DETAILED ESTIMATE
2.0 PREPARATION FOR ENTRY AND EXIT POINTS lumpsum 1.00 5,000.00 5,000.00 10,000.00 10,000.00 7,000.00 7,000.00 22,000.00 1,980.00 2,200.00 1,309.00 27,489.00 27,489.00
Cutting and Breaking of Entry and Exit points including the labor and equipments in
digging
3.0 DRILLING OF PILOT HOLE lm 80 1350 108,000.00 1350 108,000.00 450.00 36,000.00 252,000.00 22,680.00 25,200.00 14,994.00 3,935.93 314,874.00
Including the supply of water and labor in conducting the drilling
4.0 PULLBACK OF 3" HDPE PIPE lm 80 437.5 35,000.00 - 150.00 12,000.00 47,000.00 4,230.00 4,700.00 2,796.50 734.08 58,726.50
Supply of 3" HDPE pipe and labor in buttfusing the HDPE pipes including the
pullback of HDPE pipe
TOTAL COST 613,504.50