Académique Documents
Professionnel Documents
Culture Documents
Problem Statement
1
The dead loads are considered as per [14]:
• 1.0 kN/m2, Floor finishes (including Ceiling finish)
• 2.0 kN/m2, Terrace Water proofing
• 1.0 kN/m2, Terrace finishes (including ceiling finish)
Tie beams are provided at 100 mm below ground level.
2
11. At ground level, the floor beams (FB) are not provided as the floor directly rests on
ground (earth filling and 1:4:8 c.c. at plinth level) and no slab is provided. The ground
beams will be provided at 100 mm below ground level.
12. All dimensions are in mm, unless specified otherwise.
3
Fig. 1.2: Elevation of Buildings
1.5 Loadings
The total seismic weight W of the building is calculated by considering all dead loads and
percentage of the live load. The simplest procedure to perform this work is to first
prepare the lumped mass model [1] and then add all the weights at all floor level. The
unit weight of material used in the construction of the building is given in Table 1.1. The
dimensions of the building components are given in Table 1.2. The Dead load of building
components is shown in Table 1.3. The lumped mass model of the building is shown in
Fig. 1.3.
4
Table 1.1: Unit Weight of Material of Building Components [12]
Member Density
Beam, Column & Slab 25(kN/m3)
Infills & Parapet 19(kN/m3)
Plaster 20.4(kN/m3)
Water proofing 2 ( kN/m2)
Floor finish 1 (kN/m2)
Roof
M4
K4
M3 G+3
K3
M2
G+2
K2
M1
G+1
K1
G (Tie Beam)
5
No. of Length(m Width(m Depth(m
Building Component Elements ) ) )
Beams 40 4.05 0.25 0.40
Columns Below Tie Beam 25 1.05 0.40 0.40
Columns Above Tie Beam 25 2.75 0.40 0.40
Slab 1 18 18 0.15
Roof (or floor) Finishes 1 17.86 17.86
Outer Walls 16 4.05 0.23 2.75
Inner Walls 24 4.05 0.115 2.75
Plaster & Finishing on Outer Walls 16 4.5 0.015 3.2
Plaster & Finishing on Inner Walls 64 4.05 0.015 2.75
Parapet Wall 1 72 0.115 1
Parapet Finish 2 73.2 0.015 1
Table 1.3: Dead Load of Building Components Lumped at Different Floor Levels
Building component Nomenclature Load (kN)
Columns below tie beam a 105.00
Columns in each storey b 275.00
Outer walls c 778.70
Slab d 1215.00
Floor and ceiling finishes e 318.98
Roof finishes f 956.90
Beam g 405.00
Parapet h 157.30
Inner wall i 584.10
Plaster and finishes on outer wall j 69.90
Plaster and finishes on inner wall k 218.80
Parapet finishes l 44.80
6
Table 1.5: Live Load Acting on Building Components
Building component on which Live Load is Acting Nomenclature Load (kN)
Roof m 121.5
Floor(except ground floor and roof) n 243
Table 1.7: Mass Matrix for Lumped Mass Model (M) (in tonnes)
7
418.74 0 0 0 G+1
0 418.74 0 0 G+2
0 0 418.74 0 G+3
0 0 0 393.83 Roof
Table 1.9: Stiffness Matrix for Lumped Mass Model (K) (in N/mm)
8.73E+06 -4.37E+05 0.0 0.0 G+1
-4.37E+05 8.73E+06 -4.37E+05 0.0 G+2
0.0 -4.37E+05 8.73E+06 -4.37E+05 G+3
0.0 0.0 -4.37E+05 4.37E+05 Roof
The calculated base shear V′B by seismic coefficient method for fixed-base building for
all cases is shown in Table 1.10, where seismic weight of building is taken from Table
1.6.
8
The load combinations as per clause 6.3.1.2 [15] are used for the analysis of building as
given below:
1) 1.5 (DL + IL)
2) 1.2 (DL + IL ± EL)
3) 1.5 (DL ± EL)
4) 0.9 DL ± 1.5 EL
Earthquake load must be considered for +X, -X, +Y and –Y directions. Moreover,
accidental eccentricity can be such that it causes clockwise or anticlockwise moments.
Thus, ±EL above implies 8 cases, and in all, 25 cases as per Table 1.11 must be
considered. The load combinations are reduced to 13 instead of 25 by not using negative
torsion as the building is symmetric. Since earthquake load along Y-direction (EYTP and
EYTN) induces very small moments and shears, the same can be neglected from load
combinations. Load combinations 6 to 9, 14 to 17, and 22 to 25 are thus not considered.
Also, the effect of positive torsion (due to accidental eccentricity) for beams will be more
than that of negative torsion [9]. Hence, the combinations 3, 5, 11, 13, 19 and 21 will not
be considered in design. Thus, the combinations to be used for the designs are 1, 2, 4, 10,
12, 18 and 20, which are shown in bold face in Table 1.11.
9
1.6 Modeling
The frame-model developed in SAP [28] consists of beams, columns and footings with
fixed base. The material properties (as defined in section 1.4.1) of these elements are
assigned to the model. Slabs have not been modeled, rather to give a slab action, rigid
floor diaphragm are applied in model so that a particular floor because of slab action
behaves as a rigid body, i.e., all the nodes of the slab in the same plane have same amount
of displacement in its plane. As we know that the superimposed loads are transferred to
the slabs, and then the superimposed loads along with the loads of slab get transferred to
the beams. After this the superimposed load, the slab load and the beam load get
transferred to the columns, and finally these loads are transferred to the footings and
ultimately whole weight of building is transferred to the soil. This is known as load
transfer action.
The dead load of the slab and the superimposed load on the slab are considered as if they
are acting on the beams. Table 1.12 shows the unit load definition of loads acting on the
beam in model. Table 1.13 shows the calculations of these unit loads to be applied on
beams.
The frame consists of beams at floors and roof and they are further subdivided into
exterior and interior beams. This nomenclature is made to distinguish the loading pattern
on these beams. Table 1.14 shows the load application procedure on these beams.
After the load application, the parameters such as response spectrum function (Sa/g Vs Tn)
and scale factor (SF = ZIg/2R) are assigned for our building. The scale factor and
response spectrum used here are equivalent to horizontal seismic coefficient (Ah).
10
D Roof_Live Imposed load on roof slab transferring to exterior beams at roof
level.
E Infill Dead Load of exterior wall on exterior beams at floor level.
11
12