø 8 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 123 m
1.0 m on clayey charge with flexible plastic pipes of diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 124 m
1.0 m on clayey charge with flexible plastic pipes of diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 131 m 1.0 m on under laid course of cement concrete, with flexible plastic pipes
of diameter Ø 5 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 132 m 1.0 m on under laid course of cement concrete, with flexible plastic pipes
of diameter Ø 8 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 133 m 1.0 m on under laid course of cement concrete, with flexible plastic pipes
of diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 134 m 1.0 m on under laid course of cement concrete, with flexible plastic pipes
of diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 141 m 1.0 m on the excavation formation level with hard plastic pipes of diameter
Ø 8 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 142 m 1.0 m on the excavation formation level with hard plastic pipes of diameter
Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 143 m 1.0 m on the excavation formation level with hard plastic pipes of diameter
Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 144 m 1.0 m on the excavation formation level with hard plastic pipes of diameter
Ø 20 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 145 m 1.0 m on the excavation formation level with hard plastic pipes of diameter
Ø 25 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 146 m 1.0 m on the excavation formation level with hard plastic pipes of diameter
Ø 30 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 151 m 1.0 m on under laid course of cement concrete with hard plastic pipes of
diameter Ø 8 cm

Draft of Version 1 – March 2008 Page 62


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse shallow drainage of depth up to
42 152 m 1.0 m on under laid course of cement concrete with hard plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 153 m 1.0 m on under laid course of cement concrete with hard plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 154 m 1.0 m on under laid course of cement concrete with hard plastic pipes of
diameter Ø 20 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 155 m 1.0 m on under laid course of cement concrete with hard plastic pipes of
diameter Ø 25 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 156 m 1.0 m on under laid course of cement concrete with hard plastic pipes of
diameter Ø 30 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 161 m
1.0 m on clayey charge with hard plastic pipes of diameter Ø 8 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 162 m
1.0 m on clayey charge with hard plastic pipes of diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 163 m
1.0 m on clayey charge with hard plastic pipes of diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 164 m
1.0 m on clayey charge with hard plastic pipes of diameter Ø 20 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 165 m
1.0 m on clayey charge with hard plastic pipes of diameter Ø 25 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 166 m
1.0 m on clayey charge with hard plastic pipes of diameter Ø 30 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 171 m 1.0 m on the excavation formation level with perforated pipes of cement
concrete of diameter Ø 8 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 172 m 1.0 m on the excavation formation level with perforated pipes of cement
concrete of diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 173 m 1.0 m on the excavation formation level with perforated pipes of cement
concrete of diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 174 m 1.0 m on the excavation formation level with perforated pipes of cement
concrete of diameter Ø 20 cm

Draft of Version 1 – March 2008 Page 63


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse shallow drainage of depth up to
42 175 m 1.0 m on the excavation formation level with perforated pipes of cement
concrete of diameter Ø 25 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 176 m 1.0 m on the excavation formation level with perforated pipes of cement
concrete of diameter Ø 30 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 181 m 1.0 m, on clayey charge with perforated pipes of cement concrete of
diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 182 m 1.0 m, on clayey charge with perforated pipes of cement concrete of
diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 183 m 1.0 m, on clayey charge with perforated pipes of cement concrete of
diameter Ø 20 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 184 m 1.0 m, on clayey charge with perforated pipes of cement concrete of
diameter Ø 30 cm
Execution of longitudinal and transverse shallow drainage of depth up to
42 183 m 1.0 m, on clayey charge with perforated pipes of cement concrete of
diameter Ø 40 cm
Execution of longitudinal and transverse shallow drainage of depth above
42 191 m 1.0 m, on under laid course of cement concrete, with perforated pipes of
cement concrete of diameter Ø 10 cm
Execution of longitudinal and transverse shallow drainage of depth above
42 192 m 1.0 m, on under laid course of cement concrete, with perforated pipes of
cement concrete of diameter Ø 15 cm
Execution of longitudinal and transverse shallow drainage of depth above
42 193 m 1.0 m, on under laid course of cement concrete, with perforated pipes of
cement concrete of diameter Ø 20 cm
Execution of longitudinal and transverse shallow drainage of depth above
42 194 m 1.0 m, on under laid course of cement concrete, with perforated pipes of
cement concrete of diameter Ø 25 cm
Execution of longitudinal and transverse shallow drainage of depth above
42 195 m 1.0 m, on under laid course of cement concrete, with perforated pipes of
cement concrete of diameter Ø 30 cm
Execution of longitudinal and transverse shallow drainage of depth above
42 196 m 1.0 m, on under laid course of cement concrete, with perforated pipes of
cement concrete of diameter Ø 40 cm

Draft of Version 1 – March 2008 Page 64


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse shallow drainage of depth up to
42 211 m
1.0 m of stone granules mixture on the formation level of the excavation
Execution of longitudinal and transverse shallow drainage of depth up to
42 212 m
1.0 m of stone granules mixture on clayey charge
Execution of longitudinal and transverse shallow drainage of depth up to
42 213 m
1.0 m of stone granules mixture on under laid layer of cement concrete
Execution of longitudinal and transverse shallow drainage of depth up to
42 221 m 1.0 m of stone granules mixture, wrapped with fabric on formation level of
excavation
Execution of longitudinal and transverse shallow drainage of depth up to
42 222 m
1.0 m of stone granules mixture, wrapped with fabric on the clayey charge
Execution of longitudinal and transverse shallow drainage of depth up to
42 223 m 1.0 m of stone granules mixture, wrapped with fabric on under laid course
of cement concrete
Execution of longitudinal and transverse shallow drainage to depth up to
42 231 m 1.0 m from the mixture of single grained cement concrete wrapped with
fabric on the formation level of the excavation
Execution of longitudinal and transverse shallow drainage to depth up to
42 232 m 1.0 m from the mixture of single grained cement concrete wrapped with
fabric on the clayey charge
Execution of longitudinal and transverse shallow drainage to depth up to
42 233 m 1.0 m from the mixture of single grained cement concrete wrapped with
fabric on the under laid course of cement concrete
Execution of longitudinal and transverse shallow drainage of depth up to
42 241 m 1.0 m from the mixture of single grained cement concrete on formation
level of excavation
Execution of longitudinal and transverse shallow drainage of depth up to
42 242 m 1.0 m from the mixture of single grained cement concrete on the clayey
charge
Execution of longitudinal and transverse shallow drainage of depth up to
42 243 m 1.0 m from the mixture of single grained cement concrete on under laid
course of cement concrete

Draft of Version 1 – March 2008 Page 65


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

4.2.1 Flexible Plastic Pipes

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 311 m 2.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 6 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 312 m 2.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 313 m 2.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 314 m 2.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 321 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 6 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 322 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 323 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 324 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 331 m 2.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 332 m 2.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 6 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 333 m 2.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 334 m 2.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 15 cm

Draft of Version 1 – March 2008 Page 66


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

4.2.2 Hard Plastic Pipes

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 341 m 2.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 342 m 2.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 343 m 2.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 344 m 2.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 345 m 2.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 346 m 2.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–
42 361 m 2.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0
42 362 m m, on under laid course of cement concrete hard plastic pipes of diameter
Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0
42 363 m m, on under laid course of cement concrete hard plastic pipes of diameter
Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0
42 364 m m, on under laid course of cement concrete hard plastic pipes of diameter
Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0
42 365 m m, on under laid course of cement concrete hard plastic pipes of diameter
Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0
42 366 m m, on under laid course of cement concrete hard plastic pipes of diameter
Ø 30 cm

Draft of Version 1 – March 2008 Page 67


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

4.2.3 Perforated Pipes

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 371 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 372 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 373 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 374 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 375 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 376 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 40 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 381 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 382 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 383 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 384 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 385 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 386 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 40 cm

Draft of Version 1 – March 2008 Page 68


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 391 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 392 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 393 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 394 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 395 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 396 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 40 cm
Execution of longitudinal and transverse shallow drainage of depth to 1.0–
42 411 m
2.0 m of stone granules mixture on the formation level of the excavation
Execution of longitudinal and transverse shallow drainage of depth to 1.0–
42 412 m
2.0 m of stone granules mixture on clayey charge
Execution of longitudinal and transverse shallow drainage of depth to 1.0–
42 413 m
2.0 m of stone granules mixture on under laid layer of cement concrete
Execution of longitudinal and transverse shallow drainage of depth to 1.0–
42 421 m 2.0 m of stone granules mixture, wrapped with fabric on formation level of
excavation
Execution of longitudinal and transverse shallow drainage of depth to 1.0–
42 422 m
2.0 m of stone granules mixture, wrapped with fabric on the clayey charge
Execution of longitudinal and transverse shallow drainage of depth to 1.0–
42 423 m 2.0 m of stone granules mixture, wrapped with fabric on under laid course
of cement concrete
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 431 m of single grained mixture of cement concrete wrapped with fabric on the
formation level of the excavation
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 432 m of single grained mixture of cement concrete wrapped with fabric on the
clayey charge

Draft of Version 1 – March 2008 Page 69


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 433 m of single grained mixture of cement concrete wrapped with fabric on the
under laid course of cement concrete
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 441 m of single grained mixture of cement concrete on the formation level of the
excavation
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 442 m
of single grained mixture of cement concrete on the clayey charge
Execution of longitudinal and transverse deep drainage of depth 1.0–2.0 m
42 443 m of single grained mixture of cement concrete on the under laid course of
cement concrete
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 511 m 4.0 m, on the formation level of the excavation plastic pipes of diameter
Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 512 m 4.0 m, on the formation level of the excavation plastic pipes of diameter
Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 513 m 4.0 m, on the formation level of the excavation plastic pipes of diameter
Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 514 m 4.0 m, on the formation level of the excavation plastic pipes of diameter
Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 521 m
4.0 m, clayey charge with plastic pipes of diameter Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 522 m
4.0 m, clayey charge with plastic pipes of diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 523 m
4.0 m, clayey charge with plastic pipes of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 524 m
4.0 m, clayey charge with plastic pipes of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 531 m 4.0 m, on under laid course of cement with flexible plastic pipes of
diameter Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 532 m 4.0 m, on under laid course of cement with flexible plastic pipes of
diameter Ø 8 cm

Draft of Version 1 – March 2008 Page 70


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 533 m 4.0 m, on under laid course of cement with flexible plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 534 m 4.0 m, on under laid course of cement with flexible plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 541 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 542 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 543 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 544 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 545 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 546 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 551 m
on clayey charge with hard plastic pipes of diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 552 m
on clayey charge with hard plastic pipes of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 553 m
on clayey charge with hard plastic pipes of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 554 m
on clayey charge with hard plastic pipes of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 555 m
on clayey charge with hard plastic pipes of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 556 m
on clayey charge with hard plastic pipes of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 561 m 4.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 8 cm

Draft of Version 1 – March 2008 Page 71


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 562 m 4.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 563 m 4.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 564 m 4.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 565 m 4.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 566 m 4.0 m, on under laid course of cement concrete hard plastic pipes of
diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 571 m 4.0 on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 572 m 4.0 on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 573 m 4.0 on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 574 m 4.0 on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–
42 575 m 4.0 on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 576 m on the formation level of the excavation with perforated pipes of cement
concrete of diameter Ø 40 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 581 m on clayey charge with perforated pipes of cement concrete of diameter Ø
10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 582 m on clayey charge with perforated pipes of cement concrete of diameter Ø
15 cm

Draft of Version 1 – March 2008 Page 72


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 583 m on clayey charge with perforated pipes of cement concrete of diameter Ø
20 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 584 m on clayey charge with perforated pipes of cement concrete of diameter Ø
25 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 585 m on clayey charge with perforated pipes of cement concrete of diameter Ø
30 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 586 m on clayey charge with perforated pipes of cement concrete of diameter
Ø 40 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 591 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 592 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 593 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 594 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 595 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 596 m on under laid course of cement concrete with perforated pipes of cement
concrete of diameter Ø 40 cm
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 611 m
of stone granules mixture on the formation level of the excavation
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 612 m
of stone granules mixture on clayey charge
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 613 m
of stone granules mixture on under laid layer of cement concrete
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 621 m of stone granules mixture, wrapped with fabric on formation level of
excavation

Draft of Version 1 – March 2008 Page 73


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 622 m
of stone granules mixture, wrapped with fabric on the clayey charge
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 623 m of stone granules mixture, wrapped with fabric on under laid course of
cement concrete
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 631 m of single grained mixture of cement concrete wrapped with fabric on the
formation level of the excavation
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 632 m of single grained mixture of cement concrete wrapped with fabric on the
clayey charge
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 633 m of single grained mixture of cement concrete wrapped with fabric on the
under laid course of cement concrete
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 641 m of single grained mixture of cement concrete on the formation level of the
excavation
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 642 m
of single grained mixture of cement concrete on the clayey charge
Execution of longitudinal and transverse deep drainage of depth 2.0–4.0 m
42 643 m of single grained mixture of cement concrete on the under laid course of
cement concrete
Execution of longitudinal and transverse deep drainage of depth above
42 711 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth above
42 712 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth above
42 713 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 714 m 4.0 m, on the formation level of the excavation with flexible plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 721 m
4.0 m, on clayey charge with flexible plastic pipes of diameter Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth above
42 722 m
4.0 m, on clayey charge with flexible plastic pipes of diameter Ø 8 cm

Draft of Version 1 – March 2008 Page 74


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth above
42 723 m
4.0 m, on clayey charge with flexible plastic pipes of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 724 m
4.0 m, on clayey charge with flexible plastic pipes of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 731 m 4.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 5 cm
Execution of longitudinal and transverse deep drainage of depth above
42 732 m 4.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth above
42 733 m 4.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 734 m 4.0 m, on under laid course of cement concrete with flexible plastic pipes
of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 741 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth above
42 742 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 743 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 744 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth above
42 745 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth above
42 746 m 4.0 m, on the formation level of the excavation with hard plastic pipes of
diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth above
42 751 m
4.0 m on clayey charge with plastic pipes of diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth above
42 752 m
4.0 m on clayey charge with plastic pipes of diameter Ø 10 cm

Draft of Version 1 – March 2008 Page 75


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth above
42 753 m
4.0 m on clayey charge with plastic pipes of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 754 m
4.0 m on clayey charge with plastic pipes of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth above
42 755 m
4.0 m on clayey charge with plastic pipes of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth above
42 756 m
4.0 m on clayey charge with plastic pipes of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth above
42 761 m 4.0 m, on under laid course of cement concrete with hard plastic pipes of
diameter Ø 8 cm
Execution of longitudinal and transverse deep drainage of depth above
42 762 m 4.0 m, on under laid course of cement concrete with hard plastic pipes of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 763 m 4.0 m, on under laid course of cement concrete with hard plastic pipes of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 764 m 4.0 m, on under laid course of cement concrete with hard plastic pipes of
diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth above
42 765 m 4.0 m, on under laid course of cement concrete with hard plastic pipes of
diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth above
42 766 m 4.0 m, on under laid course of cement concrete with hard plastic pipes of
diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth above
42 771 m 4.0 m on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 772 m 4.0 m on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 773 m 4.0 m on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth above
42 774 m 4.0 m on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 25 cm

Draft of Version 1 – March 2008 Page 76


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth above
42 775 m 4.0 m on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth above
42 776 m 4.0 m on the formation level of the excavation with perforated pipes of
cement concrete of diameter Ø 35 cm
Execution of longitudinal and transverse deep drainage of depth above
42 781 m 4.0 m on clayey charge with perforated pipes of cement concrete of
diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 782 m 4.0 m on clayey charge with perforated pipes of cement concrete of
diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 783 m 4.0 m on clayey charge with perforated pipes of cement concrete of
diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth above
42 784 m 4.0 m on clayey charge with perforated pipes of cement concrete of
diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth above
42 785 m 4.0 m on clayey charge with perforated pipes of cement concrete of
diameter Ø 30 cm
Execution of longitudinal and transverse deep drainage of depth above
42 786 m 4.0 m on clayey charge with perforated pipes of cement concrete of
diameter Ø 40 cm
Execution of longitudinal and transverse deep drainage of depth above
42 791 m 4.0 m on under laid course of cement concrete with perforated pipes of
cement concrete of diameter Ø 10 cm
Execution of longitudinal and transverse deep drainage of depth above
42 792 m 4.0 m on under laid course of cement concrete with perforated pipes of
cement concrete of diameter Ø 15 cm
Execution of longitudinal and transverse deep drainage of depth above
42 793 m 4.0 m on under laid course of cement concrete with perforated pipes of
cement concrete of diameter Ø 20 cm
Execution of longitudinal and transverse deep drainage of depth above
42 794 m 4.0 m on under laid course of cement concrete with perforated pipes of
cement concrete of diameter Ø 25 cm
Execution of longitudinal and transverse deep drainage of depth above
42 795 m 4.0 m on under laid course of cement concrete with perforated pipes of
cement concrete of diameter Ø 30 cm

Draft of Version 1 – March 2008 Page 77


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of longitudinal and transverse deep drainage of depth above
42 796 m 4.0 m on under laid course of cement concrete with perforated pipes of
cement concrete of diameter Ø 40 cm
Execution of longitudinal and transverse deep drainage of depth above
42 811 m
4.0 m of stone granules mixture on the formation level of the excavation
Execution of longitudinal and transverse deep drainage of depth above
42 812 m
4.0 m of stone granules mixture on clayey charge
Execution of longitudinal and transverse deep drainage of depth above
42 813 m
4.0 m of stone granules mixture on under laid layer of cement concrete
Execution of longitudinal and transverse deep drainage of depth above
42 821 m 4.0 m of stone granules mixture, wrapped with fabric on formation level of
excavation
Execution of longitudinal and transverse deep drainage of depth above
42 822 m
4.0 m of stone granules mixture, wrapped with fabric on the clayey charge
Execution of longitudinal and transverse deep drainage of depth above
42 823 m 4.0 m of stone granules mixture, wrapped with fabric on under laid course
of cement concrete
Execution of longitudinal and transverse deep drainage of depth above
42 831 m 4.0 m of single grain mixture of cement concrete on the formation level of
the excavation
Execution of longitudinal and transverse deep drainage of depth above
42 832 m
4.0 m of single grain mixture of cement concrete on the clayey charge
Execution of longitudinal and transverse deep drainage of depth above
42 833 m 4.0 m of single grain mixture of cement concrete on the under laid course
of cement concrete
Execution of longitudinal and transverse deep drainage of depth 4.0 m of
42 841 m single grain mixture of cement concrete on the formation level of the
excavation
Execution of longitudinal and transverse deep drainage of depth 4.0 m of
42 842 m
single grain mixture of cement concrete on the clayey charge
Execution of longitudinal and transverse deep drainage of depth 4.0 m of
42 843 m single grain mixture of cement concrete on the under laid course of
cement concrete
42 911 Piece Execution of outlet with shallow or deep drainage of diameter Ø 8 cm
42 912 Piece Execution of outlet with shallow or deep drainage of diameter Ø 10 cm
42 913 Piece Execution of outlet with shallow or deep drainage of diameter Ø 15 cm
42 914 Piece Execution of outlet with shallow or deep drainage of diameter Ø 20 cm
42 915 Piece Execution of outlet with shallow or deep drainage of diameter Ø 25 cm

Draft of Version 1 – March 2008 Page 78


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
42 916 Piece Execution of outlet with shallow or deep drainage of diameter Ø 32 cm
42 917 Piece Execution of outlet with shallow or deep drainage of diameter Ø 40 cm
Execution of vertical drainage, driven and filled with sand granules mixture
42 921 m
of diameter Ø 6 cm
Execution of vertical drainage, driven and filled with sand granules mixture
42 922 m
of diameter Ø 8 cm
Execution of vertical drainage, driven and filled with sand granules mixture
42 923 m
of diameter Ø 10 cm
Execution of vertical drainage, driven and filled with sand granules mixture
42 924 m
of diameter Ø 12 cm
Execution of vertical drainage, driven and filled with sand granules mixture
42 925 m
of diameter Ø 15 cm
Execution of vertical drainage (pile) driven, and filled with gravel and
42 931 m
crushed stone granules mixture of diameter Ø 10 cm
Execution of vertical drainage (pile) driven, and filled with gravel and
42 932 m
crushed stone granules mixture of diameter Ø 15 cm
Execution of vertical drainage (pile) driven, and filled with gravel and
42 933 m
crushed stone granules mixture of diameter Ø 20 cm
Execution of vertical drainage (pile) driven, and filled with gravel and
42 934 m
crushed stone granules mixture of diameter Ø 25 cm
Execution of vertical drainage (pile) driven, and filled with gravel and
42 935 m
crushed stone granules mixture of diameter Ø 30 cm
Execution of vertical drainage (pile) inserted, and filled with gravel and
42 941 m
crushed stone granules mixture of diameter Ø 10 cm
Execution of vertical drainage (pile) inserted, and filled with gravel and
42 942 m
crushed stone granules mixture of diameter Ø 15 cm
Execution of vertical drainage (pile) inserted, and filled with gravel and
42 943 m
crushed stone granules mixture of diameter Ø 20 cm
Execution of vertical drainage (pile), inserted, and filled with gravel and
42 944 m
crushed stone granules mixture of diameter Ø 30 cm
Execution of vertical drainage (pile), inserted, and filled with gravel and
42 945 m
crushed stone granules mixture of diameter Ø 40 cm
Execution of vertical drainage (pile), inserted, and filled with gravel and
42 946 m
crushed stone granules mixture of diameter Ø 50 cm
Execution of vertical drainage (pile), inserted, and filled with gravel and
42 947 m
crushed stone granules mixture of diameter Ø 60 cm
Execution of vertical drainage (pile), inserted, and filled with gravel and
42 948 m
crushed stone granules mixture of diameter Ø 80 cm

Draft of Version 1 – March 2008 Page 79


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
42 921 m Execution of longitudinal drainage, inserted, with a fabric tape
Execution of longitudinal drainage, inserted, with nailed core, wrapped with
42 922 m
fabric
Execution of longitudinal drainage, inserted, with nailed hollow core,
42 923 m
wrapped with fabric

4.3 Deep Drainage Systems – Storm Sewerage System

Unit
Code Description of work
measure
Execution of sewerage of plastic pipes, placed on the formation level of the
43 111 m
excavation of diameter Ø 15 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 112 m
excavation of diameter Ø 20 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 113 m
excavation of diameter Ø 25 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 114 m
excavation of diameter Ø 30 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 115 m
excavation of diameter Ø 40 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 116 m
excavation of diameter Ø 50 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 117 m
excavation of diameter Ø 60 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 118 m
excavation of diameter Ø 80 cm
Execution of sewerage of plastic pipes, placed on the formation level of the
43 119 m
excavation of diameter Ø 100 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
42 121 m
stone granules mixture of diameter Ø 15 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 122 m
stone granules mixture of diameter Ø 20 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 123 m
stone granules mixture of diameter Ø 25 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 124 m
stone granules mixture of diameter Ø 30 cm

Draft of Version 1 – March 2008 Page 80


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of plastic pipes, placed on the under laid course of
43 125 m
stone granules mixture of diameter Ø 40 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 126 m
stone granules mixture of diameter Ø 50 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 127 m
stone granules mixture of diameter Ø 60 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 128 m
stone granules mixture of diameter Ø 80 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 129 m
stone granules mixture of diameter Ø 100 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 131 m
cement concrete of diameter Ø 15 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 132 m
cement concrete of diameter Ø 20 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 133 m
cement concrete of diameter Ø 25 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 134 m
cement concrete of diameter Ø 30 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 135 m
cement concrete of diameter Ø 40 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 136 m
cement concrete of diameter Ø 50 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 137 m
cement concrete of diameter Ø 60 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 138 m
cement concrete of diameter Ø 80 cm
Execution of sewerage of plastic pipes, placed on the under laid course of
43 139 m
cement concrete of diameter Ø 100 cm
Execution of sewerage of stone pipes, placed on the formation level of the
43 211 m
excavation of diameter Ø 10 cm
Execution of sewerage of stone pipes, placed on the formation level of the
43 212 m
excavation of diameter Ø 15 cm
Execution of sewerage of stone pipes, placed on the formation level of the
43 213 m
excavation of diameter Ø 20 cm
Execution of sewerage of stone pipes, placed on the formation level of the
43 214 m
excavation of diameter Ø 25 cm
Execution of sewerage of stone pipes, placed on the formation level of the
43 215 m
excavation of diameter Ø 30 cm

Draft of Version 1 – March 2008 Page 81


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of stone pipes, placed on the formation level of the
43 216 m
excavation of diameter Ø 35 cm
Execution of sewerage of stone pipes, placed on the formation level of the
43 217 m
excavation of diameter Ø 40 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 221 m
stone granules mixture of diameter Ø 10 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 222 m
stone granules mixture of diameter Ø 15 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 223 m
stone granules mixture of diameter Ø 20 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 224 m
stone granules mixture of diameter Ø 25 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 225 m
stone granules mixture of diameter Ø 30 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 226 m
stone granules mixture of diameter Ø 35 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 227 m
stone granules mixture of diameter Ø 40 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 231 m
cement concrete of diameter Ø 10 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 232 m
cement concrete of diameter Ø 15 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 233 m
cement concrete of diameter Ø 20 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 234 m
cement concrete of diameter Ø 25 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 235 m
cement concrete of diameter Ø 30 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 236 m
cement concrete of diameter Ø 35 cm
Execution of sewerage of stone pipes, placed on under laid course of
43 237 m
cement concrete of diameter Ø 40 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 311 m
level of the excavation of diameter Ø 15 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 312 m
level of the excavation of diameter Ø 20 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 313 m
level of the excavation of diameter Ø 25 cm

Draft of Version 1 – March 2008 Page 82


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of cement concrete pipes, placed on the formation
43 314 m
level of the excavation of diameter Ø 30 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 315 m
level of the excavation of diameter Ø 40 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 316 m
level of the excavation of diameter Ø 50 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 317 m
level of the excavation of diameter Ø 60 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 318 m
level of the excavation of diameter Ø 80 cm
Execution of sewerage of cement concrete pipes, placed on the formation
43 319 m
level of the excavation of diameter Ø 100 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 321 m
course of stone granules mixture of diameter Ø 15 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 322 m
course of stone granules mixture of diameter Ø 20 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 323 m
course of stone granules mixture of diameter Ø 25 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 324 m
course of stone granules mixture of diameter Ø 30 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 325 m
course of stone granules mixture of diameter Ø 40 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 326 m
course of stone granules mixture of diameter Ø 50 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 327 m
course of stone granules mixture of diameter Ø 60 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 328 m
course of stone granules mixture of diameter Ø 80 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 329 m
course of stone granules mixture of diameter Ø 100 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 331 m
course of cement concrete of diameter Ø 15 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 332 m
course of cement concrete of diameter Ø 20 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 333 m
course of cement concrete of diameter Ø 25 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 334 m
course of cement concrete of diameter Ø 30 cm

Draft of Version 1 – March 2008 Page 83


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of cement concrete pipes, placed on the under laid
43 335 m
course of cement concrete of diameter Ø 40 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 336 m
course of cement concrete of diameter Ø 50 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 337 m
course of cement concrete of diameter Ø 60 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 338 m
course of cement concrete of diameter Ø 80 cm
Execution of sewerage of cement concrete pipes, placed on the under laid
43 339 m
course of cement concrete of diameter Ø 100 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 411 m
under laid course of stone granules mixture of diameter Ø 120 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 412 m
under laid course of stone granules mixture of diameter Ø 140 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 413 m
under laid course of stone granules mixture of diameter Ø 150 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 414 m
under laid course of stone granules mixture of diameter Ø 160 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 415 m
under laid course of stone granules mixture of diameter Ø 180 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 416 m
under laid course of stone granules mixture of diameter Ø 200 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 421 m
under laid course of cement concrete of diameter Ø 120 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 422 m
under laid course of cement concrete of diameter Ø 140 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 423 m
under laid course of cement concrete of diameter Ø 150 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 424 m
under laid course of cement concrete of diameter Ø 160 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 425 m
under laid course of cement concrete of diameter Ø 180 cm
Execution of sewerage of reinforced cement concrete pipes, placed on
43 426 m
under laid course of cement concrete of diameter Ø 200 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 511 m
level of the excavation of diameter Ø 15 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 512 m
level of the excavation of diameter Ø 20 cm

Draft of Version 1 – March 2008 Page 84


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 513 m
level of the excavation of diameter Ø 25 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 514 m
level of the excavation of diameter Ø 30 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 515 m
level of the excavation of diameter Ø 40 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 516 m
level of the excavation of diameter Ø 50 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 517 m
level of the excavation of diameter Ø 60 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 518 m
level of the excavation of diameter Ø 70 cm
Execution of sewerage of asbestos–cement pipes, placed on the formation
43 519 m
level of the excavation of diameter Ø … cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 521 m
course of stone granules mixture of diameter Ø 15 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 522 m
course of stone granules mixture of diameter Ø 20 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 523 m
course of stone granules mixture of diameter Ø 25 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 524 m
course of stone granules mixture of diameter Ø 30 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 525 m
course of stone granules mixture of diameter Ø 40 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 526 m
course of stone granules mixture of diameter Ø 50 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 527 m
course of stone granules mixture of diameter Ø 60 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 528 m
course of stone granules mixture of diameter Ø 70 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 529 m
course of stone granules mixture of diameter Ø … cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 531 m
course of cement concrete of diameter Ø 15 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 532 m
course of cement concrete of diameter Ø 20 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 533 m
course of cement concrete of diameter Ø 25 cm

Draft of Version 1 – March 2008 Page 85


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 534 m
course of cement concrete of diameter Ø 30 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 535 m
course of cement concrete of diameter Ø 40 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 536 m
course of cement concrete of diameter Ø 50 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 537 m
course of cement concrete of diameter Ø 60 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 538 m
course of cement concrete of diameter Ø 70 cm
Execution of sewerage of asbestos–cement pipes, placed on under laid
43 539 m
course of cement concrete of diameter Ø … cm
Execution of sewerage of cast iron pipes, placed on the formation level of
43 611 m
the excavation of diameter Ø 50 mm
Execution of sewerage of cast iron pipes, placed on the formation level of
43 612 m
the excavation of diameter Ø 70 mm
Execution of sewerage of cast iron pipes, placed on the formation level of
43 613 m
the excavation of diameter Ø 100 mm
Execution of sewerage of cast iron pipes, placed on the formation level of
43 614 m
the excavation of diameter Ø 125 mm
Execution of sewerage of cast iron pipes, placed on the formation level of
43 615 m
the excavation of diameter Ø 150 mm
Execution of sewerage of cast iron pipes, placed on the formation level of
43 616 m
the excavation of diameter Ø 200 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 621 m
stone granules mixture of diameter Ø 50 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 622 m
stone granules mixture of diameter Ø 70 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 623 m
stone granules mixture of diameter Ø 100 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 624 m
stone granules mixture of diameter Ø 125 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 625 m
stone granules mixture of diameter Ø 150 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 626 m
stone granules mixture of diameter Ø 200 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 631 m
cement concrete of diameter Ø 50 mm

Draft of Version 1 – March 2008 Page 86


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of sewerage of cast iron pipes, placed on under laid course of
43 632 m
cement concrete of diameter Ø 70 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 633 m
cement concrete of diameter Ø 100 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 634 m
cement concrete of diameter Ø 125 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 635 m
cement concrete of diameter Ø 150 mm
Execution of sewerage of cast iron pipes, placed on under laid course of
43 636 m
cement concrete of diameter Ø 200 mm
Sewage system construction – centrifuged polyester pipes, nominal
43 711 m
stiffness 10000 N/m2, on aggregate underlay Ø 20 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 712 m
stiffness 10000 N/m2, on aggregate underlay Ø 25 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 713 m
stiffness 10000 N/m2, on aggregate underlay Ø 30 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 714 m
stiffness 10000 N/m2, on aggregate underlay Ø 40 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 715 m
stiffness 10000 N/m2, on aggregate underlay Ø 50 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 716 m
stiffness 10000 N/m2, on aggregate underlay Ø 60 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 717 m
stiffness 10000 N/m2, on aggregate underlay Ø 80 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 718 m
stiffness 10000 N/m2, on aggregate underlay Ø 100 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 719 m
stiffness 10000 N/m2, on aggregate underlay Ø 120 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 721 m
stiffness 5000 N/m2, on excavation formation level Ø 20 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 722 m
stiffness 5000 N/m2, on excavation formation level Ø 25 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 723 m
stiffness 5000 N/m2, on excavation formation level Ø 30 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 724 m
stiffness 5000 N/m2, on excavation formation level Ø 40 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 725 m
stiffness 5000 N/m2, on excavation formation level Ø 50 cm

Draft of Version 1 – March 2008 Page 87


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Sewage system construction – centrifuged polyester pipes, nominal
43 726 m
stiffness 5000 N/m2, on excavation formation level Ø 60 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 727 m
stiffness 5000 N/m2, on excavation formation level Ø 80 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 728 m
stiffness 5000 N/m2, on excavation formation level Ø 100 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 729 m
stiffness 5000 N/m2, on excavation formation level Ø 120 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 731 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 20 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 732 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 25 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 733 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 30 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 734 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 40 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 735 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 50 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 736 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 60 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 737 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 80 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 738 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 100 cm
Sewage system construction – centrifuged polyester pipes, nominal
43 739 m
stiffness 2500 N/m2, on cement-concrete underlay Ø 120 cm

Draft of Version 1 – March 2008 Page 88


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

4.4 Manholes

Unit
Code Description of work
measure
Execution of shaft of cement concrete, circular section of diameter 30 cm
44 111 Piece
and of depth up to 1 m
Execution of shaft of cement concrete, circular section of diameter 30 cm
44 112 Piece
and of depth 1 to 2 m
Execution of shaft of cement concrete, circular section of diameter 30 cm
44 113 Piece
and of depth above 2 m
Execution of shaft of cement concrete, circular section of diameter 40 cm
44 121 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 40 cm
44 122 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 40 cm
44 123 Piece
and a depth 1.5–2.0 m
Execution of shaft of cement concrete, circular section of diameter 40 cm
44 124 Piece
and a depth 2.0–2.5 m
Execution of shaft of cement concrete, circular section of diameter 40 cm
44 125 Piece
and a depth above 2.5 m
Execution of shaft of cement concrete, circular section of diameter 50 cm
44 131 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 50 cm
44 132 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 50 cm
44 133 Piece
and a depth 1.5–2.0 m
Execution of shaft of cement concrete, circular section of diameter 50 cm
44 134 Piece
and a depth 2.0 to 2.5 m
Execution of shaft of cement concrete, circular section of diameter 50 cm
44 135 Piece
and a depth 2.5 m
Execution of shaft of cement concrete, circular section of diameter 60 cm
44 141 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 60 cm
44 142 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 60 cm
44 143 Piece
and a depth 1.5–2.0 m
Execution of shaft of cement concrete, circular section of diameter 60 cm
44 144 Piece
and a depth 2.0 to 2.5 m

Draft of Version 1 – March 2008 Page 89


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of shaft of cement concrete, circular section of diameter 60 cm
44 145 Piece
and a depth above 2.5 m
Execution of shaft of cement concrete, circular section of diameter 70 cm
44 151 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 70 cm
44 152 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 70 cm
44 153 Piece
and a depth 1.5–2.0 m
Execution of shaft of cement concrete, circular section of diameter 70 cm
44 154 Piece
and a depth 2.0 to 2.5 m
Execution of shaft of cement concrete, circular section of diameter 70 cm
44 155 Piece
and a depth above 2.5 m
Execution of shaft of cement concrete, circular section of diameter 80 cm
44 161 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 80 cm
44 162 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 80 cm
44 163 Piece
and a depth 1.5–2.0 m
Execution of shaft of cement concrete, circular section of diameter 80 cm
44 164 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 80 cm
44 165 Piece
and a depth above 2.5 m
Execution of shaft of cement concrete, circular section of diameter 100 cm
44 171 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 100 cm
44 172 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 100 cm
44 173 Piece
and a depth 1.5–2.0 m
Execution of shaft of cement concrete, circular section of diameter 100 cm
44 174 Piece
and a depth 2.0–2.5 m
Execution of shaft of cement concrete, circular section of diameter 100 cm
44 175 Piece
and a depth above 2.5 m
Execution of shaft of cement concrete, circular section of diameter 120 cm
44 181 Piece
and a depth up to 1.0 m
Execution of shaft of cement concrete, circular section of diameter 120 cm
44 182 Piece
and a depth 1.0–1.5 m
Execution of shaft of cement concrete, circular section of diameter 120 cm
44 183 Piece
and a depth 1.5–2.0 m

Draft of Version 1 – March 2008 Page 90


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of shaft of cement concrete, circular section of diameter 120 cm
44 184 Piece
and a depth 2.0–2.5 m
Execution of shaft of cement concrete, circular section of diameter 120 cm
44 185 Piece
and a depth above 2.5 m
44 211 Piece Execution of grate of cast iron for 1.5 Mp of diameter Ø 450 mm
44 212 Piece Execution of grate of cast iron for 1.5 Mp of diameter Ø 500 mm
44 213 Piece Execution of grate of cast iron for 1.5 Mp of diameter Ø 600 mm
44 214 Piece Execution of grate of cast iron for 1.5 Mp of diameter Ø 700 mm
44 215 Piece Execution of grate of cast iron for 1.5 Mp of diameter Ø 800 mm
44 221 Piece Execution of grate of cast iron for 5 Mp of diameter Ø 450 mm
44 222 Piece Execution of grate of cast iron for 5 Mp of diameter Ø 500 mm
44 223 Piece Execution of grate of cast iron for 5 Mp of diameter Ø 600 mm
44 224 Piece Execution of grate of cast iron for 5 Mp of diameter Ø 700 mm
44 225 Piece Execution of grate of cast iron for 5 Mp of diameter Ø 800 mm
44 231 Piece Execution of grate of cast iron for 15 Mp of diameter Ø 500 mm
44 232 Piece Execution of grate of cast iron for 15 Mp of diameter Ø 600 mm
44 233 Piece Execution of grate of cast iron for 15 Mp of diameter Ø 700 mm
44 234 Piece Execution of grate of cast iron for 15 Mp of diameter Ø ….. mm
44 241 Piece Execution of grate of cast iron for 25 Mp of diameter Ø 500 mm
44 242 Piece Execution of grate of cast iron for 25 Mp of diameter Ø 600 mm
44 243 Piece Execution of grate of cast iron for 25 Mp of diameter Ø 700 mm
44 244 Piece Execution of grate of cast iron for 25 Mp of diameter Ø ….. mm
Execution of lid of reinforced cement concrete of diameter Ø 40 cm
44 311 Piece
(40/40 cm)
Execution of lid of reinforced cement concrete of diameter Ø 50 cm
44 312 Piece
(50/50 cm)
Execution of lid of reinforced cement concrete of diameter Ø 60 cm
44 313 Piece
(60/60 cm)
Execution of lid of reinforced cement concrete of diameter Ø 70 cm
44 314 Piece
(70/70 cm)
Execution of lid of reinforced cement concrete of diameter Ø 80 cm
44 315 Piece
(80/80 cm)
Execution of lid of reinforced cement concrete of diameter Ø 100 cm
44 316 Piece
(100/100 cm)
Execution of shaft of cement concrete of square section 50/50 cm and
44 411 Piece
depth up 1.0 m

Draft of Version 1 – March 2008 Page 91


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of shaft of cement concrete of square section 50/50 cm and
44 412 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 50/50 cm and
44 413 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 50/50 cm and
44 414 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 50/50 cm and
44 415 Piece
depth above 2.5 m
Execution of shaft of cement concrete of square section 60/60 cm and
44 421 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 60/60 cm and
44 422 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 60/60 cm and
44 423 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 60/60 cm and
44 424 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 60/60 cm and
44 425 Piece
depth above 2.5 m
Execution of shaft of cement concrete of square section 80/80 cm and
44 431 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 80/80 cm and
44 432 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 80/80 cm and
44 433 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 80/80 cm and
44 434 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 80/80 cm and
44 435 Piece
depth above 2.5 m
Execution of shaft of cement concrete of square section 100/100 cm and
44 441 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 100/100 cm and
44 442 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 100/100 cm and
44 443 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 100/100 cm and
44 444 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 100/100 cm and
44 445 Piece
depth above 2.5 m

Draft of Version 1 – March 2008 Page 92


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of shaft of cement concrete of square section 60/100 cm and
44 511 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 60/100 cm and
44 512 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 60/100 cm and
44 513 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 60/100 cm and
44 514 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 60/100 cm and
44 515 Piece
depth above 2.5 m
Execution of shaft of cement concrete of square section 60/120 cm and
44 521 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 60/120 cm and
44 522 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 60/120 cm and
44 523 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 60/120 cm and
44 524 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 60/120 cm and
44 525 Piece
depth above 2.5 m
Execution of shaft of cement concrete of square section 80/100 cm and
44 531 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 80/100 cm and
44 532 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 80/100 cm and
44 533 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 80/100 cm and
44 534 Piece
depth 2.0–2.5 m
Execution of shaft of cement concrete of square section 80/100 cm and
44 535 Piece
depth above 2.5 m
Execution of shaft of cement concrete of square section 80/120 cm and
44 541 Piece
depth up to 1.0 m
Execution of shaft of cement concrete of square section 80/120 cm and
44 542 Piece
depth 1.0–1.5 m
Execution of shaft of cement concrete of square section 80/120 cm and
44 543 Piece
depth 1.5–2.0 m
Execution of shaft of cement concrete of square section 80/120 cm and
44 544 Piece
depth 2.0–2.5 m

Draft of Version 1 – March 2008 Page 93


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of shaft of cement concrete of square section 80/120 cm and
44 545 Piece
depth above 2.5 m
44 611 Piece Execution of lid of cast iron for 1.5 Mp of diameter Ø 500 mm
44 612 Piece Execution of lid of cast iron for 1.5 Mp of diameter Ø 600 mm
44 613 Piece Execution of lid of cast iron for 1.5 Mp of diameter Ø 700 mm
44 614 Piece Execution of lid of cast iron for 1.5 Mp of diameter Ø 800 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 621 Piece
cement concrete, for 5 Mp of diameter Ø 500 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 622 Piece
cement concrete, for 5 Mp of diameter Ø 600 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 623 Piece
cement concrete, for 5 Mp of diameter Ø 700 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 624 Piece
cement concrete, for 5 Mp of diameter Ø 800 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 631 Piece
cement concrete, for 15 Mp of diameter Ø 500 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 632 Piece
cement concrete, for 15 Mp of diameter Ø 600 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 633 Piece
cement concrete, for 15 Mp of diameter Ø 700 mm
Execution of lid of a combination, consisting of cast iron and reinforced
44 634 Piece
cement concrete, for 15 Mp of diameter Ø 800 mm
44 641 Piece Execution of lid of cast iron for 25 Mp - type A, of diameter Ø 500 mm
44 642 Piece Execution of lid of cast iron for 25 Mp - type A, of diameter Ø 600 mm
44 643 Piece Execution of lid of cast iron for 25 Mp - type A, of diameter Ø 700 mm
44 644 Piece Execution of lid of cast iron for 25 Mp - type A, of diameter Ø 800 mm
44 651 Piece Execution of lid of cast iron for 25 Mp - type B, of diameter Ø 500 mm
44 652 Piece Execution of lid of cast iron for 25 Mp - type B, of diameter Ø 600 mm
44 653 Piece Execution of lid of cast iron for 25 Mp - type B, of diameter Ø 700 mm
44 654 Piece Execution of lid of cast iron for 25 Mp - type B, of diameter Ø 800 mm
44 661 Piece Execution of lid of cast iron for 25 Mp - type C, of diameter Ø 500 mm
44 662 Piece Execution of lid of cast iron for 25 Mp - type C, of diameter Ø 600 mm
44 663 Piece Execution of lid of cast iron for 25 Mp - type C, of diameter Ø 700 mm
44 664 Piece Execution of lid of cast iron for 25 Mp - type C, of diameter Ø 800 mm
44 761 Piece Execution of lid of cast iron for 25 Mp - type D, of diameter Ø 500 mm
44 762 Piece Execution of lid of cast iron for 25 Mp - type D, of diameter Ø 600 mm

Draft of Version 1 – March 2008 Page 94


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
44 763 Piece Execution of lid of cast iron for 25 Mp - type D, of diameter Ø 700 mm
44 764 Piece Execution of lid of cast iron for 25 Mp - type D, of diameter Ø 800 mm
Execution of lid of cast iron for 25 and 40 Mp - type E, of diameter
44 681 Piece
Ø 500 mm
Execution of lid of cast iron for 25 and 40 Mp - type E, of diameter
44 682 Piece
Ø 600 mm
Execution of lid of cast iron for 25 and 40 Mp - type E, of diameter
44 683 Piece
Ø 800 mm
44 711 Piece Execution of catcher of zincified steel sheet–metal, of diameter Ø 450 mm
44 712 Piece Execution of catcher of zincified steel sheet–metal, of diameter Ø 500 mm
44 713 Piece Execution of catcher of zincified steel sheet–metal, of diameter Ø 600 mm
44 714 Piece Execution of catcher of zincified steel sheet–metal, of diameter Ø 700 mm
44 715 Piece Execution of catcher of zincified steel sheet–metal, of diameter Ø 800 mm
Construction of shaft: slab deck – polyester laminate, Ø 40 cm; depth up to
44 811 Piece
1.0 m
Construction of shaft: slab deck – polyester laminate, Ø 40 cm; depth 1.0–
44 812 Piece
1.5 m
Construction of shaft: slab deck – polyester laminate, Ø 40 cm; depth 1.5–
44 813 Piece
2.0 m
Construction of shaft: slab deck – polyester laminate, Ø 40 cm; depth 2.0–
44 814 Piece
2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 40 cm; depth
44 815 Piece
above 2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 60 cm; depth up to
44 821 Piece
1.0 m
Construction of shaft: slab deck – polyester laminate, Ø 60 cm; depth 1.0–
44 822 Piece
1.5 m
Construction of shaft: slab deck – polyester laminate, Ø 60 cm; depth 1.5–
44 823 Piece
2.0 m
Construction of shaft: slab deck – polyester laminate, Ø 60 cm; depth 2.0–
44 824 Piece
2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 60 cm; depth
44 825 Piece
above 2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 80 cm; depth up to
44 831 Piece
1.0 m
Construction of shaft: slab deck – polyester laminate, Ø 80 cm; depth 1.0–
44 832 Piece
1.5 m

Draft of Version 1 – March 2008 Page 95


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of shaft: slab deck – polyester laminate, Ø 80 cm; depth 1.5–
44 833 Piece
2.0 m
Construction of shaft: slab deck – polyester laminate, Ø 80 cm; depth 2.0–
44 834 Piece
2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 80 cm; depth
44 835 Piece
above 2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 100 cm; depth up
44 841 Piece
to 1.0 m
Construction of shaft: slab deck – polyester laminate, Ø 100 cm; depth
44 842 Piece
1.0–1.5 m
Construction of shaft: slab deck – polyester laminate, Ø 100 cm; depth
44 843 Piece
1.5–2.0 m
Construction of shaft: slab deck – polyester laminate, Ø 100 cm; depth
44 844 Piece
2.0–2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 100 cm; depth
44 845 Piece
above 2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 110 cm; depth up
44 851 Piece
to 1.0 m
Construction of shaft: slab deck – polyester laminate, Ø 110 cm; depth
44 852 Piece
1.0–1.5 m
Construction of shaft: slab deck – polyester laminate, Ø 110 cm; depth
44 853 Piece
1.5–2.0 m
Construction of shaft: slab deck – polyester laminate, Ø 110 cm; depth
44 854 Piece
2.0–2.5 m
Construction of shaft: slab deck – polyester laminate, Ø 110 cm; depth
44 855 Piece
above 2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 40 cm;
44 911 Piece
depth up to 1.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 40 cm;
44 912 Piece
depth 1.0–1.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 40 cm;
44 913 Piece
depth 1.5–2.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 40 cm;
44 914 Piece
depth 2.0–2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 40 cm;
44 915 Piece
depth above 2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 60 cm;
44 921 Piece
depth up to 1.0 m

Draft of Version 1 – March 2008 Page 96


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of shaft: other than slab deck – polyester laminate, Ø 60 cm;
44 922 Piece
depth 1.0–1.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 60 cm;
44 923 Piece
depth 1.5–2.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 60 cm;
44 924 Piece
depth 2.0–2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 60 cm;
44 925 Piece
depth above 2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 80 cm;
44 931 Piece
depth up to 1.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 80 cm;
44 932 Piece
depth 1.0–1.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 80 cm;
44 933 Piece
depth 1.5–2.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 80 cm;
44 934 Piece
depth 2.0–2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 80 cm;
44 935 Piece
depth above 2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 100 cm;
44 941 Piece
depth up to 1.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 100 cm;
44 942 Piece
depth 1.0–1.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 100 cm;
44 943 Piece
depth 1.5–2.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 100 cm;
44 944 Piece
depth 2.0–2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 100 cm;
44 945 Piece
depth above 2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 110 cm;
44 951 Piece
depth up to 1.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 110 cm;
44 952 Piece
depth 1.0–1.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 110 cm;
44 953 Piece
depth 1.5–2.0 m
Construction of shaft: other than slab deck – polyester laminate, Ø 110 cm;
44 954 Piece
depth 2.0–2.5 m
Construction of shaft: other than slab deck – polyester laminate, Ø 110 cm;
44 955 Piece
depth above 2.5 m

Draft of Version 1 – March 2008 Page 97


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of ductile casting shaft of circular cross section Ø 80 cm,
44 961 Piece
depth up to 1.0 m
Construction of ductile casting shaft of circular cross section Ø 80 cm,
44 962 Piece
depth 1.0–2.0 m
Construction of ductile casting shaft of circular cross section Ø 80 cm,
44 963 Piece
depth over 2.0 m
Construction of ductile casting shaft of circular cross section Ø 90 cm,
44 971 Piece
depth up to 1.0 m
Construction of ductile casting shaft of circular cross section Ø 90 cm,
44 972 Piece
depth 1.0–2.0 m
Construction of ductile casting shaft of circular cross section Ø 90 cm,
44 973 Piece
depth over 2.0 m
Construction of ductile casting shaft of circular cross section Ø 100 cm,
44 981 Piece
depth up to 1.0 m
Construction of ductile casting shaft of circular cross section Ø 100 cm,
44 982 Piece
depth 1.0–2.0 m
Construction of ductile casting shaft of circular cross section Ø 100 cm,
44 983 Piece
depth over 2.0 m
Construction of ductile casting shaft of circular cross section Ø 120 cm,
44 991 Piece
depth up to 1.0 m
Construction of ductile casting shaft of circular cross section Ø 120 cm,
44 992 Piece
depth 1.0–2.0 m
Construction of ductile casting shaft of circular cross section Ø 120 cm,
44 993 Piece
depth over 2.0 m

4.5 Culverts

Unit
Code Description of work
measure
Execution of culvert of circular section of cement concrete pipe, of
45 111 m
diameter Ø 40 cm
Execution of culvert of circular section of cement concrete pipe, of
45 112 m
diameter Ø 50 cm
Execution of culvert of circular section of cement concrete pipe, of
45 113 m
diameter Ø 60 cm

Draft of Version 1 – March 2008 Page 98


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of culvert of circular section of cement concrete pipe, of
45 114 m
diameter Ø 80 cm
Execution of culvert of circular section of cement concrete pipe, of
45 115 m
diameter Ø 100 cm
Execution of culvert of circular section of cement concrete pipe, of
45 116 m
diameter Ø 120 cm
Execution of culvert of circular section of cement concrete pipe, of
45 117 m
diameter Ø 150 cm
Execution of culvert of circular section of cement concrete pipe, of
45 118 m
diameter Ø 200 cm
Execution of culvert of circular section of cement concrete pipe, of
45 119 m
diameter Ø …. cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 121 m
Ø 40 cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 122 m
Ø 50 cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 123 m
Ø 60 cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 124 m
Ø 80 cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 125 m
Ø 100 cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 126 m
Ø 120 cm
Execution of culvert of parabolic section, of cement concrete, of diameter
45 127 m
Ø 150 cm
Execution of flat culvert of reinforced cement concrete with span up to
45 131 Piece
2.0 m
45 132 Piece Execution of flat culvert of reinforced cement concrete with span 2.0–2.5 m
45 133 Piece Execution of flat culvert of reinforced cement concrete with span 2.5–3.0 m
45 134 Piece Execution of flat culvert of reinforced cement concrete with span 3.0–4.0 m
45 135 Piece Execution of flat culvert of reinforced cement concrete with span 4.0–5.0 m
Execution of inlet and outlet culvert head of circular section, of cement
45 211 Piece
concrete, of diameter 40 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 212 Piece
concrete, of diameter 50 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 213 Piece
concrete, of diameter 60 cm

Draft of Version 1 – March 2008 Page 99


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Execution of inlet and outlet culvert head of circular section, of cement
45 214 Piece
concrete, of diameter 80 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 215 Piece
concrete, of diameter 100 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 216 Piece
concrete, of diameter 120 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 217 Piece
concrete, of diameter 150 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 218 Piece
concrete, of diameter 200 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 219 Piece
concrete, of diameter …... cm
Execution of inlet and outlet culvert head of circular section, of cement
45 221 Piece
concrete, of diameter 80 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 222 Piece
concrete, of diameter 100 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 223 Piece
concrete, of diameter 120 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 224 Piece
concrete, of diameter 150 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 225 Piece
concrete, of diameter 200 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 226 Piece
concrete, of diameter 250 cm
Execution of inlet and outlet culvert head of circular section, of cement
45 227 Piece
concrete, of diameter ….. cm
45 311 m Construction of polyethylene culvert of cross section Ø 40 cm
45 312 m Construction of polyethylene culvert of cross section Ø 50 cm
45 313 m Construction of polyethylene culvert of cross section Ø 60 cm
45 314 m Construction of polyethylene culvert of cross section Ø 70 cm
45 315 m Construction of polyethylene culvert of cross section Ø 80 cm
45 316 m Construction of polyethylene culvert of cross section Ø 90 cm
45 317 m Construction of polyethylene culvert of cross section Ø 100 cm
45 318 m Construction of polyethylene culvert of cross section Ø 120 cm
45 321 m Construction of ductile casting culvert of cross section Ø 40 cm
45 322 m Construction of ductile casting culvert of cross section Ø 50 cm
45 323 m Construction of ductile casting culvert of cross section Ø 60 cm

Draft of Version 1 – March 2008 Page 100


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
45 324 m Construction of ductile casting culvert of cross section Ø 70 cm
45 325 m Construction of ductile casting culvert of cross section Ø 80 cm
45 326 m Construction of ductile casting culvert of cross section Ø 90 cm
45 327 m Construction of ductile casting culvert of cross section Ø 100 cm
45 328 m Construction of ductile casting culvert of cross section Ø 120 cm

4.6 Sources, Wells, Sink Holes, Funnel-Shaped Holes

Unit
Code Description of work
measure
Regulating the source within the route with perforated pipe of cement
46 111 Piece
concrete, of depth up to 1 m, of diameter Ø 30 cm
Regulating the source within the route with perforated pipe of cement
46 112 Piece
concrete, of depth up to 1 m, of diameter Ø 40 cm
Regulating the source within the route with perforated pipe of cement
46 113 Piece
concrete, of depth up to 1 m, of diameter Ø 50 cm
Regulating the source within the route with perforated pipe of cement
46 114 Piece
concrete, of depth up to 1 m, of diameter Ø 60 cm
Regulating the source within the route with perforated pipe of cement
46 115 Piece
concrete, of depth up to 1 m, of diameter Ø 80 cm
Regulating the source within the route with perforated pipe of cement
46 116 Piece
concrete, of depth up to 1 m, of diameter Ø 100 cm
Regulating the source within the route with perforated pipe of cement
46 117 Piece
concrete, of depth up to 1 m, of diameter Ø . . . cm
Regulating the source within the route with perforated pipe of cement
46 121 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø 30 cm
Regulating the source within the route with perforated pipe of cement
46 122 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø 40 cm
Regulating the source within the route with perforated pipe of cement
46 123 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø 50 cm
Regulating the source within the route with perforated pipe of cement
46 124 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø 60 cm
Regulating the source within the route with perforated pipe of cement
46 125 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø 80 cm
Regulating the source within the route with perforated pipe of cement
46 126 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø 100 cm

Draft of Version 1 – March 2008 Page 101


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Regulating the source within the route with perforated pipe of cement
46 127 Piece
concrete, of depth 1.1–2.0 m, of diameter Ø . . . cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 211 m
Ø 10 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 212 m
Ø 15 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 213 m
Ø 20 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 214 m
Ø 25 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 215 m
Ø 30 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 216 m
Ø 40 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 217 m
Ø 50 cm
Regulating the well with perforated asbestos – cement pipes, of diameter
46 218 m
Ø . . . cm
Regulating the source within the route with perforated pipe of cement
46 221 m
concrete, of depth 1.1–2.0 m, of diameter Ø 30 cm
Regulating the source within the route with perforated pipe of cement
46 222 m
concrete, of depth 1.1–2.0 m, of diameter Ø 40 cm
Regulating the source within the route with perforated pipe of cement
46 223 m
concrete, of depth 1.1–2.0 m, of diameter Ø 50 cm
Regulating the source within the route with perforated pipe of cement
46 224 m
concrete, of depth 1.1–2.0 m, of diameter Ø 60 cm
Regulating the source within the route with perforated pipe of cement
46 225 m
concrete, of depth 1.1–2.0 m, of diameter Ø 80 cm
Regulating the source within the route with perforated pipe of cement
46 226 m
concrete, of depth 1.1–2.0 m, of diameter Ø 100 cm
Regulating the source within the route with perforated pipe of cement
46 227 m
concrete, of depth 1.1–2.0 m, of diameter Ø . . . cm
Regulating the source within the route with perforated pipe of cement
46 228 m
concrete, of depth 1.1–2.0 m, of diameter Ø 100 cm
Regulating the source within the route with perforated pipe of cement
46 229 m
concrete, of depth 1.1–2.0 m, of diameter Ø . . . cm
Regulating the sink hole within the route with perforated pipes of cement
46 311 Piece
concrete of diameter 60 cm, of depth up to 1.0 m

Draft of Version 1 – March 2008 Page 102


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Regulating the sink hole within the route with perforated pipes of cement
46 312 Piece
concrete of diameter 60 cm, of depth 1.0–2.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 313 Piece
concrete of diameter 60 cm, of depth 2.0–3.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 314 Piece
concrete of diameter 60 cm, of depth 3.0–4.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 315 Piece
concrete of diameter 60 cm, of depth above 4.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 321 Piece
concrete of diameter 80 cm, of depth up to 1.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 322 Piece
concrete of diameter 80 cm, of depth 1.0–2.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 323 Piece
concrete of diameter 80 cm, of depth 2.0–3.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 324 Piece
concrete of diameter 80 cm, of depth 3.0–4.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 325 Piece
concrete of diameter 80 cm, of depth above 4.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 331 Piece
concrete of diameter 100 cm, of depth up to 1.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 332 Piece
concrete of diameter 100 cm, of depth 1.0–2.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 333 Piece
concrete of diameter 100 cm, of depth 2.0–3.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 334 Piece
concrete of diameter 100 cm, of depth 3.0–4.0 m
Regulating the sink hole within the route with perforated pipes of cement
46 335 Piece
concrete of diameter 100 cm, of depth above 4.0 m
Regulating the funnel-shaped holes with bound stones and sprinkling
46 411 m3
(concrete)
Regulating the funnel-shaped holes with bound stones and sprinkling
46 421 m3
(concrete)
Regulating the funnel-shaped holes with bound stones and sprinkling
46 422 m3
(concrete)

Draft of Version 1 – March 2008 Page 103


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

5 Construction and Specialist Work

5.1 Carpentry Work

Unit
Code Description of work
measure
51 111 m2 Construction of portable scaffold, height up to 4 m
2
51 112 m Construction of portable scaffold, height over 4 m
51 121 m2 Construction of portable scaffold, height up to 4 m
2
51 122 m Construction of portable scaffold, height over 4 m
51 123 m2 Construction of portable scaffold, height up to 4 m
2
51 124 m Construction of portable scaffold, height over 4 m
51 131 m2 Construction of safety platform
2
51 141 m Construction of transportable platform
51 151 m2 Construction of platform railings
2
51 211 m Construction of supported shuttering for level foundations
51 221 m2 Construction of double- sided linked shuttering for level foundations
2
51 311 m Construction of supported shuttering for level walls, height to 2 m
51 312 m2 Construction of supported shuttering for level walls, height to 4 m
2
51 313 m Construction of supported shuttering for level walls, height to 6 m
51 314 m2 Construction of supported shuttering for level walls, height to 8 m
2
51 315 m Construction of supported shuttering for level walls, height over 8 m
2
51 321 m Construction of double-sided linked shuttering for level walls, height to 2 m
2
51 322 m Construction of double-sided linked shuttering for level walls, height to 4 m
2
51 323 m Construction of double-sided linked shuttering for level walls, height to 6 m
2
51 324 m Construction of double-sided linked shuttering for level walls, height to 8 m
Construction of double-sided linked shuttering for level walls, height over
51 325 m2
8m
Construction of supported shuttering for rectangular columns, height to
51 411 m2
4m
Construction of supported shuttering for rectangular columns, height to
51 412 m2
8m
Construction of supported shuttering for rectangular columns, height over
51 413 m2
8m
51 421 m2 Construction of linked shuttering for round columns, height to 4 m
2
51 422 m Construction of linked shuttering for round columns, height to 8 m
2
51 423 m Construction of linked shuttering for round columns, height over 8 m

Draft of Version 1 – March 2008 Page 104


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
51 431 m2 Construction of shutterings for round columns, height to 2 m
51 432 m2 Construction of shutterings for round columns, height to 4 m
2
51 433 m Construction of shutterings for round columns, height to 6 m
51 434 m2 Construction of shutterings for round columns, height to 8 m
2
51 435 m Construction of shutterings for round columns, height over 8 m
Construction of supported shuttering for service girders with supports,
51 511 m2
height to 2 m
Construction of supported shuttering for service girders with supports,
51 512 m2
height to 4 m
Construction of supported shuttering for service girders with supports,
51 513 m2
height to 6 m
Construction of supported shuttering for service girders with supports,
51 514 m2
height over 6 m
51 521 m2 Construction of double-sided linked shuttering for level girders
2
51 531 m Construction of double-sided linked shuttering for level girders 2 m
2
51 532 m Construction of double-sided linked shuttering for level girders 4 m
2
51 533 m Construction of double-sided linked shuttering for level girders 6 m
2
51 534 m Construction of double-sided linked shuttering for level girders over 6 m
2
51 541 m Construction of double-sided linked shuttering for partitioning girders
Construction of supported shuttering for service girders with supports,
51 611 m2
height to 2 m
Construction of supported shuttering for service girders with supports,
51 612 m2
height to 4 m
Construction of supported shuttering for service girders with supports,
51 613 m2
height to 6 m
Construction of supported shuttering for service girders with supports,
51 614 m2
height to 8 m
Construction of supported shuttering for service girders with supports,
51 615 m2
height over 8 m
Construction of supported shuttering for partitioning slabs with supporters,
51 621 m2
height to 2 m
Construction of supported shuttering for partitioning slabs with supporters,
51 622 m2
height to 4 m
Construction of supported shuttering for partitioning slabs with supporters,
51 623 m2
height to 6 m
Construction of supported shuttering for partitioning slabs with supporters,
51 624 m2
height to 8 m

Draft of Version 1 – March 2008 Page 105


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of supported shuttering for partitioning slabs with supporters,
51 625 m2
height over 8 m

5.2 Work with Steel for Reinforcement

Unit
Code Description of work
measure
Preparation and installation of smooth wire from soft steel S 185, diameter
52 111 kg
12 mm, for simple reinforcement
Preparation and installation of smooth wire from soft steel S 185, diameter
52 112 kg
12 mm, for medium demanding reinforcement
Preparation and installation of smooth wire from soft steel S 185, diameter
52 113 kg
12 mm, for demanding reinforcement
Preparation and installation of smooth wire from soft steel E 295, diameter
52 121 kg
12 mm, for simple reinforcement
Preparation and installation of smooth wire from soft steel E 295, diameter
52 122 kg
12 mm, for medium demanding reinforcement
Preparation and installation of smooth wire from soft steel E 295, diameter
52 123 kg
12 mm, for demanding reinforcement
Preparation and installation of smooth rods from soft steel E 295, 14 mm
52 131 kg
diameter and over, for simple reinforcement
Preparation and installation of smooth rods from soft steel E 295, 14 mm
52 132 kg
diameter and over, for medium demanding reinforcement
Preparation and installation of smooth rods from soft steel E 295, 14 mm
52 133 kg
diameter and over, for demanding reinforcement
Preparation and installation of ribbed wire from high value natural hard
52 221 kg
steel E 360, diameter to 12 mm, for simple reinforcement
Preparation and installation of ribbed wire from high value natural hard
52 222 kg
steel E 360, diameter to 12 mm, for medium demanding reinforcement
Preparation and installation of ribbed wire from high value natural hard
52 223 kg
steel E 360, diameter to 12 mm, for demanding reinforcement
Preparation and installation of ribbed rods from high value natural hard
52 231 kg
steel E 360, 14 mm diameter and over, for simple reinforcement
Preparation and installation of ribbed rods from high value natural hard
52 232 kg steel E 360, 14 mm diameter and over, for medium demanding
reinforcement

Draft of Version 1 – March 2008 Page 106


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and installation of ribbed rods from high value natural hard
52 233 kg
steel E 360, 14 mm diameter and over, for demanding reinforcement
Preparation and installation of nets from rolled steel, diameter 4 ≤ Ø ≥ 12
52 311 kg
mm, weight up to 2 kg/m2
52 312 kg Preparation and installation of nets from rolled steel over 2–3 kg/m2
52 313 kg Preparation and installation of nets from rolled steel over 3–4 kg/m2
52 314 kg Preparation and installation of nets from rolled steel over 4–6 kg/m2
52 315 kg Preparation and installation of nets from rolled steel over 6 kg/m2
Preparation and installation of nets from stretched steel sheet, weight up
52 321 kg
to 2 kg/m2
Preparation and installation of nets from stretched steel sheet, weight over
52 322 kg
2–3 kg/m2
Preparation and installation of nets from stretched steel sheet, weight over
52 323 kg
3–4 kg/m2
Preparation and installation of nets from stretched steel sheet, weight over
52 324 kg
4–6 kg/m2
Preparation and installation of nets from stretched steel sheet, weight
52 325 kg
over 6 kg/m2
Preparation and installation of smooth steel wire of a circular section and
52 411 kg
high tensile strength for pre-stressed constructions
Preparation and installation of profiled steel wire of a circular section and
52 421 kg
high tensile strength for pre-stressed constructions
Preparation and installation of smooth steel rods of a circular section and
52 431 kg
high tensile strength for pre-stressed constructions
Preparation and installation of ribbed steel rods of a circular section and
52 441 kg
high tensile strength for pre-stressed constructions
Preparation and installation of cables from smooth steel wires of a circular
52 451 kg section and a high tensile strength for pre-stressed constructions: cables
twined from two wires
Preparation and installation of cables from smooth steel wires of a circular
52 452 kg section and a high tensile strength for pre-stressed constructions: cables
twined from three wires
Preparation and installation of cables from smooth steel wires of a circular
52 453 kg section and a high tensile strength for pre-stressed constructions: cables
twined from four wires
52 511 Piece Preparation and installation of anchor heads, type ……..
52 521 Piece Preparation and installation of extension heads, type

Draft of Version 1 – March 2008 Page 107


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
52 531 Piece Preparation and installation of tension heads, type ………
52 611 kg Preparation and installation of steel arch from TH sections
52 612 kg Preparation and installation of steel arch from I sections
52 621 Piece Preparation and installation of steel linking locks for arches
52 711 Piece Preparation and installation of steel shuttering – tunnel boards
52 811 Piece Preparation and installation of steel spears IBO, length 4 m
52 812 Piece Preparation and installation of steel spears IBO, length 6 m
52 813 Piece Preparation and installation of steel spears IBO, length 9 m
52 814 Piece Preparation and installation of steel spears IBO, length 12 m
52 815 Piece Preparation and installation of steel spears IBO, length 15 m
52 816 Piece Preparation and installation of steel spears IBO, length 18 m
52 817 Piece Preparation and installation of steel spears IBO, length 21 m
52 818 Piece Preparation and installation of steel spears IBO, length … m
52 911 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 2 m
52 912 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 2.5 m
52 913 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 3 m
52 914 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 3.5 m
52 915 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 4 m
52 916 Piece Preparation and installation of steel needles, RA Ø 25 mm, length … m
52 921 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 2 m
52 922 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 2.5 m
52 923 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 3 m
52 924 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 3.5 m
52 925 Piece Preparation and installation of steel needles, RA Ø 25 mm, length 4 m
52 926 Piece Preparation and installation of steel needles, RA Ø 25 mm, length … m

Draft of Version 1 – March 2008 Page 108


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

5.3 Work with Cement Concrete

Unit
Code Description of work
measure
Preparation and placement of mixtures of ordinary cement concrete
53 111 m3
MB 10, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 112 m3
MB 10, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 113 m3
MB 10, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 114 m3
MB 10, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 121 m3
MB 15, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 122 m3
MB 15, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 123 m3
MB 15, in section 0.31 to 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 124 m3
MB 15, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 131 m3
MB 20, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 132 m3
MB 20, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 133 m3
MB 20, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 134 m3
MB 20, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 141 m3
MB 25, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 142 m3
MB 25, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 143 m3
MB 25, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 144 m3
MB 25, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 151 m3
MB …., in section to 0.15 m3/m2-m

Draft of Version 1 – March 2008 Page 109


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and placement of mixtures of ordinary cement concrete
53 152 m3
MB …., in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 153 m3
MB …., in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 154 m3
MB …., in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 211 m3
MB 15, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 212 m3
MB 15, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 213 m3
MB 15, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 214 m3
MB 15, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 221 m3
MB 20, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 222 m3
MB 20, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 223 m3
MB 20, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 224 m3
MB 20, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 231 m3
MB 25, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 232 m3
MB 25, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 233 m3
MB 25, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of ordinary cement concrete
53 234 m3
MB 25, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 241 m3
MB 30, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 242 m3
MB 30, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 243 m3
MB 30, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 244 m3
MB 30, in section over 0.50 m3/m2-m

Draft of Version 1 – March 2008 Page 110


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and placement of mixtures of reinforced cement concrete
53 251 m3
MB 35, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 252 m3
MB 35, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 253 m3
MB 35, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 254 m3
MB 35, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 261 m3
MB 40, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 262 m3
MB 40, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 263 m3
MB 40, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 264 m3
MB 40, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 271 m3
MB 45, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 272 m3
MB 45, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 273 m3
MB 45, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 274 m3
MB 45, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 281 m3
MB 50, in section to 0.15 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 282 m3
MB 50, in section 0.16–0.30 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 283 m3
MB 50, in section 0.31–0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 284 m3
MB 50, in section over 0.50 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 291 m3
MB …., in section to 0.15 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 292 m3
MB …., in section 0.16 to 0.30 m3/m2-m
Preparation and placement of mixtures of reinforced cement concrete
53 293 m3
MB …., in section 0.31 to 0.50 m3/m2-m

Draft of Version 1 – March 2008 Page 111


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and placement of mixtures of reinforced cement concrete
53 294 m3
MB …., in section over 0.50 m3/m2-m
Use of additive – accelerating agent for bonding fresh cement concrete of
53 311 m3
a chlorine basis
Use of additive accelerating agent for bonding fresh cement concrete of a
53 321 m3
non-chlorine basis
53 331 m3 Use of additive – retarder for bonding fresh cement concrete
3
53 341 m Use of additive – fresh cement concrete plastificiser
3
53 351 m Use of additive – fresh cement concrete superplastificiser
3
53 361 m Use of additive – cement concrete densifier
53 371 m3 Use of additive – fresh cement concrete aerant
3
53 381 m Use of additive – heat developer in fresh cement concrete
Preparation and placement of mixtures of porous (drainage ) cement
53 411 m3
concrete
53 421 m3 Preparation and placement of mixtures of foam cement concrete MB 15
3
53 422 m Preparation and placement of mixtures of foam cement concrete MB 20
3
53 423 m Preparation and placement of mixtures of foam cement concrete MB 25
3
53 424 m Preparation and placement of mixtures of foam cement concrete MB 30
3
53 425 m Preparation and placement of mixtures of foam cement concrete MB 35
3
53 426 m Preparation and placement of mixtures of foam cement concrete MB 40
3
53 427 m Preparation and placement of mixtures of foam cement concrete MB 45
3
53 431 m Preparation and placement of mixtures of light cement concrete MB 15
3
53 432 m Preparation and placement of mixtures of light cement concrete MB 20
3
53 433 m Preparation and placement of mixtures of light cement concrete MB 25
3
53 434 m Preparation and placement of mixtures of light cement concrete MB 30
3
53 435 m Preparation and placement of mixtures of light cement concrete MB ….
Preparation and replacement of mixtures of concrete MB 20, in section to
53 511 m3
0.10 m3/m2
Preparation and replacement of mixtures of concrete MB 20, in section
53 512 m3
0.11–0.20 m3/m2
Preparation and replacement of mixtures of concrete MB 20, in section
53 513 m3
over 0.20 m3/m2
Preparation and replacement of mixtures of concrete MB 30, in section to
53 521 m3
0.10 m3/m2
Preparation and replacement of mixtures of concrete MB 30, in section
53 522 m3
0.11–0.20 m3/m2

Draft of Version 1 – March 2008 Page 112


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and replacement of mixtures of concrete MB 30, in section
53 523 m3
over 0.20 m3/m2
Preparation and replacement of mixtures of concrete MB …., in section to
53 531 m3
0.10 m3/m2
Preparation and replacement of mixtures of concrete MB …., in section
53 532 m3
0.11–0.20 m3/m2
Preparation and replacement of mixtures of concrete MB …., in section
53 533 m3
over 0.20 m3/m2
53 611 m3 Preparation and placement of mixtures of poured cement concrete MB 15
3
53 612 m Preparation and placement of mixtures of poured cement concrete MB 20
3
53 613 m Preparation and placement of mixtures of poured cement concrete MB 25
3
53 614 m Preparation and placement of mixtures of poured cement concrete MB 30
3
53 615 m Preparation and placement of mixtures of poured cement concrete MB 35
3
53 616 m Preparation and placement of mixtures of poured cement concrete MB 40
3
53 617 m Preparation and placement of mixtures of poured cement concrete MB 45
3
53 618 m Preparation and placement of mixtures of poured cement concrete MB ….
3
53 711 m Preparation and placement of mixtures of slag cement concrete MB 15
3
53 712 m Preparation and placement of mixtures of slag cement concrete MB 20
3
53 713 m Preparation and placement of mixtures of slag cement concrete MB 25
3
53 714 m Preparation and placement of mixtures of slag cement concrete MB 30
3
53 715 m Preparation and placement of mixtures of slag cement concrete MB 35
3
53 716 m Preparation and placement of mixtures of slag cement concrete MB 40
3
53 717 m Preparation and placement of mixtures of slag cement concrete MB 45
3
53 718 m Preparation and placement of mixtures of slag cement concrete MB ….
Preparation and placement of mixtures of cement concrete, watertight
53 811 m3
brand B-2
Preparation and placement of mixtures of cement concrete, watertight
53 812 m3
brand B-4
Preparation and placement of mixtures of cement concrete, watertight
53 813 m3
brand B-6
Preparation and placement of mixtures of cement concrete, watertight
53 814 m3
brand B-8
Preparation and placement of mixtures of cement concrete, watertight
53 815 m3
brand B-12
Preparation and placement of mixtures which prevent the wear of resistant
53 821 m3
cement concrete MB 20

Draft of Version 1 – March 2008 Page 113


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and placement of mixtures which prevent the wear of resistant
53 822 m3
cement concrete MB 25
Preparation and placement of mixtures which prevent the wear of resistant
53 823 m3
cement concrete MB 30
Preparation and placement of mixtures which prevent the wear of resistant
53 824 m3
cement concrete MB 35
Preparation and placement of mixtures which prevent the wear of resistant
53 825 m3
cement concrete MB 40
Preparation and placement of mixtures which prevent the wear of resistant
53 826 m3
cement concrete MB …
Preparation and placement of cement concrete resistant against chemical
53 831 m3
effects MB 30
Preparation and placement of cement concrete resistant against chemical
53 832 m3
effects MB 35
Preparation and placement of cement concrete resistant against chemical
53 833 m3
effects MB 40
Preparation and placement of cement concrete resistant against chemical
53 834 m3
effects MB ….

5.4 Masonry and Stonemasonry Work

Unit
Code Description of work
measure
Cladding with chipping from silicate rock, bound with cement mortar, in
54 111 m2
thickness to 10 cm
Cladding with chipping from silicate rock, bound with cement mortar, in
54 112 m2
thickness 11–15 cm
Cladding with chipping from silicate rock, bound with cement mortar, in
54 113 m2
thickness 16–20 cm
Cladding with chipping from silicate rock, bound with cement mortar, in
54 114 m2
thickness over 20 cm
Cladding with chipping from carbonate rock, bound with cement mortar, in
54 121 m2
thickness to 10 cm
Cladding with chipping from carbonate rock, bound with cement mortar, in
54 122 m2
thickness 11–15 cm

Draft of Version 1 – March 2008 Page 114


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Cladding with chipping from carbonate rock, bound with cement mortar, in
54 123 m2
thickness 16–20 cm
Cladding with chipping from carbonate rock, bound with cement mortar, in
54 124 m2
thickness over 20 cm
Cladding with processed stone from silicate rock, bound with cement
54 131 m2
mortar, in thickness to 10 cm
Cladding with processed stone from silicate rock, bound with cement
54 132 m2
mortar, in thickness 11–15 cm
Cladding with processed stone from silicate rock, bound with cement
54 133 m2
mortar, in thickness 16–20 cm
Cladding with processed stone from silicate rock, bound with cement
54 134 m2
mortar, in thickness over 20 cm
Cladding with processed stone from carbonate rock, bound with cement
54 141 m2
mortar, in thicknessto 10 cm
Cladding with processed stone from carbonate rock, bound with cement
54 142 m2
mortar, in thickness11–15 cm
Cladding with processed stone from carbonate rock, bound with cement
54 143 m2
mortar, in thickness16–20 cm
Cladding with processed stone from carbonate rock, bound with cement
54 144 m2
mortar, in thicknessover 20 cm
54 151 m Manufacture of sunken joints
Building with chipping from silicate rock in cement mortar, on one face,
54 211 m3
section to 0.15 m3/m3
Building with chipping from silicate rock in cement mortar, on one face,
54 212 m3
section 0.16–0.25 m3/m3
Building with chipping from silicate rock in cement mortar, on one face,
54 213 m3
section 0.26–0.35 m3/m3
Building with chipping from silicate rock in cement mortar, on one face,
54 214 m3
section 0.36–0.50 m3/m3
Building with chipping from silicate rock in cement mortar, on one face,
54 215 m3
section over 0.50 m3/m3
Building with chipping from silicate rock in cement mortar, on two faces,
54 221 m3
section to 0.15 m3/m3
Building with chipping from silicate rock in cement mortar, on two faces,
54 222 m3
section 0.16–0.25 m3/m3
Building with chipping from silicate rock in cement mortar, on two faces,
54 223 m3
section 0.26–0.35 m3/m3

Draft of Version 1 – March 2008 Page 115


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Building with chipping from silicate rock in cement mortar, on two faces,
54 224 m3
section 0.36–0.50 m3/m3
Building with chipping from silicate rock in cement mortar, on two faces,
54 225 m3
section over 0.50 m3/m3
Building with chipping from carbonate rock in cement mortar, on one face,
54 231 m3
section to 0.15 m3/m3
Building with chipping from carbonate rock in cement mortar, on one face,
54 232 m3
section 0.16–0.25 m3/m3
Building with chipping from carbonate rock in cement mortar, on one face,
54 233 m3
section 0.26–0.35 m3/m3
Building with chipping from carbonate rock in cement mortar, on one face,
54 234 m3
section 0.36–0.50 m3/m3
Building with chipping from carbonate rock in cement mortar, on one face,
54 235 m3
section over 0.50 m3/m3
Building with chipping from carbonate rock in cement mortar, on two
54 241 m3
faces, section to 0.15 m3/m3
Building with chipping from carbonate rock in cement mortar, on two
54 242 m3
faces, section 0.16–0.25 m3/m3
Building with chipping from carbonate rock in cement mortar, on two
54 243 m3
faces, section 0.26–0.35 m3/m3
Building with chipping from carbonate rock in cement mortar, on two
54 244 m3
faces, section 0.36–0.50 m3/m3
Building with chipping from carbonate rock in cement mortar, on two
54 245 m3
faces, section over 0.50 m3/m3
Building with processed stone from silicate rock in cement mortar, on one
54 251 m3
face, section to 0.15 m3/m3
Building with processed stone from silicate rock in cement mortar, on one
54 252 m3
face, section 0.16–0.25 m3/m3
Building with processed stone from silicate rock in cement mortar, on one
54 253 m3
face, section 0.26–0.35 m3/m3
Building with processed stone from silicate rock in cement mortar, on one
54 254 m3
face, section 0.36–0.50 m3/m3
Building with processed stone from silicate rock in cement mortar, on one
54 255 m3
face, section over 0.50 m3/m3
Building with processed stone from silicate rock in cement mortar, on two
54 261 m3
faces, section to 0.15 m3/m3
Building with processed stone from silicate rock in cement mortar, on two
54 262 m3
faces, section 0.16–0.25 m3/m3

Draft of Version 1 – March 2008 Page 116


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Building with processed stone from silicate rock in cement mortar, on two
54 263 m3
faces, section 0.26–0.35 m3/m3
Building with processed stone from silicate rock in cement mortar, on two
54 264 m3
faces, in section 0.36–0.50 m3/m3
Building with processed stone from silicate rock in cement mortar, on two
54 265 m3
faces, in section over 0.50 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 271 m3
one face, in section to 0.15 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 272 m3
one face, in section 0.16–0.25 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 273 m3
one face, in section 0.26–0.35 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 274 m3
one face, in section 0.36–0.50 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 275 m3
one face, in section over 0.50 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 281 m3
two faces, section to 0.15 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 282 m3
two faces, section 0.16–0.25 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 283 m3
two faces, section 0.26–0.35 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 284 m3
two faces, section 0.36–0.50 m3/m3
Building with processed stone from carbonate rock in cement mortar, on
54 285 m3
two faces, section over 0.50 m3/m3
Cladding with prefabricated elements from cement concrete, bound with
54 311 m2
cement mortar, in thickness to 10 cm
Cladding with prefabricated elements from cement concrete, bound with
54 312 m2
cement mortar, in thickness 11–15 cm
Cladding with prefabricated elements from cement concrete, bound with
54 313 m2
cement mortar, in thickness 16–20 cm
Cladding with prefabricated elements from cement concrete, bound with
54 314 m2
cement mortar, in thickness over 20 cm
54 321 m2 Cladding with face bricks, bound with cement mortar, thickness to 12 cm
Building with prefabricated elements from cement concrete in cement
54 411 m
mortar, on one face, section to 0.15 m3/m3

Draft of Version 1 – March 2008 Page 117


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Building with prefabricated elements from cement concrete in cement
54 412 m3
mortar, on one face, in section 0.16–0.25 m3/m3
Building with prefabricated elements from cement concrete in cement
54 413 m3
mortar, on one face, in section 0.26–0.35 m3/m3
Building with prefabricated elements from cement concrete in cement
54 414 m3
mortar, on one face, in section 0.36–0.50 m3/m3
Building with prefabricated elements from cement concrete in cement
54 415 m3
mortar, on one face, in section over 0.50 m3/m3
Building with prefabricated elements from cement concrete in cement
54 421 m
mortar, on two faces, in section to 0.15 m3/m3
Building with prefabricated elements from cement concrete in cement
54 422 m3
mortar, on two faces, in section 0.16–0.25 m3/m3
Building with prefabricated elements from cement concrete in cement
54 423 m3
mortar, on two faces, in section 0.26–0.35 m3/m3
Building with prefabricated elements from cement concrete in cement
54 424 m3
mortar, on two faces, in section 0.36–0.50 m3/m3
Building with prefabricated elements from cement concrete in cement
54 425 m3
mortar, on two faces, in section over 0.50 m3/m3
54 461 m2 Building with face bricks in cement mortar, thickness to 12 cm
54 462 m2 Building with face bricks in cement mortar, thickness to 25 cm
2
54 471 m Building with bricks in cement mortar, on one face, thickness 12 cm
54 472 m2 Building with bricks in cement mortar, on one face, thickness 18 cm
2
54 473 m Building with bricks in cement mortar, on one face, thickness 25 cm
54 474 m2 Building with bricks in cement mortar, on one face, thickness 31 cm
2
54 475 m Building with bricks in cement mortar, on one face, thickness 38 cm
54 481 m2 Building with bricks in cement mortar, on two faces, thickness 12 cm
2
54 482 m Building with bricks in cement mortar, on two faces, thickness 25 cm
54 483 m2 Building with bricks in cement mortar, on two faces, thickness 38 cm
2
54 511 m Manufacture of coating with cement mortar, thickness 1 cm
2
54 512 m Manufacture of coating with cement mortar, thickness 2 cm
2
54 513 m Manufacture of coating with cement mortar, thickness 3 cm
2
54 514 m Manufacture of coating with cement mortar, thickness 4 cm
2
54 521 m Grinding surface coating with cement mortar
2
54 531 m Smoothing surface coatings with cement mortar
2
54 541 m Brushing surface coatings with cement mortar
2
54 611 m Chopping – stamping surface from cement concrete

Draft of Version 1 – March 2008 Page 118


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
54 621 m2 Chopping – stamping surface from silicate rock
54 631 m2 Chopping – stamping surface from carbonate rock
2
54 711 m Sanding surfaces from cement concrete
54 721 m2 Sanding surfaces from silicate rock
2
54 731 m Sanding surfaces from carbonate rock

5.4.1 Anchoring

Unit
Code Description of work
measure
55 111 m Drilling of boreholes in unstabilised stone material for rock-bolts Ø 45 mm
55 112 m Drilling of boreholes in unstabilised stone material for rock-bolts Ø 60 mm
55 113 m Drilling of boreholes in unstabilised stone material for rock-bolts Ø 75 mm
55 114 m Drilling of boreholes in unstabilised stone material for rock-bolts Ø 90 mm
55 115 m Drilling of boreholes in unstabilised stone material for rock-bolts Ø …. mm
55 121 m Drilling of boreholes for rock-bolts Ø 45 mm
55 122 m Drilling of boreholes for rock-bolts Ø 60 mm
55 123 m Drilling of boreholes for rock-bolts Ø 75 mm
55 124 m Drilling of boreholes for rock-bolts Ø 90 mm
55 125 m Drilling of boreholes for rock-bolts Ø …. mm
Preparation and installation of steel expansion rock-bolts 150 kN, with
55 211 Piece
heads, length 2 m
Preparation and installation of steel expansion rock-bolts 150 kN, with
55 212 Piece
heads, length 3 m
Preparation and installation of steel expansion rock-bolts 150 kN, with
55 213 Piece
heads, length 4 m
Preparation and installation of steel expansion rock -bolts 150 kN, with
55 214 Piece
heads, length … m
Preparation and installation of steel expansion rock-bolt s 250 kN, with
55 221 Piece
heads, length 2 m
Preparation and installation of steel expansion rock-bolt s 250 kN, with
55 222 Piece
heads, length 3 m
Preparation and installation of steel expansion rock-bolt s 250 kN, with
55 223 Piece
heads, length 4 m

Draft of Version 1 – March 2008 Page 119


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and installation of steel expansion rock-bolt s 250 kN, with
55 224 Piece
heads, length … m
55 231 Piece Preparation and installation of alluvial rock-bolt s 60 kN, length 10 m
55 232 Piece Preparation and installation of alluvial rock-bolt s 60 kN, length 10–20 m
55 233 Piece Preparation and installation of alluvial rock-bolt s 60 kN, length over 20 m
55 241 Piece Preparation and installation of measurement rock-bolts length 10 m
55 242 Piece Preparation and installation of measurement rock-bolts length 10–20 m
55 243 Piece Preparation and installation of measurement rock-bolts length over 20 m
Preparation and installation of steel friction rock-bolts 150 kN, without pre-
55 311 Piece
stressing, length 3 m
Preparation and installation of steel friction rock-bolts 150 kN, without pre-
55 312 Piece
stressing, length 6 m
Preparation and installation of steel friction rock-bolts 150 kN, without pre-
55 313 Piece
stressing, length 9 m
Preparation and installation of steel friction rock-bolts 150 kN, without pre-
55 314 Piece
stressing, length … m
Preparation and installation of steel friction rock-bolt s 250 kN, without
55 321 Piece
pre-stressing, length 3 m
Preparation and installation of steel friction rock-bolt s 250 kN, without
55 322 Piece
pre-stressing, length 6 m
Preparation and installation of steel friction rock-bolt s 250 kN, without
55 323 Piece
pre-stressing, length 9 m
Preparation and installation of steel friction rock-bolt s 250 kN, without
55 324 Piece
pre-stressing, length … m
Preparation and installation of steel friction rock-bolt s 350 kN, without
55 331 Piece
pre-stressing, length 3 m
Preparation and installation of steel friction rock-bolt s 350 kN, without
55 332 Piece
pre-stressing, length 6 m
Preparation and installation of steel friction rock-bolt s 350 kN, without
55 333 Piece
pre-stressing, length 9 m
Preparation and installation of steel friction rock-bolt s 350 kN, without
55 334 Piece
pre-stressing, length … m
55 341 Piece Preparation and installation of steel rock-bolt s IBO 200, length 6 m
55 342 Piece Preparation and installation of steel rock-bolt s IBO 200, length 8 m
55 343 Piece Preparation and installation of steel rock-bolt s IBO 200, length 9 m
55 344 Piece Preparation and installation of steel rock-bolt s IBO 200, length 10 m
55 345 Piece Preparation and installation of steel rock-bolt s IBO 200, length 12 m

Draft of Version 1 – March 2008 Page 120


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
55 346 Piece Preparation and installation of steel rock-bolt s IBO 200, length 14 m
55 347 Piece Preparation and installation of steel rock-bolt s IBO 200, length 16 m
55 348 Piece Preparation and installation of steel rock-bolt s IBO 200, length 18 m
55 349 Piece Preparation and installation of steel rock-bolt s IBO 200, length … m
55 351 Piece Preparation and installation of steel rock-bolt s SWELEX, length 3 m
55 352 Piece Preparation and installation of steel rock-bolt s SWELEX, length 6 m
55 353 Piece Preparation and installation of steel rock-bolt s SWELEX, length 9 m
55 354 Piece Preparation and installation of steel rock-bolt s SWELEX, length … m
Preparation and installation of steel friction rock-bolts 250 kN, with pre-
55 361 Piece
stressing, length 3 m
Preparation and installation of steel friction rock-bolts 250 kN, with pre-
55 362 Piece
stressing, length 6 m
Preparation and installation of steel friction rock-bolts 250 kN, with pre-
55 363 Piece
stressing, length 9 m
Preparation and installation of steel friction rock-bolts 250 kN, with pre-
55 364 Piece
stressing, length … m
Preparation and installation of steel friction rock-bolt s 350 kN, with pre-
55 371 Piece
stressing, length 3 m
Preparation and installation of steel friction rock-bolt s 350 kN, with pre-
55 372 Piece
stressing, length 6 m
Preparation and installation of steel friction rock-bolt s 350 kN, with pre-
55 373 Piece
stressing, length 9 m
Preparation and installation of steel friction rock-bolt s 350 kN, with pre-
55 374 Piece
stressing, length … m
Preparation and installation of steel friction rock-bolts 500 kN, with pre-
55 381 Piece
stressing, length 3 m
Preparation and installation of steel friction rock-bolts 500 kN, with pre-
55 382 Piece
stressing, length 6 m
Preparation and installation of steel friction rock-bolts 500 kN, with pre-
55 383 Piece
stressing, length 9 m
Preparation and installation of steel friction rock-bolts 500 kN, with pre-
55 384 Piece
stressing, length … m
55 411 Piece Preparation and installation of steel rock-bolt head 400 kN
55 412 Piece Preparation and installation of steel rock-bolt head 600 kN
55 413 Piece Preparation and installation of steel rock-bolt head 800 kN
55 414 Piece Preparation and installation of steel rock-bolt head 1000 kN
55 415 Piece Preparation and installation of steel rock-bolt head …… kN

Draft of Version 1 – March 2008 Page 121


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and installation of steel grouting tube needle 200 kN, length
55 421 Piece
2m
Preparation and installation of steel grouting tube needle 200 kN, length
55 422 Piece
4m
Preparation and installation of steel grouting tube needle 200 kN, length
55 423 Piece
6m
Preparation and installation of steel grouting tube needle 200 kN, length
55 424 Piece
…m
Preparation and installation of rock-bolts from glass and artificial resin
55 511 Piece
250 kN, length 3 m
Preparation and installation of rock-bolts from glass and artificial resin
55 512 Piece
250 kN, length 6 m
Preparation and installation of rock-bolts from glass and artificial resin
55 513 Piece
250 kN, length 9 m
Preparation and installation of rock-bolts from glass and artificial resin
55 514 Piece
250 kN, length 12 m
Preparation and installation of rock-bolts from glass and artificial resin
55 515 Piece
250 kN, length ….m
55 611 Piece Test of rock-bolt bearing strength by loading to destruction
Preparation and organisation of niches for equipment of the measuring
55 612 Piece
rock-bolts
55 631 Piece Additional rock-bolts tensioning

5.4.2 Grouting

Unit
Code Description of work
measure
56 111 m Execution of boreholes in earth Ø 45 mm
56 112 m Execution of boreholes in earth Ø 60 mm
56 113 m Execution of boreholes in earth Ø 70 mm
56 114 m Execution of boreholes in earth Ø 90 mm
56 115 m Execution of boreholes in earth Ø 100 mm
56 116 m Execution of boreholes in earth Ø 110 mm
56 121 m Execution of boreholes in rock Ø 45 mm
56 122 m Execution of boreholes in rock Ø 60 mm

Draft of Version 1 – March 2008 Page 122


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
56 123 m Execution of boreholes in rock Ø 70 mm
56 124 m Execution of boreholes in rock Ø 90 mm
56 125 m Execution of boreholes in rock Ø 100 mm
56 126 m Execution of boreholes in rock Ø 110 mm
Preparation of dry mixture for grounding (Including the necessary water
56 211 t
for the mixture): Portland cement PC 25
Preparation of dry mixture for grounding (Including the necessary water
56 212 t
for the mixture): Portland cement PC 35
Preparation of dry mixture for grounding (Including the necessary water
56 213 t
for the mixture): Portland cement PC 45
Preparation of dry mixture for grounding (Including the necessary water
56 214 t
for the mixture): Portland cement PC 55
Preparation of dry mixture for grounding (Including the necessary water
56 221 t
for the mixture): Portland cement, sulphate resistant PC 25
Preparation of dry mixture for grounding (Including the necessary water
56 231 t
for the mixture): Portland cement with pozzolan additive PC 15 p 25
Preparation of dry mixture for grounding (Including the necessary water
56 232 t
for the mixture): Portland cement with pozzolan additive PC 15 p 35
Preparation of dry mixture for grounding (Including the necessary water
56 233 t
for the mixture): Portland cement with pozzolan additive PC 15 p 45
Preparation of dry mixture for grounding (Including the necessary water
56 234 t
for the mixture): Portland cement with pozzolan additive PC 30 p 25
Preparation of dry mixture for grounding (Including the necessary water
56 235 t
for the mixture): Portland cement with pozzolan additive PC 30 p 35
Preparation of dry mixture for grounding (Including the necessary water
56 236 t
for the mixture): Portland cement with pozzolan additive PC 30 p 45
Preparation of mixture for grouting (including the necessary water for the
56 241 t
mixture): lime
Preparation of mixture for grouting (including the necessary water for the
56 251 t
mixture): fly ash
Preparation of mixture for grouting (including the necessary water for the
56 261 t
mixture): rock dust
Preparation of mixture for grouting (including the necessary water for the
56 262 t
mixture): sand 0/2 mm
Preparation of mixture for grouting (including the necessary water for the
56 263 t
mixture): sand 0/4 mm
Preparation of mixture for grouting (including the necessary water for the
56 271 t
mixture): bentonite

Draft of Version 1 – March 2008 Page 123


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation of mixture for grouting (including the necessary water for the
56 281 t
mixture): clay
Preparation of mixture for grouting (including the necessary water for the
56 291 t
mixture): ………
56 311 t Preparation of chemical additives: accelerating agent for binding
Preparation of chemical additives: accelerating agent for binding retarding
56 312 t
agent for binding
Preparation of chemical additives: accelerating agent for binding
56 313 t
plastificiser
Preparation of chemical additives: accelerating agent for binding for
56 314 t
swelling
Preparation of chemical additives: accelerating agent for binding for
56 315 t
preventing sedimentation
56 411 kg Preparation of liquid mixtures for grouting: silicate gel
Preparation of liquid mixture for grouting: two-components resin, mixture
56 421 t
ratio 10 : 1
Preparation of liquid mixture for grouting: two-components resin, mixture
56 422 t
ratio 4 : 1
Preparation of liquid mixture for grouting: two-components resin, mixture
56 423 t
ratio .. : 1
Preparation of liquid mixture for grouting: two-components resin, mixture
56 424 t
ratio .. : 1
Preparation of liquid mixture for grouting: triple-components resin, mixture
56 431 t
ratio 6 : 1 : 0.5
Preparation of liquid mixture for grouting: triple-components resin, mixture
56 432 t
ratio 4 : 3 : 1
Preparation of liquid mixture for grouting: triple-components resin, mixture
56 433 t
ratio .. : .. : ..
Preparation of liquid mixture for grouting: triple-components resin, mixture
56 434 t
ratio .. : .. : ..
Grounding or pre-grounding boreholes with cement suspension with
56 511 t
Portland cement PC 25
Grounding or pre-grounding boreholes with cement suspension with
56 512 t
Portland cement PC 35
Grounding or pre-grounding boreholes with cement suspension with
56 513 t
Portland cement PC 45
Grounding or pre-grounding boreholes with cement suspension with
56 514 t
Portland cement PC 55

Draft of Version 1 – March 2008 Page 124


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Grounding or pre-grounding boreholes with cement suspension with
56 521 t
Portland cement, resistant against sulphate
Grounding or pre-grounding boreholes with cement suspension with
56 531 t
Portland cement and pozzolan additive PC 15 p 25
Grounding or pre-grounding boreholes with cement suspension with
56 532 t
Portland cement and pozzolan additive PC 15 p 35
Grounding or pre-grounding boreholes with cement suspension with
56 533 t
Portland cement and pozzolan additive PC 15 p 45
Grounding or pre-grounding boreholes with cement suspension with
56 534 t
Portland cement and pozzolan additive PC 30 p 25
Grounding or pre-grounding boreholes with cement suspension with
56 535 t
Portland cement and pozzolan additive PC 30 p 35
Grounding or pre-grounding boreholes with cement suspension with
56 536 t
Portland cement and pozzolan additive PC 30 p 45
Grounding boreholes with cement mortar with Portland cement PC 25 and
56 611 t
a mixing mass ratio of cement and gravel 1 : 0.5
Grounding boreholes with cement mortar with Portland cement PC 25 and
56 612 t
a mixing mass ratio of cement and gravel 1 : 1
Grounding boreholes with cement mortar with Portland cement PC 25 and
56 613 t
a mixing mass ratio of cement and gravel 1 : 2
Grounding boreholes with cement mortar with Portland cement PC 35 and
56 621 t
a mixing mass ratio cement and sand 1 : 0.5
Grounding boreholes with cement mortar with Portland cement PC 35 and
56 622 t
a mixing mass ratio cement and sand 1 : 1
Grounding boreholes with cement mortar with Portland cement PC 35 and
56 623 t
a mixing mass ratio cement and sand 1 : 2
Grounding boreholes with cement mortar with Portland cement PC 45 and
56 631 t
a mixing mass ratio of cement and gravel 1 : 0.5
Grounding boreholes with cement mortar with Portland cement PC 45 and
56 632 t
a mixing mass ratio of cement and gravel 1 : 1
Grounding boreholes with cement mortar with Portland cement PC 45 and
56 633 t
a mixing mass ratio of cement and gravel 1 : 2
56 711 t Grouting rock-bolt with cement suspension with Portland cement PC 25
56 712 t Grouting rock-bolt with cement suspension with Portland cement PC 35
56 713 t Grouting rock-bolt with cement suspension with Portland cement PC 45
56 714 t Grouting rock-bolt with cement suspension with Portland cement PC 55
Grouting rock–bolts with cement suspension with Portland cement,
56 721 t
resistant against sulphates

Draft of Version 1 – March 2008 Page 125


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Grounding rock-bolts with cement suspension with Portland cement and
56 731 t
pozzolan additive PC 15 p 25
Grounding rock-bolts with cement suspension with Portland cement and
56 732 t
pozzolan additive PC 15 p 35
Grounding rock-bolts with cement suspension with Portland cement and
56 733 t
pozzolan additive PC 15 p 45
Grounding rock-bolts with cement suspension with Portland cement and
56 734 t
pozzolan additive PC 30 p 25
Grounding rock-bolts with cement suspension with Portland cement and
56 735 t
pozzolan additive PC 30 p 35
Grounding rock-bolts with cement suspension with Portland cement and
56 736 t
pozzolan additive PC 30 p 45
Grounding rock-bolts with cement mortar with Portland cement PC 25 and
56 811 t
a mixing mass ratio of cement and sand 1 : 0.5
Grounding rock-bolts with cement mortar with Portland cement PC 25 and
56 812 t
a mixing mass ratio of cement and sand 1 : 1
Grounding rock-bolts with cement mortar with Portland cement PC 25 and
56 813 t
a mixing mass ratio of cement and sand 1 : 2
Grounding rock-bolts with cement mortar with Portland cement PC 35 and
56 821 t
a mixing mass ratio of cement and sand 1 : 0.5
Grounding rock-bolts with cement mortar with Portland cement PC 35 and
56 822 t
a mixing mass ratio of cement and sand 1 : 1
Grounding rock-bolts with cement mortar with Portland cement PC 35 and
56 823 t
a mixing mass ratio of cement and sand 1 : 2
Grounding rock-bolts with cement mortar with Portland cement PC 45 and
56 831 t
a mixing mass ratio of cement and sand 1 : 0.5
Grounding rock-bolts with cement mortar with Portland cement PC 45 and
56 832 t
a mixing mass ratio of cement and sand 1 : 1
Grounding rock-bolts with cement mortar with Portland cement PC 45 and
56 833 t
a mixing mass ratio of cement and sand 1 : 2

Draft of Version 1 – March 2008 Page 126


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

5.4.3 Waterproofing

Unit
Code Description of work
measure
Manufacture of under (preliminary) coating with bituminous binding
57 111 m2
solution, average consumption to 0.2 kg/ m2
Manufacture of under (preliminary) coating with bituminous binding
57 112 m2
solution, average consumption 0.2–0.3 kg/ m2
Manufacture of under (preliminary) coating with bituminous binding
57 113 m2
solution, average consumption over 0.3 kg/ m2
Manufacture of undercoat with bituminous emulsion, average consumption
57 121 m2
to 0.2 kg/ m2
Manufacture of undercoat with bituminous emulsion, average consumption
57 122 m2
0.2–0.3 kg/ m2
Manufacture of undercoat with bituminous emulsion, average consumption
57 123 m2″
over 0.3 kg/ m2
Preparation and installation of adhesive bituminous mixture, average
57 211 m2
consumption to 0.2 kg/ m2
Preparation and installation of adhesive bituminous mixture, average
57 212 m2
consumption 0.2–0.3 kg/ m2
Preparation and installation of adhesive bituminous mixture, average
57 213 m2
consumption over 0.3 kg/ m2
Preparation and installation of bituminous adhesive tapes with glass fibre
57 311 m2
textile, thickness to 3 mm
Preparation and installation of bituminous adhesive tapes with glass fibre
57 312 m2
textile, thickness 4 mm
Preparation and installation of bituminous adhesive tapes with glass fibre
57 313 m2
textile, thickness 5 mm
Preparation and installation of welded bitumen tape with glass fibre textile,
57 321 m2
thickness to 3 mm
Preparation and installation of welded bitumen tape with glass fibre textile,
57 322 m2
thickness 4 mm
Preparation and installation of welded bitumen tape with glass fibre textile,
57 323 m2
thickness 5 mm
Preparation and installation of adhesive bitumen tape with glass fibre
57 331 m2
textile and aluminum foil thickness to 3 mm
Preparation and installation of adhesive bitumen tape with glass fibre
57 332 m2
textile and aluminum foil thickness 4 mm

Draft of Version 1 – March 2008 Page 127


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Preparation and installation of adhesive bitumen tape with glass fibre
57 333 m2
textile and aluminum foil thickness 5 mm
Preparation and installation of designed aluminum foil tape, width 200
57 351 m2
mm, to thickness of 0.1 mm
Preparation and installation of welded bitumen tape with aluminum foil,
57 361 m
width 200 mm, thickness to 1.5 mm
Preparation and installation of welded bitumen tape with aluminum foil,
57 362 m
width 200 mm, thickness to 2.0 mm
Preparation and installation of welded bitumen tape with aluminum foil,
57 363 m
width 200 mm, thickness to 2.5 mm
Manufacture of waterproof from layer bituminous mastic (in two layers),
57 411 m2
with a protective layer from bituminous paperboard, thickness to 17 mm
Manufacture of waterproof from layer bituminous mastic (in two layers),
57 412 m2 with a protective layer from bituminous paperboard, thickness over 17–
20 mm
Manufacture of waterproof layer from modified bitumen in thickness to
57 511 m2
1 mm
Manufacture of waterproof layer from modified bitumen in thickness 1–2
57 512 m2
mm
Manufacture of waterproof layer from modified bitumen, reinforced with felt
57 521 m2
from PE fibres, in thickness to 1 mm
Manufacture of waterproof layer from modified bitumen, reinforced with felt
57 522 m2
from PE fibres, in thickness 1–2 mm
Manufacture of waterproof layer from modified bitumen, reinforced with felt
57 523 m2
from PE fibres, in thickness 2–3 mm
Manufacture of waterproof layer from modified bitumen, reinforced with
57 531 m2
glass fibre textiles, in thickness to 1 mm
Manufacture of waterproof layer from modified bitumen, reinforced with
57 532 m2
glass fibre textiles, in thickness 1–2 mm
Manufacture of waterproof layer from modified bitumen, reinforced with
57 533 m2
glass fibre textiles, in thickness 2–3 mm
Manufacture of waterproof layer with artificial liquid agents in an average
57 611 m2
in thickness to 2.0 mm
Manufacture of waterproof layer with artificial liquid agents in an average
57 612 m2
in thickness 2.0–2.5 mm
Manufacture of waterproof layer with artificial liquid agents in an average
57 613 m2
in thickness 2.5–3.0 mm
57 621 m2 Manufacture of waterproof layer from polymeric foil, thickness to 1.5 mm

Draft of Version 1 – March 2008 Page 128


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
57 622 m2 Manufacture of waterproof layer from polymeric foil, thickness 1.5–2.0 mm
57 623 m2 Manufacture of waterproof layer from polymeric foil, thickness 2.0–2.5 mm
2
57 711 m Manufacture of partitioning layers from felt with mass of 300 g / m2
57 712 m2 Manufacture of partitioning layers from felt with mass of 400 g / m2
57 713 m2 Manufacture of partitioning layers from felt with mass of 500 g / m2
Manufacture of protective layer of bituminous concrete from granule
57 811 m2
mixture of 0 / 8 mm from carbonate rock, in thickness to 3.0 cm
Manufacture of protective layer of bituminous concrete from granule
57 812 m2
mixture of 0 / 8 mm from carbonate rock, in thickness to 4.0 cm
Manufacture of protective layer of bituminous concrete from granule
57 821 m2
mixture of 0 / 11 mm from carbonate rock, in thickness to 3.0 cm
Manufacture of protective layer of bituminous concrete from granule
57 822 m2
mixture of 0 / 11 mm from carbonate rock, in thickness to 4.0 cm
Manufacture of protective layer of poured asphalt from granule mixture of
57 831 m2
0 / 11 mm from carbonate rock, in thickness to 3.0 cm
Manufacture of protective layer of poured asphalt from granule mixture of
57 832 m2
0 / 11 mm from carbonate rock, in thickness to 4.0 cm
Manufacture of protective layers from cement mortar 1:4, in thickness of
57 841 m2
4 cm
Manufacture of protective layers from cement mortar 1:4, in thickness of
57 842 m2
5 cm
Manufacture of protective layers from cement mortar 1:4, in thickness of
57 843 m2
6 cm
Waterproofing of border vertical surfaces (seams) of protective layers with
57 911 m a preliminary coating and a bituminous mixture poured in thickness to
15 mm
Waterproofing of border vertical surfaces (seams) of protective layers with
57 912 m a preliminary coating and a bituminous mixture poured in thickness 15–20
mm
Waterproofing of border vertical surfaces (seams) of protective layers with
57 913 m a preliminary coating and a bituminous mixture poured in thickness 20–25
mm
Waterproofing of border vertical surfaces (seams) of protective layers with
57 914 m a preliminary coating and a bituminous mixture poured in thickness 25–30
mm
Waterproofing of borders of vertical surfaces of protective layers with
57 921 m
bituminous sealing tape

Draft of Version 1 – March 2008 Page 129


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Waterproofing borders of horizontal surfaces of protective layers, 100 mm
57 931 m
in width, with a bituminous mixture that can be poured

5.5 Metalwork

Unit
Code Description of work
measure
Manufacture and preparation for installing supporting constructions of
58 111 m
guards rails (by design) from steel tubes with a circular section
Manufacture and preparation for installing supporting constructions of
58 112 m
guards rails (by design) from steel tubes with a rectangular section
Manufacture and preparation for installing supporting constructions of
58 121 m
safety rails from aluminum tubes with a circular section
Manufacture and preparation for installing supporting constructions of
58 122 m
safety rails from aluminum tubes with a rectangular section
Manufacture and installation of struts for guard rails (by design) from
58 131 m2
horizontal or vertical steel rods, mass to 10 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 132 m2
horizontal or vertical steel rods, mass 10.5–12 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 133 m2
horizontal or vertical steel rods, mass 12.5–14 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 134 m2
horizontal or vertical steel rods, mass 14.5–16 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 135 m2
horizontal or vertical steel rods, mass over 16 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 141 m2
horizontal or vertical aluminum rods, mass to 10 kg / m2
Manufacture and installation of struts for guard rails (by design) from
58 142 m2
horizontal or vertical aluminum rods, mass 10.5–12 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 143 m2
horizontal or vertical aluminum rods, mass 12.5–14 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 144 m2
horizontal or vertical aluminum rods, mass 14.5–16 kg/m2
Manufacture and installation of struts for guard rails (by design) from
58 145 m2
horizontal or vertical aluminum rods, mass over 16 kg/m2

Draft of Version 1 – March 2008 Page 130


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Manufacture and installation of closed struts for guard rails (by design)
58 151 m2
from steel sheet metal
Manufacture and installation of closed struts for guard rails (by design)
58 152 m2
from aluminum sheet metal
Manufacture and installation of guard rails, protection against electric
58 161 m2
current passing over railway lines
Manufacture and protection for installing provisional (dilatational)
58 211 m
constructions (by the design) without clearance
Manufacture and protection for installing provisional (dilatational)
58 212 m
constructions (by the design) with T section, open
Manufacture and protection for installing provisional (dilatational)
58 213 m
constructions (by the design) with T section, sealed with neoprene tape
Manufacture and protection for installing provisional (dilatational)
58 214 m
constructions (by the design) with T section, sealed with rubber tape
Manufacture and protection for installing provisional (dilatational)
58 215 m
constructions (by the design) with distancer
Manufacture and protection for installing provisional (dilatational)
58 216 m
constructions (by the design) with sliding sheet metal
Manufacture and protection for installing provisional (dilatational)
58 217 m
constructions (by the design) with member boards on rollers
Supply and preparation for installing (by the design) fixed linear rotating
58 311 Piece
bearing
Supply and preparation for installing (by the design) fixed point rotating
58 312 Piece
bearing
58 313 Piece Supply and preparation for installing (by the design) fixed cup bearing
Supply and preparation for installing (by the design) fixed armored
58 314 Piece
cylindric bearing
Supply and preparation for installing (by the design) fixed member
58 315 Piece
bearing from cement concrete
Supply and preparation for installing (by the design) fixed elastomeric
58 316 Piece
block bearing
Supply and preparation for installing (by design) one–way point rotating
58 321 Piece
bearings
58 322 Piece Supply and preparation for installing (by design) one–cylinder bearings
58 323 Piece Supply and preparation for installing (by design) two–cylinder bearings
Supply and preparation (by the design) multi-directional mobile linear
59 331 Piece
rotating (PTFE) slide bearing

Draft of Version 1 – March 2008 Page 131


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and preparation (by the design) multi-directional mobile point
59 332 Piece
rotating (PTFE) slide bearing
Supply and preparation (by the design) multi-directional mobile cup
59 333 Piece
(PTFE) slide bearing
Supply and preparation (by the design) multi-directional mobile
59 334 Piece
elastomeric block bearing
Supply and preparation (by the design) multi-directional mobile
59 335 Piece
elastomeric (PTFE) slide bearing
Supply and preparation (by the design) multi-directional mobile calotte
59 336 Piece
bearing
Supply and preparation for installment (by design) tensile- compressive
58 341 Piece
pre- stressed bearing type 1
Supply and preparation for installment (by design) tensile- compressive
58 342 Piece
pre- stressed bearing type 2
Supply and preparation for installing (by design) bearings for taking over
58 351 Piece
vertical forces
58 361 Piece Supply and preparation for installment (by design) of shear pins
58 371 Piece Supply and preparation for installment (by design) of guiding bearing
Supply and preparation for installment of edges (final section) with tie-
58 411 m
bars and reinforcements (by the design) from L sections 40/40/4 mm
Supply and preparation for installment of edges (final section) with tie-
58 412 m
bars and reinforcements (by the design) from L sections 50/50/5 mm
Supply and preparation for installment of edges (final section) with tie-
58 413 m
bars and reinforcements (by the design) from L sections 60/60/6 mm
Supply and preparation for installment of edges (final section) with tie-
58 414 m
bars and reinforcements (by the design) from L sections 70/70/7 mm
Supply and preparation for installment of edges (final section) with tie-
58 415 m
bars and reinforcements (by the design) from L sections 80/80/8 mm
Supply and preparation for installment of edges (final section) with tie
58 421 m
bars and reinforcements (by the design) from sections T–80
Supply and preparation for installment of edges (final section) with tie
58 422 m
bars and reinforcements (by the design) from sections T–100
Supply and preparation for installment of edges (final section) with tie
58 423 m
bars and reinforcements (by the design) from sections T–120
Supply and preparation for installment of edges (final section) with tie
58 424 m
bars and reinforcements (by the design) from sections T–140
Supply and preparation for installment of edges (final section) with tie
58 425 m
bars and reinforcements (by the design) from sections T–160

Draft of Version 1 – March 2008 Page 132


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and preparation for installment of edges (final section) with tie
58 431 m
bars and reinforcements (by the design) from half sections I – 160
Supply and preparation for installment of edges (final section) with tie
58 432 m
bars and reinforcements (by the design) from half sections I – 180
Supply and preparation for installment of edges (final section) with tie
58 433 m
bars and reinforcements (by the design) from half sections I – 200
Supply and preparation for installment of edges (final section) with tie
58 434 m
bars and reinforcements (by the design) from half sections I – 220
Supply and preparation for installment of edges (final section) with tie
58 435 m
bars and reinforcements (by the design) from half sections I – 240
Supply and preparation for installment of edges (final section) with tie
58 441 m
bars and reinforcements (by the design) from flat iron 50/5 mm
Supply and preparation for installment of edges (final section) with tie
58 442 m
bars and reinforcements (by the design) from flat iron 60/5 mm
Supply and preparation for installment of edges (final section) with tie
58 443 m
bars and reinforcements (by the design) from flat iron 70/5 mm
Supply and preparation for installment of edges (final section) with tie
58 444 m
bars and reinforcements (by the design) from flat iron 80/6 mm
Supply and preparation for installment of edges (final section) with tie
58 445 m
bars and reinforcements (by the design) from flat iron 90/6 mm
Supply and preparation for installment of edges (final section) with tie
58 446 m
bars and reinforcements (by the design) from flat iron 100/6 mm
58 511 t Tracks for inspection trolley
58 521 Piece Section for protection against contact made from angle iron 60/60/6 mm
58 522 Piece Section for protection against contact made from flat iron 60/5 mm
58 531 Piece Plug for additional installation of protection sections against contact
58 541 Piece Tie-bars for fixing the earthing and a protective section against contact
58 611 t Inspection corridor, 600 mm wide, 1100 mm high
58 621 m Climbing ladder, without safety basket
58 621 m Climbing ladder, with safety basket
58 623 Piece Tie-bars for fixing climbing ladder
58 624 Piece Climbing iron
58 631 Piece One-wing steel door with ventilation grid
58 632 Piece One-wing steel door without ventilation grid
58 641 Piece Ventilation grids ……. x…….mm

Draft of Version 1 – March 2008 Page 133


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

5.6 Protection of Metal Against Corrosion

Unit
Code Description of work
measure
59 111 m2 Manual degreasing of metal surfaces with organic solute
2
59 112 m Manual degreasing of metal surfaces with organic solute with tensides
2
59 121 m Machine degreasing of metal surfaces with organic solute
2
59 122 m Machine degreasing of metal surfaces with tensides
2
59 131 m Cleaning metal surfaces with sharp edged abrasives
2
59 132 m Cleaning metal surfaces with rounded abrasives
2
59 133 m Cleaning metal surfaces with siliceous sand
2
59 134 m Cleaning metal surfaces with granulated furnace slag
2
59 141 m Cleaning metal surfaces by torching
2
59 151 m Cleaning metal surfaces with acid solution
2
59 152 m Cleaning metal surfaces with lye solution
2
59 161 m Machine cleaning of metal surfaces
2
59 171 m Manual cleaning of metal surfaces
2
59 181 m Dusting of cleaned metal surfaces with jets of compressed dry air
2
59 191 m Preliminary protection of metal surfaces with wash primer
2
59 192 m Preliminary protection of metal surfaces with rising agent
2
59 193 m Preliminary protection of metal surfaces with etch primer
59 211 m2 Manufacture of workshop coating with unreathed oil
2
59 212 m Manufacture of workshop coating with alkyne resin
59 213 m2 Manufacture of workshop coating with epoxy – ester resin
2
59 221 m Manufacture of workshop coating with chloride – rubber
59 222 m2 Manufacture of workshop coating with vinylchloride – copolymers
2
59 231 m Manufacture of workshop coating with polyvinyl – butyral
59 241 m2 Manufacture of workshop coating with epoxy
2
59 242 m Manufacture of workshop coating with epoxy - polyurethane
59 251 m2 Manufacture of workshop coating with alkali – silicate
2
59 252 m Manufacture of workshop coating with silicate esters
59 311 m2 Protection with basic coat of red lead
2
59 312 m Protection with basic coat of of zinc chromate
59 313 m2 Protection with basic coat of of zinc dust
2
59 314 m Protection with basic coat of oily, with red lead
59 315 m2 Protection with basic coat of with calcium plumbate

Draft of Version 1 – March 2008 Page 134


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
59 321 m2 Protection of basic coating with hot bitumen
59 332 m2 Protection with basic coating from alkali – silicate
2
59 333 m Protection with basic coating from ethyl – silicate
59 341 m2 Protection with basic or top coat with alkyd resin
2
59 342 m Protection with basic or top coat with epoxy – ester resin
59 351 m2 Protection with basic or top coat with chloride rubber
2
59 352 m Protection with basic or top coat with vinylchloride – copolymers
59 361 m2 Protection with under or top coat of epoxides
2
59 362 m Protection with epoxy – polyurethane
2
59 371 m Protection finish with titanic dioxide
2
59 372 m Protection finish with iron oxide
2
59 373 m Protection finish with oily, with iron oxide
2
59 381 m Protective coating with topcoat of bitumen
2
59 382 m Protective coating with topcoat of tar
2
59 383 m Protective coating with t topcoat of tar with filling
2
59 384 m Protective coating with topcoat of bitumen and aluminum dust
2
59 391 m Protection with topcoat of tar – epoxides
2
59 392 m Protection with topcoat of tar – polyurethane
2
59 411 m Protection with hot- dip galvanising, average thickness, 37 µm
2
59 412 m Protection with hot- dip galvanising, average thickness, 43 µm
2
59 413 m Protection with hot- dip galvanising, average thickness, 54 µm
2
59 414 m Protection with hot- dip galvanising, average thickness, 57 µm
2
59 415 m Protection with hot- dip galvanising, average thickness, 71 µm
2
59 416 m Protection with hot- dip galvanising, average thickness, 86 µm
2
59 417 m Protection with hot- dip galvanising, average thickness, … µm
2
59 511 m Protective finish of metal with zinc, thickness at least 40 µm
2
59 512 m Protective finish of metal with zinc, thickness at least 80 µm
2
59 513 m Protective finish of metal with zinc, thickness at least 120 µm
2
59 514 m Protective finish of metal with zinc, thickness at least 200 µm
2
59 515 m Protective finish of metal with zinc, thickness at least….. µm
59 521 m2 Protective finish of metal with aluminum, thickness at least 120 µm
2
59 522 m Protective finish of metal with aluminum, thickness at least 200 µm
59 523 m2 Protective finish of metal with aluminum, thickness at least 300 µm
2
59 524 m Protective finish of metal with aluminum, thickness at least ….. µm
59 531 m2 Protective finish of metal with lead, thickness at least 300 µm

Draft of Version 1 – March 2008 Page 135


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
59 532 m2 Protective finish of metal with lead, thickness at least 500 µm
59 533 m2 Protective finish of metal with lead, thickness at least 1000 µm
2
59 534 m Protective finish of metal with lead, thickness at least ….. µm
59 611 Piece Cathode protection of structure with anodes
59 612 Piece Cathode protection of structure with an exterior source of energy
59 621 Piece Cathode protection of structure with galvanic anodes
59 622 Piece Cathode protection of structure
Basic protection with self - adhesive tape from polyethylene foil, thickness
59 711 m2
0.3 mm
59 712 m2 Basic protection with self 0.4 mm
2
59 713 m Basic protection with self 0.5 mm
59 714 m2 Basic protection with self . . . mm

Draft of Version 1 – March 2008 Page 136


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

6 Road Equipment

6.1 Roadside and Overhead Road Equipment

Unit
Code Description of work
measure
61 111 Piece Construction of foundation of cement concrete MB 10, 50 cm long Ø 20 cm
61 112 Piece Construction of foundation of cement concrete MB 10, 50 cm long Ø 30 cm
61 113 Piece Construction of foundation of cement concrete MB 10, 50 cm long Ø 40 cm
61 114 Piece Construction of foundation of cement Ø 50 cm concrete MB 10, 50 cm long
61 115 Piece Construction of foundation of cement concrete MB 10, 50 cm long Ø . . cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 121 Piece
Ø 20 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 122 Piece
Ø 30 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 123 Piece
Ø 40 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 124 Piece
Ø 50 cm
61 125 Piece Construction of foundation of cement concrete MB 10, 80 cm long, Ø . . cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 131 Piece
Ø 20 cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 132 Piece
Ø 30 cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 133 Piece
Ø 40 cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 134 Piece
Ø 50 cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 135 Piece
Ø 60 cm
Construction of foundation of cement concrete MB 10, 100 cm long, Ø .
61 136 Piece
. cm
Construction of foundation of cement concrete MB 10, 50 cm long,
61 141 Piece
Ø 20 cm
Construction of foundation of cement concrete MB 10, 50 cm long,
61 142 Piece
Ø 30 cm
Construction of foundation of cement concrete MB 10, 50 cm long,
61 143 Piece
Ø 40 cm

Draft of Version 1 – March 2008 Page 137


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of foundation of cement concrete MB 10, 50 cm long,
61 144 Piece
Ø 50 cm
61 145 Piece Construction of foundation of cement concrete MB 10, 50 cm long, Ø . . cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 151 Piece
Ø 20 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 152 Piece
Ø 30 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 153 Piece
Ø 40 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 154 Piece
Ø 50 cm
Construction of foundation of cement concrete MB 10, 80 cm long,
61 155 Piece
Ø 60 cm
61 156 Piece Construction of foundation of cement concrete MB 10, 80 cm long, Ø . . cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 161 Piece
Ø 20 cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 162 Piece
Ø 30 cm
Construction of foundation of cement Ø 40 cm concrete MB 10, 100 cm
61 163 Piece
long,
Construction of foundation of cement concrete MB 10, 100 cm long,
61 164 Piece
Ø 50 cm
Construction of foundation of cement concrete MB 10, 100 cm long,
61 165 Piece
Ø 60 cm
Construction of foundation of cement concrete MB 10, 100 cm long, Ø .
61 166 Piece
. cm
Construction of foundation of cement concrete MB 15, up to 0.10 m3 /
61 171 m3
foundation
Construction of foundation of cement concrete MB 15, from 0.11 to 0.20
61 172 m3
m3 / foundation
Construction of foundation of cement concrete MB 15, from 0.21 to 0.40
61 173 m3
m3 / foundation
Construction of foundation of cement concrete MB 15, from 0.41 to 0.80
61 174 m3
m3 / foundation
Construction of foundation of cement concrete MB 15, more than 0.80 m3 /
61 175 m3
foundation
Construction of foundation of cement concrete MB 10, up to 0.10 m3 /
61 181 m3
foundation

Draft of Version 1 – March 2008 Page 138


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of foundation of cement concrete MB 10, from 0.11 to
61 182 m3
0.20 m3 / foundation
Construction of foundation of cement concrete MB 10, from 0.21 to
61 183 m3
0.40 m3 / foundation
Construction of foundation of cement concrete MB 10, from 0.41 to
61 184 m3
0.80 m3 / foundation
Construction of foundation of cement concrete MB 10, more than 0.80 m3 /
61 185 m3
foundation
Construction of reinforced concrete foundation for vertical post, as per
61 191 Piece
drawing ………………
Construction of reinforced concrete foundation for vertical post, as per
61 192 Piece
drawing ………………
Construction of reinforced concrete foundation for cantilever post, as per
61 193 Piece
drawing ………………
Construction of reinforced concrete foundation for cantilever post, as per
61 194 Piece
drawing ………………
Construction of reinforced concrete foundation for semi- portal, as per
61 195 Piece
drawing ………………
Construction of reinforced concrete foundation for semi- portal, as per
61 196 Piece
drawing ………………
Construction of reinforced concrete foundation for portal, as per drawing
61 197 Piece
………………
Construction of reinforced concrete foundation for portal, as per drawing
61 198 Piece
………………
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 211 Piece
length 1000 mm
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 212 Piece
length 1200 mm
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 213 Piece
length 1500 mm
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 214 Piece
length 2000 mm
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 215 Piece
length 2500 mm
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 216 Piece
length 3000 mm
Supply and erection of traffic sign post of painted steel pipe Ø 51 mm,
61 217 Piece
length . . . . mm

Draft of Version 1 – March 2008 Page 139


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 221 Piece
length 1000 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 222 Piece
length 1200 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 223 Piece
length 1500 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 224 Piece
length 2000 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 225 Piece
length 2500 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 226 Piece
length 3000 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 227 Piece
length 3500 mm
Supply and erection of traffic sign post of painted steel pipe Ø 64 mm,
61 228 Piece
length . . . . mm
Supply and erection of traffic sign post of hot- galvanised steel pipe Ø 51
61 231 Piece
mm, length 1000 mm
61 232 Piece Supply and erection of traffic sign post of hot length 1200 mm
61 233 Piece Supply and erection of traffic sign post of hot length 1500 mm
61 234 Piece Supply and erection of traffic sign post of hot length 2000 mm
61 235 Piece Supply and erection of traffic sign post of hot length 2500 mm
61 236 Piece Supply and erection of traffic sign post of hot length 3000 mm
61 237 Piece Supply and erection of traffic sign post of hot length . . . . mm
Supply and erection of traffic sign post of hot- galvanised steel pipe
61 241 Piece
Ø 64 mm, length 1000 mm
61 242 Piece Supply and erection of traffic sign post of hot length 1200 mm
61 243 Piece Supply and erection of traffic sign post of hot length 1500 mm
61 244 Piece Supply and erection of traffic sign post of hot length 2000 mm
61 245 Piece Supply and erection of traffic sign post of hot length 2500 mm
61 246 Piece Supply and erection of traffic sign post of hot length 3000 mm
61 247 Piece Supply and erection of traffic sign post of hot length 3500 mm
61 248 Piece Supply and erection of traffic sign post of hot length . . . . mm
Supply and erection of traffic sign post of plastic - coated steel pipe
61 251 Piece
Ø 51 mm, length 1000 mm
61 252 Piece Supply and erection of traffic sign post of plastic length 1200 mm
61 253 Piece Supply and erection of traffic sign post of plastic length 1500 mm

Draft of Version 1 – March 2008 Page 140


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
61 254 Piece Supply and erection of traffic sign post of plastic length 2000 mm
61 255 Piece Supply and erection of traffic sign post of plastic length 2500 mm
61 256 Piece Supply and erection of traffic sign post of plastic length 3000 mm
61 257 Piece Supply and erection of traffic sign post of plastic length . . . . mm
Supply and erection of traffic sign post of hot- galvanised steel pipe
61 261 Piece
Ø 64 mm, length 1000 mm
61 262 Piece Supply and erection of traffic sign post of hot length 1200 mm
61 263 Piece Supply and erection of traffic sign post of hot length 1500 mm
61 264 Piece Supply and erection of traffic sign post of hot length 2000 mm
61 265 Piece Supply and erection of traffic sign post of hot length 2500 mm
61 266 Piece Supply and erection of traffic sign post of hot length 3000 mm
61 267 Piece Supply and erection of traffic sign post of hot length 3500 mm
61 268 Piece Supply and erection of traffic sign post of hot length . . . . mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 271 Piece
length 1000 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 272 Piece
length 1200 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 273 Piece
length 1500 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 274 Piece
length 2000 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 275 Piece
length 2500 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 276 Piece
length 3000 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 277 Piece
length 3500 mm
Supply and erection of traffic sign post of ……………………. Ø (‫ )ٱ‬. . . . .,
61 278 Piece
length . . . . mm
Supply and erection of vertical traffic light signal support of protected steel
61 311 kg
pipe, as per drawing……………….., length 3000 mm
Supply and erection of vertical traffic light signal support of protected steel
61 312 kg
pipe, as per drawing……………….., length 3500 mm
Supply and erection of vertical traffic light signal support of protected steel
61 313 kg
pipe, as per drawing……………….., length . . . . mm

Draft of Version 1 – March 2008 Page 141


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 321 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 4000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 322 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 4500 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 323 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 5000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 324 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 5500 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 325 kg of protected steel pipe, as per drawing ………………, height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 6000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 326 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 6500 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 327 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 7000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 328 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = . . . . mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 331 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 4000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 332 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 5000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 333 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 6000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 334 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = 7000 mm
Supply and erection of cantilever post for illuminated traffic sign and lamp,
61 335 kg of protected steel pipe, as per drawing ……………., height H = . . . . mm,
headroom (under the sign h = 5200 mm ), cantilever length L = . . . . mm

Draft of Version 1 – March 2008 Page 142


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of supporting frame for traffic sign, of hot-galvanised
61 341 kg
steel pipe, as per drawing …………
Supply and erection of supporting frame for traffic sign, of hot-galvanised
61 342 kg
steel pipe, as per drawing …………
Supply and erection of supporting frame for traffic sign, of hot-galvanised
61 343 kg
steel pipe, as per drawing …………
Supply and erection of supporting frame for traffic sign, of plastic- coated
61 346 kg
steel pipe, as per drawing …………
Supply and erection of supporting frame for traffic sign, of plastic as per
61 347 kg
drawing …………
Supply and erection of supporting frame for traffic sign, of plastic as per
61 348 kg
drawing …………
Supply and erection of semi - portal, of hot- galvanised steel, for mild
61 351 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 5000 mm
Supply and erection of semi - portal, of hot- galvanised steel, for mild
61 352 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 6000 mm
Supply and erection of semi - portal, of hot- galvanised steel, for mild
61 353 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 7000 mm
Supply and erection of semi - portal, of hot- galvanised steel, for mild
61 354 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = . . . . mm
Supply and erection of semi - portal, of hot- galvanised steel, for severe
61 356 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 5000 mm
Supply and erection of semi - portal, of hot- galvanised steel, for severe
61 357 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 6000 mm
Supply and erection of semi - portal, of hot- galvanised steel, for severe
61 358 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 7000 mm
Supply and erection of semi - portal, of hot- galvanised steel, for severe
61 359 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = . . . . mm
Supply and erection of T portal, of hot- galvanised steel, for mild
61 361 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 5000 mm

Draft of Version 1 – March 2008 Page 143


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of T portal, of hot- galvanised steel, for mild
61 362 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 6000 mm
Supply and erection of T portal, of hot- galvanised steel, for mild
61 363 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 7000 mm
Supply and erection of T portal, of hot- galvanised steel, for mild
61 364 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = . . . . mm
Supply and erection of T portal, of hot- galvanised steel, for severe
61 365 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 5000 mm
Supply and erection of T portal, of hot- galvanised steel, for severe
61 366 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 6000 mm
Supply and erection of T portal, of hot- galvanised steel, for severe
61 367 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 7000 mm
Supply and erection of T portal, of hot- galvanised steel, for severe
61 368 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = . . . . mm
Supply and erection of portal, of hot- galvanised steel, for mild conditions,
61 371 kg as per drawing …………. , headroom H = 5200 mm, cantilever length L =
12000 mm
Supply and erection of portal, of hot- galvanised steel, for mild conditions,
61 372 kg as per drawing …………. , headroom H = 5200 mm, cantilever length L =
15000 mm
Supply and erection of portal, of hot- galvanised steel, for mild conditions,
61 373 kg as per drawing …………. , headroom H = 5200 mm, cantilever length L =
20000 mm
Supply and erection of portal, of hot- galvanised steel, for mild conditions,
61 374 kg as per drawing …………. , headroom H = 5200 mm, cantilever length L =
25000 mm
Supply and erection of portal, of hot- galvanised steel, for mild conditions,
61 375 kg as per drawing …………. , headroom H = 5200 mm, cantilever length L = .
. . . . mm
Supply and erection of portal, of hot- galvanised steel, for severe
61 381 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 12000 mm

Draft of Version 1 – March 2008 Page 144


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of portal, of hot- galvanised steel, for severe
61 382 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 15000 mm
Supply and erection of portal, of hot- galvanised steel, for severe
61 383 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 20000 mm
Supply and erection of portal, of hot- galvanised steel, for severe
61 384 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = 25000 mm
Supply and erection of portal, of hot- galvanised steel, for severe
61 385 kg conditions, as per drawing …………. , headroom H = 5200 mm, cantilever
length L = . . . . . mm
61 391 kg Extra payment for cantilever, as per drawing, length L = 3000 mm
61 392 kg Extra payment for cantilever, as per drawing, length L = 4000 mm
61 393 kg Extra payment for cantilever, as per drawing, length L = 5000 mm
61 394 kg Extra payment for cantilever, as per drawing, length L = . . . . mm
61 396 Piece Supply of tripod base for traffic sign stand, as per drawing ……………..
61 397 Piece Supply of tripod base for traffic sign stand, as per drawing ……………..
Supply of four-legged base for traffic sign stand, as per drawing
61 398 Piece
……………..
Supply of four-legged base for traffic sign stand, as per drawing
61 399 Piece
……………..
Supply and mounting of triangular traffic sign, hot-galvanised steel sheet
61 411 Piece
backing, with 1st class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel sheet
61 412 Piece
backing, with 1st class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel sheet
61 413 Piece
backing, with 1st class reflecting foil sign, length of side a = 1200 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel sheet
61 421 Piece
backing, with 2nd class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel sheet
61 422 Piece
backing, with 2nd class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel sheet
61 423 Piece
backing, with 2nd class reflecting foil sign, length of side a = 1200 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel housing
61 431 Piece
internally illuminated, reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, hot-galvanised steel housing
61 432 Piece
internally illuminated, reflecting foil sign, length of side a = 900 mm

Draft of Version 1 – March 2008 Page 145


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of triangular traffic sign, hot-galvanised steel housing
61 433 Piece
internally illuminated, reflecting foil sign, length of side a = 1200 mm
Supply and mounting of triangular traffic sign, aluminum sheet backing,
61 441 Piece
with 1st class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, aluminum sheet backing,
61 442 Piece
with 1st class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, aluminum sheet backing,
61 443 Piece
with 1st class reflecting foil sign, length of side a = 1200 mm
Supply and mounting of triangular traffic sign, aluminum sheet backing,
61 451 Piece
with 2nd class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, aluminum sheet backing,
61 452 Piece
with 2nd class reflecting foil sign, length of side a = 900 mm
Supply and mounting of triangular traffic sign, aluminum sheet backing,
61 453 Piece
with 2nd class reflecting foil sign, length of side a = 1200 mm
Supply and mounting of triangular traffic sign, aluminum sheet housing,
61 461 Piece
internally illuminated, length of side a = 900 mm
Supply and mounting of triangular traffic sign, aluminum sheet housing,
61 462 Piece
internally illuminated, length of side a = 900 mm
Supply and mounting of triangular traffic sign, aluminum sheet housing,
61 463 Piece
internally illuminated, length of side a = 1200 mm
Supply and mounting of triangular traffic sign, glass- reinforced polyester,
61 471 Piece
internally illuminated, length of side a = 900 mm
Supply and mounting of triangular traffic sign, glass- reinforced polyester,
61 472 Piece
internally illuminated, length of side a = 900 mm
Supply and mounting of triangular traffic sign, glass- reinforced polyester,
61 473 Piece
internally illuminated, length of side a = 1200 mm
Supply and mounting of simple St. Andrew’s cross, backing sheet of
61 511 Piece
………… , size 1000 x 120 mm, with ordinary paint coating
Supply and mounting of simple St. Andrew’s cross, backing sheet of
61 512 Piece
………… , size 1000 x 120 mm, with unreflecting foil
Supply and mounting of simple St. Andrew’s cross, backing sheet of
61 513 Piece
………… , size 1000 x 120 mm, with 1st class reflecting foil
Supply and mounting of simple St. Andrew’s cross, backing sheet of
61 514 Piece
………… , size 1000 x 120 mm, with 2nd class reflecting foil
Supply and mounting of simple St. Andrew’s cross, backing sheet of
61 521 Piece
………… , size 1000 x 120 mm, with 1st class reflecting foil
Supply and mounting of simple St. Andrew’s cross, backing sheet of
61 522 Piece
………… , size 1000 x 120 mm, with 2nd class reflecting foil

Draft of Version 1 – March 2008 Page 146


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of “count down” markers for approaching concealed
61 531 Piece level crossing, backing sheet of ………………., size 300 x 1000 mm (3x),
with 1st class reflecting foil
Supply and mounting of “count down” markers for approaching concealed
61 532 Piece level crossing, backing sheet of ………………., size 300 x 1000 mm (3x),
with 2nd class reflecting foil
Supply and mounting of traffic sign, housing of ………………., single-face
61 541 Piece
internal illumination, size 600 x 600 mm
Supply and mounting of traffic sign, housing of ………………., single-face
61 542 Piece
internal illumination, size 600 x 900 mm
Supply and mounting of traffic sign, housing of ………………., single-face
61 543 Piece
internal illumination, size 900 x 900 mm
Supply and mounting of traffic sign, housing of ………………., single-face
61 544 Piece
internal illumination, size 1300 x 250 mm
Supply and mounting of traffic sign, housing of ………………., single-face
61 545 Piece
internal illumination, size 1600 x 350 mm
Supply and mounting of traffic sign, housing of ………………., single-face
61 546 Piece
internal illumination, size . . . . x . . . mm
Supply and mounting of traffic sign, housing of ………………., double-face
61 551 Piece
internal illumination, size 600 x 600 mm
Supply and mounting of traffic sign, housing of ………………., double-face
61 552 Piece
internal illumination, size 600 x 900 mm
Supply and mounting of traffic sign, housing of ………………., double-face
61 553 Piece
internal illumination, size 900 x 900 mm
Supply and mounting of traffic sign, housing of ………………., double-face
61 554 Piece
internal illumination, size 1300 x 250 mm
Supply and mounting of traffic sign, housing of ………………., double-face
61 555 Piece
internal illumination, size 1600 x 350 mm
Supply and mounting of traffic sign, housing of ………………., double-face
61 556 Piece
internal illumination, size . . . . x . . . mm
Supply and mounting of lighting fixture with luminous element 125 W for
61 561 Piece
external traffic sign illumination, as per drawing …………………….
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 611 Piece
backing, with 1st class reflecting foil sign, Ø 400 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 612 Piece
backing, with 1st class reflecting foil sign, Ø 600 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 613 Piece
backing, with 1st class reflecting foil sign, Ø 900 mm

Draft of Version 1 – March 2008 Page 147


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 621 Piece
backing, with 2nd class reflecting foil sign, Ø 400 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 622 Piece
backing, with 2nd class reflecting foil sign, Ø 600 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 623 Piece
backing, with 2nd class reflecting foil sign, Ø 900 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 631 Piece
backing, internally illuminated, Ø 400 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 632 Piece
backing, internally illuminated, Ø 600 mm
Supply and mounting of round traffic sign, hot-galvanised steel sheet
61 633 Piece
backing, internally illuminated, Ø 900 mm
Supply and mounting of round traffic sign, aluminum sheet backing, with
61 641 Piece
1st class reflecting foil sign, Ø 400 mm
Supply and mounting of round traffic sign, aluminum sheet backing, with
61 642 Piece
1st class reflecting foil sign, Ø 600 mm
Supply and mounting of round traffic sign, aluminum sheet backing, with
61 643 Piece
1st class reflecting foil sign, Ø 900 mm
Supply and mounting of round traffic sign, aluminum steel sheet backing,
61 651 Piece
with 2nd class reflecting foil sign, Ø 400 mm
Supply and mounting of round traffic sign, aluminum steel sheet backing,
61 652 Piece
with 2nd class reflecting foil sign, Ø 600 mm
Supply and mounting of round traffic sign, aluminum steel sheet backing,
61 653 Piece
with 2nd class reflecting foil sign, Ø 900 mm
Supply and mounting of round traffic sign, aluminum steel sheet backing,
61 661 Piece
internally illuminated, Ø 400 mm
Supply and mounting of round traffic sign, aluminum steel sheet backing,
61 662 Piece
internally illuminated, Ø 600 mm
Supply and mounting of round traffic sign, aluminum steel sheet backing,
61 663 Piece
internally illuminated, Ø 900 mm
Supply and mounting of round traffic sign, glass – reinforced polyester
61 671 Piece
housing, internally illuminated, Ø 400 mm
Supply and mounting of round traffic sign, glass – reinforced polyester
61 672 Piece
housing, internally illuminated, Ø 600 mm
Supply and mounting of round traffic sign, glass – reinforced polyester
61 673 Piece
housing, internally illuminated, Ø 900 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 711 Piece
sign with ………………… paint-foil, class ………, size 350 x 250 mm

Draft of Version 1 – March 2008 Page 148


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 712 Piece
sign with ………………… paint-foil, class ………, size 350 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 713 Piece
sign with ………………… paint-foil, class ………, size 400 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 714 Piece
sign with ………………… paint-foil, class ………, size 400 x 400 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 715 Piece
sign with ………………… paint-foil, class ………, size 400 x 600 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 716 Piece
sign with ………………… paint-foil, class ………, size 450 x 400 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 717 Piece
sign with ………………… paint-foil, class ………, size 500 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 718 Piece
sign with ………………… paint-foil, class ………, size 600 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 719 Piece
sign with ………………… paint-foil, class ………, size 600 x 600 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 721 Piece
sign with ………………… paint-foil, class ………, size 600 x 900 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 722 Piece
sign with ………………… paint-foil, class ………, size 750 x 750 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 723 Piece
sign with ………………… paint-foil, class ………, size 900 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 724 Piece
sign with ………………… paint-foil, class ………, size 900 x 900 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 725 Piece
sign with ………………… paint-foil, class ………, size 900 x 1350 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 726 Piece
sign with ………………… paint-foil, class ………, size 1000 x 500 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 727 Piece
sign with ………………… paint-foil, class ………, size 1000 x 750 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 728 Piece
sign with ………………… paint-foil, class ………, size 1200 x 900 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 729 Piece
sign with ………………… paint-foil, class ………, size 1300 x 500 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 731 Piece
sign with ………………… paint-foil, class ………, size 1300 x 750 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 732 Piece
sign with ………………… paint-foil, class ………, size 1300 x 1200 mm

Draft of Version 1 – March 2008 Page 149


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 733 Piece
sign with ………………… paint-foil, class ………, size 1500 x 900 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 734 Piece
sign with ………………… paint-foil, class ………, size 1500 x 1000 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 735 Piece
sign with ………………… paint-foil, class ………, size 1600 x 500 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 736 Piece
sign with ………………… paint-foil, class ………, size 1600 x 750 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 737 Piece
sign with ………………… paint-foil, class ………, size 1700 x 1200 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 738 Piece
sign with ………………… paint-foil, class ………, size 1900 x 500 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 739 Piece
sign with ………………… paint-foil, class ………, size 1900 x 750 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 741 Piece
sign with ………………… paint-foil, class ………, size 2100 x 1200 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 742 Piece
sign with ………………… paint-foil, class ………, size 2250 x 1500 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 743 Piece
sign with ………………… paint-foil, class ………, size 3000 x 2000 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 744 Piece
sign with ………………… paint-foil, class ………, size . . . . x . . . . mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 751 Piece
sign with ………………… paint-foil, class ………, size 1000 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 752 Piece
sign with ………………… paint-foil, class ………, size 1300 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 753 Piece
sign with ………………… paint-foil, class ………, size 1300 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 754 Piece
sign with ………………… paint-foil, class ………, size 1300 x 350 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 755 Piece
sign with ………………… paint-foil, class ………, size 1300 x 450 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 756 Piece
sign with ………………… paint-foil, class ………, size 1300 x 550 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 757 Piece
sign with ………………… paint-foil, class ………, size 1300 x 650 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 758 Piece
sign with ………………… paint-foil, class ………, size 1600 x 250 mm

Draft of Version 1 – March 2008 Page 150


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 759 Piece
sign with ………………… paint-foil, class ………, size 1600 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 761 Piece
sign with ………………… paint-foil, class ………, size 1600 x 350 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 762 Piece
sign with ………………… paint-foil, class ………, size 1600 x 450 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 763 Piece
sign with ………………… paint-foil, class ………, size 1600 x 550 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 764 Piece
sign with ………………… paint-foil, class ………, size 1600 x 650 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 765 Piece
sign with ………………… paint-foil, class ………, size 1900 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 766 Piece
sign with ………………… paint-foil, class ………, size 1900 x 350 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 767 Piece
sign with ………………… paint-foil, class ………, size 1900 x 450 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 768 Piece
sign with ………………… paint-foil, class ………, size 1900 x 550 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 769 Piece
sign with ………………… paint-foil, class ………, size 1900 x 650 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 771 Piece
sign with ………………… paint-foil, class ………, size 400 x 120 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 772 Piece
sign with ………………… paint-foil, class ………, size 400 x 200 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 773 Piece
sign with ………………… paint-foil, class ………, size 600 x 150 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 774 Piece
sign with ………………… paint-foil, class ………, size 600 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 775 Piece
sign with ………………… paint-foil, class ………, size 600 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 776 Piece
sign with ………………… paint-foil, class ………, size 850 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 777 Piece
sign with ………………… paint-foil, class ………, size 850 x 350 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 778 Piece
sign with ………………… paint-foil, class ………, size 850 x 450 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 779 Piece
sign with ………………… paint-foil, class ………, size 900 x 250 mm

Draft of Version 1 – March 2008 Page 151


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 781 Piece
sign with ………………… paint-foil, class ………, size 900 x 350 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 782 Piece
sign with ………………… paint-foil, class ………, size 900 x 450 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 783 Piece
sign with ………………… paint-foil, class ………, size 1150 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 784 Piece
sign with ………………… paint-foil, class ………, size 1150 x 500 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 785 Piece
sign with ………………… paint-foil, class ………, size 1150 x 600 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 791 Piece
sign with ………………… paint-foil, class ………, size 400 x 250 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 792 Piece
sign with ………………… paint-foil, class ………, size 400 x 300 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 793 Piece
sign with ………………… paint-foil, class ………, size 500 x 400 mm
Supply and mounting of traffic sign, hot- galvanised steel sheet backing,
61 794 Piece
sign with ………………… paint-foil, class ………, size 500 x 500 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 811 Piece
………………… paint-foil, class ………, size 350 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 812 Piece
………………… paint-foil, class ………, size 350 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 813 Piece
………………… paint-foil, class ………, size 400 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 814 Piece
………………… paint-foil, class ………, size 400 x 400 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 815 Piece
………………… paint-foil, class ………, size 400 x 600 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 816 Piece
………………… paint-foil, class ………, size 450 x 400 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 817 Piece
………………… paint-foil, class ………, size 500 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 818 Piece
………………… paint-foil, class ………, size 600 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 819 Piece
………………… paint-foil, class ………, size 600 x 600 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 821 Piece
………………… paint-foil, class ………, size 600 x 900 mm

Draft of Version 1 – March 2008 Page 152


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 822 Piece
………………… paint-foil, class ………, size 750 x 750 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 823 Piece
………………… paint-foil, class ………, size 900 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 824 Piece
………………… paint-foil, class ………, size 900 x 900 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 825 Piece
………………… paint-foil, class ………, size 900 x 1350 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 826 Piece
………………… paint-foil, class ………, size 1000 x 500 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 827 Piece
………………… paint-foil, class ………, size 1000 x 750 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 828 Piece
………………… paint-foil, class ………, size 1200 x 900 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 829 Piece
………………… paint-foil, class ………, size 1300 x 500 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 831 Piece
………………… paint-foil, class ………, size 1300 x 750 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 832 Piece
………………… paint-foil, class ………, size 1300 x 1200 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 833 Piece
………………… paint-foil, class ………, size 1500 x 900 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 834 Piece
………………… paint-foil, class ………, size 1500 x 1000 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 835 Piece
………………… paint-foil, class ………, size 1600 x 500 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 836 Piece
………………… paint-foil, class ………, size 1600 x 750 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 737 Piece
………………… paint-foil, class ………, size 1700 x 1200 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 838 Piece
………………… paint-foil, class ………, size 1900 x 500 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 839 Piece
………………… paint-foil, class ………, size 1900 x 750 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 841 Piece
………………… paint-foil, class ………, size 2100 x 1200 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 842 Piece
………………… paint-foil, class ………, size 2250 x 1500 mm

Draft of Version 1 – March 2008 Page 153


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 843 Piece
………………… paint-foil, class ………, size 3000 x 2000 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 844 Piece
………………… paint-foil, class ………, size . . . . x . . . . mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 851 Piece
………………… paint-foil, class ………, size 1000 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 852 Piece
………………… paint-foil, class ………, size 1300 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 853 Piece
………………… paint-foil, class ………, size 1300 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 854 Piece
………………… paint-foil, class ………, size 1300 x 350 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 855 Piece
………………… paint-foil, class ………, size 1300 x 450 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 856 Piece
………………… paint-foil, class ………, size 1300 x 550 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 857 Piece
………………… paint-foil, class ………, size 1300 x 650 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 858 Piece
………………… paint-foil, class ………, size 1600 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 859 Piece
………………… paint-foil, class ………, size 1600 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 861 Piece
………………… paint-foil, class ………, size 1600 x 350 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 862 Piece
………………… paint-foil, class ………, size 1600 x 450 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 863 Piece
………………… paint-foil, class ………, size 1600 x 550 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 864 Piece
………………… paint-foil, class ………, size 1600 x 650 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 865 Piece
………………… paint-foil, class ………, size 1900 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 866 Piece
………………… paint-foil, class ………, size 1900 x 350 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 867 Piece
………………… paint-foil, class ………, size 1900 x 450 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 868 Piece
………………… paint-foil, class ………, size 1900 x 550 mm

Draft of Version 1 – March 2008 Page 154


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 869 Piece
………………… paint-foil, class ………, size 1900 x 650 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 871 Piece
………………… paint-foil, class ………, size 400 x 120 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 872 Piece
………………… paint-foil, class ………, size 400 x 200 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 873 Piece
………………… paint-foil, class ………, size 600 x 150 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 874 Piece
………………… paint-foil, class ………, size 600 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 875 Piece
………………… paint-foil, class ………, size 600 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 876 Piece
………………… paint-foil, class ………, size 850 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 877 Piece
………………… paint-foil, class ………, size 850 x 350 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 878 Piece
………………… paint-foil, class ………, size 850 x 450 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 879 Piece
………………… paint-foil, class ………, size 900 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 881 Piece
………………… paint-foil, class ………, size 900 x 350 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 882 Piece
………………… paint-foil, class ………, size 900 x 450 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 883 Piece
………………… paint-foil, class ………, size 1150 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 884 Piece
………………… paint-foil, class ………, size 1150 x 500 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 885 Piece
………………… paint-foil, class ………, size 1150 x 600 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 891 Piece
………………… paint-foil, class ………, size 400 x 250 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 892 Piece
………………… paint-foil, class ………, size 400 x 300 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 893 Piece
………………… paint-foil, class ………, size 500 x 400 mm
Supply and mounting of traffic sign, aluminum sheet backing, sign with
61 894 Piece
………………… paint-foil, class ………, size 500 x 500 mm

Draft of Version 1 – March 2008 Page 155


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
61 911 Piece Supply and erection of traffic light signal with one signal heads
61 912 Piece Supply and erection of traffic light signal with two signal heads
61 913 Piece Supply and erection of traffic light signal with three signal heads
61 921 Piece Supply and mounting of extra signal head for traffic light signal

6.2 Road Markings

Unit
Code Description of work
measure
Machine marking, with single-component white paint, of continuous thin-layer
62 111 m
line, dry layer thickness 200 µm, line width 10 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 112 m
line, dry layer thickness 200 µm, line width 12 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 113 m
line, dry layer thickness 200 µm, line width 15 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 114 m
line, dry layer thickness 200 µm, line width 20 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 115 m
line, dry layer thickness 200 µm, line width 25 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 116 m
line, dry layer thickness 200 µm, line width 30 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 117 m
line, dry layer thickness 200 µm, line width 50 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 118 m
line, dry layer thickness 200 µm, line width . . cm
Machine marking, with single-component white paint, of continuous thin-layer
62 121 m
line, dry layer thickness 250 µm, line width 10 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 122 m
line, dry layer thickness 250 µm, line width 12 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 123 m
line, dry layer thickness 250 µm, line width 15 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 124 m
line, dry layer thickness 250 µm, line width 20 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 125 m
line, dry layer thickness 250 µm, line width 25 cm

Draft of Version 1 – March 2008 Page 156


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with single-component white paint, of continuous thin-layer
62 126 m
line, dry layer thickness 250 µm, line width 30 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 127 m
line, dry layer thickness 250 µm, line width 50 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 128 m
line, dry layer thickness 250 µm, line width . . cm
Machine marking, with single-component white paint, of continuous thin-layer
62 131 m
line, dry layer thickness 300 µm, line width 10 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 132 m
line, dry layer thickness 300 µm, line width 12 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 133 m
line, dry layer thickness 300 µm, line width 15 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 134 m
line, dry layer thickness 300 µm, line width 20 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 135 m
line, dry layer thickness 300 µm, line width 25 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 136 m
line, dry layer thickness 300 µm, line width 30 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 137 m
line, dry layer thickness 300 µm, line width 50 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 138 m
line, dry layer thickness 300 µm, line width . . cm
Machine marking, with single-component white paint, of continuous thin-layer
62 141 m
line, dry layer thickness 400 µm, line width 10 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 142 m
line, dry layer thickness 400 µm, line width 12 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 143 m
line, dry layer thickness 400 µm, line width 15 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 144 m
line, dry layer thickness 400 µm, line width 20 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 145 m
line, dry layer thickness 400 µm, line width 25 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 146 m
line, dry layer thickness 400 µm, line width 30 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 147 m
line, dry layer thickness 400 µm, line width 50 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 148 m
line, dry layer thickness 400 µm, line width . . cm

Draft of Version 1 – March 2008 Page 157


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with single-component white paint, of continuous thin-layer
62 151 m
line, dry layer thickness 500 µm, line width 10 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 152 m
line, dry layer thickness 500 µm, line width 12 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 153 m
line, dry layer thickness 500 µm, line width 15 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 154 m
line, dry layer thickness 500 µm, line width 20 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 155 m
line, dry layer thickness 500 µm, line width 25 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 156 m
line, dry layer thickness 500 µm, line width 30 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 157 m
line, dry layer thickness 500 µm, line width 50 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 158 m
line, dry layer thickness 500 µm, line width . . cm
Machine marking, with single-component white paint, of continuous thin-layer
62 161 m
line, dry layer thickness . . . µm, line width 10 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 162 m
line, dry layer thickness . . . µm, line width 12 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 163 m
line, dry layer thickness . . . µm, line width 15 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 164 m
line, dry layer thickness . . . µm, line width 20 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 165 m
line, dry layer thickness . . . µm, line width 25 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 166 m
line, dry layer thickness . . . µm, line width 30 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 167 m
line, dry layer thickness . . . µm, line width 50 cm
Machine marking, with single-component white paint, of continuous thin-layer
62 168 m
line, dry layer thickness . . . µm, line width . . cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 171 m
line, dry layer thickness 200 µm, line width 10 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 172 m
line, dry layer thickness 200 µm, line width 12 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 173 m
line, dry layer thickness 200 µm, line width 15 cm

Draft of Version 1 – March 2008 Page 158


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with multi- component white paint, of continuous thin-layer
62 174 m
line, dry layer thickness 200 µm, line width 20 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 175 m
line, dry layer thickness 200 µm, line width 25 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 176 m
line, dry layer thickness 200 µm, line width 30 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 177 m
line, dry layer thickness 200 µm, line width 50 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 178 m
line, dry layer thickness 200 µm, line width . . cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 181 m
line, dry layer thickness 250 µm, line width 10 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 182 m
line, dry layer thickness 250 µm, line width 12 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 183 m
line, dry layer thickness 250 µm, line width 15 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 184 m
line, dry layer thickness 250 µm, line width 20 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 185 m
line, dry layer thickness 250 µm, line width 25 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 186 m
line, dry layer thickness 250 µm, line width 30 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 187 m
line, dry layer thickness 250 µm, line width 50 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 188 m
line, dry layer thickness 250 µm, line width . . cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 191 m
line, dry layer thickness 300 µm, line width 10 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 192 m
line, dry layer thickness 300 µm, line width 12 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 193 m
line, dry layer thickness 300 µm, line width 15 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 194 m
line, dry layer thickness 300 µm, line width 20 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 195 m
line, dry layer thickness 300 µm, line width 25 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 196 m
line, dry layer thickness 300 µm, line width 30 cm

Draft of Version 1 – March 2008 Page 159


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with multi- component white paint, of continuous thin-layer
62 197 m
line, dry layer thickness 300 µm, line width 50 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 198 m
line, dry layer thickness 300 µm, line width . . cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 211 m
line, dry layer thickness 400 µm, line width 10 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 212 m
line, dry layer thickness 400 µm, line width 12 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 213 m
line, dry layer thickness 400 µm, line width 15 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 214 m
line, dry layer thickness 400 µm, line width 20 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 215 m
line, dry layer thickness 400 µm, line width 25 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 216 m
line, dry layer thickness 400 µm, line width 30 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 217 m
line, dry layer thickness 400 µm, line width 50 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 218 m
line, dry layer thickness 400 µm, line width . . cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 221 m
line, dry layer thickness 500 µm, line width 10 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 222 m
line, dry layer thickness 500 µm, line width 12 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 223 m
line, dry layer thickness 500 µm, line width 15 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 224 m
line, dry layer thickness 500 µm, line width 20 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 225 m
line, dry layer thickness 500 µm, line width 25 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 226 m
line, dry layer thickness 500 µm, line width 30 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 227 m
line, dry layer thickness 500 µm, line width 50 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 228 m
line, dry layer thickness 500 µm, line width . . cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 231 m
line, dry layer thickness . . . µm, line width 10 cm

Draft of Version 1 – March 2008 Page 160


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with multi- component white paint, of continuous thin-layer
62 232 m
line, dry layer thickness . . . µm, line width 12 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 233 m
line, dry layer thickness . . . µm, line width 15 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 234 m
line, dry layer thickness . . . µm, line width 20 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 235 m
line, dry layer thickness . . . µm, line width 25 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 236 m
line, dry layer thickness . . . µm, line width 30 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 237 m
line, dry layer thickness . . . µm, line width 50 cm
Machine marking, with multi- component white paint, of continuous thin-layer
62 238 m
line, dry layer thickness . . . µm, line width . . cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 241 m
layer thickness 200 µm, line width 10 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 242 m
layer thickness 200 µm, line width 12 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 243 m
layer thickness 200 µm, line width 15 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 244 m
layer thickness 200 µm, line width 20 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 245 m
layer thickness 200 µm, line width 25 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 246 m
layer thickness 200 µm, line width 30 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 247 m
layer thickness 200 µm, line width 50 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 248 m
layer thickness 200 µm, line width . . cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 251 m
layer thickness 250 µm, line width 10 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 252 m
layer thickness 250 µm, line width 12 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 253 m
layer thickness 250 µm, line width 15 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 254 m
layer thickness 250 µm, line width 20 cm

Draft of Version 1 – March 2008 Page 161


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 255 m
layer thickness 250 µm, line width 25 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 256 m
layer thickness 250 µm, line width 30 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 257 m
layer thickness 250 µm, line width 50 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 258 m
layer thickness 250 µm, line width . . cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 261 m
layer thickness 300 µm, line width 10 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 262 m
layer thickness 300 µm, line width 12 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 263 m
layer thickness 300 µm, line width 15 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 264 m
layer thickness 300 µm, line width 20 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 265 m
layer thickness 300 µm, line width 25 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 266 m
layer thickness 300 µm, line width 30 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 267 m
layer thickness 300 µm, line width 50 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 268 m
layer thickness 300 µm, line width . . cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 271 m
layer thickness 400 µm, line width 10 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 272 m
layer thickness 400 µm, line width 12 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 273 m
layer thickness 400 µm, line width 15 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 274 m
layer thickness 400 µm, line width 20 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 275 m
layer thickness 400 µm, line width 25 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 276 m
layer thickness 400 µm, line width 30 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 277 m
layer thickness 400 µm, line width 50 cm

Draft of Version 1 – March 2008 Page 162


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 278 m
layer thickness 400 µm, line width . . cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 281 m
layer thickness 500 µm, line width 10 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 282 m
layer thickness 500 µm, line width 12 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 283 m
layer thickness 500 µm, line width 15 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 284 m
layer thickness 500 µm, line width 20 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 285 m
layer thickness 500 µm, line width 25 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 286 m
layer thickness 500 µm, line width 30 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 287 m
layer thickness 500 µm, line width 50 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 288 m
layer thickness 500 µm, line width . . cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 291 m
layer thickness . . . µm, line width 10 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 292 m
layer thickness . . . µm, line width 12 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 293 m
layer thickness . . . µm, line width 15 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 294 m
layer thickness . . . µm, line width 20 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 295 m
layer thickness . . . µm, line width 25 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 296 m
layer thickness . . . µm, line width 30 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 297 m
layer thickness . . . µm, line width 50 cm
Machine marking, with premix white paint, of continuous thin-layer line, dry
62 298 m
layer thickness . . . µm, line width . . cm
Machine marking with single-component yellow paint, of continuous thin-
62 311 m
layer, dry layer thickness 200 µm, line width 10 cm
Machine marking with single-component yellow paint, of continuous thin-
62 312 m
layer, dry layer thickness 200 µm, line width 12 cm

Draft of Version 1 – March 2008 Page 163


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking with single-component yellow paint, of continuous thin-
62 313 m
layer, dry layer thickness 200 µm, line width 15 cm
Machine marking with single-component yellow paint, of continuous thin-
62 314 m
layer, dry layer thickness 200 µm, line width 20 cm
Machine marking with single-component yellow paint, of continuous thin-
62 315 m
layer, dry layer thickness 200 µm, line width . . cm
Machine marking with single-component yellow paint, of continuous thin-
62 321 m
layer, dry layer thickness 250 µm, line width 10 cm
Machine marking with single-component yellow paint, of continuous thin-
62 322 m
layer, dry layer thickness 250 µm, line width 12 cm
Machine marking with single-component yellow paint, of continuous thin-
62 323 m
layer, dry layer thickness 250 µm, line width 15 cm
Machine marking with single-component yellow paint, of continuous thin-
62 324 m
layer, dry layer thickness 250 µm, line width 20 cm
Machine marking with single-component yellow paint, of continuous thin-
62 325 m
layer, dry layer thickness 250 µm, line width . . cm
Machine marking with single-component yellow paint, of continuous thin-
62 331 m
layer, dry layer thickness 300 µm, line width 10 cm
Machine marking with single-component yellow paint, of continuous thin-
62 332 m
layer, dry layer thickness 300 µm, line width 12 cm
Machine marking with single-component yellow paint, of continuous thin-
62 333 m
layer, dry layer thickness 300 µm, line width 15 cm
Machine marking with single-component yellow paint, of continuous thin-
62 334 m
layer, dry layer thickness 300 µm, line width 20 cm
Machine marking with single-component yellow paint, of continuous thin-
62 335 m
layer, dry layer thickness 300 µm, line width . . cm
Machine marking with single-component yellow paint, of continuous thin-
62 341 m
layer, dry layer thickness 400 µm, line width 10 cm
Machine marking with single-component yellow paint, of continuous thin-
62 342 m
layer, dry layer thickness 400 µm, line width 12 cm
Machine marking with single-component yellow paint, of continuous thin-
62 343 m
layer, dry layer thickness 400 µm, line width 15 cm
Machine marking with single-component yellow paint, of continuous thin-
62 344 m
layer, dry layer thickness 400 µm, line width 20 cm
Machine marking with single-component yellow paint, of continuous thin-
62 345 m
layer, dry layer thickness 400 µm, line width . . cm
Machine marking with single-component yellow paint, of continuous thin-
62 351 m
layer, dry layer thickness 500 µm, line width 10 cm

Draft of Version 1 – March 2008 Page 164


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking with single-component yellow paint, of continuous thin-
62 352 m
layer, dry layer thickness 500 µm, line width 12 cm
Machine marking with single-component yellow paint, of continuous thin-
62 353 m
layer, dry layer thickness 500 µm, line width 15 cm
Machine marking with single-component yellow paint, of continuous thin-
62 354 m
layer, dry layer thickness 500 µm, line width 20 cm
Machine marking with single-component yellow paint, of continuous thin-
62 355 m
layer, dry layer thickness 500 µm, line width . . cm
Machine marking with single-component yellow paint, of continuous thin-
62 361 m
layer, dry layer thickness . . . µm, line width 10 cm
Machine marking with single-component yellow paint, of continuous thin-
62 362 m
layer, dry layer thickness . . . µm, line width 12 cm
Machine marking with single-component yellow paint, of continuous thin-
62 363 m
layer, dry layer thickness . . . µm, line width 15 cm
Machine marking with single-component yellow paint, of continuous thin-
62 364 m
layer, dry layer thickness . . . µm, line width 20 cm
Machine marking with single-component yellow paint, of continuous thin-
62 365 m
layer, dry layer thickness . . . µm, line width . . cm
Machine marking with multi- component yellow paint, of continuous thin-
62 371 m
layer, dry layer thickness 200 µm, line width 10 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 372 m
layer, dry layer thickness 200 µm, line width 12 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 373 m
layer, dry layer thickness 200 µm, line width 15 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 374 m
layer, dry layer thickness 200 µm, line width 20 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 375 m
layer, dry layer thickness 200 µm, line width . . cm
Machine marking with multi- component yellow paint, of continuous thin-
62 381 m
layer, dry layer thickness 250 µm, line width 10 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 382 m
layer, dry layer thickness 250 µm, line width 12 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 383 m
layer, dry layer thickness 250 µm, line width 15 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 384 m
layer, dry layer thickness 250 µm, line width 20 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 385 m
layer, dry layer thickness 250 µm, line width

Draft of Version 1 – March 2008 Page 165


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking with multi- component yellow paint, of continuous thin-
62 391 m
layer, dry layer thickness 300 µm, line width 10 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 392 m
layer, dry layer thickness 300 µm, line width 12 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 393 m
layer, dry layer thickness 300 µm, line width 15 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 394 m
layer, dry layer thickness 300 µm, line width 20 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 395 m
layer, dry layer thickness 300 µm, line width . . cm
Machine marking with multi- component yellow paint, of continuous thin-
62 411 m
layer, dry layer thickness 400 µm, line width 10 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 412 m
layer, dry layer thickness 400 µm, line width 12 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 413 m
layer, dry layer thickness 400 µm, line width 15 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 414 m
layer, dry layer thickness 400 µm, line width 20 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 415 m
layer, dry layer thickness 400 µm, line width . . cm
Machine marking with multi- component yellow paint, of continuous thin-
62 421 m
layer, dry layer thickness 500 µm, line width 10 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 422 m
layer, dry layer thickness 500 µm, line width 12 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 423 m
layer, dry layer thickness 500 µm, line width 15 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 424 m
layer, dry layer thickness 500 µm, line width 20 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 425 m
layer, dry layer thickness 500 µm, line width . . cm
Machine marking with multi- component yellow paint, of continuous thin-
62 431 m
layer, dry layer thickness . . . µm, line width 10 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 432 m
layer, dry layer thickness . . . µm, line width 12 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 433 m
layer, dry layer thickness . . . µm, line width 15 cm
Machine marking with multi- component yellow paint, of continuous thin-
62 434 m
layer, dry layer thickness . . . µm, line width 20 cm

Draft of Version 1 – March 2008 Page 166


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking with multi- component yellow paint, of continuous thin-
62 435 m
layer, dry layer thickness . . . µm, line width . . cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 441 m
thickness 200 µm, line width 10 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 442 m
thickness 200 µm, line width 12 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 443 m
thickness 200 µm, line width 15 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 444 m
thickness 200 µm, line width 20 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 445 m
thickness 200 µm, line width . . cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 451 m
thickness 250 µm, line width 10 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 452 m
thickness 250 µm, line width 12 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 453 m
thickness 250 µm, line width 15 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 454 m
thickness 250 µm, line width 20 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 455 m
thickness 250 µm, line width . . cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 461 m
thickness 300 µm, line width 10 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 462 m
thickness 300 µm, line width 12 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 463 m
thickness 300 µm, line width 15 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 464 m
thickness 300 µm, line width 20 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 465 m
thickness 300 µm, line width . . cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 471 m
thickness 400 µm, line width 10 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 472 m
thickness 400 µm, line width 12 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 473 m
thickness 400 µm, line width 15 cm

Draft of Version 1 – March 2008 Page 167


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 474 m
thickness 400 µm, line width 20 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 475 m
thickness 400 µm, line width . . cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 481 m
thickness 500 µm, line width 10 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 482 m
thickness 500 µm, line width 12 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 483 m
thickness 500 µm, line width 15 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 484 m
thickness 500 µm, line width 20 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 485 m
thickness 500 µm, line width . . cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 491 m
thickness . . . µm, line width 10 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 492 m
thickness . . . µm, line width 12 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 493 m
thickness . . . µm, line width 15 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 494 m
thickness . . . µm, line width 20 cm
Machine marking with yellow premix paint, of continuous thin-layer, dry layer
62 495 m
thickness . . . µm, line width . . cm
62 511 m Extra payment for machine marking of thin-layer broken line, line width 10 cm
61 512 m Extra payment for machine marking of thin-layer broken line, line width 12 cm
61 513 m Extra payment for machine marking of thin-layer broken line, line width 15 cm
61 514 m Extra payment for machine marking of thin-layer broken line, line width 20 cm
61 515 m Extra payment for machine marking of thin-layer broken line, line width . . cm
Extra payment for manual marking of thin-layer continuous line, line width
62 521 m
10 cm
Extra payment for manual marking of thin-layer continuous line, line width
61 522 m
12 cm
Extra payment for manual marking of thin-layer continuous line, line width
61 523 m
15 cm
Extra payment for manual marking of thin-layer continuous line, line width
61 524 m
20 cm

Draft of Version 1 – March 2008 Page 168


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Extra payment for manual marking of thin-layer continuous line, line width
61 525 m
. . cm
62 531 m Extra payment for manual marking of thin-layer broken line, line width 10 cm
61 532 m Extra payment for manual marking of thin-layer broken line, line width 12 cm
61 533 m Extra payment for manual marking of thin-layer broken line, line width 15 cm
61 534 m Extra payment for manual marking of thin-layer broken line, line width 20 cm
61 535 m Extra payment for manual marking of thin-layer broken line, line width . . cm
2
62 541 m Extra payment for spreading reflecting glass beads, 0.07 kg / m2
62 542 m2 Extra payment for spreading reflecting glass beads, line width 10 cm
2
62 543 m Extra payment for spreading reflecting glass beads, line width 12 cm
2
62 544 m Extra payment for spreading reflecting glass beads, line width 15 cm
62 545 m2 Extra payment for spreading reflecting glass beads, line width 20 cm
2
62 546 m Extra payment for spreading reflecting glass beads, line width … cm
62 551 kg Extra payment for red paint
62 552 kg Extra payment for blue paint
62 553 kg Extra payment for ………. paint
62 611 m Marking, with foil, of thick- layer line, line width 10 cm
62 612 m Marking, with foil, of thick- layer line, line width 12 cm
62 613 m Marking, with foil, of thick- layer line, line width 15 cm
62 614 m Marking, with foil, of thick- layer line, line width 20 cm
62 615 m Marking, with foil, of thick- layer line, line width 25 cm
62 616 m Marking, with foil, of thick- layer line, line width 30 cm
62 617 m Marking, with foil, of thick- layer line, line width 50 cm
62 618 m Marking, with foil, of thick- layer line, line width . . cm
Machine marking, with plastic compound, of thicker- layer line on
62 621 m
carriageway surface, line width 10 cm
Machine marking, with plastic compound, of thicker- layer line on
62 622 m
carriageway surface, line width 12 cm
Machine marking, with plastic compound, of thicker- layer line on
62 623 m
carriageway surface, line width 15 cm
Machine marking, with plastic compound, of thicker- layer line on
62 624 m
carriageway surface, line width 20 cm
Machine marking, with plastic compound, of thicker- layer line on
62 625 m
carriageway surface, line width 25 cm
Machine marking, with plastic compound, of thicker- layer line on
62 626 m
carriageway surface, line width 30 cm

Draft of Version 1 – March 2008 Page 169


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Machine marking, with plastic compound, of thicker- layer line on
62 627 m
carriageway surface, line width 50 cm
Machine marking, with plastic compound, of thicker- layer line on
62 628 m
carriageway surface, line width . . cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 631 m
surface, line width 10 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 632 m
surface, line width 12 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 633 m
surface, line width 15 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 634 m
surface, line width 20 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 635 m
surface, line width 25 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 636 m
surface, line width 30 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 637 m
surface, line width 50 cm
Manual marking, with plastic compound, of thicker- layer line on carriageway
62 638 m
surface, line width . . cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 711 m
layer thickness up to 8 mm, line width 10 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 712 m
layer thickness up to 8 mm, line width 12 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 713 m
layer thickness up to 8 mm, line width 15 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 714 m
layer thickness up to 8 mm, line width 20 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 715 m
layer thickness up to 8 mm, line width 25 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 716 m
layer thickness up to 8 mm, line width 30 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 717 m
layer thickness up to 8 mm, line width 50 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 718 m
layer thickness up to 8 mm, line width . . cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 721 m
thickness up to 8 mm, line width 10 cm

Draft of Version 1 – March 2008 Page 170


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 722 m
thickness up to 8 mm, line width 12 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 723 m
thickness up to 8 mm, line width 15 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 724 m
thickness up to 8 mm, line width 20 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 725 m
thickness up to 8 mm, line width 25 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 726 m
thickness up to 8 mm, line width 30 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 727 m
thickness up to 8 mm, line width 50 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 728 m
thickness up to 8 mm, line width . . cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 731 m
layer thickness more than 8 mm, line width 10 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 732 m
layer thickness more than 8 mm, line width 12 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 733 m
layer thickness more than 8 mm, line width 15 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 734 m
layer thickness more than 8 mm, line width 20 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 735 m
layer thickness more than 8 mm, line width 25 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 736 m
layer thickness more than 8 mm, line width 30 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 737 m
layer thickness more than 8 mm, line width 50 cm
Machine marking, with plastic compound, of recessed thicker- layer line,
62 738 m
layer thickness more than 8 mm, line width . . cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 741 m
thickness more than 8 mm, line width 10 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 742 m
thickness more than 8 mm, line width 12 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 743 m
thickness more than 8 mm, line width 15 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 744 m
thickness more than 8 mm, line width 20 cm

Draft of Version 1 – March 2008 Page 171


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 745 m
thickness more than 8 mm, line width 25 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 746 m
thickness more than 8 mm, line width 30 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 747 m
thickness more than 8 mm, line width 50 cm
Manual marking, with plastic compound, of recessed thicker- layer line, layer
62 748 m
thickness more than 8 mm, line width . . cm
62 751 kg Extra payment for red paint
62 752 kg Extra payment for blue paint
62 753 kg Extra payment for ………. paint
Machine marking of other thin-layer road markings with single-component
62 811 m2
paint
Machine marking of other thin-layer road markings with multi-component
62 812 m2
paint
62 813 m2 Machine marking of other thin-layer road markings with premix paint
2
62 814 m Machine marking of other thin-layer road markings with yellow paint
Machine marking of other thin-layer road markings with ………………………
62 815 m2
paint
Manual marking of other thin-layer road markings with single-component
62 821 m2
paint
62 822 m2 Manual marking of other thin-layer road markings with multi-component paint
2
62 823 m Manual marking of other thin-layer road markings with premix paint
2
62 824 m Manual marking of other thin-layer road markings with yellow paint
2
62 825 m Manual marking of other thin-layer road markings with ………………… paint
2
62 831 m Application of foil for other thick-layer markings
Machine marking, with plastic compound, of other thick-layer markings on
62 841 m2
carriageway surface
Machine marking, with plastic compound, of recessed type, layer thickness
62 842 m2
up to 8 mm
62 843 m2 Machine marking, with plastic compound, more than 8 mm
Manual marking, with plastic compound, of other thick-layer markings on
62 851 m2
carriageway surface
Manual marking, with plastic compound, of recessed type, layer thickness up
62 852 m2
to 8 mm
62 853 m2 Manual marking, with plastic compound, more than 8 mm

Draft of Version 1 – March 2008 Page 172


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and placing on the carriageway of reflecting prism, reflecting element
62 911 Piece
of plastic material, body of plastic material
Supply and placing on the carriageway of reflecting prism, reflecting element
62 912 Piece
of plastic material, body of steel
Supply and placing on the carriageway of reflecting prism, reflecting element
62 913 Piece
of plastic material, body of aluminium
Supply and placing on the carriageway of reflecting prism, reflecting element
62 914 Piece
of plastic material, body of ceramics
Supply and placing on the carriageway of reflecting prism, reflecting element
62 915 Piece
of plastic material, body of ………………..

6.3 Traffic Guiding Equipment

Unit
Code Description of work
measure
Supply and erection of delineation marker of plastic material, hollow
63 111 Piece
section, length 1200 mm, with reflector of foil
Supply and erection of delineation marker of plastic material, hollow
63 112 Piece
section, length 1200 mm, with reflector of plastic material
Supply and erection of delineation marker of plastic material, hollow
63 113 Piece
section, length 1200 mm, with reflector of …………………
Supply and erection of delineation marker of plastic material, solid section,
63 121 Piece
length 1200 mm, with reflector of foil
Supply and erection of delineation marker of plastic material, solid section,
63 122 Piece
length 1200 mm, with reflector of plastic material
Supply and erection of delineation marker of plastic material, solid section,
63 123 Piece
length 1200 mm, with reflector of …………………
Supply and erection of delineation marker of ……………….., length
63 131 Piece
……………….. mm, with reflector of foil
Supply and erection of delineation marker of ……………….., length
63 132 Piece
……………….. mm, with reflector of plastic material
Supply and erection of delineation marker of ……………….., length
63 133 Piece
……………….. mm, with reflector of …………………
Supply and erection of marker post of cement concrete, with reflector of
63 141 Piece
foil

Draft of Version 1 – March 2008 Page 173


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of marker post of cement concrete, with reflector of
63 142 Piece
plastic material
Supply and erection of marker post of cement concrete, with reflector of
63 143 Piece
………………….
63 151 Piece Supply and erection of marker post of natural stone, with reflector of foil
Supply and erection of marker post of natural stone, with reflector of
63 152 Piece
plastic material
Supply and erection of marker post of natural stone, with reflector of
63 153 Piece
………………….
Supply and erection of marker post of wood, as per drawing, with reflector
63 161 Piece
of foil
Supply and erection of marker post of wood, as per drawing, with reflector
63 162 Piece
of plastic material
Supply and erection of marker post of wood, as per drawing, with reflector
63 163 Piece
of ………………….
Supply and erection of plate bollard, backing sheet of glass-reinforced
63 211 Piece
polyester, with markings of 1st class reflecting foil
Supply and erection of plate bollard, backing sheet of glass-reinforced
63 212 Piece
polyester, with markings of 2nd class reflecting foil
Supply and erection of plate bollard, backing sheet of glass-reinforced
63 213 Piece
polyester, with markings of ………………………….
Supply and erection of plate bollard, backing hot-galvanised steel sheet ,
63 221 Piece
with markings of 1st class reflecting foil
Supply and erection of plate bollard, backing hot-galvanised steel sheet ,
63 222 Piece
with markings of 2nd class reflecting foil
Supply and erection of plate bollard, backing hot-galvanised steel sheet ,
63 223 Piece
with markings of ………………………….
Supply and erection of plate bollard, backing of aluminum sheet, with
63 231 Piece
markings of 1st class reflecting foil
Supply and erection of plate bollard, backing of aluminum sheet, with
63 232 Piece
markings of 2nd class reflecting foil
Supply and erection of plate bollard, backing of aluminum sheet, with
63 233 Piece
markings of ………………………….
Supply and erection of cylindrical bollard, internally illuminated, backing
63 241 Piece
sheet of glass- reinforced polyester
63 251 Piece Extra payment for supplementary illuminated traffic sign (a, Ø = 600 mm )
63 261 Piece Extra payment for supplementary illuminated traffic sign, double

Draft of Version 1 – March 2008 Page 174


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply of portable traffic cone, with weight, of plastic material, height
63 271 Piece
33 cm
Supply of portable traffic cone, with weight, of plastic material, height
63 272 Piece
45 cm
Supply of portable traffic cone, with weight, of plastic material, height
63 273 Piece
60 cm
Supply of portable traffic cone, with weight, of plastic material, height
63 274 Piece
70 cm
63 281 Piece Supply of portable traffic cone, with weight, of rubber, height 33 cm
63 282 Piece Supply of portable traffic cone, with weight, of rubber, height 45 cm
63 283 Piece Supply of portable traffic cone, with weight, of rubber, height 60 cm
63 284 Piece Supply of portable traffic cone, with weight, of rubber, height 70 cm
Supply and erection of chevron alignment and stop board of glass –
63 311 Piece reinforced polyester, with markings of 1st class reflecting foil, size 330 x
1200 mm
Supply and erection of chevron alignment and stop board of glass –
63 312 Piece reinforced polyester, with markings of 1st class reflecting foil, size 500 x
500 mm
Supply and erection of chevron alignment and stop board of glass –
63 313 Piece reinforced polyester, with markings of 1st class reflecting foil, size 750 x
750 mm
Supply and erection of chevron alignment and stop board of glass –
63 314 Piece reinforced polyester, with markings of 1st class reflecting foil, size 1500 x
250 mm
Supply and erection of chevron alignment and stop board of glass –
63 315 Piece reinforced polyester, with markings of 1st class reflecting foil, size 1500 x
500 mm
Supply and erection of chevron alignment and stop board of glass –
63 316 Piece reinforced polyester, with markings of 1st class reflecting foil, size 2250 x
750 mm
Supply and erection of chevron alignment and stop board of glass –
63 317 Piece reinforced polyester, with markings of 1st class reflecting foil, size 3000 x
250 mm
Supply and erection of chevron alignment and stop board of glass –
63 318 Piece reinforced polyester, with markings of 1st class reflecting foil, size
. . . . x . . . . mm

Draft of Version 1 – March 2008 Page 175


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of chevron alignment and stop board of hot-
63 321 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 330 x
1200 mm
Supply and erection of chevron alignment and stop board of hot-
63 322 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 500 x
500 mm
Supply and erection of chevron alignment and stop board of hot-
63 323 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 750 x
750 mm
Supply and erection of chevron alignment and stop board of hot-
63 324 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 1500
x 250 mm
Supply and erection of chevron alignment and stop board of hot-
63 325 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 1500
x 500 mm
Supply and erection of chevron alignment and stop board of hot-
63 326 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 2250
x 750 mm
Supply and erection of chevron alignment and stop board of hot-
63 327 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size 3000
x 250 mm
Supply and erection of chevron alignment and stop board of hot-
63 328 Piece galvanised steel sheet, with markings of 1st class reflecting foil, size . . . . x
. . . . mm
Supply and erection of chevron alignment and stop board of aluminum
63 331 Piece
sheet, with markings of 1st class reflecting foil, size 330 x 1200 mm
Supply and erection of chevron alignment and stop board of aluminum
63 332 Piece
sheet, with markings of 1st class reflecting foil, size 500 x 500 mm
Supply and erection of chevron alignment and stop board of aluminum
63 333 Piece
sheet, with markings of 1st class reflecting foil, size 750 x 750 mm
Supply and erection of chevron alignment and stop board of aluminum
63 334 Piece
sheet, with markings of 1st class reflecting foil, size 1500 x 250 mm
Supply and erection of chevron alignment and stop board of aluminum
63 335 Piece
sheet, with markings of 1st class reflecting foil, size 1500 x 500 mm
Supply and erection of chevron alignment and stop board of aluminum
63 336 Piece
sheet, with markings of 1st class reflecting foil, size 2250 x 750 mm
Supply and erection of chevron alignment and stop board of aluminum
63 337 Piece
sheet, with markings of 1st class reflecting foil, size 3000 x 250 mm

Draft of Version 1 – March 2008 Page 176


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and erection of chevron alignment and stop board of aluminum
63 338 Piece
sheet, with markings of 1st class reflecting foil, size . . . . x . . . . mm
Supply and erection of chevron alignment and stop board of wood, with
63 341 Piece
paint coat markings, size 330 x 1200 mm
Supply and erection of chevron alignment and stop board of wood, with
63 342 Piece
paint coat markings, size 500 x 500 mm
Supply and erection of chevron alignment and stop board of wood, with
63 343 Piece
paint coat markings, size 750 x 750 mm
Supply and erection of chevron alignment and stop board of wood, with
63 344 Piece
paint coat markings, size 1500 x 250 mm
Supply and erection of chevron alignment and stop board of wood, with
63 345 Piece
paint coat markings, size 1500 x 500 mm
Supply and erection of chevron alignment and stop board of wood, with
63 346 Piece
paint coat markings, size 2250 x 750 mm
Supply and erection of chevron alignment and stop board of wood, with
63 347 Piece
paint coat markings, size 3000 x 250 mm
Supply and erection of chevron alignment and stop board of wood, with
63 348 Piece
paint coat markings, size . . . . x . . . . mm
Supply and erection of chevron alignment and stop board of …………….,
63 351 Piece
with markings of ………………., size 330 x 1200 mm
Supply and erection of chevron alignment and stop board of …………….,
63 352 Piece
with markings of …………………, size 500 x 500 mm
Supply and erection of chevron alignment and stop board of …………….,
63 353 Piece
with markings of ………………., size 750 x 750 mm
Supply and erection of chevron alignment and stop board of …………….,
63 354 Piece
with markings of ………………., size 1500 x 250 mm
Supply and erection of chevron alignment and stop board of …………….,
63 355 Piece
with markings of ………………., size 1500 x 500 mm
Supply and erection of chevron alignment and stop board of …………….,
63 356 Piece
with markings of ………………., size 2250 x 750 mm
Supply and erection of chevron alignment and stop board of …………….,
63 357 Piece
with markings of ………………., size 3000 x 250 mm
Supply and erection of chevron alignment and stop board of …………….,
63 358 Piece
with markings of ………………., size . . . . x . . . . mm
63 411 Piece Supply and erection of carriers, as per drawing …………………
63 412 Piece Supply and erection of carriers, as per drawing …………………
Supply and incorporation of reflective traffic marker with base of hot-
63 511 Piece
galvanised steel sheet and with 1st class reflecting foil

Draft of Version 1 – March 2008 Page 177


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and incorporation of reflective traffic marker with base of hot-
63 512 Piece
galvanised steel sheet and with 2nd class reflecting foil
Supply and incorporation of reflective traffic marker with base of hot-
63 513 Piece
galvanised steel sheet and with reflecting plastic material
Supply and incorporation of reflective traffic marker with base of hot-
63 514 Piece
galvanised steel sheet and with …………………
Supply and incorporation of reflective traffic marker with base of
63 521 Piece
aluminium sheet and with 1st class reflecting foil
Supply and incorporation of reflective traffic marker with base of
63 522 Piece
aluminium sheet and with 2nd class reflecting foil
Supply and incorporation of reflective traffic marker with base of
63 523 Piece
aluminium sheet and with reflecting plastic material
Supply and incorporation of reflective traffic marker with base of
63 524 Piece
aluminium sheet and with …………………
Supply and installation of autonomous, single-head signal with blinking
63 531 Piece
yellow light Ø 200 mm
Supply and installation of autonomous, single-head signal with blinking
63 532 Piece
yellow light Ø 300 mm
Supply and installation of autonomous, single-head signal with blinking
63 533 Piece
yellow light Ø . . . mm
Supply and installation of autonomous, double-head signal, alternately
63 541 Piece
blinking yellow light Ø 200 mm
Supply and installation of autonomous, double-head signal, alternately
63 542 Piece
blinking yellow light Ø 300 mm
Supply and installation of autonomous, double-head signal, alternately
63 543 Piece
blinking yellow light Ø . . . mm
Supply and installation of direction indicating blinking lamps Ø 180 mm, in
63 551 Piece
series of 4 lamps
Supply and installation of direction indicating blinking lamps Ø 180 mm, in
63 552 Piece
series of 8 lamps
Supply and installation of direction indicating flashing lamps Ø 180 mm, in
63 561 Piece
series of 4 lamps
Supply and installation of direction indicating flashing lamps Ø 180 mm, in
63 562 Piece
series of 8 lamps
63 571 Piece Supply and mounting of road mirror (without post)
Supply and incorporation of raised-type temporary reflective traffic marker
63 611 Piece
of ………………..

Draft of Version 1 – March 2008 Page 178


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and incorporation of raised-type temporary reflective traffic marker
63 612 Piece
of ………………..

6.4 Traffic Safety Equipment

Unit
Code Description of work
measure
Supply and erection of steel post for guard rail, length 1900 mm,
64 111 Piece
I - section
Supply and erection of steel post for guard rail, length 1900 mm,
64 112 Piece
U - section
Supply and erection of steel post for guard rail, length 1900 mm,
64 113 Piece
C - section
Supply and erection of steel post for guard rail, length 1900 mm,
64 114 Piece
…- section
Supply and erection of steel post for guard rail, length . . . . mm,
64 121 Piece
I - section
Supply and erection of steel post for guard rail, length . . . . mm,
64 122 Piece
U - section
Supply and erection of steel post for guard rail, length . . . . mm,
64 123 Piece
C - section
Supply and erection of steel post for guard rail, length . . . . mm,
64 124 Piece
…- section
64 131 Piece Supply and fitting of single steel spacer for guard rail
64 132 Piece Supply and fitting of double steel spacer for guard rail
Supply and mounting of rail for guard rail, including fixing accessories, of
64 141 m
steel sheet
Supply and mounting of rail for guard rail, including fixing accessories, of
64 142 m
aliminium sheet
Supply and mounting of rail for guard rail, including fixing accessories, of
64 143 m
cement concrete
Supply and mounting of rail for guard rail, including fixing accessories, of
64 144 m
reinforced plastic material
Supply and mounting of rail for guard rail, including fixing accessories, of
64 145 m
……………………………..

Draft of Version 1 – March 2008 Page 179


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and mounting of rounded end piece for guard rail, including fixing
64 151 m
accessories, of steel sheet
Supply and mounting of rounded end piece for guard rail, including fixing
64 152 m
accessories, of of aliminium sheet
Supply and mounting of rounded end piece for guard rail, including fixing
64 153 m
accessories, of cement concrete
Supply and mounting of rounded end piece for guard rail, including fixing
64 154 m
accessories, of reinforced plastic material
Supply and mounting of rounded end piece for guard rail, including fixing
64 155 m
accessories, of ……………………………..
64 161 m Extra payment for execution of buried end piece, length 4 m
64 162 m Extra payment for execution of buried end piece, length 12 m
Supply and installation of foundation for tension column, MB 20,
64 211 Piece
Ø 300 mm, h = 800 mm
Supply and installation of foundation of intermediate or anchor column
64 212 Piece
MB 20, Ø 200 mm, h = 700 mm
Supply and installation of aluminium pipe for tension column, Ø 65 mm,
64 213 Piece
L = 2350 mm
Supply and installation of aluminium pipe for tension column, Ø 65 mm,
64 214 Piece
L = 2550 mm
Supply and installation aluminium pipe for intermediate column, Ø 50
64 215 Piece
mm, L = 1300 mm
Supply and installation aluminium pipe for intermediate column, Ø 50
64 216 Piece
mm, L = 1950 mm
Supply and installation aluminium pipe for intermediate column, Ø 50
64 217 Piece
mm, L = 2150 mm
Supply and installation of aluminium pipe for diagonal support, Ø 50 mm,
64 218 Piece
L = 2400 mm
Supply and installation of aluminium pipe for anchor column, Ø 50 mm,
64 219 Piece
L = 300 mm
Supply and placing of safety fence mesh of hot-galvanised steel wire,
64 221 m2
including mesh fixing wire
Supply and installation of wire grid for self-supporting fence for protection
2
64 222 m of amphibians made of hot-dipped steel wire, including entire material for
fixing
Supply of hot-dipped steel wire grid for protection of amphibians, and
64 223 m2
installation onto the existing protecting fence, including material for fixing

Draft of Version 1 – March 2008 Page 180


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply and installation of plastified steel wire grid for protecting fence,
64 226 m2
including material for fixing
Supply and placing of safety fence mesh of aluminium wire, including
64 231 m2
mesh fixing wire
Supply and installation of aluminium wire grid for self-supporting fence for
64 232 m2
protection of amphibians, including entire material for fixing
Supply of aluminium wire grid for protection of amphibians, and
64 233 m2
installation onto the existing protecting fence, including material for fixing
Supply and straining of elevated portion of safety fence of hot-galvanised
64 241 m
steel wire
Supply and straining of elevated portion of safety fence of hot-aluminium
64 242 m
wire
64 251 m Supply and installation of additional wire over grid, spacing = 200 mm
64 254 m Supply and installation of reinforced tensioning wire – charged extra
Supply of galvanised wire – electrical fence conductor for protection of
64 261 m game – and installation above the existing protecting wire grid fence,
including insulators and entire material for fixing
Supply of livestock electric fence (15 to 20 J), including entire equipment
64 262 Piece
for operating on protecting fence and grounding
64 271 Piece Supply and installation of steel inlay for tensioning column L = 1000 mm
Supply and installation of steel inlay for intermediate column L = 1000
64 272 Piece
mm
Planting of live fence for median glare fence, as per drawing
64 311 m
………………
64 321 m Supply and mounting to the safety fence of antiglare elements of metal
Supply and mounting to the safety fence of antiglare elements of plastic
64 322 m
material
Supply and mounting to the safety fence of antiglare elements of
64 323 m
………………….
Supply and installation of warning device for poor visibility, as per drawing
64 411 Piece
………………..
64 412 Piece Supply and installation of warning device for poor visibility, ………………..
Supply and installation of warning device for concentration of CO in the
64 421 Piece
air, as per drawing ………………..
Supply and installation of warning device for concentration of CO in the
64 422 Piece
air, ………………..
Supply and installation of fire hazard warning device, as per drawing
64 431 Piece
………………..

Draft of Version 1 – March 2008 Page 181


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
64 432 Piece Supply and installation of fire hazard warning device, ………………..
64 441 Piece Supply and installation of wind hazard warning device

6.5 Road Equipment for Snow Removal and Ice Control

Unit
Code Description of work
measure
65 111 Piece Supply of wooden marker post for snow removal, length 2 m
65 112 Piece Supply of wooden marker post for snow removal, length 2.5 m
65 113 Piece Supply of wooden marker post for snow removal, length 3 m
65 114 Piece Supply of wooden marker post for snow removal, length . . . m
65 121 Piece Supply of plastic material marker post for snow removal, length 2 m
65 122 Piece Supply of plastic material marker post for snow removal, length 2.5 m
65 123 Piece Supply of plastic material marker post for snow removal, length 3 m
65 124 Piece Supply of plastic material marker post for snow removal, length . . . m
Supply of wooden element for snow drift fence, with wooden post, support,
65 211 m2
and/or anchor, of wooden bars
Supply of wooden element for snow drift fence, with wooden post, support,
65 212 m2
and/or anchor, offcuts
Supply of wooden element for snow drift fence, with wooden post, support,
65 213 m2
and/or anchor, ………………
Supply of mesh of plastic material for snow drift fence, with anchor and
65 221 m2
metal post
Supply of mesh of plastic material for snow drift fence, with anchor and
65 222 m2
wooden post
Supply of mesh of plastic material for snow drift fence, with anchor and
65 223 m2
……….. post
65 231 m Planting of live fence for snow drift fence, as per drawing ……………..
Supply of material for, and erection of, snow drift fence, as per drawing
65 241 Piece
……………
Supply of material for, and erection of, snow drift fence, as per drawing
65 242 Piece
……………
Supply of material for, and erection of, snow slide fence, as per drawing
65 311 Piece
……………

Draft of Version 1 – March 2008 Page 182


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Supply of material for, and erection of, snow slide fence, as per drawing
65 312 Piece
……………
Supply of material for, and erection of, windbreaker fence, as per drawing
65 321 Piece
……………
Supply and erection of thermometer shelter (incorporating thermometer,
65 411 Piece
hygrometer, and barometer), as per drawing …………….
Supply and erection of thermometer shelter (incorporating thermometer,
65 412 Piece
hygrometer, and barometer), as per drawing …………….
Supply and incorporation of glazed frost detecting and warning devices,
65 421 Piece
as per drawing …………….
Supply and incorporation of glazed frost detecting and warning devices, as
65 422 Piece
per drawing ……………
Supply and incorporation of snow quantity measuring device, as per
65 431 Piece
drawing …………….
Supply and incorporation of snow quantity measuring device, as per
65 432 Piece
drawing ……………
Supply of device for measuring the quantity of salt remaining on the
65 441 Piece
carriageway, as per drawing …………….
Supply of device for measuring the quantity of salt remaining on the
65 442 Piece
carriageway, as per drawing ……………

6.6 Other Road Equipment

Unit
Code Description of work
measure
66 111 m Planting with shrubs of a noise barrier belt, as per drawing ……………
66 112 m Planting with shrubs of a noise barrier belt,as per drawing …………….
66 121 m Planting with trees of a noise barrier belt, as per drawing ……………
66 122 m Planting with trees of a noise barrier belt, as per drawing …………….
3
66 131 m Construction of noise barriers embankment of soil material
3
66 132 m Construction of noise barriers embankment of rock material
3
66 133 m Construction of noise barriers embankment of mixed material
Construction of steep noise barrier embankment, with revetment of
66 141 m
cement concrete elements, height 1.5 m

Draft of Version 1 – March 2008 Page 183


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
Construction of steep noise barrier embankment, with revetment of
66 142 m
cement concrete elements, height 2.0 m
Construction of steep noise barrier embankment, with revetment of
66 143 m
cement concrete elements, height 2.5 m
Construction of steep noise barrier embankment, with revetment of
66 144 m
cement concrete elements, height 3.0 m
Construction of steep noise barrier embankment, with revetment of
66 145 m
cement concrete elements, height . . . m
Construction of steep noise barrier embankment, with revetment of
66 151 m
…………………. elements, height 1.5 m
Construction of steep noise barrier embankment, with revetment of
66 152 m
…………………. elements, height 2.0 m
Construction of steep noise barrier embankment, with revetment of
66 153 m
…………………. elements, height 2.5 m
Construction of steep noise barrier embankment, with revetment of
66 154 m
…………………. elements, height 3.0 m
Construction of steep noise barrier embankment, with revetment of
66 155 m
…………………. elements, height . . . m
66 211 m3 Construction of foundation for noise barrier wall, as per drawing …………..
66 212 m3 Construction of foundation for noise barrier wall, as per drawing …………..
Construction of foundation of prefab units for noise barrier wall, as per
66 221 m3
drawing …………..
Construction of foundation of prefab units for noise barrier wall, as per
66 222 m3
drawing …………..
66 231 m3 Construction of wooden noise barrier, as per drawing …………..
3
66 232 m Construction of wooden noise barrier, as per drawing …………..
66 241 m3 Construction of wooden noise barrier, as per drawing …………..
3
66 242 m Construction of wooden noise barrier, as per drawing …………..
66 251 m3 Construction of plastic material noise barrier, as per drawing …………..
3
66 252 m Construction of plastic material noise barrier,as per drawing …………..
3
66 261 m Construction of cement concrete noise barrier, as per drawing …………..
3
66 262 m Construction of cement concrete noise barrier, as per drawing …………..
Construction of asbestos-cement concrete noise barrier, as per drawing
66 271 m3
…………..
Construction of asbestos-cement concrete noise barrier, as per drawing
66 272 m3
…………..
66 281 m3 Construction of steel sheet noise barrier, as per drawing …………..

Draft of Version 1 – March 2008 Page 184


Albanian Road Construction Standards – ARCS 7 – List of Works
Albanian Road Design and Construction Standards

Unit
Code Description of work
measure
66 282 m3 Construction of steel sheet noise barrier,as per drawing …………..
66 291 m3 Construction of ……………. noise barrier , as per drawing …………..
3
66 292 m Construction of ……………. noise barrier, as per drawing …………..
Construction of urgent call telephone exchange,
66 311 Piece
as per drawing ……………..
Construction of urgent call telephone exchange,
66 312 Piece
as per drawing ……………..
66 321 Piece Erection of urgent call telephone post, as per drawing ……………..
66 322 Piece Erection of urgent call telephone post, as per drawing ……………..
Construction of power supply and telecommunication system for urgent
66 331 Piece
call equipment, as per drawing ……………..
Construction of power supply and telecommunication system for urgent
66 332 Piece
call equipment, as per drawing …………….
Execution of traffic counting device with induction loop, as per drawing
66 411 Piece
…………….
Execution of traffic counting device with induction loop, as per drawing
66 412 Piece
……………..
Execution of axle load counter per classes of vehicles, as per drawing
66 421 Piece
…………….
Execution of axle load counter per classes of vehicles, as per drawing
66 422 Piece
……………..