Académique Documents
Professionnel Documents
Culture Documents
VERSION NO.: 1
WORK INSTRUCTION PROCESS FOR REVISION NO.: FIELD CHANGE
INSPECTION, TESTING & FIELD CODE:
COMMISSIONING OF ELECTRICAL DATE
SWITCH BOARD & SWITCHYARD PAGES: 1 OF 22
PREPARED BY LEGALIZED BY
___________ ___________
PROJECT DIRECTOR QMR
SIGNATURE: SIGNATURE:
SIGNATURE:
DATE:
Amendment record
Page Rev. Description of Amendment Date of QMR Electrical
No. No. issue Legalized Authorized
Date Date
N/A N/A First Issue of WI016, Ver. 1 & Rev. 0 for
PT _______
N/A N/A Page OF 22
Revision 1
Battery & Battery Charger Inspection Record
Incorporated
DISTRIBUTION TO:
1.0 PURPOSE
2.0 SCOPE
RESPONSIBILITIES
3.0
DEFINITIONS
4.0
5.0 PROCEDURES
5.1 GENERAL
5.2 POLARITY CHECKS
5.3 RATIO CHECKS
5.4 MAGNETIZATION CURVE
5.5 VOLTAGE TRANSFORMER TEST
5.6 RATIO CHECK
5.7 PHASING CHECK
5.8 SECONDARY INJECTION
5.9 HI-POT TESTING USING FERRANTI HI-POT SET
5.10 HI-POT TESTING USING BIDDLE HI-POT TEST SET
5.11 EARTH RESISTANCE TEST (ET5) TO AS3000
5.12 DUCTER TESTING (SWITCH GEAR)
5.13 BLOCK DIAGRAM OF COMMISSIONING HV SWITCH YARD
5.14 BLOCK DIAGRAM OF COMMISSIONING HV SWITCH BOARDS
5.15 MIDOS RELAY TYPES
5.16 COMMISSIONING CHECK LIST
QUALITY RECORDS
6.0
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
1.0 PURPOSE
1.1 To ensure testing carried out in Switch Yards and Switch Boards is done so in a
planned acceptable manner.
2.0 SCOPE
2.1 This procedure applied to the testing of all switch gear undertaken by PT ______
Technical Services Division except if otherwise directed by the Client.
3.0 DEFINITIONS
4.0 RESPONSIBILITIES
4.2 Technical Services Technicians are responsible for carrying out tests as directed in
accordance with these procedures, and recording the test or inspection results on
the correct form.
5.0 PROCEDURES
5.1 General
5.1.1 All results of equipment tested shall be recorded on the relevant test sheet,
refer Section 5.0, copies being in Procedures Manual PM2.
5.1.2 All equipment used for inspection and testing shall carry a current
calibration sticker is not affixed, contact the Technical Services Supervisor.
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
5.1.3 If any equipment should fail inspection and/or testing, the client will be
notified at the time of testing or, if not available, at the earliest possible time.
5.1.4 A test report will be issued to the Client for all inspection and testing
undertaken if the specified in the contract or on request from the Client.
Each current transformer should be individually tested to verified that the primary
and secondary polarity markings are the same as drawings supplied by client.
NOTE: The above identifications always starts with A, C or D but the numbers
may be slightly different. The numbers always use 10, 30 and 50 but
maybe the number is C110. This is done when there are several
protection schemes on the same feeder.
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
Method
Connect polarity test set as per drawing, Fig. 1, by pushing test button down, a
positive flick on the meter should occur. If this does not occur follow check chart
below.
FIGURE 1 POLARITY
CHECK
P2 P1
S2 S1
Button Push
- +
NO FLICK ON METER
P2 P1
S2 S1
A2
A1 51
250V AC supply
A1
in series
51
51
64
IMPORTANT: When injection of current is taking place make sure, if there is more than 1 CT
in that Phase that the CT’s not in test are shorted out and not open circuit.
When checking aboard with metering, over-current and differential the knee point
curve should be very low with saturation flux as low as 20-30V were as the over-
current voltage will be around 120V to 180V. Differential CT’s have a knee point
around 500V upwards.
V
Knee Point of C.T. 50% increase
in current to 10% increase in
voltage
C10 CII
Step up transformer
250V 1000V if required
Variable
Transformer
250V supply
METHOD
Several points must be checked on each CT. This is done through a variable
transformer while the primary CT circuit remains open. See Figure 5. The
magnetizing current is measured on the ammeter A and the secondary voltage
using a voltmater. The applied voltage would be slowly raised until the
magnetizing current is seen to rise rapidly (50% increase in current to 10%
increase in voltage), for a small increase in voltage. This indicates the
approximate knee point of the CT. The magnetizing current should be recorded
using Technical Service sheets.
It is often found that the current transformer with a secondary rating of 1 ampere or
less have a knee point voltage higher than the legal main supply. In this case a
step up transformer may be required to obtain the necessary voltage to check the
curve.
The voltage transformer polarity can be checked with the test described for the
main current transformers, care must be taken to connect the battery supply to the
primary winding, with the polarity ammeter connected to the secondary winding if
the voltage transformer is of the capacitor type, then the polarity of the transformer
at the bottom of the capacitor stack should be checked.
This check is carried out on HV voltage transformers to verify the ratio is correct.
Method
Ratio 200:1
110V
LV Winding
HV Winding
These test are generally described in the manufactures service manual for relays,
but brief details are given below for the main types of protection relays.
Equipment
It is common practice to provide test blocks or test sockets in the relay circuits so
that connections can readily be made to test without disturbing wiring. A later
development was the test plug which can be used to plug into draw-out relay case
or into test block nominated near to a non draw-out relay case.
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
When used with a draw-ou relay the multiple figures of the test plug are inserted
between the contract stripes of the case and the draw-out chassis are normally
spinning together to make firm contact.
Since the top and bottom contact or each test plug finger is separated by an
insulation strip to relay circuits can be completely isolated from the switchgear wire
when the test plug is inserted, ie is most important to remember, that the correct
transformer shorting switches, will not be shorted links are fitted across all live side
CT terminals of the test plugs before it is inserted. When the test plus is inserted
in position all the test circuitry can now be connected to the isolated ‘Relay Side’
test plug terminals.
Withdrawing the test plug immediately restores the connections to the main current
transformers and voltage transformers removed is the test connections and also
the short circuits which had been applied to the main CT secondary circuits.
A recent development has been the testing facilities provided for the modular type
case. The heavy current connectors at the extreme right hand side of the case are
normally connecting the main A.C. and D.C. incoming supplies to the relay and
hold open short circuiting switches provided in the case to prevent CT secondary
circuits from being open circuited.
When these connections are removed, the relay is isolated and the main current
transformer incoming connections are automatically short circuited.
A test plug may then be inserted so that secondary injection test can take place.
As previously described for the draw-out case, care must be taken then inserting
plug as the CT terminals are open circuited. As previously described CT terminals
must have shorting links in before plug is inserted. The relay is now isolated for
testing in the case of an MCGG63 (over-current and earth fault relay) terminals 13
and 14 must be linked, 15 and 16 must be linked this give the relay its supply.
Care must be taken to make sure 13 is positive and 14 is negative at relay
terminals.
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
For cables which are not individually screened, each core should be tested
to earth with the other cores at earth potential. Results should be in high
Meg-ohms. Each test, should be 1 minute.
The above test should be carried out using test report number-------.
5.9.2 HV Test
For cables which are not individually screened, each core should be tested
to earth with the other cores at earth potential. Results should be in the
high Meg-ohms. These test should be for 1 minute.
(a) Make sure, cable clearances are followed, Eg: Core to core clearance,
and core to earth are far enough apart to stop flash over during HV
Tests.
(b) Place danger sings at both ends of cable, warning Personnel of High
Voltage testing.
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
(c) Place barriers around both ends of cable preventing Personnel from
entering test area.
(d) If cables is in a situation where Personnel could come in contact with it,
or if it would be safer to have someone at the open end, do so.
(e) Take time in carrying out test, as High Voltage test sets have the
potential to KILL.
For cables which are not individually screened, each core should be tested
to earth with the other cores at earth potential. Results should be the high
Meg-ohms. Each test should be for 1 minute. The above test should be
carried out using test report number -------.
5.10.2 HV Test
Connect HV probe to core. Short other cores to earth. With foot switch
in position and depressed, set dial to zero, this allows HV to be
energized. Turn dial clockwise observing kV and milli-amps meters,
until required voltage is reached. Carry out test to all three cores
individually. After each test discharge cores using discharge stick.
For a XLPE cable which is individually screened each core should be tested
between screen and core. Results should be in the high Meg-ohms. This
test should be for 1 minute.
For cables which are not individually screened each core should be tested
to earth with the other cores at earth potential. Result should be in the high
Meg-ohms. This test should be for 1 minute.
2. For each repeat Hi-Pot test carried out on the same cable reduce
voltage 20%.
(a) Make sure cable clearance are followed. Eg: Core to core clearances,
and core to earth are far enough apart to stop flash over during HV
tests.
(b) Place Danger signs at both ends of cable warning Personal of High
Voltage testing.
(c) Place barriers around both ends of cable, preventing Personal form
entering test area.
(d) If cable is in a situation were Personnel could come in contract with it,
or if it would be safer to have someone at the open end, do so. Take
your time in carrying out test as High Voltage test sets have the
potential to KILL.
NOTE: This rule can only apply when all electrodes are in line and the earth
is a single electrode, pipe or plate.
(c) Set range switch to X1 and resistor dial to 010 (eg 10 ohms).
(e) If the deflection is (+) increase resistor dial to provide more resistance
until pointer comes back to the center. Increase range switch if needed,
(eg X10).
(f) If the deflection is (-) decrease resistor dial to reduce resistance, until
pointer comes back to the center. Reduce range switch if required, (eg
X0-01).
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
All personnel involved in testing, should be warned of the voltage that can
be generated by earth tester.
5.12.1 Connect load to Ducter test set, BLACK on the outer side and RED on the
inner. Select scale required, either micro-ohms or milli-ohms. Place probe
on busbar under test keeping the ‘P’ on probe on the inside while testing.
Wait until the reading settles then record on ____ test sheet.
Set
Protection
Scheme
SWITCHBOARD HV/MV :
LOCATION:
YES NO
1. Polarity test to current transformers
2. Ratio test to current transformers
3. Magnetisation curves to current transformers
4. Polarity test to voltage transformers
5. Ratio test to voltage transformers
6. Set all protection relays
7. Secondary injection of all protection relays
8. Ducter test all connections (bus bar joints, etc)
9. Ducter test all circuit breakers with breakers closed
10. Secondary injection to prove metering
11. High Pot Switchboard
12. High Pot Circuit breakers
13. Energise Switchboard
14. Phase Rotation if required
SWITCH YARD HV :
LOCATION:
YES NO
1. Polarity test to CT’s
2. Ratio test to CT’s
3. Magnetisation curves to current transformers
4. Polarity test to voltage transformers
5. Ratio test to voltage transformers
6. Set protection scheme (relay settings)
7. Secondary injection of protection relays
8. Ducter test to bus bars and connections
Work Instruction Process for Inspection, Testing & Commissioning
of Electrical Switch Board & Switch Yard
YES NO
9. Ducter test to bus bars and connections
10. Secondary injection to prove metering
11. Function test to circuit breaker
12. Energise switch yard and carry out phase rotation
Tested By Tested By
Date Date
Certified By Certified By
Accepted By Accepted By
Dielectric Test (After termination kit fitted)
Test INSULATION Applied Time Leakage INSULATION
Connection Test Volts Reading Pressure Seconds Current m Test Volts Reading
kV M kV Amps kV M
R-YBE
Y-RBE
B-RYE
E-RYB
Cable Continuity Checked YES/NO (Delete whichever is not applicable)
Cable Polarity Checked YES/NO
Connection Polarity Checked and Correct YES/NO
Connection Bolts Torque Checked YES/NO
REMARKS
R = Red, Y = Yellow, B = Black
TESTED BY DATE
CERTIFIED BY ACCEPTED BY
_________________ Client