Vous êtes sur la page 1sur 1

Third Party Inspection (TPI) services for on-site construction activities of

Ammonia Storage Tank Project

Preliminary Deployment plan

Sr.
Activities Days Tank
No. DPT MPT UT RT
Inspector
01 Outer Tank(OT) bottom
7   
annular plate
02 OT Shell course 10 5   
03 OT Shell course 11 11   
04 Roof Compression Ring 6   
05 Roof rafters/beams 12    
06 Suspended Deck 6   
07 Roof plates 9  
08 OT Shell course 09 to 01 86   
09 OT Shell to bottom corner
13   
weld
10 Inner Tank(IT) bottom
5   
annular plate
11 IT shell course 10 6   
12 IT shell compression ring 6   
13 IT shell course 09 to 01 79   
14 IT shell to bottom corner
13   
weld
15 OT bottom central plates 9  
16 IT bottom central plates 10  
17 Shell and roof nozzles 18    
18 Internal and external piping
18   
/ structure
19 NDT during/after tank
9     
hydrotest
TOTAL 328 27 328 65 256

*Other activities in parallel such as compressor, piping, pipe rack and flare has not been
mentioned above, whereas same will also be in TPI scope of supervision.