Vous êtes sur la page 1sur 5

Project Name: PKI WasteWater Tank

Owner: Pilipinas Kao Inc. ID-2017-SCH-005.8


Updated : 25-Oct-17

ACCOMPLISHMENTS REPORT JULY AUGUST SEPTEMBER OCT. NOVEMBER


FIT-UP & TESTING/I % %
Item Relative Wt. WELDING
No.
Activity / Task
(%)
ASSY
WORKS
NSPECTIO ACCOMP ACCOMP Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19
WORKS N PER ITEM OVERALL

###
###
###
###
###
###
###
###
###
###
###
###
###

1
2
3
4
5
6
7
8
9

1
2
3
4
5
6
7
8
9

1
2
3
4
5
6
7
8
9

1
2
3
4
5
6
7
8
9
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
2 UNITS WASTE WATER TANK 100.00% 40.00% 50.00% 10.00% 67.51%

3
4
5
6
7
8
9
STEEL WORKS
T-411(65cu.m.)Fabrication 45.10% 86.53% 39.02% Received FC Drawings on
Plate Assembly ONLY for
Bottom Plate Fabrication 1.89% 100.00% 100.00% 100.00% 100.00% 1.89% ###
###
###
###
###
###
T 411
Side Shell 17.77% 100.00% 100.00% 100.00% 100.00% 17.77% ###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
Material inspection for
Roof Plate Fabrication 2.29% 100.00% 100.00% 100.00% 100.00% 2.29% Plate ###
###
###
###
###

Handrail Fabrication 0.98% 100.00% 92.88% 92.88% 95.73% 0.94% ###


###
###
###
###
###
###
###
###

Ladder Cage Fabrication 1.03% 100.00% 90.00% 90.00% 94.00% 0.97% ###
###
###
###
###
###
###

Manhole & Nozzles 4.97% 100.00% 100.00% 100.00% 100.00% 4.97% ###
###
###
###
###
###
###
###
###
No FC Drawing Received
Scrubber Platform 1.51% 100.00% 100.00% 90.00% 1.36% for Manhole, Nozzle, ###
###
###
###
###
###
Ladder and Cage
HydroTest 1.09% 100.00% 80.20% 80.10% 0.87% ###

Deliver & Site Installation 3.62% 100.00% 56.78% 68.39% 2.48%

FRP Lining 5.38% 100.00% 56.40% 68.20% 3.67% ###


### ###
###
###
###
###
###

Painting 4.58% 100.00% 40.00% 1.83% ###


###
###
###
###

T-400(45cu.m.)Fabrication 27.18% 42.99% 11.69%


Bottom Plate Fabrication 1.63% 100.00% 100.00% 100.00% 90.00% 1.46% ###
###
###
###
###

Side Shell 10.69% 100.00% 40.00% 4.28% ###


###
###
###
###
###
###
###
###
###

Roof Plate Fabrication 1.97% 100.00% 40.00% 0.79% ###


###
###
###
###

Handrail Fabrication 0.85% 100.00% 40.00% 0.34% ###


###
###
###
###

Ladder Cage Fabrication 0.88% 100.00% 40.00% 0.35% ###


###
###
###
###

Manholes & Nozzle Fabrication 1.86% 100.00% 40.00% 0.74% ###


###
###
###
###
###

HydroTest 0.62% 100.00% 40.00% 0.25% ###

Deliver & Site Installation 2.05% 100.00% 40.00% 0.82% ###

FRP Lining 3.59% 100.00% 40.00% 1.43% ###


###
### ###
###
###
###
###
### ###
###

Painting 3.05% 100.00% 40.00% 1.22% ###


###
###

% %
Relative Wt. PREP. ACTUAL
CIVIL WORKS ACCOMP ACCOMP
(%) WORKS WORKS
PER ITEM OVERALL

T-411 Foundation 15.03% 20.00% 80.00% 97.49% 14.65%


Idle Tank Foundation Demolition 2.25% 100.00% 100.00% 100.00% 2.25% ###
### ###
###
###
###
###
### ###
### ### Lean Concrete Pouring
sched on holt due to All Rebars site sample
Excavation 0.52% 100.00% 100.00% 100.00% 0.52% ###
###
###
###
@Tensile,Bending,Deform
### ###
### ### testing preparation set by ation Test
Disposal 0.21% 100.00% 100.00% 100.00% 0.21% ###
###
###
JGC
###
###
###
Provision for Jig Plate HDPE and Polylock
Compaction 0.14% 100.00% 100.00% 100.00% 0.14% ######
###
received received
######
###
###
Lean Concrete 0.23% 100.00% 100.00% 100.00% 0.23% ###
Trial Mix design @ ### 50 dia PVC and Nuts
Rebar Works 3.03% 100.00% 100.00% 100.00% 3.03% 4000 psi 7 days ######
###
###
###
### Received
###
### ###
###
### ###
Form Works 0.57% 100.00% 100.00% 100.00% 0.57% Test for Compression
###
###
###
###
###
### Jig Plate Installation
@ 3 days age for 4000
### ### ###
### ###
Concrete Works 4.59% 100.00% 100.00% 100.00% 4.59%
psi ###
###
###
Elevation and leveling
Inspection
BackFill 0.34% 100.00% 100.00% 100.00% 0.34% 4000 psi Test for ###
###
###
###
Compression @ 7 days
Restoration works 3.14% 100.00% 85.00% 88.00% 2.76% age ### ###
###
###

T-400 Foundation 12.69% 16.97% 2.15% Received FC Drawings


Existing Tank Foundation Demoli 1.71% 100.00% 100.00% 100.00% 1.71% for Tank Fabrication ###
###
###
###
###
###

Excavation 0.52% 87.00% 87.00% 87.00% 0.45% Testing of Lean Concrete ###
###
###
###
###
Compressive Test @ age
of 7 days
Testing of Lean Concrete
Compressive Test @ age
Disposal 0.21% 0.00% 0.00% of 7 days ###
###
###
###
###
###

Compaction 0.14% 0.00% 0.00% ###


###
###

Lean Concrete 0.23% 0.00% 0.00% ###


###
###

Rebar Fabrication 3.03% 0.00% 0.00% ###


###
### ###
###
###

Form Works 0.57% 0.00% 0.00% ###


###
### ###
###
###

Concrete Works 4.59% 0.00% 0.00% ###


###
###
`
BackFill 0.34% 0.00% 0.00% ### ###
###
###

Restoration works 1.34% 0.00% 0.00% ###


###
### ###
###

Prepaird by

JCRecablanca
WELD LINE ASSEMBLY LENGTH UNIT FIT UP FULL WELD TEST/INSPECTION

CWL -1 10,091 mm
CWL -2 10,091 mm
CWL -3 10,091 mm
CWL -4 10,091 mm
CWL -5 10,091 mm

LWL -1 2,203 mm
LWL -2 2,203 mm
LWL -3 2,203 mm
LWL -4 2,203 mm
LWL -5 2,203 mm
LWL -6 2,203 mm
LWL -7 2,203 mm
LWL -8 2,203 mm

M-3 20 inches
M-2 20 inches
M-1 20 inches
N-21 2
N-20 3/4
N-19 3
N-18 2
N-17 3
N-16 3
N-15 4
N-14 3
N-13 2
N-12 3/4
N-11 3/4
N-10 2
N-9 1 1/2
N-8 3/4
N-7 1
N-6 2
N-5 2
N-4 3
N-3 3/4
N-2 3
N-1
T411 For Idle Foundation
ITEM NO. PARTICULARS SPECS QTY
1 Cement Portland 10
2 Sand Washed 6
3 Gravel 3/4 1
4 Gravel G1" 1
5 Plywood Marine 3/4" x 4' x 8' 9
6 Plywood Marine 1/2" x 4' x 8' 9
7 Good lumber 2x4 40
8 Form Oil 1
9 Reinforced Steel Bar 16 dia x 6m Grade 60 130
10 Reinforced Steel Bar 12 dia x 6m Grade 60 36
11 Wire Mesh 150 x 150 x 5.5 mm 4
12 HDPE 4x7x1.5mm thk. 2
13 Polylock 24
14 Corkboard 4m x 8m x 4mm thk. 2
15 Oiled Sand used Engine oil 40 0.46
16 PVC pipe Series 1000, 3mm thk. 50 dia. 1
17 Joint Sealant 9
18 Ready Mix Concrete 4,000 psi, 3/4",28 days, S6 6.5
19 Ready Mix Concrete 4,000 psi, 3/4",28 days, S6 3
20 Ready Mix Concrete 3,000 psi, 3/4",28 days, S4 1.5
21 Mesh Net Cover 2mm thk. 1
22 CRS Bar A36 x 6m long 2
23 Washers and Nuts 16
UNITS
bags Lean Concrete
cu.m Lean Concrete
cu.m Lean Concrete
cu.m Subbase for Paving
shts. Form
shts. Form
pcs. Form
gal
pcs Rebar
pcs Rebar
shts. Rebar
shts. Moisture Barrier/Vapor Membrane
m Lock HDPE
shts Joint Filler
cu.m. Top Covering Sand
pcs Leak Detector
tube Sealed Isolation Joint
cu.m. Footing
cu.m. Pedestal
cu.m. Paving
sht. Leak Detector
LE Anchor bolts
pcs Anchor bolts

Vous aimerez peut-être aussi