Vous êtes sur la page 1sur 65

Project N° Unit Document Code Serial N° Rev.

Page
2408 0000 MS 6740 52 0 1/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Job Specification
for
Material Preservation During
Storage, Construction,
Precommissioning &
Commissioning
it is specifically furnished or outside the extent of the agreed upon right of use.

0 03-MAY-13 ISSUED FOR EXECUTION COVASSIN SCHIAROLI / DI GENNARO FIDICCI / MAGARINI / VIDAL

A 05-OCT-11 ISSUED FOR REVIEW ROSSI SCHIAROLI / DI GENNARO FIDICCI / MAGARINI / VIDAL
REV. DATE STATUS WRITTEN BY CHECKED BY APPROV./AUTHOR. BY
(name & visa) (name & visa) (name & visa)
DOCUMENT REVISIONS

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 2/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

INDEX
Page

1.  SCOPE 6 
2.  REFERENCE DOCUMENT 7 
3.  DEFINITION AND ACRONYM 8 
4.  RESPONSIBILITIES 9 
4.1.  CONTRACTOR 9 
4.2.  CONSTRUCTION CONTRACTOR 10 
5.  PRESERVATION MANAGEMENT SYSTEM 12 
6.  SUMMARY OF PRESERVATION ACTIVITIES AND RESPONSIBILITIES 13 
7.  PRESERVATION PHILOSOPHY 15 
7.1.  GENERAL 15 
7.1.1.  Influence of climate and cyclic operations 15 
7.1.2.  Rain, moisture and high humidity 15 
7.1.3.  Idle rotating equipment 15 
7.2.  PRESERVATION PERIODS AND PHASES 15 
8.  RUST PREVENTIVES 17 
8.1.  PROTECTIVE PRODUCTS 17 
8.2.  METHODS OF PROTECTION 18 
9.  PRESERVATION FOR SPECIAL MATERIALS 20 
9.1.  Austenitic Stainless Steel 20 
9.2.  FERRITIC STAINLESS STEEL 20 
9.3.  ALUMINIUM, NICKEL, NICKEL ALLOY AND NICKEL STEEL 20 
9.4.  BRICK-LINED/REFRACTORY-LINED EQUIPMENT 20 
10.  PIPING SYSTEM 21 
10.1.  PIPING MATERIALS 21 
10.1.1.  Storage 21 
10.1.2.  Initial Preservation 23 
10.1.3.  Maintenance during Preservation (Interval: 4 weeks) 24 
it is specifically furnished or outside the extent of the agreed upon right of use.

10.1.4.  Restoration 24 


10.1.5.  Notes 24 
11.  STATIC EQUIPMENT 25 
11.1.  SHELL AND TUBE HEAT EXCHANGER 25 
11.1.1.  Storage 25 
11.1.2.  Initial Preservation 26 
11.1.3.  Maintenance during Preservation (Interval: 4 weeks): 26 
11.1.4.  Restoration 26 
11.1.5.  Notes 27 
11.2.  AIR - COOLED HEAT EXCHANGER 28 

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 3/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.2.1.  Storage 28 


11.2.2.  Initial Preservation 28 
11.2.3.  Maintenance during Preservation (Interval: 4 weeks) 29 
11.2.4.  Restoration 29 
11.2.5.  Notes 29 
11.3.  FLOATING ROOF TANK, FIXED ROOF TANK AND SPHERE 30 
11.3.1.  Storage 30 
11.3.2.  Initial Preservation 30 
11.3.3.  Maintenance during Preservation (Interval: 4 weeks) 30 
11.3.4.  Restoration 30 
11.4.  VESSEL, FILTERS, COLUMN AND REACTOR 31 
11.4.1.  Storage 31 
11.4.2.  Initial Preservation 32 
11.4.3.  Maintenance during Preservation (Interval: 4 weeks) 32 
11.4.4.  Restoration 32 
11.4.5.  Notes 33 
11.5.  FURNACE 34 
11.5.1.  Storage 34 
11.5.2.  Initial Preservation 34 
11.5.3.  Maintenance during Preservation (Interval: 4 weeks) 34 
11.5.4.  Restoration 35 
11.6.  BOILER 36 
11.6.1.  Storage 36 
11.6.2.  Initial Preservation 36 
11.6.3.  Maintenance during Preservation (Interval: 4 weeks) 36 
11.6.4.  Restoration 37 
11.6.5.  Notes 37 
12.  ROTATING EQUIPMENT 38 
12.1.  Centrifugal Pump with Lube Oil System 38 
12.1.1.  Storage 38 
12.1.2.  Initial Preservation 38 
12.1.3.  Maintenance during Preservation (Interval: 2 weeks) 39 
12.1.4.  Restoration 39 
12.1.5.  Notes 39 
12.2.  CENTRIFUGAL PUMP AND BLOWER 40 
12.2.1.  Storage 40 
it is specifically furnished or outside the extent of the agreed upon right of use.

12.2.2.  Initial Preservation 40 


12.2.3.  Maintenance during Preservation (Interval: 4 weeks) 40 
12.2.4.  Restoration 41 
12.2.5.  Notes 41 
12.3.  RECIPROCATING PUMP 42 
12.3.1.  Storage 42 
12.3.2.  Initial Preservation 42 
12.3.3.  Maintenance during Preservation (Interval: 2 weeks) 42 
12.3.4.  Restoration 43 
12.3.5.  Notes 43 

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 4/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.4.  DOSING AND ROTARY PUMP 44 


12.4.1.  Storage 44 
12.4.2.  Initial Preservation 44 
12.4.3.  Maintenance during Preservation (Interval: 4 weeks) 44 
12.4.4.  Restoration 44 
12.4.5.  Notes 44 
12.5.  CENTRIFUGAL COMPRESSOR 45 
12.5.1.  Storage 45 
12.5.2.  Initial Preservation 45 
12.5.3.  Maintenance during Preservation (Interval: 2 weeks) 45 
12.5.4.  Restoration 45 
12.5.5.  Notes 46 
12.6.  CENTRIFUGAL COMPRESSOR WITH LUBE OIL SYSTEM 47 
12.6.1.  Storage 47 
12.6.2.  Initial Preservation 47 
12.6.3.  Maintenance during Preservation (Interval: 2 weeks) 47 
12.6.4.  Restoration 48 
12.6.5.  Notes 48 
12.7.  RECIPROCATING AND SCREW COMPRESSOR 49 
12.7.1.  Storage 49 
12.7.2.  Initial Preservation 49 
12.7.3.  Maintenance during Preservation (Interval: 2 weeks) 49 
12.7.4.  Restoration 50 
12.7.5.  Notes 50 
12.8.  DIESEL ENGINE 51 
12.8.1.  Storage 51 
12.8.2.  Initial Preservation 51 
12.8.3.  Maintenance during Preservation (Interval: 4 weeks) 51 
12.8.4.  Restoration 51 
12.8.5.  Notes 52 
12.9.  STEAM AND GAS TURBINE 52 
12.9.1.  Storage and Preservation 52 
13.  ELECTRICAL EQUIPMENT AND MATERIALS 53 
13.1.  Electrical Panel Boards 53 
13.1.1.  Storage and Preservation 53 
it is specifically furnished or outside the extent of the agreed upon right of use.

13.2.  BULK ELECTRICAL MATERIAL 53 


13.2.1.  Storage and Preservation 53 
13.3.  CABLES 53 
13.3.1.  Storage and Preservation 53 
13.4.  BATTERIES 53 
13.4.1.  Storage and Preservation 53 
13.5.  TRANSFORMERS 54 
13.5.1.  Storage and Preservation 54 
13.6.  ELECTRIC MOTOR 54 
13.6.1.  Storage 54 

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 5/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

13.6.2.  Initial Preservation 54 


13.6.3.  Maintenance during Preservation (Interval: 4 weeks) 55 
13.6.4.  Restoration 55 
13.6.5.  Notes 55 
13.7.  GENERATOR 56 
13.7.1.  Storage 56 
13.7.2.  Initial Preservation 56 
13.7.3.  Maintenance during Preservation (Interval: 4 weeks) 56 
13.7.4.  Restoration 57 
14.  INSTRUMENTAL EQUIPMENT AND MATERIALS 58 
14.1.  Valves and accessories 58 
14.1.1.  Storage 58 
14.1.2.  Initial Preservation 59 
14.1.3.  Maintenance during Preservation (Interval: 3 months) 59 
14.1.4.  Notes 59 
14.2.  ELECTRONIC AND PNEUMATIC TRANSMITTER (FIELD AND BOARD TYPE) 60 
14.2.1.  Storage 60 
14.2.2.  Initial Preservation 60 
14.2.3.  Maintenance during Preservation (Interval: 3 months) 60 
14.2.4.  Notes 60 
14.3.  FIELD INSTRUMENTS 61 
14.3.1.  Storage 61 
14.3.2.  Initial Preservation 61 
14.3.3.  Notes 61 
14.4.  LOCAL CABINETS, PANEL AND JUNCTION BOXES 62 
14.4.1.  Storage 62 
14.4.2.  Initial Preservation 62 
14.4.3.  Maintenance during Preservation (Interval: 4 weeks) 62 
14.4.4.  Restoration 62 
14.5.  ELECTRONIC CONTROL BOARDS AND CABINETS – DCS/COMPUTERS (FOR
CONTROL AND TERMINATING ROOMS) 62 
14.5.1.  Storage 62 
14.5.2.  Preservation 63 
14.6.  BULK MATERIAL FOR INSTRUMENTS 63 
14.6.1.  Storage 63 
it is specifically furnished or outside the extent of the agreed upon right of use.

14.7.  INSTRUMENT CABLES 63 


14.7.1.  Storage 63 
14.7.2.  Preservation 63 
15.  MISCELLANEOUS MATERIALS 64 
15.1.  PAINTING MATERIALS 64 
15.1.1.  Storage 64 
15.2.  INSULATION MATERIALS 65 
15.2.1.  Storage 65 

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 6/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

1. SCOPE

Scope of this document is to specify responsibilities, requirements and recommendations


for the preservation of all plant permanent materials.

The preservation activity includes all protection and maintenance operation of all plant
material, equipment and component to be carried out up to Ready for Start-Up (RFSU).

The general guidance given in this manual summarizes the procedures to be used to
ensure the adequately preservation of all plant components in order to maintain their
technical integrity for the period standing idle.

The general guidance given in this manual has to be considered as an integration of


Supplier/Manufacturer Instructions. As general requirement, if available,
Supplier/Manufacturer's Preservation Instructions shall be referred to.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 7/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

2. REFERENCE DOCUMENT

The reference documents are:

Document Description Doc Code

Construction Quality Control Procedure 1000-PA-8018

Start Up Field Quality Control Procedure 1000-PA-9002

Instruction Manual Precommissioning of Industrial Plant 1000-MU-9002

Site Material Management Procedure 2408-0000-PP-806

Hand Over Procedure 2408-0000-PP-903

Site Inspection Coordination Procedure 2408-0000-PP-810

Job Construction Specification for Material Receiving


2408-0000-MS-6740.51
and Warehousing
Quality Control Plan for Material Receiving, Warehousing
2408-0000-QCP-0000.01
and Maintenance
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 8/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

3. DEFINITION AND ACRONYM

OWNER BRASKEM IDESA SAPI

The company that will provide detail


CONTRACTOR engineering, procurement, construction
and precommissioning services.
CONSTRUCTION CONTRACTOR Entity executing the work

SQCM Site Quality Control Manager

(Construction, Precommissioning &


QCP
Commissioning) Quality Control Plan
(Construction, Precommissioning &
QCF
Commissioning) Quality Control Form
(Construction, Precommissioning &
QCR
Commissioning) Quality Control Report

MS–XXXX-XX Job Specifications for Construction

PRE-COMMISSIONING Conformity checks and cold tests

Live (energized) tests and major


COMMISSIONING
equipment on line test (operational tests)
Major subdivision of an installation which
SYSTEM performs a major operational function of
the plant (e.g. a process unit)
Further subdivision of a system, which
performs a partial operational function to
SUBSYSTEM
the system, with no interference with other
subsystems.
Status of a subsystem when all Pre-
READY FOR COMMISSIONING (RFC) commissioning operations on that
subsystem are complete
Status of a subsystem when all
it is specifically furnished or outside the extent of the agreed upon right of use.

READY FOR START-UP (RFSU) Commissioning operations on that


subsystem are complete
Status of a system when all
READY FOR INITIAL START-UP (RFISU) Commissioning operations on that
subsystem are complete
READY FOR INITIAL START-UP Acceptance Notice by OWNER to the
ACCEPTANCE NOTICE (RFISUAN) requested RFISU of the system

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 9/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

4. RESPONSIBILITIES

4.1. CONTRACTOR

Depending on Project phases duties of Preservation Manager are performed by:


ƒ Material Handling Coordinator during Construction phase (or Site Manager if Material
Handling Coordinator is not present at jobsite);
ƒ Precommissioning/Commissioning Manager during Precommissioning/Commissioning
phase (or a person officially appointed by Precommissioning/Commissioning Manager).
Due to the overlapping of Construction phase and Precommissioning/Commissioning
phase (even if in different area of the plant) the two Preservation Managers will coexist
during most of the site works.

Material Handling Coordinator / Preservation Manager is responsible to:


ƒ Start and control the entire process with the support of:
9 Preservation Management System Operator (PMSO);
9 Construction - Discipline Supervisor;
9 QC Inspector;
9 Plant Maintenance Section;
9 Construction Contractor;
ƒ Issue the Quality Control Form QC 04a and QC 04b (see 2408 0000 QCP 0000.01, Att.
A), including Material Maintenance Cards.
ƒ Transfer all information to Precommissioning/Commissioning Manager when
equipment is handed over to Precommissioning/Commissioning team.

Precommissioning/Commissioning Manager is responsible to


ƒ Control the entire process with the support of:
9 Preservation Management System Operator (PMSO);
9 Precommissioning - Discipline Supervisor;
9 Plant Maintenance Section;
9 Construction Contractor;
ƒ Distribute and retain final record (Material Maintenance Card – Quality Control Form
QC 04a/QC 04b, see 2408 0000 QCP 0000.01, Att. A) in his archives at time of issuing
of final Hand Over (RFISU – Ready for Initial Start-Up) to OWNER;
ƒ Include it in the Hand Over (RFISU – Ready for Initial Start-Up) Dossier to be
transferred to OWNER.
it is specifically furnished or outside the extent of the agreed upon right of use.

Plant Maintenance Section, supported by Construction Technical Services, is responsible


to:
ƒ Prepare;
ƒ Issue;
ƒ Update (when Vendor Preservation Recommendation is available);
the Preservation Instructions and Material Maintenance Cards (see Quality Control Form
QC 04a & b, see 2408 0000 QCP 0000.01, Att. A).

Above activities are performed at CONTRACTOR home-office.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 10/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Preservation Management System Operator (PMSO), part of Warehouse Management


Team, is responsible to:
ƒ Obtain information on the material arrival date at site;
ƒ Insert such date in the Preservation Management System in order to start the
preservation schedule;
ƒ Upon receipt of equipment at site, hand over through email/transmittal the Material
Maintenance Card to Construction Contractor, copy to Discipline Supervisors and QC
Inspector;
ƒ Maintain, through Preservation Management System report, a log book for tracking
and periodical follow-up with Construction and Precommissioning Discipline
Supervisors (DS);
ƒ Update the Preservation Management System once the duly filled and signed Material
Maintenance Card copy is returned back.

Construction - Discipline Supervisors are responsible to:


ƒ Validate the Quality Control Form QC 04a (see 2408 0000 QCP 0000.01, Att. A);
ƒ Witness, by its presence, the preservation activities execution and signs the Material
Maintenance Card – Quality Control Form QC 04a, QC 04b (see 2408 0000 QCP
0000.01, Att. A).

Precommissiong - Discipline Supervisors are responsible to:


ƒ Verify the Material Maintenance Card – Quality Control Form QC 04a / QC 04b (given
to Construction Contractor by Construction - Discipline Supervisors) (see 2408 0000
QCP 0000.01, Att. A), from the Precommissioning/Commissioning point of view in
order to define specific needs or updates;
ƒ Witness, by its presence, the preservation activities execution and signs the Material
Maintenance Card – Quality Control Form QC 04b (see 2408 0000 QCP 0000.01, Att.
A).

QC Inspector is responsible to:


ƒ Authorize, by signature, the issuing of the Material Maintenance Card – Quality Control
Form QC 04a (see 2408 0000 QCP 0000.01, Att. A).

4.2. CONSTRUCTION CONTRACTOR


it is specifically furnished or outside the extent of the agreed upon right of use.

CONSTRUCTION CONTRACTOR, before starting preservation activities, has to nominate


a reference person responsible of all concerning activities.

CONSTRUCTION CONTRACTOR reference person is responsible for the execution of


the preservation activities (starting from material receiving at jobsite until material hand
over according to Contract terms between CONTRACTOR and CONSTRUCTION

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 11/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

CONTRACTOR), as defined by CONTRACTOR, of all the plant components (equipment,


lines, instruments, etc.) during the following project phase:
ƒ Storage/Warehousing
ƒ Erection;
ƒ Precommissioning;
ƒ Commissioning phases up to Ready for Initial Start-Up (RFISU).

During Construction, Precommissioning and Commissioning phases, CONSTRUCTION


CONTRACTOR closely coordinates and communicates with CONTRACTOR Preservation
Manager (Material Manager or Precommissioning/Commissioning Manager depending by
project phase) and strictly follows the Permit to work procedure and the Site Inspection
Coordination Procedure (see 2408-0000-PP-810) in order to prevent “cross work”
conditions.

CONSTRUCTION CONTRACTOR reference person keeps the Material Maintenance


Card at his care and updates it every time a preservation activity is done. Material
Maintenance Card shall be made available at CONSTRUCTION CONTRACTOR filing
room and shown during QC audit/inspection.

CONSTRUCTION CONTRACTOR executes all the preservation activities in a proper and


safe manner following the procedures issued by CONTRACTOR, procedures developed
in compliance with Supplier/Manufacturer Instructions.

CONSTRUCTION CONTRACTOR fills in and retains all the preservation forms on a


“system wise” approach, subdivided by type of equipment (where applicable and/or
required by CONTRACTOR) in accordance to the Preservation Plan issued by
CONTRACTOR.

CONSTRUCTION CONTRACTOR has to inform by means of formal communication (on


weekly basis, every Thursday) CONTRACTOR Discipline Supervisors in order to allow
them to be present during preservation activities.
When activities is completed and the Material Maintenance Card – Quality Control Form
QC 04a / QC 04b (see 2408 0000 QCP 0000.01, Att. A) is duly filled in and signed by
CONTRACTOR Discipline Supervisor, sends a copy to the Preservation Management
System Operator (PMSO).

CONSTRUCTION CONTRACTOR, at time of issuing the Ready for Initial Start-Up


it is specifically furnished or outside the extent of the agreed upon right of use.

Certificate (RFISU Certificate) (see 2408-0000-PP-903), submits the Preservation folder


containing all the preservation reports to the Precommissioning/commissioning Manager
for:
ƒ Final record, distribution and retention in his archives;
ƒ Inclusion in the RFISU Dossier to be transferred to OWNER.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 12/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

5. PRESERVATION MANAGEMENT SYSTEM

Starting from the Engineering phase, CONTRACTOR will develop the Preservation
Management System to manage all preservation activities.

Data coming from CONTRACTOR Engineering and Supplier/Manufacturer documentation


will be checked, prepared and loaded into the Preservation Management System.
The Preservation Management System will be used for:
ƒ Itemized mechanical, electrical equipment and other special items (with reference to
the Project Item Index);
ƒ Preservation activities definition;
ƒ Preservation activities scheduling;
ƒ Preservation activities control.

For each itemized equipment or group of itemized equipment, a summary report with the
following data, will be issued:
ƒ Plant area / unit code;
ƒ System and subsystem hand over code.
ƒ Date of arrival at site;
ƒ Date of installation.
ƒ Preservation activities.

Preservation activities instructions will be developed in accordance with:


ƒ Supplier/Manufacturer Instructions;
ƒ CONTRACTOR internal instructions (in case of missing data/information by
Supplier/Manufacturer).

Remarks: all Preservation Instructions, included in this procedure, have been developed
by CONTRACTOR in accordance with International Standard, and they will be applied in
case of missing data/information by Supplier/Manufacturer.
In case of contrast between the instruction for storage/preservation given on the
packages/packing lists, and that given by the Supplier/Manufacturer’s storage
instructions, the last prevails.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 13/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

6. SUMMARY OF PRESERVATION ACTIVITIES AND RESPONSIBILITIES

The following table summarizes the key activities and the main responsibilities of involved
parties during the Material and Equipment Preservation.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which
it is specifically furnished or outside the extent of the agreed upon right of use.

CONTRACTOR CODE: N.A.


2408
Project N°

ETILENO XXI PROJECT


Unit
0000

BRASKEM-IDESA CODE:

CLIENT: BRASKEM IDESA SAPI


MS 6740
Document Code

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


52
Serial N°
0
Rev.

EXXI-040-00-00-CM-MS-0004
Page
14/65
Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 15/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

7. PRESERVATION PHILOSOPHY

7.1. GENERAL

Preservation philosophy should be developed and implemented considering conditions


causing incipient failure as hereafter detailed.

7.1.1. Influence of climate and cyclic operations

Climatic conditions can be the cause of incipient failure of equipment standing idle: it is
important that these conditions and the effect they can have on various types of
equipment are analysed before determining which preservation procedures and methods
of protection should be applied.

7.1.2. Rain, moisture and high humidity

The rate of corrosion may increase greatly in areas where the atmosphere has a high
humidity and contains corrosive contaminants. In coastal areas, salt deposited by sea
spray or rain can have similar adverse effects. High concentrations of these contaminants
can collect in crevices and under insulation if the external sheeting is not water-tight.
Severe corrosion can be expected, particularly in plants where the maximum operating
temperature of the plant did not permit the application of an effective paint coating. This
situation will be aggravated where such plant is in intermittent operation. In such cases
additional inspection will be required to determine the degradation rate particularly if the
equipment or piping is insulated.
If "cold" insulation (i.e. insulation for cryogenic systems which operate below 0 °C)
absorbs moisture during the period standing idle, it can be damaged upon commissioning
when the plant is cooled down.
Similar problems may arise with valves in cryogenic service. Should moisture become
trapped in the crevices between the spindle and valve body during the idle period, then
the water will freeze when the plant is subsequently cooled down, and the valve may
become inoperable.

7.1.3. Idle rotating equipment

Slender horizontal rotor shafts when not rotating could be subjected to a plastic
it is specifically furnished or outside the extent of the agreed upon right of use.

deformation. Such a deformation, even if only very small, will cause damage during
subsequent start-up.
Bearings could be damaged by high pressure contact over a long period between two
locally contacting surfaces.

7.2. PRESERVATION PERIODS AND PHASES

The extent of preservation is primarily a function of the time for which a plant is to be
standing idle, consequently preservation periods can be defined as:

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 16/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

ƒ Temporary preservation when the period of idleness may be about 2 months (1 year
for civil engineering items, storage tanks, stacks, structural steelwork);
ƒ Short-term preservation when the period of idleness may about 1 year (2 years for
civil engineering items, storage tanks, stacks, structural steelwork);
ƒ Long-term preservation (not included in this procedure: if required refer to Mfr
manual) when the period of idleness is more than 1 year (more than 2 years for civil
engineering items, storage tanks, stacks, structural steelwork).

It is recognized that in some cases there will be justification for adopting a preservation
procedure lying between the terms defined above.

For each single preservation period (temporary, short-term and long-term preservation),
three time phases can be defined:

ƒ Initial preservation, when plant systems are physically prepared and treated for a
temporary, short or long period of non-use;
ƒ Maintenance during Preservation, when plant systems are periodically inspected and
treated to ensure that deterioration of system parts is nil or is restricted to within
acceptable limits;
ƒ Restoration, when plant systems are returned to their original condition (i.e. prior
preservation) and in conformity with plant Precommissioning/commissioning
requirements. The removal of petroleum-based protective product by means of
hydrocarbon solvents with low flash point has to be handled carefully to prevent fires.
VPI powders are flammable: their removal either by air blasting or water washing is
necessary as a safety precaution before starting up fired equipment.

It is always advisable to recall the Supplier/Manufacturers' representatives to assist with


the reassembly and test running of major rotating items.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 17/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

8. RUST PREVENTIVES

Residues of perspiration, soldering fluxes, grinding compounds, atmospheric dust


particles, etc., can greatly reduce the effectiveness of rust preventive.
In order that rust preventive may function with maximum effectiveness, it is essential that
the surface be thoroughly cleaned prior to its application: surfaces shall be cleaned with
mineral spirit, aliphatic petroleum naphtha or any other standard solvent, prior to
application of any rust preventive product. Kerosene shall not be used as cleaning agents.
Where the surfaces are rusting, it has to be necessary to remove the rust by mechanical
or hand brush, clean the surfaces with solvent and coat them with anti-rust product.

The severity of exposure to rusting naturally determines the degrees of protection


required. The first factor to be considered is the amount of exposure to air and moisture.
The higher the humidity of the atmosphere, the greater will be the tendency to rust.
It is generally considered that the critical relative humidity for iron is 40 to 60 percent and
that rusting is likely in atmospheres of relative humidity above this range.
Packaging alone will not prevent condensation of atmospheric moisture: it still occurs in
the air space in the wrapped enclosure.
The degree of protection also depends on external circumstances. A given protective
product will give freedom from corrosion for a much longer time in a dry atmosphere
indoors than if stored outside exposed directly to the weather.

8.1. PROTECTIVE PRODUCTS

The use of protective products such as fluids and oils, vapour-phase corrosion inhibitors
and certain grades of greases are recommended, wherever possible, for the preservation
of equipment standing idle.

Protective products belong mainly to the following types:


ƒ Rust-ban lube compatible preservative oils, used for internal parts and surfaces
protected by casing (gears, bearings, shafts, levers, etc.). They have some lubrication
properties; they are compatible with conventional mineral oil lubricants and are usually
applied by brush, by filling or by spray. After initial application, they must be checked
for contamination and renewed, if necessary.
ƒ Rust-ban for exterior surfaces. These will not have lubricating properties and they
should be removed before placing protected part in service. They are usually divided
it is specifically furnished or outside the extent of the agreed upon right of use.

in:
9 Dry layer for external parts of equipment/materials requiring long-term outdoor
storage: this coating must be inspected periodically and renewed in case of breaks
in the film. Solvent must remove the said layer before assembling the relative
protected parts;
9 Soft layer for external or internal parts of equipment and machines: this layer, for
some applications, does not require removal by solvent before assembling.
ƒ Protective grease wrapped with oiled paper;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 18/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

ƒ Vapour phase corrosion inhibitors. When they are used in the proper quantities, these
vapour-phase corrosion inhibitors can be applied advantageously for the internal
protection of turbines, compressors, hydraulic systems, bearings, engines, heat
exchangers, pipes, vessels, etc. Under adverse conditions (e.g. high humidity, widely
fluctuating temperatures and corrosive atmospheres) the periods of protection will be
reduced and periodic inspection should be performed: Low temperature will reduce the
vapour production rate. These corrosion inhibitors can be divided into two types:
9 VPIs (Vapour Phase Inhibitors), crystalline powders which slowly vaporise into the
enclosed space inside a package;
9 VSI (Vapour Space Inhibited) concentrate, an oily concentrate that can be added
to lubrication/sealing oil system when equipment is not going to be completed filled.
The protection is obtained by the evaporation of the medium, the vapour being
absorbed as an invisible film on the protected surfaces.
ƒ Desiccants are drying agents, such as silica gel, to be used inside closed equipment.
The desiccant should be placed in a suitable container and periodically renewed. It
shall not be used in combination with VPI

Certain products used in formulating rust preventatives have a low to moderate level of
oral toxicity. Applicators should follow the regulations recommended for the safe handling
and use of these products.

8.2. METHODS OF PROTECTION

Typical methods of protection can be divided in the following two groups:

ƒ Exterior protection, including:


9 Cocooning, envelopment of equipment in a single plastic coating. The coating is
applied by spraying either directly onto the equipment body or onto a special
wrapping of paper or wire netting. Before cocooning, the equipment shall be
carefully cleaned of grease and dust, and then dried. Cocooning should conform to
the equipment Supplier/Manufacturer's recommendations. Where possible, the
envelope should be pressurized by inert gas (small overpressure);
9 Coating to be applied on the bright-finished moving parts of mechanical equipment
but only after cleaning and drying of the surfaces;
9 Wrapping with waterproof paper or VPI paper. It is a cheap method of protection.
However, the equipment protected in this way should be stored under cover.

ƒ Interior protection, including:


it is specifically furnished or outside the extent of the agreed upon right of use.

9 Oil coating of the interior of the stationary equipment may be carried out by
spraying to form a protective film on the surface or, if the foundation is strong
enough, by filling and subsequent draining;
9 Filling. Often one of the factors limiting the filling of process and storage equipment
is the strength of the foundation. Adequate measures shall be taken to allow for
expansion of the filling fluid, which can be a gas oil or inhibited fresh water;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 19/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

9 Vapour-phase corrosion inhibitor method can be used advantageously for the


internal protection of engines, bearings, turbines, heat exchangers, pipes, drums,
small tanks and like equipment. Care should be taken to ensure that no pockets of
water are present and that the piece of equipment to be protected is dry and
properly closed off from the atmosphere;
9 Dry inert gas filling. All hermetically closed equipment may be protected by drying
the air or displacing it by an inert gas, e.g. nitrogen, and maintaining a slight positive
internal pressure.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 20/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

9. PRESERVATION FOR SPECIAL MATERIALS

9.1. Austenitic Stainless Steel

Equipment and piping of austenitic stainless steel shall be thoroughly cleaned and dried
internally because deposits, pockets of water or oil can lead to serious corrosion.
Water containing a concentration of chlorides may precipitate stress corrosion cracking or
pitting. Due to biological components left in systems or introduced with the testing or
flushing water, there is also the possibility of microbiological induced corrosion.
After drying, equipment and piping have to fill with dry inert gas, maintaining a slight
positive internal pressure, to prevent the introduction of oxygen.

9.2. FERRITIC STAINLESS STEEL

Ferritic stainless (chromium) steel equipment should be cleaned and dried and be closed
for preservation. If pitting corrosion is possible, austenitic stainless steel procedure has to
be applied.

9.3. ALUMINIUM, NICKEL, NICKEL ALLOY AND NICKEL STEEL

Aluminium equipment shall be kept clean and dry.

Nickel, nickel alloy and nickel steel equipment shall be cleaned and kept dry.
If pitting corrosion is possible, austenitic stainless steel procedure has to be applied to
nickel, nickel alloy and nickel steels.

9.4. BRICK-LINED/REFRACTORY-LINED EQUIPMENT

Pre-stressed brick lining should be kept above 0 °C in order to avoid excessive stresses in
the lining.
All stacks and refractory-lined equipment shall be protected against water ingress and, in
tropical areas, condensation of water vapour.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 21/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

10. PIPING SYSTEM

10.1. PIPING MATERIALS

10.1.1. Storage

10.1.1.1. Flanges

Flanges shall be stored inside the warehouse as much as possible, outside storage, if
any, shall be carefully monitored to detect any needs of flange surface protection repair.
Special care must be taken in handling flanges. Flange surface and grooves must be
carefully inspected at flange arrival at site for surface integrity checking; scratches, rust or
other damages must be immediately shown to QC Supervisor/Inspector for action.

Flanges stored inside warehouse


Check anti-rust protection on seal surfaces provided by Supplier/Manufacturer.
Renew any damaged protection by applying a coat of protection product (refer to § 8.1 -
Dry layer for external parts) and protect with plastic sheets or wooden covers.

Flanges stored outside warehouse


Repeat operations as per flanges stored inside warehouse.
Storage area must be fully drained, concrete paved or decked.
Flanges shall not be stored in direct contact with the ground.
Check every 3 months and renew protection product (refer to § 8.1 - Dry layer for external
parts) as required.

10.1.1.2. Fittings

Fittings up to and including ∅ 2” shall be stored inside the warehouse in racking.


Renew the protection selected by Supplier/Manufacturer.
Fittings of different material must be stored separately.
Check and maintenance every 3 months.

10.1.1.3. Nuts and Bolts

All nuts and bolts shall be stored inside the warehouse.


it is specifically furnished or outside the extent of the agreed upon right of use.

Protection products (refer to § 8.1 – Rust-ban lube compatible preservative oils and/or
Soft layer for external or internal parts) shall be applied to all nuts and bolts by immersion.
Nuts and bolts of different material must be stored separately.

10.1.1.4. Packing and Gaskets

Packing and gaskets shall be stored inside the warehouse. Flat packing shall be stored on
flat surfaces to avoid deformation due to stress and protected against mechanical
damage.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 22/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Ring-joints shall be stored as for flat packing above, and shall be protected with grease
and covered with oiled paper, or sprayed/brush coated with protection product (refer to §
8.1 – Soft layer for external or internal parts).
Check every 3 months.

10.1.1.5. Pipes

All pipes shall be stored outside except for special requirements.


Special attention must be taken in pipe material identification.
Pipe material must be clearly identified by painting according to color code specifications.
Different pipe material must be stored separately and each rack shall be identified with a
plate showing: size, range, quality, schedule, etc., in order to avoid any error.

Polyethylene coated pipes shall be stored separated from each other by plastic sheets.

Pipes inside the warehouse


No protection is required for pipes stored above soil on wood beams.

Pipes outside the warehouse


Check the proper drainage of the storage area.
Do not store in contact with the ground, preferable in a suitable rack.
Welding Ends shall be protected against damage and external object ingress by means of
a securely fastened bevel protector.
For large diameter pipes, check and, if necessary, renew the internal cross beam for end
concentricity protection.

Accessories
Depending on overall dimensions and diameter, where possible these materials shall be
stored inside the warehouse.
Repeat operations as per flanges stored inside warehouse. In case of storage outside do
not store in contact with the ground.
For special accessories, follow Supplier/Manufacturer’s instructions.

10.1.1.6. Non-ferrous Piping Materials

These shall be stored without special protection inside the warehouse.


it is specifically furnished or outside the extent of the agreed upon right of use.

If, by reason of dimensions or quantity, outside storage is necessary, means of suitable


protection shall be selected, case by case, together with Project management.

10.1.1.7. Prefabricated Piping Spools

The ends of field prefabricated piping spools shall be protected to avoid bevel damage
and dust entering.
The area selected for storage of field-fabricated piping shall be well graded and drained
so as to prevent accumulation of muck, mud and puddles.
Decking or paved area is suggested.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 23/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Repeat checking after sandblasting/painting and storing in painted-piping yard, renewing


where required the anti-rust protection of the flange seal surfaces, proceeding as per
flanges stored inside warehouse.

10.1.2. Initial Preservation

Temporary Preservation
Piping
- After hydrostatic test of piping systems all the circuit must be drained carefully paying
special attention to low points and dead ends. Particular attention to be paid during line
flushing to prevent dirt, scale and all contaminants from accumulating in exchangers or
equipment difficult to clean after operation;
- Blow with air;
- Plug the connections after drain;
- Close/seal vents and drains.
Valves
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;
9 Valves stems and protect with oiled paper.

Short Term Preservation


Piping (See note 1)
- After hydrostatic test of piping systems all the circuit must be drained carefully paying
special attention to low points and dead ends. Particular attention to be paid during line
flushing to prevent dirt, scale and all contaminants from accumulating in exchangers or
equipment difficult to clean after operation;
- Blow with air;
- Plug the connections after drain;
- Blind all connections to equipment and machinery;
- Close vents and drains;
- Fill:
9 Carbon steel lines with:
ƒ Dry air (where considered justified, the smaller carbon steel lines may be similarly
preserved);
ƒ Gas oil or protective oil (where oil can be tolerated);
9 Stainless steel lines with dry inert gas and maintain under inert gas pressure
it is specifically furnished or outside the extent of the agreed upon right of use.

(austenitic stainless steel shall not be left exposed to salt water or salt spray);
9 Oxygen and chlorine lines with dry inert gas and maintain under nitrogen pressure;
9 Steam lines with dry air;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Protect the ends of field prefabricated piping to avoid bevel damage and dust/sand
entering:
- Remove and store fragile accessories/instruments.
Valves
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 24/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

9 Valves stems and protect with oiled paper;


- Remove and store safety valves, protecting:
9 Internal parts with oily protective product;
9 Flanges with cardboard or plastic.
-
10.1.3. Maintenance during Preservation (Interval: 4 weeks)
- Check leakages on connections: tighten couplings and flanges if necessary;
- Check (See note 2):
9 Carbon steel lines for dry air pressurization or gas oil/protective oil efficiency;
9 Stainless steel, oxygen and chlorine lines for dry inert gas pressurization;
9 Steam lines for dry air pressurization;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Check and drain condensate from low points;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections and flanges;
9 Valves stems and protect with oiled paper.
- Check oily protective product on safety valves internals: if necessary, refurbish;
- Check valves status and efficiency: open and close them completely.
-
10.1.4. Restoration
- Remove protection products;
- Remove blinds installed on connections to equipment and machinery;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Re-install all dismantled parts (safety valves, accessories/instruments, etc.).
-
10.1.5. Notes
1. Pay particular attention where the supporting structure is not designed to carry a full
liquid load;
2. Not applicable for Temporary Preservation
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 25/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11. STATIC EQUIPMENT

11.1. SHELL AND TUBE HEAT EXCHANGER

11.1.1. Storage

Heat Exchanger
On reception, remove the mechanical joint protection provided by Supplier/Manufacturer.
Check that inside surfaces are dry: any water shall be carefully removed.
For all flanges, repeat operations as per flanges stored inside warehouse. Hermetically
seal off the inside of the exchanger from the atmosphere, proceeding as follows:
- Construct and apply rubber packing and carbon-steel blank flanges on all flanged
couplings;
- Apply plugs, of same equipment material, covered with rust-ban grease to all threaded
couplings.

Store outside, not in direct contact with the ground; no further protection is required.

Austenitic S.S. used in exchanger shall not be exposed to wetting by salt water or salt
spray. QC Supervisor shall approve protective coating or covering used to prevent such
exposure.

Where a spot check reveals some rust formation, provide for the following operations
depending by the part involved:
- Remove all flange covers of the nozzles, clean the flange faces from rust brush and
after with solvent and apply rust preventive product;
- Remove rust by mechanical or manual brush and restore painting according to painting
procedure.

Test Materials
On rings and flanges finished surfaces, repeat operations as per flanges stored outside
warehouse; paint with red lead or protection product (refer to § 8.1 - Soft layer for external
or internal parts).
Apply rust-ban grease to all protected surfaces and bolts.

Packing and gaskets shall be stored inside warehouse, as per § 10.1.1.4 Packing and
it is specifically furnished or outside the extent of the agreed upon right of use.

Gaskets.

Anchor Bolts
Anchor bolts that are not otherwise protected when received at job site, shall be cleaned
from rust, and shall be coated with rust preventative (refer to § 8.1 – Dry layer and Soft
layer for external or internal parts).

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 26/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.1.2. Initial Preservation

Temporary Preservation (See note 2)


- Isolate from process connections;
- Drain carefully paying special attention to low points and dead ends;
- Blow with air;
- Purge both shell side and tube with inert gas and maintain under inert gas pressure;
- Close/seal vents and drains.

Short Term Preservation (See note 2)


- Isolate from process connections;
- Drain carefully paying special attention to low points and dead ends;
- Blow with air;
- Blind inlet/outlet lines;
- Close vents and drains;
- Preserve:
9 Carbon steel heat exchangers:
ƒ Spraying/flushing protective oil or filling with gas oil (where oil can be tolerated);
ƒ Blowing VPI (Vapor Phase Corrosion Inhibitors) powder into the tubes and
hanging small bags of the powder in the channel ends;
ƒ Filling with dry inert gas and maintaining under dry inert gas pressure.
9 Stainless steel or copper alloy heat exchangers filling with dry inert gas and
maintaining under dry inert gas pressure;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Remove and store fragile accessories/instruments;
- Cover Exchanger with tarpaulins is a good practice. Pay attention that a sufficient gap
between equipment and tarpaulins is granted in order to allow air circulation.

11.1.3. Maintenance during Preservation (Interval: 4 weeks):


- Check leakages on connections: tighten couplings and flanges if necessary;
- Check and refill/renew, if necessary (See note 1):
9 Carbon steel heat exchangers for protective fluid, drying agent (oil, VPI, etc)
level/quantity or dry inert gas pressurization;
9 Stainless steel or copper alloy heat exchangers for dry inert gas pressurization;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
it is specifically furnished or outside the extent of the agreed upon right of use.

- Check and drain condensate from low points;


- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges;
- Check status of tarpaulins covering the equipment (if any). Repair if tears found.

11.1.4. Restoration
- Remove protection products;
- Remove tarpaulins covering the equipment (if any);
- Remove blinds installed on connections;
- Inspect equipment internals;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 27/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Re-install all dismantled accessories/instruments.

11.1.5. Notes
1. Not applicable for Short Term Preservation;
2. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 28/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.2. AIR - COOLED HEAT EXCHANGER

11.2.1. Storage

Refer to Shell and Tube Heat Exchanger procedure, where applicable.

11.2.2. Initial Preservation


Temporary Preservation (See note 2)
- Isolate from process connections;
- Drain carefully paying special attention to low points and dead ends;
- Blow with air;
- Purge with inert gas and maintain under inert gas pressure;
- Close/seal vents and drains.
Bearings and gears box (if any)
- Fill bearing housing with service oil/grease as appropriate;
- Add VSI concentrate to gears box lubrication oil.

Short Term Preservation (See note 2)


- Isolate from process connections;
- Drain water carefully after pressure/hydrostatic test paying special attention to low
points and dead ends;
- Blow with air;
- Blind inlet/outlet lines;
- Close vents and drains;
- Preserve:
9 Carbon steel air- cooled heat exchangers:
ƒ Spraying/flushing protective oil or filling with gas oil (where oil can be tolerated);
ƒ Blowing VPI (Vapor Phase Corrosion Inhibitors) powder into the tubes and
hanging small bags of the powder in the channel ends;
ƒ Filling with dry inert gas and maintaining under dry inert gas pressure.
9 Stainless steel or copper alloy air- cooled heat exchangers filling with dry inert gas
and maintaining under dry inert gas pressure;
- Coat/preserve fan blades with protective oil/grease;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Cover Exchanger with tarpaulins is a good practice. Pay attention that a sufficient gap
between equipment and tarpaulins is granted in order to allow air circulation.
it is specifically furnished or outside the extent of the agreed upon right of use.

Bearings
- Preserve bearings as described hereafter:
9 Oil-lubricated bearings have to be drained, filled with protective oil, turned for a short
while to ensure complete coverage and then closed up;
9 Grease-lubricated bearings have be cleaned, re-greased with appropriate grease,
turned and then closed up thoroughly.
Gears box (if any)
- Drain oil from gearbox at operating temperature, then refill with protective oil;
- Operate gear train for about 15 minutes.
Where the above procedure is not possible:

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 29/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Hang small bags of VPI powder inside gearbox and blank off all openings, ensuring the
gearbox is sealed air-tight;
- Treat outside of gearbox, including all sealing materials, with protective oil.

11.2.3. Maintenance during Preservation (Interval: 4 weeks)


- Check leakages on connections: tighten couplings and flanges if necessary;
- Check and refill/renew, if necessary:
9 Carbon steel heat exchangers for protective fluid, drying agent (oil, VPI, etc)
level/quantity or dry inert gas pressurization;
9 Stainless steel or copper alloy air- cooled heat exchangers for dry inert gas
pressurization;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Check and drain condensate from low points;
- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges;
- Check and refill/regrease, if necessary:
9 Protective oil level inside oil-lubricated bearings;
9 Grease-lubricated bearings;
- Check and refill/renew, if necessary, protective oil level or VPI powder inside gear box
(if any);
- Check status of tarpaulins covering the equipment (if any). Repair if tears found.

11.2.4. Restoration
- Remove protection products from:
9 Heat exchangers;
9 Bearings;
9 Gearbox (if any);
- Remove blinds installed on connections;
- Remove tarpaulins covering the equipment (if any);
- Inspect equipment internals;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled accessories/instruments.
it is specifically furnished or outside the extent of the agreed upon right of use.

11.2.5. Notes
1. Not applicable for Short Term Preservation;
2. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 30/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.3. FLOATING ROOF TANK, FIXED ROOF TANK AND SPHERE

11.3.1. Storage

Not applicable.

11.3.2. Initial Preservation

Temporary Preservation
No specific actions to be carried out.

Short Term Preservation


- Isolate from process connections;
- Blind openings;
- Ensure that sealing between foundation and tank bottom is in good condition;
- Ensure that rainwater drainage is fully effective by opening the drains and the
emergency drain in the roof;
- Grease and protect moving parts of floating roof tank (if any);
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Remove and store fragile accessories/instruments;
- Associated relief valves can be left in place or removed for servicing and storage: if left
in place, the relief valves have to be spaded off, if removed, the nozzles have to be
blanked off.

11.3.3. Maintenance during Preservation (Interval: 4 weeks)


- Check condition of sealing between foundation and tank bottom to prevent rain water
ingress under tank: if necessary refurbish;
- Check rainwater drainage efficiency opening drains and the emergency drain in the
roof: any rainwater collected on the tank bottom has to be removed;
- Check cathodic protection efficiency;
- Check insulation status: if necessary, repair;
- Check painting: if necessary, repaint;
- Grease moving parts of floating roof and check efficiency/status (if any);
- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges.
it is specifically furnished or outside the extent of the agreed upon right of use.

11.3.4. Restoration
- Remove blinds;
- Inspect equipment internals;
- Re-install removed accessories/instruments.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 31/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.4. VESSEL, FILTERS, COLUMN AND REACTOR

11.4.1. Storage

On reception, check mechanical protection on joints provided by Supplier/Manufacturer


and replace if damaged. For all flanges, repeat operations as per flanges stored inside
warehouse, and in particular protect, or renew the protection, for flanges with individual
rigid covers after renewing the protection coat.

Austenitic S.S. used in vessels shall not be exposed to wetting by salt water or salt spray.
QC Supervisor shall approve protective coating or covering used to prevent such
exposure.

Verify that temporary supports as raw wood installed for shipment or during erection, in
contact with high alloy parts of vessels, have not retained moisture.

Vessels shall be stored outdoors on a paved area or on pallets in order to avoid direct
contact to the ground.

Where a spot check reveals some rust formation, provide for the following operations
depending by the part involved:
- Remove all flange covers of the nozzles, clean the flange faces from rust brush and
after with solvent and apply rust preventive product;
- Remove rust by mechanical or manual brush and restore painting according to painting
procedure.

For Test Materials and Anchor Bolts refer to Shell and Tube Heat Exchanger.

Equipment Internals
Store plates for columns and supporting beams outside, not in direct contact with ground,
and protect with plastic sheeting.
Store nuts, bolts, plates and small fittings inside the warehouse, without removing from
their packing case.
Repeat operations as per § 11.5.1.1 for nuts and bolts and for oxidizable material.

Store demister in open shed warehouse, not in direct contact with the ground, and cover
it is specifically furnished or outside the extent of the agreed upon right of use.

with plastic sheeting. Suitable protection shall be studied for other equipment internals as
required.

The catalyst, resins, etc shall be stored in the original drums in a closed, dry, ventilated
warehouse. The catalyst drums must be stored vertically. Do not roll the drums, to avoid
catalyst breaking.
Check every 3 months the integrity of drums.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 32/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.4.2. Initial Preservation

Temporary Preservation (See note 3)


- Isolate from process connections;
- Drain carefully paying special attention to low points and dead ends;
- Purge with inert gas and maintain under inert gas pressure;
- Close/seal vents and drains.

Short Term Preservation (See note 3)


- Isolate from process connections;
- Drain carefully paying special attention to low points and dead ends;
- Blind inlet/outlet nozzles;
- Blow with air;
- Close vents and drains;
- Preserve: (See note 1)
9 Carbon steel vessels:
ƒ Spraying inside surfaces protective oil (where oil can be tolerated);
ƒ Blowing VPI (Vapor Phase Corrosion Inhibitors) powder and/or hanging small
bags of the powder.
ƒ Filling with dry inert gas and maintaining under dry inert gas pressure.
9 Stainless steel or copper alloy vessels filling with dry inert gas and maintaining
under dry inert gas pressure;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Remove and store fragile accessories/instruments;
- Associated relief valves can be left in place or removed for servicing and storage: if left
in place, the relief valves have to be spaded off, if removed, the nozzles have to be
blanked off.

11.4.3. Maintenance during Preservation (Interval: 4 weeks)


- Check leakages on connections: tighten couplings and flanges if necessary;
- Check and refill/renew, if necessary (See note 1):
9 Carbon steel vessels for protective fluid, drying agent (oil, VPI, etc) level/quantity or
dry inert gas pressurization;
9 Stainless steel or copper alloy vessels for dry inert gas pressurization;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
it is specifically furnished or outside the extent of the agreed upon right of use.

- Check and drain condensate from low points;


- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges.

11.4.4. Restoration
- Remove protection products;
- Remove blinds installed on connections;
- Inspect equipment internals;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 33/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Re-install all dismantled accessories/instruments.

11.4.5. Notes
1. All equipment to be preserved without filter cartridge, packing material, catalyst or other
inert materials: those materials have to be stored in a dry warehouse.
2. Parts removal and their storage are required only for long-term preservation;
3. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 34/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.5. FURNACE

11.5.1. Storage

All steel structures, shell plates and cast materials, may be stored in open area subject to
the weather, for a reasonable length of time. It is recommended, however, that small item
(stainless) castings, nuts, bolts, etc. be placed in a closed warehouse.

In area where climatic conditions are not too severe, all other materials may be stored
outdoors, including brick and refractory, provided that precautions are taken to keep
excessive moisture from the insulation, firebrick, mortar and other castables.
It is preferable, if freezing weather or excessive rain conditions are expected, that the
material mentioned in this paragraph be stored inside closed warehouse. These building
may remain untreated under all normal conditions.
Should the brick or refractory be extremely wet prior to being stored in the warehouse,
enough heat should be available to prevent freezing. This heat will also have a tendency
to dry out firebrick.

11.5.2. Initial Preservation


Temporary Preservation
- Isolate from process connections;
- Purge coils internal with inert gas and maintain under inert gas pressure;
- Close/seal vents and drains.

Short Term Preservation


Combustion chamber
- Isolate from process connections;
- Coat external surfaces of coils with protective oil (prevent oil from wetting firebrick
insulation);
- Blind, openings (inspection doors, etc.) and flue gas stack to prevent damage from rain
or moisture;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Remove burners to store and preserve with protective oil;
- Remove and store fragile accessories/instruments.
Coils
- Dry coil internals;
it is specifically furnished or outside the extent of the agreed upon right of use.

- Blind inlet and outlet nozzles;


- Grease bolts/threaded connections and coat flanges with heavy grease or protective
product;
- Purge with inert gas and maintain under inert gas pressure.

11.5.3. Maintenance during Preservation (Interval: 4 weeks)


- Check leakages on connections: tighten couplings and flanges if necessary;
- Check coils for dry inert gas pressurization;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 35/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Check and drain condensate from low points;


- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges.

11.5.4. Restoration
- Remove protection products;
- Remove blinds installed on connections;
- Inspect combustion chambers;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Re-install all dismantled accessories (burners, instruments, etc).
-
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 36/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

11.6. BOILER

11.6.1. Storage

Refer to § 11.5.1

11.6.2. Initial Preservation

Temporary Preservation
- Isolate from process connections;
- Drain steam/water side carefully paying special attention to low points and dead ends;
- Blow with air;
- Purge steam/water side with inert gas and maintain under inert gas pressure;
- Close/seal vents and drains.

Short Term Preservation


Combustion chamber
- Isolate from process connections;
- Coat external surfaces of coils with protective oil (prevent oil from wetting firebrick
insulation);
- Blind, openings (inspection doors, etc.) and flue gas stack to prevent damage from rain
or moisture;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Remove burners to store and preserve with protective oil;
- Remove and store fragile accessories/instruments.
Wet storage of the steam/water side (See note 1 & 2)
- Fill entire boiler (coils, steam drum, etc) and superheater completely (until vents
overflow) with water containing an approved oxygen scavenger and pH adjuster:
maintain pH above 10 (See note 3);
- Blind nozzles;
- Plug vents and drains;
- Provide external reservoir connected to boiler high point to maintain stable water level;
- Connect a inert gas supply to the highest vents and maintain overpressure of 100-
500 mm water gauge;
Dry storage of the steam/water side (See note 1)
- Drain water carefully paying special attention to low points and dead ends;
it is specifically furnished or outside the extent of the agreed upon right of use.

- Dry the boiler and superheater by blowing with dry air or inert gas, or use a de-
humidifier until existing air humidity is consistently less than 35%;
- Flush the air out with inert gas until the oxygen level is less than 1% by volume (this
requires about 5 volumes of inert gas).
- Maintain an inert gas overpressure of 100-500 mm water gauge.

11.6.3. Maintenance during Preservation (Interval: 4 weeks)


- Check leakages on connections: tighten couplings and flanges if necessary;
- Check level in boiler drums and tubes and refill with treated water;
- Sample and analyze properties of boiler water;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 37/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Check dry inert gas pressurization where provided;


- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges.

11.6.4. Restoration
- Remove protective products;
- Remove blinds installed on connections;
- Empty circuits;
- Inspect internals of combustion chamber and drums;
- Check burners;
- Check painting and if necessary repaint;
- Check insulation and if necessary repair;
- Re-install all dismantled accessories (burners, instruments, etc).

11.6.5. Notes
1. For periods up to about one year either dry or wet storage may be applied: wet storage
is normally easier to implement but routine water testing is necessary;
2. During periods when freezing is expected, apply heat by using steam or electric
heaters or by circulating hot de-aerated feed water, maintaining water conditions as
close as practicable to the specified requirements for normal operation;
3. Check if superheater material is suitable for immersion contact with treated water.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 38/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12. ROTATING EQUIPMENT

12.1. Centrifugal Pump with Lube Oil System

12.1.1. Storage

Upon arrival, all temporary protective devices previously applied by the


Supplier/Manufacturer on the flange faces and on the apertures communicating with the
interior of the machinery shall be checked. If any are missing they shall be replaced and if
any are damaged they shall be repaired. In these cases check that water or extraneous
matter has not penetrated into the machinery. If necessary, the interior of the machinery
shall be cleaned again and the damaged rust proofing shall be restored.

If necessary (rusted or dirt conditions), bearing housing, gear boxes and speed reduction
gears shall be cleaned by washing with solvents.

All machined surfaces which are uncovered and exposed to outside agents (e.g. wheels,
flange surfaces, motor coupling joints, rods, pistons, cams, etc.) shall be cleaned, if
necessary, with solvents and coated with protective products (refer to § 8.1 – Dry layer
and Soft layer for external or internal parts).

Store inside warehouse or under shelter where easily accessible.

For all preservation/protection activities refer to the following paragraphs.

12.1.2. Initial Preservation

Temporary Preservation (see note 4)


- Isolate pump from process connections;
- Drain pump casing;
- Fill pump bearing housings with service oil/grease as appropriate;
- Add VSI concentrate to:
9 Lubrication oil inside gear box (if any);
9 Lubrication/sealing oil system (See note 3).
- Blanket lubrication/seal oil tanks and maintain under inert gas pressure.
it is specifically furnished or outside the extent of the agreed upon right of use.

Short Term Preservation (see note 4)


- Isolate pump from process connections;
- Drain pump casing;
- Flush pump with protective oil;
- Fill with protective oil:
9 Pump casing (10 to 50%);
9 Bearings housing;
9 Gear box (if any).
- Plug vents on bearing housing;
- Add VSI concentrate to lubrication/sealing oil (See note 3);
- Flush with fresh water and dry with air all cooling jackets (if any);

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 39/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Plug/blind auxiliary piping and cooling water jackets (if any) but keep low point drain
valve open slightly;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;
9 Space where shaft protrudes through bearing or stuffing box housing;
9 All exposed machined surfaces, shaft and couplings (alternatively cover with
plastic);
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.

12.1.3. Maintenance during Preservation (Interval: 2 weeks)


- Check leakages on connections: tighten if necessary;
- Check and refill, if necessary, protective oil level inside:
9 Pump casing;
9 Bearings housing;
9 Gear box (if any).
- Check and drain condensate from low points;
- Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections, flanges and all exposed machined surfaces;
9 Space where shaft protrudes through bearing or stuffing box housing;
9 Shaft and couplings;
- Rotate shaft by hand (See note 1).

12.1.4. Restoration
- Remove protective oil from:
9 Pump casing;
9 Bearings housing;
9 Gear box (if any);
- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.1.5. Notes
1. Rotation through a minimum of 5 complete turns is good practice. The position of the
shaft at rest should be advanced by a ¼ turn each time;
it is specifically furnished or outside the extent of the agreed upon right of use.

2. Parts removal and their storage are required only for long-term preservation;
3. Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;
4. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 40/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.2. CENTRIFUGAL PUMP AND BLOWER

12.2.1. Storage

Refer to § 12.1.1.

For all preservation/protection activities refer to the following paragraphs.

12.2.2. Initial Preservation


Temporary Preservation (See note 3)
- Isolate pump from process connections;
- Drain pump casing;
- Fill pump bearing housings with service oil/grease as appropriate.

Short Term Preservation (See note 3)


- Isolate pump from process connections;
- Flush pump with protective oil;
- Drain pump casing;
- Fill with protective oil:
9 Pump casing 10 to 50% of internal volume;
9 Gear box (if any).
- Plug vents on bearing housing;
- Preserve bearings as described hereafter:
9 Oil-lubricated bearings have to be drained, filled with protective oil, turned for a short
while to ensure complete coverage and then closed up;
9 Grease-lubricated bearings have be cleaned, regreased with appropriate grease,
turned and then closed up thoroughly;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.

12.2.3. Maintenance during Preservation (Interval: 4 weeks)


- Check leakages on connections: tighten if necessary;
- Check and refill, if necessary, protective oil level inside:
9 Pump casing;
9 Gear box (if any).
it is specifically furnished or outside the extent of the agreed upon right of use.

- Check and drain condensate from low points;


- Check and refill/regrease, if necessary:
9 Protective oil level inside oil-lubricated bearings;
9 Grease-lubricated bearings;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;
- Check and drain condensate from low points;
- Rotate shaft by hand (See note 1).

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 41/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.2.4. Restoration
- Remove protective products from:
9 Pump casing;
9 Gear box (if any);
9 Oil-lubricated bearings and flush with lubrication oil.
- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.2.5. Notes
1. Rotation through a minimum of 5 complete turns is good practice. The position of the
shaft at rest should be advanced by a ¼ turn each time.
2. Parts removal and their storage are required only for long-term preservation;
3. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 42/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.3. RECIPROCATING PUMP

12.3.1. Storage

Refer to § 12.1.1.

For all preservation/protection activities refer to the following paragraphs.

12.3.2. Initial Preservation

Temporary Preservation (See note 3)


- Isolate pump from process connections;
- Drain pump casing;
- Fill pump bearing housings with service oil/grease as appropriate;
- Add VSI concentrate to:
9 Lubrication oil inside gear box (if any);
9 Lubrication/sealing oil system (See note 2).
- Blanket lubrication/seal oil tanks and maintain under inert gas pressure.

Short Term Preservation (See note 3)


- Isolate pump from process connections;
- Flush pump with protective oil;
- Drain pump casing;
- Fill with protective oil:
9 Pump casing;
9 Bearings housing;
9 Gear box (if any).
- Flush with fresh water, dry with air all cooling jackets (if any) and blanket with inert
gas;
- Add VSI concentrate to lubrication/seal (See note 2);
- Blind or plug auxiliary piping;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;
9 All joints where shaft protrudes from casing;
9 Exposed piston rod, shafts and all machined parts.
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.
it is specifically furnished or outside the extent of the agreed upon right of use.

12.3.3. Maintenance during Preservation (Interval: 2 weeks)


- Check leakages on connections: tighten if necessary;
- Check and refill, if necessary, protective oil level inside:
9 Pump casing;
9 Bearings housing;
9 Gear box (if any).
- Check and drain condensate from low points;
- Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 43/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Check grease/protective product coating and, if necessary, refurbish on:


9 Bolts/threaded connections and flanges;
9 All joints where shaft protrudes from casing;
9 Exposed piston rod, shafts and all machined parts.

12.3.4. Restoration
- Remove protective oil from:
9 Pump casing;
9 Bearings housing;
9 Gear box (if any).
- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.3.5. Notes
1. Parts removal and their storage are required only for long-term preservation;
2. Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;
3. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 44/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.4. DOSING AND ROTARY PUMP

12.4.1. Storage

Refer to § 12.1.1.

Particular attention must be paid for flange covers: in no case dirt and foreign material be
allowed to penetrate into rotating parts.

For all preservation/protection activities refer to the following paragraphs.

12.4.2. Initial Preservation

Temporary Preservation (See note 1)


- Isolate pump from process connections;
- Drain pump casing;
- Fill pump casing with service oil as appropriate.

Short Term Preservation (See note 1)


- Isolate pump from process connections;
- Drain pump casing;
- Fill pump casing with service oil as appropriate;
- Blind or plug auxiliary piping;
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.

12.4.3. Maintenance during Preservation (Interval: 4 weeks)


- Check leakages on connections: tighten if necessary;
- Check and refill, if necessary, protective oil level inside pump casing;
- Check and drain condensate from low points;
- Check grease/protective product coating and, if necessary, refurbish on bolts/threaded
connections and flanges.

12.4.4. Restoration
- Remove protective oil from pump casing;
it is specifically furnished or outside the extent of the agreed upon right of use.

- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.4.5. Notes
1. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 45/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.5. CENTRIFUGAL COMPRESSOR

12.5.1. Storage

Not applicable.

12.5.2. Initial Preservation

Temporary Preservation (See note 3)


- Isolate compressor/blower from process connections;
- Fill bearing housings with service oil/grease as appropriate

Short Term Preservation (See note 3)


- Isolate compressor from process connections;
- Isolate auxiliary circuits from compressor/blower;
- Purge compressor/blower casing with inert gas and maintain under inert gas pressure
or hang small bags of VPI powder inside casing;
- Preserve bearings as described hereafter:
9 Oil-lubricated bearings have to be drained, filled with protective oil, turned for a short
while to ensure complete coverage and then closed up;
9 Grease-lubricated bearings have be cleaned, regreased with appropriate grease,
turned and then closed up thoroughly;
- Fill gear box (if any)with protective oil;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;
- Drain water side cooling system (if any) and refill with inhibited water: if freezing is
possible, drain system, dry it and then close it up;
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.

12.5.3. Maintenance during Preservation (Interval: 2 weeks)


- Check leakages on connections: tighten if necessary;
- Check compressor/blower casing inert gas pressurization or VPI powder quantity;
- Check and refill/regrease, if necessary:
9 Protective oil level inside oil-lubricated bearings;
9 Grease-lubricated bearings;
it is specifically furnished or outside the extent of the agreed upon right of use.

- Check oil level inside gear box (if any): refill if necessary;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;
- Check inhibited water in cooling water system (if any): refill if necessary;
- Check and drain condensate from low points;
- Rotate shaft by hand (See note 1).

12.5.4. Restoration
- Remove protective products from:

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 46/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

9 Gear box (if any);


9 Cooling system (if any);
9 Oil-lubricated bearings and flush with lubrication oil.
- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.5.5. Notes
1. Rotation through a minimum of 5 complete turns is good practice. The position of the
shaft at rest should be advanced by a ¼ turn each time.
2. Parts removal and their storage are required only for long-term preservation;
3. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 47/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.6. CENTRIFUGAL COMPRESSOR WITH LUBE OIL SYSTEM

12.6.1. Storage

Not applicable.

12.6.2. Initial Preservation

Temporary Preservation (See note 4)


- Isolate compressor from process connections;
- Purge compressor casing with inert gas and maintain under inert gas pressure;
- Add VSI concentrate to:
9 Lubrication oil inside gear box (if any);
9 Lubrication/sealing oil system (See note 3);
- Blanket lubrication/seal oil tanks and maintain under inert gas pressure.

Short Term Preservation (See note 4)


- Isolate compressor from process connections;
- Purge compressor casing with inert gas and maintain under inert gas pressure;
- Add VSI concentrate lubrication/sealing oil system (See note 3);
- Isolate lubricant lines (discharge and returns) from compressor;
- Blanket lubrication/seal oil tanks and maintain under inert gas pressure;
- Fill with protective oil:
9 Bearings housing;
9 Oil console;
9 Gear box (if any).
- Coat with heavy grease or protective product:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;
- Drain water side cooling system and refill with inhibited water: if freezing is possible,
drain system, dry it and then close it up;
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.

12.6.3. Maintenance during Preservation (Interval: 2 weeks)


- Check leakages on connections: tighten if necessary;
- Check inert gas pressurization of:
9 Compressor casing;
it is specifically furnished or outside the extent of the agreed upon right of use.

9 Lubrication/seal oil tanks;


- Check and refill, if necessary, protective oil level inside:
9 Bearings housing;
9 Oil console;
9 Gear box (if any).
- Check oil level in lube circuits;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 48/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Check inhibited water in cooling water system: refill if necessary;


- Check and drain condensate from low points;
- Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;
- Rotate shaft simultaneously with the operation of the lubrication/seal oil system (See
notes 1 and 3).

12.6.4. Restoration
- Remove protective oil from:
9 Bearings housing;
9 Oil console;
9 Gear box (if any);
- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.6.5. Notes
1. Rotation through a minimum of 5 complete turns is good practice. The position of the
shaft at rest should be advanced by a ¼ turn each time.
2. Parts removal and their storage are required only for long-term preservation.
3. Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;
4. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 49/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.7. RECIPROCATING AND SCREW COMPRESSOR

12.7.1. Storage

Not applicable.

12.7.2. Initial Preservation

Temporary Preservation (See note 5)


- Isolate unit from process connections;
Compressor
- Purge compressor casing with inert gas and maintain under inert gas pressure;
- Add VSI concentrate to:
9 Lubrication oil inside gear box (if any);
9 Lubrication/sealing oil system (See note 3).
- Blanket lubrication/seal oil tanks and maintain under inert gas pressure.
Suction and Discharge Vessels
- Drain carefully paying special attention to low points and dead ends;
- Purge with inert gas and maintain under inert gas pressure;
- Close/seal vents and drains.

Short Term Preservation (See note 5)


- Isolate unit from process connections;
Compressor
- Add VSI concentrate to lubrication/sealing oil system (See note 3);
- Rotate by barring gear compressor unloaded to distribute oil on all surfaces (See note
4);
- Blanket lubrication/seal oil system and maintain under inert gas pressure;
- Fill with protective oil:
9 Crankcase;
9 Gear box (if any).
- Purge compressor unit with inert gas and maintain under inert gas pressure;
- Blind or plug auxiliary piping;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections, flanges and;
9 All joints where shaft protrudes from casing;
9 Exposed piston rod, shafts and all machined parts.
it is specifically furnished or outside the extent of the agreed upon right of use.

- Drain cooling system (if any) and refill with inhibited water or, if freezing is possible,
drain system, dry it then close it up;
- Remove and store fragile accessories such as rotameters, oilers, level glasses, etc.
Suction and Discharge Vessels
- Refer to Temporary Preservation

12.7.3. Maintenance during Preservation (Interval: 2 weeks)


- Check leakages on connections: tighten if necessary;
- Check inert gas pressurization of:

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 50/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

9 Compressor unit (compressor and vessels);


9 Lubrication/seal oil system;
- Check and refill, if necessary, protective oil level inside:
9 Crankcase;
9 Gear box (if any).
- Check oil level in lube circuits (See note 3);
- Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections and flanges;
9 All exposed machined surfaces, shaft and couplings;
- Check inhibited water in cooling water system: refill if necessary;
- Check and drain condensate from low points;
- Check protections inside suction and discharge dumper: renew if necessary;
- Rotate by barring gear compressor unloaded (See note 1 and 4).

12.7.4. Restoration
- Remove protective oil from:
9 Crankcase;
9 Gear box (if any);
- Remove blinds;
- Check lubricant proprieties as from Mfr recommendation: refill/change if necessary;
- Re-install all dismantled parts (accessories, instruments, etc.).

12.7.5. Notes
1. The position of the shaft at rest should be advanced by a ¼ turn each time: refer to Mfr
manual for further details.
2. Parts removal and their storage are required only for long-term preservation.
3. Circulate oil through the entire system (piping, filters, coolers, etc) for about 30 minutes
if all electrical connections, lubrication oil piping and power are available.
4. Only applicable for reciprocating compressor;
5. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 51/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

12.8. DIESEL ENGINE

12.8.1. Storage

Refer to § 12.1.1.

For all preservation/protection activities refer to the following paragraphs.

12.8.2. Initial Preservation

Temporary Preservation (See note 3)


- No activities.

Short Term Preservation (See note 3)


- When engine is warm, drain lubrication oil system and fill with protective oil to normal
level (See note 1);
- Fill injection system with protective oil (See note 1);
- Spray protective oil inside cylinders through the spark-plug or injection connections;
- Hang small bags of VPI powder in inlet and exhaust manifolds, then close up;
- Drain cooling water system, flush out, then fill with inhibited water, depending on
building/environment temperature, or drain system, dry it and close up;
- Disconnect battery;
- Remove and store magnetos and electrical accessories subject to damage from
moisture;
- Remove fragile components (e.g. instruments);
- Coat with heavy grease or protective product bolts/threaded connections and flanges;
- Protect flue gas stacks;
- Plug/blind openings.
-
12.8.3. Maintenance during Preservation (Interval: 4 weeks)
- Check leakages on connections: tighten or repair if necessary;
- Check and refill, if necessary, protective oil (if any) or lubrication oil level inside:
9 Lubrication oil system;
9 Injection system;
- Check and renew, if necessary, VPI powder in inlet and exhaust manifolds;
- Check grease/protective product coating on bolts/threaded connections and flanges: if
it is specifically furnished or outside the extent of the agreed upon right of use.

necessary, refurbish;
- Check inhibited water (if any) in cooling water system: refill if necessary;
- Run engine for about 30 minutes (See note 2).

12.8.4. Restoration
- Remove protective oil (if any) from:
9 Lubrication oil system;
9 Injection system;
- Remove blinds;
- Check with lubricants recommended by Mfr;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 52/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

- Fill cooling water system with service water (if any);


- Re-install all dismantled parts (magnetos, electrical accessories, instruments,
couplings, etc.).
-
12.8.5. Notes
1. Activity to be carried out only if recommended by Mfr: refer to Mfr manual for further
details;
2. Activity to be carried out only during temporary preservation;
3. If any preservation product (VPI, preservation oil, etc.) has been applied to the
equipment by Supplier/Manufacturer, renew it if necessary and follow the same
preservation method (Refer to Supplier/Manufacturer documentation).

12.9. STEAM AND GAS TURBINE

12.9.1. Storage and Preservation

For short-term storage no protective treatment shall be given.


For long storage, the Supplier/Manufacturers instructions shall be followed under
supervision of Supplier/Manufacturers representative.
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 53/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

13. ELECTRICAL EQUIPMENT AND MATERIALS

13.1. Electrical Panel Boards

13.1.1. Storage and Preservation

Switchgears, MCC, electric switchboards or control boards shall be stored inside the
warehouse, or directly in the electrical substation, in a dry, warm place where
condensation of humidity can not occur and the following shall be made:
- Assure good ventilation.
- If high relative humidity and rapid changes in temperature are experienced, heater shall
be used to maintain the temperature at a level approximately 10 °F (6 °C) above
minimum daily temperature.

In case of expected long storage, space heaters within the equipment (if provided) shall
be connected to a continuous provisional electrical power supply.

Oil immersed starters, circuit breakers, and similar items, which are shipped dry, shall be
filled with insulating liquid as soon as they are received on site.

Insulation resistance values of such parts as operating coils shall be spot checked every 6
weeks. If any readings are low, the affected parts shall be dried out before they are placed
in operation.

13.2. BULK ELECTRICAL MATERIAL

13.2.1. Storage and Preservation

Bulk electrical material, such as lighting fixtures, control stations, junction boxes, etc. shall
be stored inside the warehouse.
Material shall be wrapped in plastic bags, with drying agent inside for delicate material.
Check silica gel every 3 months.

13.3. CABLES

13.3.1. Storage and Preservation


it is specifically furnished or outside the extent of the agreed upon right of use.

Reels of paper-insulated lead sheated cable shall be rotated 90° every 2 weeks.

13.4. BATTERIES

13.4.1. Storage and Preservation

All batteries shall be stored indoors, in a dry place.


Batteries shipped dry and sealed shall be inspected on receipt at site.
Any damaged seal shall be renewed.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 54/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Lead-acid batteries shipped wet shall be handled as follows:


- Electrolyte level shall be inspected when batteries are received at the site. Electrolyte
shall be topped up if necessary.
- Three months after shipment from factory, and every 3 months thereafter, batteries
shall be charged according to Supplier/Manufacturer instructions.
- The charging rate shall not exceed the Supplier/Manufacturer’s recommended value;
batteries shall not be overcharged.

13.5. TRANSFORMERS

13.5.1. Storage and Preservation

- Temporary mechanical protection is required for all transformers;


- Drums of insulating oil stored outdoors shall be checked for their tightness and put
under shelter;
- Transformer to be liquid filled shall have silica-gel filters installed on vents during
storage;
- Transformers filled with insulating oil:
9 If the transformer is shipped with its main tank filled with insulating liquid, measure
and record the level of the oil and the ambient temperature when the unit arrives on
site and every month thereafter;
9 If the level falls, repair leaks and add insulating liquid to keep the level within
tolerances. Follow Supplier/Manufacturer instruction to avoid humidity contamination
of oil.
- Transformer filled with insulating oil with gas under pressure:
9 If the transformer is shipped with its main tank filled with insulating oil and blanketed
with gas under pressure, or filled with gas under pressure, then measure and record
the gas pressure and the ambient temperature when the unit arrives on site, and
every month thereafter;
9 If the pressure falls, repair leaks and add gas to keep the pressure within
tolerances.

13.6. ELECTRIC MOTOR

13.6.1. Storage
it is specifically furnished or outside the extent of the agreed upon right of use.

These shall be stored under shed, except motors designed for outdoor use.
Check anti-rust protection on the coupling extremities.

13.6.2. Initial Preservation

All motors designed for outdoor use shall be installed with protective covering, permitting
good ventilation

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 55/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Temporary Preservation
- Switch on anti condensation heaters, if they are fitted: electrical heaters shall not be
turned only after a check of qualified electrician.

Short Term Preservation


- Switch on anti condensation heaters, if they are fitted: electrical heaters shall not be
turned only after a check of qualified electrician;
- Add VSI concentrate lubrication oil system (if any);
- Preserve bearings as described hereafter:
9 Oil-lubricated bearings have to be drained, filled with protective oil, turned for a short
while to ensure complete coverage and then closed up;
9 Grease-lubricated bearings have be cleaned, regreased with appropriate grease,
turned and then closed up thoroughly;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections;
9 All exposed machined surfaces, shaft and couplings.
- Protect terminals of the cable box with vaseline, or antirust products;
- Plug box will with a suitable cover to avoid the entrance of foreign matters: apply the
same procedure for space heaters terminals box.

13.6.3. Maintenance during Preservation (Interval: 4 weeks)


- Check and refill/regrease, if necessary:
9 Protective oil level inside oil-lubricated bearings;
9 Grease-lubricated bearings;
- Check anti condensation heaters (if they are fitted) for proper functioning;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections;
9 All exposed machined surfaces, shaft and couplings;
- Check external protections status;
- Carry out an insulation tests;
- Operate switches and push buttons;
- Energize local panels, (if electrical power is available);
- Perform running tests of uncoupled motors (if electrical power is available). Otherwise
rotate shaft manually. (See note 1)

13.6.4. Restoration
it is specifically furnished or outside the extent of the agreed upon right of use.

- Remove protection products;


- Switch off anti condensation heaters, if they are fitted;
- Check insulation on motors and cables;
- Check direction of rotation.
-
13.6.5. Notes
1. Rotation through a minimum of 5 complete turns is good practice. The position of the
shaft at rest should be advanced by a ¼ turn each time.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 56/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

13.7. GENERATOR

13.7.1. Storage

Refer to § 13.1.1.

13.7.2. Initial Preservation

All generators designed for outdoor use shall be installed with protective covering,
permitting good ventilation

Temporary Preservation
- Switch on anti condensation heaters, if they are fitted.

Short Term Preservation


- Switch on anti condensation heaters, if they are fitted. All other auxiliary supplies shall
be switched off;
- Add VSI concentrate lubrication oil system (if any);
- Preserve bearings as described hereafter:
9 Oil-lubricated bearings have to be drained, filled with protective oil, turned for a short
while to ensure complete coverage and then closed up;
9 Grease-lubricated bearings have be cleaned, regreased with appropriate grease,
turned and then closed up thoroughly;
- Coat with heavy grease or protective product:
9 Bolts/threaded connections;
9 All exposed machined surfaces, shaft and couplings.
- Batteries (if any):
9 Leave Nickel-Cadmium batteries fully charged and disconnected (where possible);
9 Leave Lead-acid batteries on float charge.
- Chargers (if any):
9 De-energize chargers for Nickel-Cadmium batteries (where possible);
9 Leave chargers for Lead-acid batteries energized for “float charging” the associated
batteries.

13.7.3. Maintenance during Preservation (Interval: 4 weeks)


- Check and refill/regrease, if necessary:
9 Protective oil level inside oil-lubricated bearings;
it is specifically furnished or outside the extent of the agreed upon right of use.

9 Grease-lubricated bearings;
- Check anti condensation heaters (if they are fitted) for proper functioning;
- Check grease/protective product coating and, if necessary, refurbish on:
9 Bolts/threaded connections;
9 All exposed machined surfaces, shaft and couplings;
- Check external protections status;
- Check chargers and batteries status;
- Carry out an insulation tests;
- Operate switches and push buttons;

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 57/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

13.7.4. Restoration
- Remove protection products;
- Switch off anti condensation heaters, if they are fitted;
- Energize battery chargers where required;
- Check insulation on motors and cables.
-
it is specifically furnished or outside the extent of the agreed upon right of use.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 58/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

14. INSTRUMENTAL EQUIPMENT AND MATERIALS

14.1. Valves and accessories

14.1.1. Storage

General
Check and maintain according to Supplier/Manufacturer instructions, considering, as
minimum, the following:
- Valves up to and including ∅ 1½” shall be stored inside the warehouse;
- Valves of ∅ 2” and over, of whatever type of material shall be stored outside. Flange
facing shall be carefully inspected. Protection will be renewed immediately when
necessary;
- Soft sealed ball and plug vales shall be stored in the closed position. All other manually
operated valves shall be seated.
- Where it is known that valves are to be in storage for a period of three (3) months or
more, the flange faces covers shall be removed and flange faces and interiors cleaned
with a solvent and coat with rust preventives (refer to § 8.1 - Dry layer for external
parts) applied before replacing cover;
- Inspect for corrosion and open and close the valves every 2 months in order to avoid
blockage; each time, close completely the valve in order to avoid corrosion.

Valves stored inside the warehouse


Check the mechanical protection of flanges supplied by Vendor, on reception, and repair
any damage.
Repeat operations as per flanges stored inside warehouse.
Apply grease or brush or spray protection product (refer to § 8.1 - Soft layer for external or
internal parts) to valve pins and screws.

Valves stored outside the warehouse


Carry out all operations as per valves stored inside the warehouse, protecting the steam
with grease and oiled paper.
Storage area must be fully drained, concrete paved or decked.
Do not store in contact with the ground and cover with plastic sheeting.
Check every 3 months and replace protection as required.
it is specifically furnished or outside the extent of the agreed upon right of use.

Valves with reducer


Inspect the gear combination, remove any rust, and clean the gear casing, the gears, rod
and other mechanical parts.
Protect the reduction mechanism with a plastic cover, after greasing appropriately or
spraying protection product (refer to § 8.1 - Soft layer for external or internal parts).
Repeat operations as per valves stored outside the warehouse.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 59/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

Motor-operated valves
On reception, check that the crown gears of the reducers are not oxidized and, if
necessary, proceed with cleaning operations: all machined surfaces which are uncovered
and exposed to outside agents (e.g. wheels, flange surfaces, motor coupling joints, rods,
pistons, cams, etc.) shall be cleaned, if necessary, with solvents and coated with
protective product type (refer to § 8.1 – Dry layer and Soft layer for external or internal
parts).
Completely fill torque case with oil repeat operations as per Valves stored outside the
warehouse.
Actuators shall be protected against mechanical damage.

Control Valves/On-Off Valves/Safety Valves


This material shall be stored in the warehouse up to a size of ∅ 2” inches.
For size over than ∅ 2” the storage can be handled outside, on paved areas, protected
against rain, with the valve stem upright.

All flanges or termination of valves must be protected against sand, dirt and foreign
bodies.

14.1.2. Initial Preservation

Temporary Preservation
- No specific actions to be carried out.
-
Short-Term Preservation
- Tightly seal isolating valves on air supply;
- Protect control valves with plastic or other cover;
- Place drying agent, such as sachet(s) of silica gel crystals inside positioner cases;
- Release packing completely and cover with oiled paper;
- Coat bolts, stems, limit switches and handwheels with heavy grease;
- Isolate air filters/regulators;
- Protect accessories;
- Plug air tubing.
-
14.1.3. Maintenance during Preservation (Interval: 3 months)
- Operate valves (opening and closure);
it is specifically furnished or outside the extent of the agreed upon right of use.

- Restore protection on thread.


-
14.1.4. Notes
1. Initial preservation measures to be checked and renewed (if necessary) during
construction, precommissioning and commissioning phase and maintained till Ready
for Initial Start-Up

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 60/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

14.2. ELECTRONIC AND PNEUMATIC TRANSMITTER (FIELD AND BOARD TYPE)

14.2.1. Storage

These materials shall be stored in warehouse, with controlled temperature, in plastic bags
or manufacture enclosure, with drying agent (silica-gel).

14.2.2. Initial Preservation

Temporary Preservation
- No specific actions to be carried out.

Short-Term Preservation
As a rule all transmitters should be dismantled and stored in a suitably air-conditioned
area.
If it is decided to keep these instruments field erected, follow the procedure given here:
- Protect single instruments with plastic or other cover;
- Place drying agent, such as sachet(s) of silica gel crystals under cover;
- Seal cover tightly;
- Coat cover screws and bolts with heavy grease;
- Grease displacers;
- Tightly seal isolating valves on process and air supply connections.

14.2.3. Maintenance during Preservation (Interval: 3 months)

- Check silica-gel status;


- When the material is installed, but not pneumatically or electrically energized, ensure
the minimum as follows:
9 Tightness of covers
9 Greasing of screwed parts
9 Plugging of holes: process side and power or signal side
9 Protection with plastic bags or covers against environmental conditions.

14.2.4. Notes

1. Initial preservation measures to be checked and renewed (if necessary) during


it is specifically furnished or outside the extent of the agreed upon right of use.

construction, precommissioning and commissioning phase and maintained till Ready


for Initial Start-Up

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 61/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

14.3. FIELD INSTRUMENTS

14.3.1. Storage

- This material shall be stored in warehouse according Supplier/Manufacturer’s


recommendations.
- Temperature shall be controlled to prevent the condensation of humidity on analyzers;
- Bulk material (accessories) shall be clearly tagged to provide proper identification and
protected with plastic bags;
- Bottles and calibration kits shall be stored in warehouse and a record of the expiry date
for gas validity shall be kept.

14.3.2. Initial Preservation

Temporary Preservation
- No specific actions to be carried out.

Short-Term Preservation
Level gauges, thermometers, manometers:
- Protect with plastic or other suitable cover;
- Seal isolating valves.
-
Field analyzers
- Seal local analyzer cabinets;
- Isolate power source;
- Remove and store catalysts and reagents (if any):
- Place drying agent, such as sachet(s) of silica gel crystals inside housing;
- Protect with plastic or other suitable cover;

Gas alarm detectors


- Seal detector head filters with cap and suitable waterproof adhesive tape;
- Isolate power source;
- Place drying agent, such as sachet(s) of silica gel crystals inside housing.

14.3.3. Notes
1. Initial preservation measures to be checked and renewed (if necessary) during
it is specifically furnished or outside the extent of the agreed upon right of use.

construction, precommissioning and commissioning phase and maintained till Ready


for Initial Start-Up.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 62/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

14.4. LOCAL CABINETS, PANEL AND JUNCTION BOXES

14.4.1. Storage

To be stored in warehouse, or directly in field, taking into account to:


- Plug any spare or not used hole for cables or instrument installation.
- Protect with covers and bags the panels up to energization, against external conditions
and mechanical damages.

14.4.2. Initial Preservation

Temporary/Short-Term Preservation
- Place drying agent, such as sachet(s) of silica gel crystals inside cabinets and boxes;
- Seal openings on cabinets and boxes;
- Spray electrical connections with protective product for electrical parts;
- Coat door hinges screws and bolts with heavy grease.
-
14.4.3. Maintenance during Preservation (Interval: 4 weeks)
- Check drying agent efficiency and, if necessary, refurbish;
- Check electrical connections and spray with protective oil, if necessary;
- Check door hinges, screws, bolts grease coatings and, if necessary, refurbish;
- Check cable status;
- Check condition of external protections.
-
14.4.4. Restoration
- Renew drying agents;
- Switch on power to local panels.
-

14.5. ELECTRONIC CONTROL BOARDS AND CABINETS – DCS/COMPUTERS (FOR


CONTROL AND TERMINATING ROOMS)

14.5.1. Storage

To be stored in warehouse with controlled temperature or directly inside control room or


terminating rooms, in a dry, warm place, where condensation of humidity cannot occur
it is specifically furnished or outside the extent of the agreed upon right of use.

and where:
- Good ventilation is guaranteed;
- Conditioned ambient must be provided, if high relative humidity rapid changes in
temperature are experienced.

In case of long storage period, equipment shall remain in its original packing.
Storage condition shall be according to Supplier/Manufacturer’s requirements, but as
minimum:
- Temperature +5 °C +40 °C
- Relative humidity lowers than 60%.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 63/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

14.5.2. Preservation

During operating conditions (control rooms energization) the following minimum conditions
shall be ensured:
- Temperature and humidity control in the ambient where electronics are installed;
- Smoke and fire detection system activated;
- Absence of sand, dust or other detrimental components in control and terminating
rooms.

14.6. BULK MATERIAL FOR INSTRUMENTS

14.6.1. Storage

Bulk material for instruments shall be stored in warehouse, except rigid pipe, that can be
stored outside.

Accessories as union, flanges, nipples, special pieces as elbows, T pieces, compression


fittings, shall be stored in warehouse and clearly identified with different colors or codes,
according different type of material (AISI 316, AISI 304, CS, etc.).

Loose material as ammeters, push buttons, instrument material for packages, shall be
stored inside bags in warehouse and clearly identified. At least it will be stored as packed
by different Vendors, after a visual check to allow integrity status.

14.7. INSTRUMENT CABLES

14.7.1. Storage

Coils and reels shall be stored outside, before damage checks.

Loose cables, as special or prefabricated cables with connectors and pins, shall be stored
in warehouses.

14.7.2. Preservation
it is specifically furnished or outside the extent of the agreed upon right of use.

During construction, ensure that no cable suffered evident damages, before energization.
Follow resistance test for multi-cables and continuity check.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 64/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

15. MISCELLANEOUS MATERIALS

15.1. PAINTING MATERIALS

15.1.1. Storage

Check the integrity of the original containers, the legibility of technical data, product
identification and expiry date. Damaged containers or not-identifiable products shall be
rejected.

Check local storage conditions, which shall be in accordance with paint


Supplier/Manufacturer’s instructions.

Products for painting shall be stored in their original sealed containers in covered
warehouse well ventilated, protected from temperatures exceeding the
Supplier/Manufacturer’s recommendations.

Refrigerated storage areas shall be considered where too high ambient temperatures are
expected (storage temperature should be between 5 °C and 35 °C, as far as possible, but
in any case not exceeding 45 °C).

Where warehousing is not possible, paint shall in all cases be stored in a shaded area,
not exposed to the sun at any time of day.

Paints and other highly inflammable materials shall be stored away from plant materials
and field offices.
The containers shall not come into contact with heat sources or naked flame.
Suitable fire extinguishers shall be available adjacent to enclosed storage areas.

The containers shall be stored subdivided according to the quality of the product and in
such a way as to be able to use the ones stored first.

The maximum storage time indicated on the individual container should be considered
and recorded.
it is specifically furnished or outside the extent of the agreed upon right of use.

Particular instructions are given by the Supplier/Manufacturer and may be found on the
products’ technical card.

Particular attention shall be paid to the shelf life specified in the contractual documents
and/or on the packing itself, in order to identify special items requiring specific storage
precautions, which may deviate from the above general requirements.

TECHNIP ITALY S.p.A. - 00148 ROMA - Viale Castello della Magliana, 68


Project N° Unit Document Code Serial N° Rev. Page
2408 0000 MS 6740 52 0 65/65

BRASKEM-IDESA CODE: EXXI-040-00-00-CM-MS-0004


CONTRACTOR CODE: N.A.

ETILENO XXI PROJECT


CLIENT: BRASKEM IDESA SAPI
The present document or drawing is property of TECHNIP ITALY S.p.A. and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in any way other than that for which

15.2. INSULATION MATERIALS

15.2.1. Storage

Check the package integrity. The main material shall be stored indoor (foamglass, mineral
wool rigid polyurethane and so on).

Polyurethane material must be stored in the original unopened container, with intact labels
and tags.

Check the material for expiring date every 6 months.