CONCEPTO EJES CALCULO TOTAL

A (1-8) 128 (1.03)(1.07)(0.251) 35.41 kg


B (1-2) 12 (1.03)(1.07)(0.251) 3.32 kg
B (2-8) 116(1.03)(1.07)(0.251) 32.09 kg
C (7-8) 21(1.03)(1.07)(0.251) 5.81 kg
D (1-8) 127(1.03)(1.07)(0.251) 4.70 kg
ESTRIBOS EN CADENA 1 (A-D) 59(1.03)(1.07)(0.251) 16.32 kg
DE CERRAMIENTO 2(A-B) 21(1.03)(1.07)(0.251) 5.81 kg
d=1/4” 2(A-B) 24(1.03)(1.07)(0.251) 6.64 kg
3(A-B) 24(1.03)(1.07)(0.251) 6.64 kg
4(A-B) 24(1.03)(1.07)(0.251) 6.64 kg
5(A-B) 24(1.03)(1.07)(0.251) 6.64 kg
7(A-C) 42(1.03)(1.07)(0.251) 11.62 kg
8(A-D) 65(1.03)(1.07)(0.251) 17.98 kg
ACERO d=1/4” (A-D)(1-8) 159.65
A (1-8) (26.19 m)(4)(1.07)(0.557) 62.43 kg
B (1-2) (2.74 m)(4)(1.07)(0.557) 6.53 kg
B (2-8) (23.69 m)(4)(1.07)(0.557) 56.47 kg
C (7-8) (4.51 m)(4)(1.07)(0.557) 10.75 kg
D (1-8) (25.84 m)(4)(1.07)(0.557) 61.60 kg
ACERO DE REFUERZO
1 (A-D) (12.01 m)(4)(1.07)(0.557) 28.63 kg
EN CADENA DE
2(A-B) (4.54 m)(4)(1.07)(0.557) 10.82 kg
CERRAMIENTO
2(A-B) (5.09 m)(4)(1.07)(0.557) 12.13 kg
d=3/8”
3(A-B) (5.10 m)(4)(1.07)(0.557) 12.16 kg
4(A-B) (5.11 m)(4)(1.07)(0.557) 12.18 kg
5(A-B) (5.11 m)(4)(1.07)(0.557) 12.18 kg
7(A-C) (8.62 m)(4)(1.07)(0.557) 20.55 kg
8(A-D) (13.45 m)(4)(1.07)(0.557) 32.06 kg
ACERO d=3/8” (A-D)(1-8) 338.44 kg
A (1-8) (25.67 m)(0.2 m)(0.15 m) 0.7701 m3
B (1-2) (2.48 m)(0.2 m)(0.15 m) 0.0744 m3
B (2-8) (23.17 m)(0.2 m)(0.15 m) 0.6951 m3
C (7-8) (4.25 m)(0.2 m)(0.15 m) 0.1275 m3
D (1-8) (25.32 m)(0.2 m)(0.15 m) 0.7596 m3
1 (A-D) (11.75 m)(0.2 m)(0.15 m) 0.3525 m3
CONCRETO EN
2(A-B) (4.28 m)(0.2 m)(0.15 m) 0.1284 m3
CADENA DE
2(A-B) (4.83 m)(0.2 m)(0.15 m) 0.1449 m3
CERRAMIENTO
3(A-B) (4.84 m)(0.2 m)(0.15 m) 0.1452 m3
4(A-B) (4.84 m)(0.2 m)(0.15 m) 0.1452 m3
5(A-B) (4.85 m)(0.2 m)(0.15 m) 0.1455 m3
7(A-C) (8.36 m)(0.2 m)(0.15 m) 0.2508 m3
8(A-D) (12.93 m)(0.2 m)(0.15 m) 0.3879 m3
(A-D)(1-8) 4.1271 m3
ESTRIBOS EN TRABE C(4-7) 70(1.23)(1.07)(0.251) 23.12 kg
d=1/4” 4(B-C) 30(1.23)(1.07)(0.251) 9.91 kg
5(B-C) 30(1.23)(1.07)(0.251) 9.91 kg
6(A-C) 54(1.23)(1.07)(0.251) 17.84 kg
ACERO d=1/4” (A-D)(1-8) 60.78 kg
C(4-7) (11.98 m)(4)(1.07)(0.996) 51.07 kg
ACERO DE REFUERZO 4(B-C) (3.84 m)(4)(1.07)(0.996) 16.37 kg
EN TRABE d=1/2” 5(B-C) (3.86 m)(4)(1.07)(0.996) 16.45 kg
6(A-C) (8.92 m)(4)(1.07)(0.996) 36.83 kg
C(4-7) (12.43 m)(2)(1.07)(0.996) 26.49 kg
COLUMPIOS EN 4(B-C) (4.29 m)(2)(1.07)(0.996) 9.14 kg
TRABE d=1/2” 5(B-C) (4.31 m)(2)(1.07)(0.996) 9.19 kg
6(A-C) (9.09 m)(2)(1.07)(0.996) 19.37 kg
ACERO d=1/2” (A-D)(1-8) 184.91 kg
C(4-7) (11.7 m)(0.3 m)(0.15 m) 0.5265 m3
4(B-C) (3.56 m)(0.3 m)(0.15 m) 0.1602 m3
CONCRETO EN TRABE 5(B-C) (3.58 m)(0.3 m)(0.15 m) 0.1611 m3
6(A-C) (8.36 m)(0.3 m)(0.15 m) 0.3762 m3
(A-D)(1-8) 1.224 m3