Unit Scope Jul 18 Aug '18 18' Sep 18' Nov 18' Dec 90% 10% Final
Sl. No. Project Details
Qty Amount Qty Amount Qty Amount Qty Amount Qty Amount
GIS -220 Kv & 66 KV
1 Set 2 2 1679.59 1 250 1 207 2 267
(Hysoung) 2403.6 267.0
55% 25% 25% 10%
Spares C4 to C11 Set 1 1 134.3 1 41.9 1 22.0 198.2 22.0
55% 25% 10%
2 Power Transformer-150 Nos 2 1 671.03 1 671.03 2 610.02 2 244.01
MVA -2 Nos with NIFPS 2196.1 244.0
55% 55% 25% 10%
Spares Set 1 1 28.51 1 12.96 1 5.2 46.6 5.2
Power Transformer-31.5
3 Nos 1 1 226.05 1 102.75 1 41.1
MVA -1 No. with NIFPS 369.9 41.0
55% 25% 10%
Spares Set 1 1 9.07 1.00 4.12 1.00 1.65 14.8 1.7
55% 25% 10%
4 CT -220 Nos 2 2 7.30 2 3.32 2 1.3 11.9 1.3
55% 25% 10%
CT-66 KV Nos 2 2 2.3 1 1.04 1.00 0.41 3.7 0.4
55%
CT-66 KV Nos 3
5 CRP Nos 35 471.02 102.5 108.0 40.0 721.5 80.1
55% 25% 25% 10%
Spares set 1 1 9.91 1 4.50 1 1.8 16.2 1.8
Spares set 1 2.97 1.35 0.54 4.9 0.5
55% 25% 10%
SAS Nos 1 1 251.4 1 114.3 1 45.70 411.3 45.7
55% 25% 10%
Spares Nos 1 1 3.96 1 1.8 1 0.72 6.5 0.7
55%
6 LA -60 KV Nos 12 3 0.9 9 2.5 12 1.5 12 0.5 5.5 0.5
Conductor, Al. Tube, HW,
7 Post Insulator (as PPP -8 & Set 1
28) 1 20.0805 1 9.1275 1 3.651 32.9 3.7
8 Post insulator 66 KV -6 Stack Nos 6 1 0.261 1 0.145 1 0.058
0.5 0.05
Aux. Transformer -250 KVA
9 Nos 2 2 11.59 2 5.27 2 2.11
-2 Nos. 19.0 2.1
55% 25% 10%
Billing Collection Plan
Unit Scope Jul 18 Aug '18 18' Sep 18' Nov 18' Dec 90% 10% Final
Sl. No. Project Details
Qty Amount Qty Amount Qty Amount Qty Amount Qty Amount
10 LT Switchgear Nos
LTAC Panel(Indoor) Nos 1 1 12.97 1 5.90 1 2.4 21.2 2.4
ACDB (Indoor) Nos 2 2 0.93 2 0.42 2 0.2 1.5 0.2
DCDB (Indoor) Nos 2 2 2.49 2 1.13 2 0.5 4.1 0.5
55% 25% 10%
Spares set 1 1 1.1 1 0.5 1 0.2 1.8 0.2
11 Cable-Power & Control KM 51 32.018 49.08 18.6 31.03 50.618 36.41 50.618 14.56 131.1 14.6
55% 55% 25% 10%
12 UG Cable -11 KV XLPE KM 1 1 17.0445 1 7.7475 1 3.099 27.9 3.1
55% 25% 10%
13 DG -63 KVA -1 No. Nos 1 1 5.3425 1 2.137 19.3 2.1
25% 10%
14 Battery - 2 Set Set 2 2 62.545 2 25.018 225.2 25.0
25% 10%
spares set 1 1 3.278 1 1.49 1 0.596 5.4 0.6
55% 25% 10%
15 Battery Charger -2 Set Set 2 1 18.3 2 16.66 2 6.664 60.0 6.7
55% 25% 10%
Spares set 1 2.948 1 1.34 1 0.536 4.8 0.5
55% 25% 10%
Power Transformer-31.5
3 Nos 1 1 226.05 1 102.75 1 41.1
MVA -1 No. with NIFPS 369.9 41.0
55% 25% 10%
Spares Set 1 1 9.07 1.00 4.12 1.00 1.65 14.8 1.7
55% 25% 10%
4 CT -220 Nos 2 2 7.30 2 3.32 2 1.3 11.9 1.3
55% 25% 10%
CT-66 KV Nos 2 2 2.3 1 1.04 1.00 0.41 3.7 0.4
55%
CT-66 KV Nos 3
5 CRP Nos 35 471.02 102.5 108.0 40.0 721.5 80.1
55% 25% 25% 10%
Spares set 1 1 9.91 1 4.50 1 1.8 16.2 1.8
Spares set 1 2.97 1.35 0.54 4.9 0.5
55% 25% 10%
SAS Nos 1 1 251.4 1 114.3 1 45.70 411.3 45.7
55% 25% 10%
Spares Nos 1 1 3.96 1 1.8 1 0.72 6.5 0.7
55%
6 LA -60 KV Nos 12 3 0.9 9 2.5 12 1.5 12 0.5 5.5 0.5
Conductor, Al. Tube, HW,
7 Post Insulator (as PPP -8 & Set 1
28) 1 20.0805 1 9.1275 1 3.651 32.9 3.7
8 Post insulator 66 KV -6 Stack Nos 6 1 0.261 1 0.145 1 0.058
0.5 0.05
Aux. Transformer -250 KVA
9 Nos 2 2 11.59 2 5.27 2 2.11
-2 Nos. 19.0 2.1
55% 25% 10%
Billing Collection Plan
Unit Scope Jul 18 Aug '18 18' Sep 18' Nov 18' Dec 90% 10% Final
Sl. No. Project Details
Qty Amount Qty Amount Qty Amount Qty Amount Qty Amount
10 LT Switchgear Nos
LTAC Panel(Indoor) Nos 1 1 12.97 1 5.90 1 2.4 21.2 2.4
ACDB (Indoor) Nos 2 2 0.93 2 0.42 2 0.2 1.5 0.2
DCDB (Indoor) Nos 2 2 2.49 2 1.13 2 0.5 4.1 0.5
55% 25% 10%
Spares set 1 1 1.1 1 0.5 1 0.2 1.8 0.2
11 Cable-Power & Control KM 51 32.018 49.08 18.6 31.03 50.618 36.41 50.618 14.56 131.1 14.6
55% 55% 25% 10%
12 UG Cable -11 KV XLPE KM 1 1 17.0445 1 7.7475 1 3.099 27.9 3.1
55% 25% 10%
13 DG -63 KVA -1 No. Nos 1 1 5.3425 1 2.137 19.3 2.1
25% 10%
14 Battery - 2 Set Set 2 2 62.545 2 25.018 225.2 25.0
25% 10%
spares set 1 1 3.278 1 1.49 1 0.596 5.4 0.6
55% 25% 10%
15 Battery Charger -2 Set Set 2 1 18.3 2 16.66 2 6.664 60.0 6.7
55% 25% 10%
Spares set 1 2.948 1 1.34 1 0.536 4.8 0.5
55% 25% 10%