C D E F G H I J
Nominated Sub Contractor Antitermite treatment 5-Jun-15 19-Jun-15 5-Jul-15 10-Jul-15 7-Aug-15 21-Aug-15 28-Aug-15 11-Sep-15 27-Oct-15 30 1.0 Appointed
22-May-15 5-Jun-15 21-Jun-15 26-Jun-15 24-Jul-15 7-Aug-15 14-Aug-15 28-Aug-15 28-Oct-15 40 1.3 Appointed
Nominated Sub Contractor Electrical and Fire Alarm Installation
Nominated Sub Contractor Plumbing, Drainage and Fire Fighting Installation 22-May-15 5-Jun-15 21-Jun-15 26-Jun-15 24-Jul-15 7-Aug-15 14-Aug-15 28-Aug-15 28-Oct-15 40 1.3 Appointed
22-May-15 5-Jun-15 21-Jun-15 26-Jun-15 24-Jul-15 7-Aug-15 14-Aug-15 28-Aug-15 28-Oct-15 40 1.3 Appointed
Nominated Sub Contractor HVAC Installation
Nominated Sub Contractor Pools (incl. MEP installation) 12-Aug-15 26-Aug-15 11-Sep-15 16-Sep-15 14-Oct-15 28-Oct-15 4-Nov-15 18-Nov-15 9-May-16 100 3.3
12-Aug-15 26-Aug-15 11-Sep-15 16-Sep-15 14-Oct-15 28-Oct-15 4-Nov-15 18-Nov-15 9-May-16 100 3.3
Nominated Sub Contractor Water features & ponds (incl. MEP installation)
18-Jan-16 1-Feb-16 17-Feb-16 22-Feb-16 21-Mar-16 4-Apr-16 11-Apr-16 25-Apr-16 2-Sep-16 90 3.0
Nominated supplier Sanitary & tapwares
20-Oct-15 3-Nov-15 19-Nov-15 24-Nov-15 22-Dec-15 5-Jan-16 12-Jan-16 26-Jan-16 24-Jun-16 100 3.3
Nominated Sub Contractor Aluminium Openings (doors, windows & glazing)
16-Nov-15 30-Nov-15 16-Dec-15 21-Dec-15 18-Jan-16 1-Feb-16 8-Feb-16 22-Feb-16 19-Jul-16 100 3.3
Nominated Sub Contractor Timber joinery & linings - External main door, internal doors, etc
Nominated Sub Contractor Gypsum / PVC ceilings (incl skimming) 16-Nov-15 30-Nov-15 16-Dec-15 21-Dec-15 18-Jan-16 1-Feb-16 8-Feb-16 22-Feb-16 10-Jun-16 65 2.1
26-Apr-16 10-May-16 26-May-16 31-May-16 28-Jun-16 12-Jul-16 19-Jul-16 2-Aug-16 15-Dec-16 90 3.0 Ext only
Nominated Sub Contractor Imported Stone Cladding (Internal & External) - External only!
Nominated supplier Ironmongery internal 16-Nov-15 30-Nov-15 16-Dec-15 21-Dec-15 18-Jan-16 1-Feb-16 8-Feb-16 22-Feb-16 19-Jul-16 100 3.3
16-Nov-15 30-Nov-15 16-Dec-15 21-Dec-15 18-Jan-16 1-Feb-16 8-Feb-16 22-Feb-16 19-Jul-16 100 3.3
Nominated Sub Contractor Shopfittings (Internal) - Built in cupboards, built-in kitchens, etc (vanity)
Nominated Sub Contractor Timber joinery (External) - decking, pergolas, cladding etc 22-Apr-16 6-May-16 22-May-16 27-May-16 24-Jun-16 8-Jul-16 15-Jul-16 29-Jul-16 13-Dec-16 90 3.0
7-Oct-15 21-Oct-15 6-Nov-15 11-Nov-15 9-Dec-15 23-Dec-15 30-Dec-15 13-Jan-16 31-May-16 90 3.0
Nominated supplier Hard Finishes - Tiling (wall and floor)
7-Oct-15 21-Oct-15 6-Nov-15 11-Nov-15 9-Dec-15 23-Dec-15 30-Dec-15 13-Jan-16 31-May-16 90 3.0
Nominated supplier Hard Finishes - Tiling to Pools
4-Jan-16 18-Jan-16 3-Feb-16 8-Feb-16 7-Mar-16 21-Mar-16 28-Mar-16 11-Apr-16 22-Aug-16 90 3.0
Nominated supplier Hard Finishes - Granite and Marble (kitchen & bathrooms)
7-Oct-15 21-Oct-15 6-Nov-15 11-Nov-15 9-Dec-15 23-Dec-15 30-Dec-15 13-Jan-16 31-May-16 90 3.0
Nominated supplier Hard Finishes - Tiling (external)
23-Feb-16 8-Mar-16 24-Mar-16 29-Mar-16 26-Apr-16 10-May-16 17-May-16 31-May-16 16-Sep-16 75 2.5
Nominated Suppliers Tempered shower glass door
18-Jan-16 1-Feb-16 17-Feb-16 22-Feb-16 21-Mar-16 4-Apr-16 11-Apr-16 25-Apr-16 2-Sep-16 90 3.0
Direct Suppliers Toilet and bathroom accessories
Nominated Suppliers Non Deco Lighting - Architectural, pool, landscape 21-Jan-16 4-Feb-16 20-Feb-16 25-Feb-16 24-Mar-16 7-Apr-16 14-Apr-16 28-Apr-16 7-Sep-16 90 3.0
18-Jan-16 1-Feb-16 17-Feb-16 22-Feb-16 21-Mar-16 4-Apr-16 11-Apr-16 25-Apr-16 21-Jun-16 40 1.3
Nominated Subcontractor Painting