CONFIDENTIAL AP/APR 2007/SUR300

-ISh

UNIVERSITI TEKNOLOGI MARA


FINAL EXAMINATION

COURSE : ENGINEERING SURVEYING 3


COURSE CODE : SUR300
EXAMINATION : APRIL 2007
TIME : 3 HOURS

INSTRUCTIONS TO CANDIDATES

1. This question paper consists of six (6) questions.

2. Answer any FOUR (4) questions in the Answer Booklet. Start each answer on a new page.

3. Do not bring any material into the examination room unless permission is given by the
invigilator.

Please check to make sure that this examination pack consists of:

i) the Question Paper


ii) an Answer Booklet - provided by the Faculty

DO NOT TURN THIS PAGE UNTIL YOU ARE TOLD TO DO SO


This examination paper consists of 3 printed pages
© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL
CONFIDENTIAL 2 AP/APR 2007/SUR300

QUESTION 1

a) With an aid of diagram, briefly explain the meaning circular curve.


(5 marks)

b) What do you understand about Point of Tangency?


(2 marks)

c) State and explain the essential control points to be marked on the ground before curve
could be set-out
(6 marks)

d) Briefly discuss the procedures of locating the tangent points of circular curves if the
intersection point (IP) is inaccessible.
(12 marks)

QUESTION 2

Two straights intersect at point IP8, chainage 3129.75 meter. Tabulate the data needed to
set out by a circular curve of radius 620 meters. The incoming and outgoing bearings of the
straight were 205° 30' 30" and 214° 00' 30" respectively, using 25 meters pegging interval.
(25 marks)

QUESTION 3

a) In the process of designing a curve, the factors listed below need to be considered for
the convenience of road users while driving. Discuss briefly the factors.

i) Intersection angle of curve


ii) Super elevation
iii) Design speed
iv) Sight Distance
v) Effect of centrifugal force
(15 marks)

b) With the aid of diagram briefly explain 4 types of vertical curves depending upon the
magnitude and sign of the gradients.
(10 marks)

© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL


CONFIDENTIAL 3 AP/APR 2007/SUR300

QUESTION 4

a) What is the difference between summit and valley curves and why are they needed?
(5 marks)

b) A vertical curve of 150m long will be inserted between two gradients. The first gradient
is + 1 % and meets a second gradient of +3% at intersection points VIP. The chainage
and reduce level (RL) of intersection point are 600.00m and 200.00m respectively.
Calculate the curve level at the various chainage points at 25m interval.
(20 marks)

QUESTION 5

a) What do you understands the term 'setting out' in engineering survey?


(5 marks)

b) Discuss the various types of horizontal grids that can be used during surveying and
setting out operations.
(12 marks)

c) In the setting out operation, there are various types of plan involved. List down the
plans.
(4 marks)
d) What is the information required to be shown on a setting out plan?
(4 marks)

QUESTION 6

a) How would you transfer the horizontal control through two shafts?
(5 marks)

b) Explain the basic operations procedure in mine surveying for determination of the
bearings and elevations.
(10 marks)

c) It is required to build a connection in the mine from the point X at R.L. of 150.00 to
another point Y at R.L. 140.00m. Determine the bearing, slope and length of the line XY
if the coordinate X (891.15N, 795.42E) and Y (880.24N, 741.25E).
(10 marks)

END OF QUESTION PAPER