REPUBLIK INDONESIA

KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAK


DIREKTORAT JENDERAL BINA MARGA
BALAI PELAKSANAAN JALAN NASIONAL XII BALIKPAPAN

SATUAN KERJA PELAKSANA JALAN NASIONAL WILAYAH I


PROVINSI KALIMANTAN UTARA

PEJABAT PEMBUAT KOMITMEN SP.3 POS GABUNGAN BTS. NEGARA - SEI UL


SEBATIK (PPK 1.4)

PAKET :
PRESERVASI RUTIN JALAN SP.3 POS BTS. NEGARA - SEI ULAR DAN SEB

JUSTIFIKASI TEKNIS

ADDENDUM 01

NOMOR KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018


TANGGAL KONTRAK : 27 Februari 2018
NILAI KONTRAK : Rp. 8.618.978.000,-
NOMOR ADDENDUM KONTRAK 01 : 06-35/APBN/PJNAS.I-KALTARA/ADD.0I/2018
TANGGAL ADDENDUM KONTRAK 01 : 26 Maret 2018
NILAI ADDENDUM KONTRAK 01 : Rp. 8.618.978.000,-
SUMBER DANA : APBN
TAHUN ANGGARAN : 2018
MAHAN RAKYAT
A
LIKPAPAN

WILAYAH I

GARA - SEI ULAR, PULAU

ULAR DAN SEBATIK

ADD.0I/2018
DAFTAR HADIR
PEMBAHASAN DRAFT JUSTIFIKASI TEKNIS
Paket : Preservasi Rutin Jalan Sp.3 Pos Batas Negara – Sei Ular dan
SATKER PELAKSANAAN JALAN NASIONAL WILAYAH I KALIMANTAN

Hari / Tanggal : Selasa, 20 Maret 2018

Waktu : 10.00 Wita s/d selesai

Tempat : Ruang Rapat Kantor PJN Wilayah I Provinsi Kalimantan Utara


Jalan Jenderal Sudirman No. 84 RT. 04 Tanjung Selor - Kalimantan Utara

No. NAMA JABATAN

1 PUJI EKO AGUS PRASETYO, ST KETUA PPPK

2 YOHANSYAH SEKRETARIS

3 KHANIF ASHAR, ST ANGGOTA PPPK

4 Ir. ROSIHAN ANWAR ANGGOTA PPPK

5 HERY MULYANTO, ST ANGGOTA PPPK

6 AHMAD ZAIS, ST ANGGOTA PPPK

7 TOMMY IRAWAN ANGGOTA PPPK


8 RIVANIZAR, ST PEJABAT PEMBUAT KOMITMEN

( PPK 1.4 )

9 Ir. JOS DONALD SIAGIAN SITE ENGINEER

PT. WAHANA MITRA AMERTA KSO

10 SUHARTO, SE DIREKTUR

PT. BUMALINDO PRIMA ABADI

11 RIYANTO, ST GENERAL SUPERINTENDENT

PT. BUMALINDO PRIMA ABADI


DAFTAR HADIR
N DRAFT JUSTIFIKASI TEKNIS
n Sp.3 Pos Batas Negara – Sei Ular dan Sebatik
N NASIONAL WILAYAH I KALIMANTAN UTARA

84 RT. 04 Tanjung Selor - Kalimantan Utara

JABATAN TANDA TANGAN

KETUA PPPK

SEKRETARIS

ANGGOTA PPPK

ANGGOTA PPPK

ANGGOTA PPPK

ANGGOTA PPPK

ANGGOTA PPPK
PEJABAT PEMBUAT KOMITMEN

( PPK 1.4 )

SITE ENGINEER

PT. WAHANA MITRA AMERTA KSO

DIREKTUR

PT. BUMALINDO PRIMA ABADI

GENERAL SUPERINTENDENT

PT. BUMALINDO PRIMA ABADI


JADUAL JUSTIFIKASI TEKNIK
PEJABAT PEMBUAT KOMITMEN SP.3 POS GABUNGAN BTS. NEGARA - S
PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS. NEGARA
KONTRAKTOR : PT. BUMALINDO PRIMA
KONSULTAN : PT. WAHANA MITRA AMER
TAHUN 2018

NO URAIAN TANGGAL

1 SK Panitia Peneliti Pelaksana Kontrak 26 Februari 2017 No.

2 SK Panitia Peneliti Pelaksana Kontrak Revisi 26 Februari 2017 No.

3 Kontrak 27 Februari 2018 No.

4 Usulan JUSTEK dari Kontraktor ke PPK ( Usulan Perubahan Kontrak Berdasarkan Hasil Kajian Teknis Lapangan ) 12 Maret 2018 No.

5 Surat PPK ke Konsultan ( Penugasan Evaluasi Usulan Perubahan Kontrak ) 13 Maret 2018 No.

6 Surat Konsultan ke PPK ( Laporan Hasil Evaluasi Usulan Perubahan Kontrak Hasil Kajian Teknis Lapangan ) 14 Maret 2018 No.

7 Surat PPK ke Kasatker ( Rekomendasi Usulan Perubahan Kontrak ) 15 Maret 2018 No.

8 Surat Kasatker ke PPPK ( Penugasan Pembahasan Justek Untuk Usulan Perubahan Kontrak ) 16 Maret 2018 No.

9 PPPK ( Undangan Rapat Pembahasan Usulan Persetujuan Perubahan Kontrak ) 19 Maret 2018 No.

10 PPPK ( Berita Acara Pembahasan Draft Justek ) 20 Maret 2018 No.

11 PPPK ( Berita Acara Evaluasi Dan Negosiasi Harga ) 21 Maret 2018 No.

12 PPPK - Satker ( Laporan Hasil Pembahasan Justek Untuk Usulan Perubahan Kontrak ) 22 Maret 2018 No.

13 Surat Kasatker ke PPK ( Persetujuan Justek Perubahan Kontrak ) 23 Maret 2018 No.

14 Proses Kontrak Addendum 01 26 Maret 2018 No.


Catatan :
- Paket Kegiatan di Lingkungan Satuan Kerja Pelaksanaan Jalan Nasional Wilayah I Provinsi Kalimantan Utara
DUAL JUSTIFIKASI TEKNIK
S GABUNGAN BTS. NEGARA - SEI ULAR, PULAU SEBATIK (PPK 1.4)
JALAN SP.3 POS BTS. NEGARA – SEI ULAR DAN SEBATIK
TOR : PT. BUMALINDO PRIMA ABADI
N : PT. WAHANA MITRA AMERTA KSO
TAHUN 2018

FEB MARET 2018


NO. SURAT
26 27 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

PW.04.01/PJNAS.I-KALTARA/SK - 166

PW.04.01/PJNAS.I-KALTARA/SK - 195.2

06-35/APBN/PJNAS.I-KALTARA/2018

SBTK-KU/20/BPA-ADD 01/KALTARA-III/APBN-2018

PW.04.01/PPK1.4/PRESERVASI/ADD-I/059

03/WMA/PW-06/SE-ADD 02/VIII/2017

UM.01.11/PPK1.4/PRESERVASI/ADD-I/061

PW.04.01/PJNAS.I-KALTARA/JUSTEK/ADD-I/264

01/PPPK/06-35/APBN/PJNAS.I-KALTARA/2018

02/PPPK/06-35/APBN/PJNAS.I-KALTARA/2018

03/PPPK/06-35/APBN/PJNAS.I-KALTARA/2018

04/PPPK/06-35/APBN/PJNAS.I-KALTARA/2018

PW.04.01/PJNAS.I-KALTARA/JUSTEK/ADD-I/286

06-35/APBN/PJNAS.I-KALTARA/ADD.0I/2018
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

Pemeliharaan Rutin Kondisi Jalan Sp.3 Pos Gab. Bts. Negara - Sei. Ular (Holding)

KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)


NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
RUAS JALAN SP. 3 BTS NEGARA - SEI. ULAR
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 - - - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 - - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 - - - - - - -
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 46.10 40,931,949.36 96.86 - 3.09 2,743,594.87
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 - - - - - - -
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 58.39 1,327,253.75 3.14 5.84 132,748.11 - -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 150.65 2,610,846.76
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 - - - - - - -
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 - - - - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 - - - - - - -
42,259,203.11 100.00

A Jumlah Harga 42,259,203.11 100.00 2,743,594.87 2,743,594.87


B PPN = (10% X A) 4,225,920.31 274,359.49 274,359.49
C Jumlah Harga + PPN = (A + B) 46,485,123.42 3,017,954.36 3,017,954.36
D Pembulatan 46,485,000.00 3,017,000.00 3,017,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

1. ..............................................................................
PUJI EKO AGUS PRASETYO, ST : 5. HERY MULYANTO, ..............................................................................
ST : Mengetahui,
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
Ketua Anggota PT. BUMALINDO PRIMA

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota
SUHARTO, SE
DIREKTUR UTAMA
3. KHANIF ASHAR, ST ..............................................................................
: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
AMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

lan Sp.3 Pos Gab. Bts. Negara - Sei. Ular (Holding)

DRAFT ADDENDUM 01 SELISIH


BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)

- - - - TETAP
- - - - TETAP
- - - TETAP
43.01 38,188,354.49 90.37 6.70 BERKURANG
- - - - TETAP
- - - TETAP
64.23 1,460,001.85 3.45 10.00 BERTAMBAH
150.65 2,610,846.76 6.18 158.01 BERTAMBAH
- - - TETAP
- - - - TETAP
- - - - TETAP
42,259,203.11 100.00

42,259,203.11 100.00
4,225,920.31
46,485,123.42
46,485,000.00

Mengetahui, Menyetujui,
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

Pemeliharaan Rutin Kondisi Jalan Sp.3 Pos Gab. Bts. Negara - Sei. Ular

KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)


NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
RUAS JALAN SP. 3 BTS NEGARA - SEI. ULAR
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 - - - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 - - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 - - - - - - -
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 51.73 45,930,796.97 16.93 77.85 69,122,608.62 - -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 60.28 224,610,855.99 82.78 - - 21.41 79,776,350.81
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 34.91 793,533.62 0.29 3.49 79,330.63 - -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 610.17 10,574,411.55
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 - - - - - - -
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 - - - - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 - - - - - - -
271,335,186.58 100.00

A Jumlah Harga 271,335,186.58 100.00 79,776,350.81 79,776,350.81


B PPN = (10% X A) 27,133,518.66 7,977,635.08 7,977,635.08
C Jumlah Harga + PPN = (A + B) 298,468,705.24 87,753,985.89 87,753,985.89
D Pembulatan 298,468,000.00 87,753,000.00 87,753,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

1. ..............................................................................
PUJI EKO AGUS PRASETYO, ST : 5. HERY MULYANTO, ..............................................................................
ST : Mengetahui,
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
Ketua Anggota PT. BUMALINDO PRIMA

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota
SUHARTO, SE
DIREKTUR UTAMA
3. KHANIF ASHAR, ST ..............................................................................
: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
AMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

si Jalan Sp.3 Pos Gab. Bts. Negara - Sei. Ular

DRAFT ADDENDUM 01 SELISIH


BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)

- - - - TETAP
- - - - TETAP
- - - TETAP
129.58 115,053,405.59 42.40 150.49 BERTAMBAH
- - - - TETAP
38.87 144,834,505.18 53.38 35.52 BERKURANG
38.40 872,864.26 0.32 10.00 BERTAMBAH
610.17 10,574,411.55 3.90 1,647.84 BERTAMBAH
- - - TETAP
- - - - TETAP
- - - - TETAP
271,335,186.58 100.00

271,335,186.58 100.00
27,133,518.66
298,468,705.24
298,468,000.00

Mengetahui, Menyetujui,
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

Pemeliharaan Rutin Jalan Sp.3 Pos Gab. Bts. Negara - Sei. Ular

KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)


NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
RUAS JALAN SP. 3 BTS NEGARA - SEI. ULAR
DIVISI 1. UMUM
1.2 Mobilisasi Ls 179,750,000.00 1.00 179,750,000.00 13.57
179,750,000.00 13.57
DIVISI 9. PEKERJAAN HARIAN
9.1(1) Mandor Jam 27,500.00 30.00 825,000.00 0.06
9.1(2) Pekerja Biasa Jam 17,518.70 30.00 525,561.00 0.04
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 30.00 683,571.30 0.05
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 30.00 13,125,745.50 0.99
9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 30.00 24,118,478.70 1.82
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 30.00 19,757,666.10 1.49
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 30.00 22,549,779.00 1.70
81,585,801.60 6.16
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 - - - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 - - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 24.81 29,556,403.08 2.23 - - 24.81 29,556,403.08
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 74.63 66,263,587.43 5.00 148.25 131,629,229.11 - -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 95.37 355,360,606.10 26.83 - - 28.51 106,237,044.81
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 864.67 19,654,675.42 1.48 86.47 1,965,535.73 - -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 163.84 2,839,430.10
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 29.60 640,747.06 0.05 - - 29.60 640,747.06
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 908,160.00 556,266,163.20 42.00 - - - -
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 3,000.00 35,221,080.00 2.66 - - - -
1,062,963,262.30 80.27

A Jumlah Harga 1,324,299,063.90 100.00 ### ###


B PPN = (10% X A) 132,429,906.39 13,643,419.50 13,643,419.50
C Jumlah Harga + PPN = (A + B) 1,456,728,970.29 ### ###
D Pembulatan 1,456,728,000.00 ### ###

PANITIA PENELITI PELAKSANAAN KONTRAK

1. ..............................................................................
PUJI EKO AGUS PRASETYO, ST : 5. HERY MULYANTO, ..............................................................................
ST : Mengetahui,
Ketua Anggota PT. BUMALINDO PRIMA

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota
SUHARTO, SE
DIREKTUR UTAMA
3. KHANIF ASHAR, ST ..............................................................................
: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
AMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

alan Sp.3 Pos Gab. Bts. Negara - Sei. Ular

DRAFT ADDENDUM 01 SELISIH


BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)

1.00 179,750,000.00 13.57 - TETAP


179,750,000.00 13.57

30.00 825,000.00 0.06 - TETAP


30.00 525,561.00 0.04 - TETAP
30.00 683,571.30 0.05 - TETAP
30.00 13,125,745.50 0.99 - TETAP
30.00 24,118,478.70 1.82 - TETAP
30.00 19,757,666.10 1.49 - TETAP
30.00 22,549,779.00 1.70 - TETAP
81,585,801.60 6.16

- - - 100.00 TETAP
- - - - TETAP
- - - 100.00 BERKURANG
222.88 197,892,816.54 14.94 198.64 BERTAMBAH
- - - - TETAP
66.86 249,123,561.29 18.81 29.90 BERKURANG
951.14 21,620,211.16 1.63 10.00 BERTAMBAH
163.84 2,839,430.10 0.21 81.05 BERTAMBAH
- - - 100.00 BERKURANG
908,160.00 556,266,163.20 42.00 - TETAP
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)
3,000.00 35,221,080.00 2.66 - TETAP
1,062,963,262.30 80.27

1,324,299,063.90 ###
132,429,906.39
1,456,728,970.29
1,456,729,000.00

Mengetahui, Menyetujui,
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

PEMELIHARAAN RUTIN KONDISI JALAN LINGKAR PULAU SEBATIK (HOLDING)

KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG


NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp)
RUAS JALAN LINGKAR PULAU SEBATIK
DIVISI 1. UMUM
1.2 Mobilisasi Ls 231,750,000.00 1.00 231,750,000.00 6.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 139,450,000.00 1.00 139,450,000.00 3.93
1.17 Pengamanan Lingkungan Hidup Ls 43,600,000.00 1.00 43,600,000.00 1.23
1.21 Manajemen Mutu Ls 126,500,000.00 1.00 126,500,000.00 3.56
541,300,000.00 15.25
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 93,608.35 - - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 305,243.64 - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 - - - - - -
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 894.05 793,822,328.06 22.36 388.70 345,124,700.99 -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 583.69 2,174,902,298.16 61.27 - - 120.61
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 1,756.63 39,929,675.47 1.12 175.66 3,992,899.35 -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 5,785.95 100,271,787.30
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 - - - - - -
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 - - - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 - - - - - -
3,008,654,301.69 84.75

A Jumlah Harga 3,549,954,301.69 100.00 ###


B PPN = (10% X A) 354,995,430.17 44,938,938.76
C Jumlah Harga + PPN = (A + B) 3,904,949,731.86 ###
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp)
D Pembulatan 3,904,950,000.00 ###

PANITIA PENELITI PELAKSANAAN KONTRAK

1. PUJI EKO AGUS PRASETYO, ST ..............................................................................


: 5. HERY MULYANTO, ..............................................................................
ST :
Ketua Anggota

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota

3. KHANIF ASHAR, ST ..............................................................................


: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
N TAMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

ONDISI JALAN LINGKAR PULAU SEBATIK (HOLDING)

PEKERJAAN KURANG (-) DRAFT ADDENDUM 01 SELISIH


BOBOT KETERANGAN
JUMLAH HARGA JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (Rp) (%)

1.00 231,750,000.00 6.53 - TETAP


1.00 139,450,000.00 3.93 - TETAP
1.00 43,600,000.00 1.23 - TETAP
1.00 126,500,000.00 3.56 - TETAP
541,300,000.00 15.25

- - - - - TETAP
- - - - - TETAP
- - - - TETAP
- 1,282.75 1,138,947,029.05 32.08 43.48 BERTAMBAH
- - - - - TETAP
449,389,387.64 463.09 1,725,512,910.52 48.61 20.66 BERKURANG
- 1,932.29 43,922,574.82 1.24 10.00 BERTAMBAH
5,785.95 100,271,787.30 2.82 229.38 BERTAMBAH
- - - - TETAP
- - - - - TETAP
- - - - - TETAP
3,008,654,301.69 84.75

### 3,549,954,301.69 ###


44,938,938.76 354,995,430.17
### 3,904,949,731.86
PEKERJAAN KURANG (-) DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (Rp) (%)
### 3,904,950,000.00

Mengetahui, Menyetujui,
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

PEMELIHARAAN RUTIN KONDISI JALAN LINGKAR PULAU SEBATIK

KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)


NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
RUAS JALAN LINGKAR PULAU SEBATIK
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 93,608.35 - - - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 305,243.64 - - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 15.37 18,310,435.93 2.63 - - 15.37 18,310,435.93
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 185.12 164,367,081.67 23.64 146.47 130,049,948.43 - -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 135.43 504,629,200.84 72.56 - 35.95 133,954,218.20
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 272.26 6,188,698.50 0.89 27.23 618,960.77 - -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 1,358.11 23,536,385.92
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 89.65 1,940,641.00 0.28 - - 89.65 1,940,641.00
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 - - - - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 - - - - - - -
695,436,057.94 100.00

A Jumlah Harga 695,436,057.94 100.00 ### ###


B PPN = (10% X A) 69,543,605.79 15,420,529.51 15,420,529.51
C Jumlah Harga + PPN = (A + B) 764,979,663.74 ### ###
D Pembulatan 764,979,000.00 ### ###

PANITIA PENELITI PELAKSANAAN KONTRAK


KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
1. PUJI EKO AGUS PRASETYO, ST ..............................................................................
: 5. HERY MULYANTO, ..............................................................................
ST : Mengetahu
Ketua Anggota PT. BUMALINDO PR

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota
SUHARTO,
DIREKTUR UT
3. KHANIF ASHAR, ST ..............................................................................
: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
MBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

ONDISI JALAN LINGKAR PULAU SEBATIK

DRAFT ADDENDUM 01 SELISIH


BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)

- - - - TETAP
- - - - TETAP
- - - 100.00 BERKURANG
331.59 294,417,030.10 42.34 79.12 BERTAMBAH
- - - - TETAP
99.48 370,674,982.65 53.30 26.55 BERKURANG
299.49 6,807,659.27 0.98 10.00 BERTAMBAH
1,358.11 23,536,385.92 3.38 398.83 BERTAMBAH
- - - 100.00 BERKURANG
- - - - TETAP
- - - - TETAP
695,436,057.94 100.00

695,436,057.94 100.00
69,543,605.79
764,979,663.74
764,979,000.00
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (%)
Mengetahui, Menyetujui,
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBERUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

PEMELIHARAAN RUTIN JALAN LINGKAR PULAU SEBATIK

KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG


NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp)
RUAS JALAN LINGKAR PULAU SEBATIK
DIVISI 1. UMUM
1.2 Mobilisasi Ls 231,750,000.00 - -
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 139,450,000.00 - -
1.17 Pengamanan Lingkungan Hidup Ls 43,600,000.00 - -
1.21 Manajemen Mutu Ls 126,500,000.00 - -

DIVISI 9. PEKERJAAN HARIAN


9.1(1) Mandor Jam 27,500.00 80.00 2,200,000.00 0.11
9.1(2) Pekerja Biasa Jam 17,518.70 80.00 1,401,496.00 0.07
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 80.00 1,822,856.80 0.09
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 80.00 35,001,988.00 1.79
9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 80.00 64,315,943.20 3.29
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 80.00 52,687,109.60 2.70
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 80.00 60,132,744.00 3.08
217,562,137.60 11.14
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 93,608.35 489.39 45,810,990.41 2.35 44.79 4,192,402.60 -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 305,243.64 55.68 16,995,965.88 0.87 5.57 1,699,596.59 -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 271,025.42 38.78 10,510,907.84
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 224.80 267,806,505.98 13.72 - - 22.78
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 200.54 178,058,419.18 9.12 27.46 24,381,590.66 -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 69.65 59,994,107.77 3.07 - - 69.65
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp)
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 59.66 222,300,658.07 11.39 8.74 32,566,338.44 -
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 229.67 5,220,592.02 0.27 22.97 522,127.39 -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 887.53 15,381,013.09
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 98.02 2,121,825.22 0.11 - - 98.02
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 1,394,400.00 854,097,888.00 43.75 - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 7,000.00 82,182,520.00 4.21 - - -
1,734,589,472.53 88.86

A Jumlah Harga 1,952,151,610.13 100.00 89,253,976.61


B PPN = (10% X A) 195,215,161.01 8,925,397.66
C Jumlah Harga + PPN = (A + B) 2,147,366,771.14 98,179,374.27
D Pembulatan 2,147,367,000.00 98,179,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

1. PUJI EKO AGUS PRASETYO, ST ..............................................................................


: 5. HERY MULYANTO, ..............................................................................
ST :
Ketua Anggota

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota

3. KHANIF ASHAR, ST ..............................................................................


: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
N TAMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

N RUTIN JALAN LINGKAR PULAU SEBATIK

PEKERJAAN KURANG (-) DRAFT ADDENDUM 01 SELISIH


BOBOT KETERANGAN
JUMLAH HARGA JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (Rp) (%)

80.00 2,200,000.00 0.11 - TETAP


80.00 1,401,496.00 0.07 - TETAP
80.00 1,822,856.80 0.09 - TETAP
80.00 35,001,988.00 1.79 - TETAP
80.00 64,315,943.20 3.29 - TETAP
80.00 52,687,109.60 2.70 - TETAP
80.00 60,132,744.00 3.08 - TETAP
217,562,137.60 11

- 534.18 50,003,393.01 2.56 9.15 BERTAMBAH


- 61.25 18,695,562.46 0.96 10.00 BERTAMBAH
38.78 10,510,907.84 0.54 30.35 BERTAMBAH
27,138,043.62 202.02 240,668,462.36 12.33 10.13 BERKURANG
- 228.00 202,440,009.84 10.37 13.69 BERTAMBAH
59,994,107.77 - - - 100.00 BERKURANG
PEKERJAAN KURANG (-) DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA JUMLAH HARGA BOBOT (%)
KUANTITAS
(Rp) (Rp) (%)
- 68.40 254,866,996.51 13.06 14.65 BERTAMBAH
- 252.64 5,742,719.42 0.29 10.00 BERTAMBAH
887.53 15,381,013.09 0.79 286.44 BERTAMBAH
2,121,825.22 - - - 100.00 BERKURANG
- 1,394,400.00 854,097,888.00 43.75 - TETAP
- 7,000.00 82,182,520.00 4.21 - TETAP
1,734,589,472.53 88.86

89,253,976.61 1,952,151,610.13 ### - 0.00


8,925,397.66 195,215,161.01
98,179,374.27 2,147,366,771.14
98,179,000.00 2,147,367,000.00
-

Mengetahui, Menyetujui,
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH KURANG
PPK PELAKSANAAN JALAN (PPK 1.4) SP.3 POS GABUNGAN BTS NEGARA – SEI ULAR, PULAU SEBATIK
PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK

( BALANCE BUDGED / TETAP )


NOMOR KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018
TANGGAL KONTRAK : 27 FEBRUARI 2018

NILAI KONTRAK : Rp. 8.618.978.000,00


KONTRAKTOR : PT. BUMALINDO PRIMA ABADI
KONSULTAN : PT. WAHANA MITRA AMERTA. JO

KOTRAK PERUBAHAN
Harga Jumlah Bobot PENGURANGAN PENAMBAHAN

SAT.
MATA PEMB. URAIAN PEKERJAAN Satuan Kontrak Harga % Jumlah Hrg Jumlah Hrg
VOL VOL
VOL VOL
(Rp) (Rp) (Rp) (Rp)
LINGKAR PULAU SEBATIK
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 231,750,000.00 231,750,000.00 2.96 - - - - 1.00
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 139,450,000.00 139,450,000.00 1.78 - - - - 1.00
1.17 Pengamanan Lingkungan Hidup LS 1.00 43,600,000.00 43,600,000.00 0.56 - - - - 1.00
1.21 Manajemen Mutu LS 1.00 126,500,000.00 126,500,000.00 1.61 - - - - 1.00
Jumlah Harga Pekerjaan DIVISI 1 541,300,000.00 - -

DIVISI 9. PEKERJAAN HARIAN


9.1(1) Mandor Jam 80.00 27,500.00 2,200,000.00 0.03 - - - - 80.00
9.1(2) Pekerja Biasa Jam 80.00 17,518.70 1,401,496.00 0.02 - - - - 80.00
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 80.00 22,785.71 1,822,856.80 0.02 - - - - 80.00
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 80.00 437,524.85 35,001,988.00 0.45 - - - - 80.00
9.1(8) Motor Gleder min.100 Pk Jam 80.00 803,949.29 64,315,943.20 0.82 - - - - 80.00
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 80.00 658,588.87 52,687,109.60 0.67 - - - - 80.00
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 80.00 751,659.30 60,132,744.00 0.77 - - - - 80.00
Jumlah Harga Pekerjaan DIVISI 2 217,562,137.60 - -

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN


Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 489.39 93,608.35 45,810,990.41 0.58 - - 44.79 4,192,402.60 534.18
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 55.68 305,243.64 16,995,965.88 0.22 - - 5.57 1,699,596.59 61.25
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran * M3 271,025.42 38.78 10,510,907.84 38.78
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 240.17 1,191,310.08 286,116,941.91 3.65 38.15 45,448,479.55 - - 202.02
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 1,279.71 887,894.78 1,136,247,828.91 14.50 - - 562.63 499,556,240.07 1,842.34
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 69.65 861,365.51 59,994,107.77 0.77 69.65 59,994,107.77 - - 0.00
Skh-2.10.a.(10) Campuran Aspal Panas M3 778.78 3,726,125.68 2,901,832,157.07 37.03 147.82 550,777,267.39 - - 630.97
Skh-2.10.a.(13) Residu Bitumen Liter 2,258.56 22,730.84 51,338,965.99 0.66 - - 225.86 5,133,987.52 2,484.42
Skh-2.10.a.(13) Residu Bitumen* Liter 0.00 17,330.22 - 0.00 - - 8,031.59 139,189,186.31 8,031.59
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 187.67 21,646.86 4,062,466.22 0.05 187.67 4,062,466.22 - - 0.00
Skh-2.10.a.(19) Pengendalian Tanaman M2 1,394,400.00 612.52 854,097,888.00 10.90 - - - - 1,394,400.00
Skh-2.10.a.(20) Pembersihan Drainase M1 7,000.00 11,740.36 82,182,520.00 1.05 - - - - 7,000.00
5,438,679,832.16 660,282,320.93 660,282,320.93
SEI ULAR
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 179,750,000.00 179,750,000.00 2.29 - - - - 1.00
Jumlah Harga Pekerjaan DIVISI 1 179,750,000.00 - -

DIVISI 9. PEKERJAAN HARIAN


9.1(1) Mandor Jam 30.00 27,500.00 825,000.00 0.01 - - - - 30.00
9.1(2) Pekerja Biasa Jam 30.00 17,518.70 525,561.00 0.01 - - - - 30.00
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 30.00 22,785.71 683,571.30 0.01 - - - - 30.00
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 30.00 437,524.85 13,125,745.50 0.17 - - - - 30.00
9.1(8) Motor Gleder min.100 Pk Jam 30.00 803,949.29 24,118,478.70 0.31 - - - - 30.00
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 30.00 658,588.87 19,757,666.10 0.25 - - - - 30.00
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 30.00 751,659.30 22,549,779.00 0.29 - - - - 30.00
Jumlah Harga Pekerjaan DIVISI 2 81,585,801.60 - -

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN


Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 0.00 93,608.35 - 0.00 - - 0.00 - 0.00
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 0.00 305,243.64 - 0.00 - - 0.00 - 0.00
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 24.81 1,191,310.08 29,556,403.08 0.38 24.81 29,556,403.08 - - 0.00
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 172.46 887,894.78 153,126,333.76 1.95 - - 223.01 198,008,242.87 395.47
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 0.00 861,365.51 - 0.00 0.00 - - - 0.00
Skh-2.10.a.(10) Campuran Aspal Panas M3 155.65 3,726,125.68 579,971,462.09 7.40 49.92 186,013,395.62 - - 105.73
Skh-2.10.a.(13) Residu Bitumen Liter 957.97 22,730.84 21,775,462.79 0.28 - - 95.80 2,177,614.47 1,053.77
Skh-2.10.a.(13) Residu Bitumen* Liter 0.00 17,330.22 - 0.00 - - 924.67 16,024,688.42 924.67
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 29.60 21,646.86 640,747.06 0.01 29.60 640,747.06 - - 0.00
Skh-2.10.a.(19) Pengendalian Tanaman M2 908,160.00 612.52 556,266,163.20 7.10 - - - - 908,160.00
Skh-2.10.a.(20) Pembersihan Drainase M1 3,000.00 11,740.36 35,221,080.00 0.45 - - - - 3,000.00
1,376,557,651.99 216,210,545.76 216,210,545.76

A JUMLAH 7,835,435,423.34 100.00 876,492,866.69 876,492,866.69


B PPN 10% 783,543,542.33 87,649,286.67 87,649,286.67
C TOTAL 8,618,978,965.68 964,142,153.36 964,142,153.36
D PEMBULATAN 8,618,978,000.00 964,142,000.00 964,142,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

Mengetahui,
PT. BUMALINDO PRIMA ABADI

1. PUJI EKO AGUS PRASETYO, ST : .............................................................


Ketua

SUHARTO, SE 2. YOHANSYAH : .............................................................


DIREKTUR UTAMA Sekertaris

3. KHANIF ASHAR, ST : .............................................................


Anggota

Menyetujui,
PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )
4. Ir. ROSIHAN ANWAR : .............................................................
Anggota

RIVANIZAR, ST
Nip. 19640811 200701 1 003 5. HERY MULYANTO, ST : .............................................................
Anggota

6. AHMAD ZAIS, ST : ............................................................


Anggota

7. TOMMY IRAWAN : ............................................................


Anggota
JAAN TAMBAH KURANG
GABUNGAN BTS NEGARA – SEI ULAR, PULAU SEBATIK
POS BTS NEGARA - SEI ULAR DAN SEBATIK

BUDGED / TETAP )

CCO. No. 1
Harga Jumlah Bobot KET
Satuan Kontrak Harga %

(Rp) (Rp)

231,750,000.00 231,750,000.00 2.96 Tetap


139,450,000.00 139,450,000.00 1.78 Tetap
43,600,000.00 43,600,000.00 0.56 Tetap
126,500,000.00 126,500,000.00 1.61 Tetap
541,300,000.00

27,500.00 2,200,000.00 0.03 Tetap


17,518.70 1,401,496.00 0.02 Tetap
22,785.71 1,822,856.80 0.02 Tetap
437,524.85 35,001,988.00 0.45 Tetap
803,949.29 64,315,943.20 0.82 Tetap
658,588.87 52,687,109.60 0.67 Tetap
751,659.30 60,132,744.00 0.77 Tetap
217,562,137.60

93,608.35 50,003,393.01 0.64 Tambah


305,243.64 18,695,562.46 0.24 Tambah
271,025.42 10,510,907.84 0.13 Tambah
1,191,310.08 240,668,462.36 3.07 Kurang
887,894.78 1,635,804,068.99 20.88 Tambah
861,365.51 - 0.00 Kurang
3,726,125.68 2,351,054,889.68 30.01 Kurang
22,730.84 56,472,953.51 0.72 Tambah
17,330.22 139,189,186.31 1.78 Tambah
21,646.86 - 0.00 Kurang
612.52 854,097,888.00 10.90 Tetap
11,740.36 82,182,520.00 1.05 Tetap
5,438,679,832.16
179,750,000.00 179,750,000.00 2.29 Tetap
179,750,000.00

27,500.00 825,000.00 0.01 Tetap


17,518.70 525,561.00 0.01 Tetap
22,785.71 683,571.30 0.01 Tetap
437,524.85 13,125,745.50 0.17 Tetap
803,949.29 24,118,478.70 0.31 Tetap
658,588.87 19,757,666.10 0.25 Tetap
751,659.30 22,549,779.00 0.29 Tetap
81,585,801.60

93,608.35 - 0.00 Tambah


305,243.64 - 0.00 Tambah
1,191,310.08 - 0.00 Kurang
887,894.78 351,134,576.62 4.48 Tambah
861,365.51 - 0.00 Kurang
3,726,125.68 393,958,066.47 5.03 Kurang
22,730.84 23,953,077.27 0.31 Tambah
17,330.22 16,024,688.42 0.20 Tambah
21,646.86 - 0.00 Tambah
612.52 556,266,163.20 7.10 Tetap
11,740.36 35,221,080.00 0.45 Tetap
1,376,557,651.99

7,835,435,423.34 100.00
783,543,542.33
8,618,978,965.68
8,618,978,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

.................................................................
.................................................................

.................................................................

.................................................................

.................................................................

.................................................................

.................................................................
LAMPIRAN DAFTAR NEGOSIASI HARGA
( BALANCE BUDGED / TETAP )
PPK PELAKSANAAN JALAN (PPK 1.4) SP.3 POS GABUNGAN BTS NEGARA – SEI ULAR, PULAU SEBATIK
PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK

VOLUME HARGA SATUAN (Rp)


HASIL NEGOSIASI

SAT.
No.MATA PEMB. URAIAN PEKERJAAN KET
KONTRAK AWAL VOLUME TAMBAH CCO 01 BOBOT % PENAWARAN OE
(Rp)

LINGKAR PULAU SEBATIK


DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 - 1.00 - 231,750,000.00 216,740,000.00 231,750,000.00 TETAP
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 - 1.00 - 139,450,000.00 110,430,000.00 139,450,000.00 TETAP
1.17 Pengamanan Lingkungan Hidup LS 1.00 - 1.00 - 43,600,000.00 40,080,000.00 43,600,000.00 TETAP
1.21 Manajemen Mutu LS 1.00 - 1.00 - 126,500,000.00 172,700,000.00 126,500,000.00 TETAP
Jumlah Harga Pekerjaan DIVISI 1

DIVISI 9. PEKERJAAN HARIAN


9.1(1) Mandor Jam 80.00 - 80.00 - 27,500.00 26,262.81 27,500.00 TETAP
9.1(2) Pekerja Biasa Jam 80.00 - 80.00 - 17,518.70 17,227.10 17,518.70 TETAP
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 80.00 - 80.00 - 22,785.71 20,052.81 22,785.71 TETAP
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 80.00 - 80.00 - 437,524.85 602,767.64 437,524.85 TETAP
9.1(8) Motor Gleder min.100 Pk Jam 80.00 - 80.00 - 803,949.29 1,067,584.95 803,949.29 TETAP
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 80.00 - 80.00 - 658,588.87 602,138.90 658,588.87 TETAP
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 80.00 - 80.00 - 751,659.30 796,256.20 751,659.30 TETAP
Jumlah Harga Pekerjaan DIVISI 2

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN


Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 489.39 44.79 534.18 9.15 93,608.35 82,603.71 93,608.35 TETAP
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 55.68 5.57 61.25 10.00 305,243.64 271,025.42 305,243.64 TETAP
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran* M3 38.78 38.78 30.35 271,025.42 271,025.42 271,025.42 NEGO
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 240.17 - 202.02 15.88 1,191,310.08 1,437,510.91 1,191,310.08 TETAP
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 1,279.71 562.63 1,842.34 43.97 887,894.78 964,050.12 887,894.78 TETAP
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 69.65 - - 100.00 861,365.51 947,475.24 861,365.51 TETAP
Skh-2.10.a.(10) Campuran Aspal Panas M3 778.78 - 630.97 18.98 3,726,125.68 4,290,241.38 3,726,125.68 TETAP
Skh-2.10.a.(13) Residu Bitumen Liter 2,258.56 225.86 2,484.42 10.00 22,730.84 17,330.22 22,730.84 TETAP
Skh-2.10.a.(13) Residu Bitumen* Liter - 8,031.59 8,031.59 255.61 17,330.22 17,330.22 17,330.22 NEGO
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 187.67 - - 100.00 21,646.86 20,933.33 21,646.86 TETAP
Skh-2.10.a.(19) Pengendalian Tanaman M2 1,394,400.00 - 1,394,400.00 - 612.52 861.21 612.52 TETAP
Skh-2.10.a.(20) Pembersihan Drainase M1 7,000.00 - 7,000.00 - 11,740.36 3,627.11 11,740.36 TETAP

SEI ULAR
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 - 1.00 - 179,750,000.00 128,660,000.00 179,750,000.00 TETAP
Jumlah Harga Pekerjaan DIVISI 1

DIVISI 9. PEKERJAAN HARIAN


9.1(1) Mandor Jam 30.00 - 30.00 - 27,500.00 26,262.81 27,500.00 TETAP
9.1(2) Pekerja Biasa Jam 30.00 - 30.00 - 17,518.70 17,227.10 17,518.70 TETAP
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 30.00 - 30.00 - 22,785.71 20,052.81 22,785.71 TETAP
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 30.00 - 30.00 - 437,524.85 602,767.64 437,524.85 TETAP
9.1(8) Motor Gleder min.100 Pk Jam 30.00 - 30.00 - 803,949.29 1,067,584.95 803,949.29 TETAP
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 30.00 - 30.00 - 658,588.87 602,138.90 658,588.87 TETAP
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 30.00 - 30.00 - 751,659.30 796,256.20 751,659.30 TETAP

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN


Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 - - - - 93,608.35 82,603.71 93,608.35 TETAP
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 - - - - 305,243.64 271,025.42 305,243.64 TETAP
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 24.81 - - 100.00 1,191,310.08 1,437,510.91 1,191,310.08 TETAP
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 172.46 223.01 395.47 129.31 887,894.78 964,050.12 887,894.78 TETAP
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 - - - - 861,365.51 947,475.24 861,365.51 TETAP
Skh-2.10.a.(10) Campuran Aspal Panas M3 155.65 - 105.73 32.07 3,726,125.68 4,290,241.38 3,726,125.68 TETAP
Skh-2.10.a.(13) Residu Bitumen Liter 957.97 95.80 1,053.77 10.00 22,730.84 17,330.22 22,730.84 TETAP
Skh-2.10.a.(13) Residu Bitumen* Liter - 924.67 924.67 3.48 17,330.22 17,330.22 17,330.22 NEGO
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 29.60 - - 100.00 21,646.86 20,933.33 21,646.86 TETAP
Skh-2.10.a.(19) Pengendalian Tanaman M2 908,160.00 - 908,160.00 - 612.52 861.21 612.52 TETAP
Skh-2.10.a.(20) Pembersihan Drainase M1 3,000.00 - 3,000.00 - 11,740.36 3,627.11 11,740.36 TETAP

PANITIA PENELITI PELAKSANAAN KONTRAK

1. PUJI EKO AGUS PRASETYO, ST : ................................................


Ketua
Mengetahui,
PT. BUMALINDO PRIMA ABADI

2. YOHANSYAH : ................................................
Sekertaris

SUHARTO, SE 3. KHANIF ASHAR, ST : ................................................


DIREKTUR UTAMA Anggota

4. Ir. ROSIHAN ANWAR : ................................................


Anggota

Menyetujui,
PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )
5. HERY MULYANTO, ST : ................................................
Anggota

RIVANIZAR, ST
Nip. 19640811 200701 1 003 6. AHMAD ZAIS, ST : ................................................
Anggota

7. TOMMY IRAWAN : ................................................


Anggota
DAFTAR PEKERJAAN TA
LAMPIRAN BERI
NOMOR : 02/PPPK/26-3

SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA


KEGIATAN : PPK SP.3 POS GABUNGAN BTS. NEGARA - SEI ULAR, PULAU SEBATIK ( PPK 1.4 )
PAKET : REHABILITASI JALAN SP.3 POS BTS. NEGARA - SEI ULAR DAN LINGKAR PULAU SEBATIK ( LONGSORAN )
NOMOR KONTRAK : 05-35/APBN/PJNAS.I-KALTARA/2017
TANGGAL KONTRAK : 10 JANUARI 2017
SUMBER DANA : APBN

NO. MATA HARGA KONTRAK HARGA PERKIRAAN BOBOT


URAIAN PEKERJAAN SATUAN
PEMBAYARAN AWAL SENDIRI %

1 2 3 4 5

LINGKAR PULAU SEBATIK

DIVISI 1. UMUM

1.2 Mobilisasi LS 231,750,000.00 216,740,000.00 106.93

1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 139,450,000.00 110,430,000.00 126.28

1.17 Pengamanan Lingkungan Hidup LS 43,600,000.00 40,080,000.00 108.78

1.21 Manajemen Mutu LS 126,500,000.00 172,700,000.00 73.25

DIVISI 9. PEKERJAAN HARIAN

9.1(1) Mandor Jam 27,500.00 26,262.81 104.71

9.1(2) Pekerja Biasa Jam 17,518.70 17,227.10 101.69

9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 20,052.81 113.63

9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 602,767.64 72.59

9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 1,067,584.95 75.31

9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 602,138.90 109.37

9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 796,256.20 94.40

Jumlah Harga Pekerjaan DIVISI 2

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN

Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 93,608.35 82,603.71 113.32

Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 305,243.64 271,025.42 112.63

Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran* M3 271,025.42


Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 1,437,510.91 82.87

Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 964,050.12 92.10

Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 947,475.24 90.91

Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 4,290,241.38 86.85

Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 17,330.22 131.16

Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 0.00

Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 20,933.33 103.41

Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 861.21 71.12

Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 3,627.11 323.68

SEI ULAR

DIVISI 1. UMUM

1.2 Mobilisasi Ls 179,750,000.00 128,660,000.00 139.71


Jumlah Harga Pekerjaan DIVISI 1

DIVISI 9. PEKERJAAN HARIAN

9.1(1) Mandor Jam 27,500.00 26,262.81 104.71

9.1(2) Pekerja Biasa Jam 17,518.70 17,227.10 101.69

9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 20,052.81 113.63

9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 602,767.64 72.59

9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 1,067,584.95 75.31

9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 602,138.90 109.37

9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 796,256.20 94.40

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN

Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Lereng M3 93,608.35 82,603.71 113.32

Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Saluran M3 305,243.64 271,025.42 112.63

Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 1,437,510.91 82.87

Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 964,050.12 92.10

Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 947,475.24 90.91

Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 4,290,241.38 86.85

Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 17,330.22 131.16

Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 0.00

Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 20,933.33 103.41

Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 861.21 71.12

Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 3,627.11 323.68

*) diisi 'Ya' atau 'Tidak"

Mengetahui,
PT. BUMALINDO PRIMA ABADI 1.

2.

SUHARTO, SE
DIREKTUR UTAMA

3.

Menyetujui, 4.
PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

5.
RIVANIZAR, ST
Nip. 19640811 200701 1 003

6.

7.
AAN TAMBAH/KURANG (BALANCE BUDGET)
AN BERITA ACARA NEGOSIASI HARGA
PK/26-35/APBN/KALTARA/LONGSORAN/02.17

TAHUN ANGGARAN
NILAI KONTRAK AWAL
NILAI CCO. 01 TETAP
KONTRAKTOR
KONSULTAN

PEKERJAAN TAMBAH PEKERJAAN KURANG KETERANGAN

VOLUME VOLUME
VOLUME BOBOT VOLUME BOBOT > 10 %
AWAL USULAN CCO HARGA
TIMPANG
Sebatik

6 8 10 12 14 16 18 19

1.00 - - - - ### 1.00 Tidak Tidak

1.00 - - - - ### 1.00 Tidak Tidak

1.00 - - - - ### 1.00 Tidak Tidak

1.00 - - - - ### 1.00 Tidak Tidak

80.00 - - - - - Tidak Tidak

80.00 - - - - 80.00 Tidak Tidak

80.00 - - - - 80.00 Tidak Tidak

80.00 - - - - 80.00 Tidak Tidak

80.00 - - - - 80.00 Tidak Tidak

80.00 - - - - 80.00 Tidak Tidak

80.00 - - - - 80.00 Tidak Tidak

489.39 44.79 9.15 - - 534.18 Tidak Tidak

55.68 5.57 10.00 - - 61.25 Ya Ya

38.78 69.65 - - 38.78 Tidak Ya

240.17 - - 38.15 15.88 202.02 Tidak Tidak

1,279.71 562.63 43.97 - - 1,842.34 Tidak Tidak

69.65 - - 69.65 100.00 - Tidak Tidak

778.78 - - 147.82 18.98 630.97 Tidak Tidak

2,258.56 225.86 10.00 - - 2,484.42 Ya Ya

- 8,031.59 355.61 - - 8,031.59 Tidak Ya

187.67 - - 187.67 100.00 - Tidak Tidak

1,394,400.00 - - - - 1,394,400.00 Tidak Tidak

7,000.00 - - - - 7,000.00 Tidak Tidak

1.00 - - - - 1.00 Tidak Tidak


30.00 - - - - 30.00 Tidak Tidak

30.00 - - - - 30.00 Tidak Tidak

30.00 - - - - 30.00 Tidak Tidak

30.00 - - - - 30.00 Tidak Tidak

30.00 - - - - 30.00 Tidak Tidak

30.00 - - - - 30.00 Tidak Tidak

30.00 - - - - 30.00 Tidak Tidak

- - - - - - Tidak Tidak

- - - - - - Tidak Tidak

24.81 - - 24.81 100.00 - Tidak Tidak

172.46 223.01 129.31 - - 395.47 Tidak Tidak

- - - - - - Tidak Tidak

155.65 - - 49.92 32.07 105.73 Tidak Tidak

957.97 95.80 10.00 - - 1,053.77 Ya Ya

- 924.67 96.52 - - 924.67 Tidak Ya

29.60 - - 29.60 100.00 - Tidak Tidak

908,160.00 - - - - 908,160.00 Tidak Tidak

3,000.00 - - - - 3,000.00 Tidak Tidak

PANITIA PENELITI PELAKSANAAN KONTRAK

PUJI EKO AGUS PRASETYO, ST : ................................................


Ketua

YOHANSYAH : ................................................
Sekertaris

KHANIF ASHAR, ST : ................................................


Anggota

Ir. ROSIHAN ANWAR : ................................................


Anggota

HERY MULYANTO, ST : ................................................


Anggota

AHMAD ZAIS, ST : ................................................


Anggota

TOMMY IRAWAN : ................................................


Anggota
KETERANGAN

NEGOSIASI
ITEM
BARU
Sebatik
21 22

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Ya

- Ya

- Tidak

- Tidak

- Tidak

- Tidak

- Ya

- Ya

- Tidak

- Tidak

- Tidak

- Tidak
- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Tidak

- Ya

- Ya

- Tidak

- Tidak

- Tidak
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK DAN SEI ULAR

PRESERVASI RUTIN JALAN SP. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
RUAS JALAN LINGKAR PULAU SEBATIK
DIVISI 1. UMUM
1.2 Mobilisasi Ls 231,750,000.00 1.00 231,750,000.00 2.96 - - - -
1.8.(1) Manajemen dan Keselamatan Lalu Lint Ls 139,450,000.00 1.00 139,450,000.00 1.78 - - - -
1.17 Pengamanan Lingkungan Hidup Ls 43,600,000.00 1.00 43,600,000.00 0.56 - - - -
1.21 Manajemen Mutu Ls 126,500,000.00 1.00 126,500,000.00 1.61 - - - -
541,300,000.00 6.91 - -
DIVISI 9. PEKERJAAN HARIAN
9.1(1) Mandor Jam 27,500.00 80.00 2,200,000.00 0.03 - - - -
9.1(2) Pekerja Biasa Jam 17,518.70 80.00 1,401,496.00 0.02 - - - -
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 80.00 1,822,856.80 0.02 - - - -
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 80.00 35,001,988.00 0.45 - - - -
9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 80.00 64,315,943.20 0.82 - - - -
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 80.00 52,687,109.60 0.67 - - - -
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 80.00 60,132,744.00 0.77 - - - -
217,562,137.60 2.78 - -
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 489.39 45,810,990.41 0.58 44.79 4,192,402.60 -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 55.68 16,995,965.88 0.22 5.57 1,699,596.59 -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M4 271,025.42 38.78 10,510,907.84
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 240.17 286,116,941.91 3.65 - 38.15 45,448,479.55
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 1,279.71 1,136,247,828.91 14.50 562.63 499,556,240.07 -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 69.65 59,994,107.77 0.77 - 69.65 59,994,107.77
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 778.78 2,901,832,157.07 37.03 - 147.82 550,777,267.39
PRESERVASI RUTIN JALAN SP. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 2,258.56 51,338,965.99 0.66 225.86 5,133,987.52 -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 8,031.59 139,189,186.31
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 187.67 4,062,466.22 0.05 - 187.67 4,062,466.22
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 1,394,400.00 854,097,888.00 10.90 - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 7,000.00 82,182,520.00 1.05 - - - -
5,438,679,832.16 69.41 660,282,320.93 660,282,320.93
RUAS JALAN SP. 3 BTS NEGARA - SEI. ULAR
DIVISI 1. UMUM
1.2 Mobilisasi Ls 179,750,000.00 1.00 179,750,000.00 2.29 - - - -
179,750,000.00 2.29
DIVISI 9. PEKERJAAN HARIAN
9.1(1) Mandor Jam 27,500.00 30.00 825,000.00 0.01 - - - -
9.1(2) Pekerja Biasa Jam 17,518.70 30.00 525,561.00 0.01 - - - -
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 30.00 683,571.30 0.01 - - - -
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 30.00 13,125,745.50 0.17 - - - -
9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 30.00 24,118,478.70 0.31 - - - -
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 30.00 19,757,666.10 0.25 - - - -
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 30.00 22,549,779.00 0.29 - - - -
81,585,801.60 1.04
PRESERVASI RUTIN JALAN SP. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 - - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 - - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 24.81 29,556,403.08 0.38 - 24.81 29,556,403.08
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 172.46 153,126,333.76 1.95 223.01 198,008,242.87 -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 155.65 579,971,462.09 7.40 - 49.92 186,013,395.62
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 957.97 21,775,462.79 0.28 95.80 2,177,614.47 -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 924.67 16,024,688.42
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 29.60 640,747.06 0.01 - 29.60 640,747.06
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 908,160.00 556,266,163.20 7.10 - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 3,000.00 35,221,080.00 0.45 - - - -
1,376,557,651.99 17.57 216,210,545.76 216,210,545.76

A Jumlah Harga 7,835,435,423.34 100.00 876,492,866.69 876,492,866.69


B PPN = (10% X A) 783,543,542.33 87,649,286.67 87,649,286.67
C Jumlah Harga + PPN = (A + B) 8,618,978,965.68 964,142,153.36 964,142,153.36
D Pembulatan 8,618,978,000.00 964,142,000.00 964,142,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

1. PUJI EKO AGUS PRASETYO, ST : ................................................................. Me


Ketua PT. BUMALI

2. YOHANSYAH : .................................................................
Sekertaris SUH
DIREK
PRESERVASI RUTIN JALAN SP. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
3. KHANIF ASHAR, ST : .................................................................
Anggota

4. Ir. ROSIHAN ANWAR : .................................................................


Anggota M
PEJABAT PEMBUA

5. HERY MULYANTO, ST : .................................................................


Anggota
RIVA
Nip. 19640

6. AHMAD ZAIS, ST : .................................................................


Anggota

7. TOMMY IRAWAN : .................................................................


Anggota
AMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

P. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK


DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
BOBOT (%)
KUANTITAS JUMLAH HARGA (Rp)
(%)

1.00 231,750,000.00 2.96 - TETAP


1.00 139,450,000.00 1.78 - TETAP
1.00 43,600,000.00 0.56 - TETAP
1.00 126,500,000.00 1.61 - TETAP
541,300,000.00 6.91

80.00 2,200,000.00 0.03 - TETAP


80.00 1,401,496.00 0.02 - TETAP
80.00 1,822,856.80 0.02 - TETAP
80.00 35,001,988.00 0.45 - TETAP
80.00 64,315,943.20 0.82 - TETAP
80.00 52,687,109.60 0.67 - TETAP
80.00 60,132,744.00 0.77 - TETAP
217,562,137.60 2.78

534.18 50,003,393.01 0.64 9.15 BERTAMBAH


61.25 18,695,562.46 0.24 10.00 BERTAMBAH
38.78 10,510,907.84 0.13 30.35 BERTAMBAH
202.02 240,668,462.36 3.07 15.88 BERKURANG
1,842.34 1,635,804,068.99 20.88 43.97 BERTAMBAH
- - - 100.00 BERKURANG
630.97 2,351,054,889.68 30.01 18.98 BERKURANG
P. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
BOBOT (%)
KUANTITAS JUMLAH HARGA (Rp)
(%)
2,484.42 56,472,953.51 0.72 10.00 BERTAMBAH
8,031.59 139,189,186.31 1.78 255.61 BERTAMBAH
- - - 100.00 BERKURANG
1,394,400.00 854,097,888.00 10.90 - TETAP
7,000.00 82,182,520.00 1.05 - TETAP
5,438,679,832.16 69.41

1.00 179,750,000.00 2.29 - TETAP


179,750,000.00 2.29

30.00 825,000.00 0.01 - TETAP


30.00 525,561.00 0.01 - TETAP
30.00 683,571.30 0.01 - TETAP
30.00 13,125,745.50 0.17 - TETAP
30.00 24,118,478.70 0.31 - TETAP
30.00 19,757,666.10 0.25 - TETAP
30.00 22,549,779.00 0.29 - TETAP
81,585,801.60 1.04
P. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
BOBOT (%)
KUANTITAS JUMLAH HARGA (Rp)
(%)

- - - TETAP
- - - TETAP
- - - 100.00 BERKURANG
395.47 351,134,576.62 4.48 129.31 BERTAMBAH
- - - TETAP
105.73 393,958,066.47 5.03 32.07 BERKURANG
1,053.77 23,953,077.27 0.31 10.00 BERTAMBAH
924.67 16,024,688.42 0.20 3.48 BERTAMBAH
- - - 100.00 BERKURANG
908,160.00 556,266,163.20 7.10 - TETAP
3,000.00 35,221,080.00 0.45 - TETAP
1,376,557,651.99 17.57 20.90

7,835,435,423.34 100.00
783,543,542.33
8,618,978,965.68
8,618,978,000.00

2,745,012,956.15

Mengetahui,
PT. BUMALINDO PRIMA ABADI

SUHARTO, SE
DIREKTUR UTAMA
P. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK
DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
BOBOT (%)
KUANTITAS JUMLAH HARGA (Rp)
(%)

Menyetujui,
PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

RIVANIZAR, ST
Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : PRESERVASI RUTIN JALAN SP.3 POS BTS NEGARA - SEI ULAR DAN SEBATIK
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : JALAN LINGKAR PULAU SEBATIK

PRESERVASI RUTIN JALAN SP. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK ( KOMULATIF S
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURAN
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT
SATUAN KUANTITAS KUANTITAS JUMLAH HARGA (Rp) KUANTITAS
(Rp) (Rp) (%)
RUAS JALAN LINGKAR PULAU SEBATIK
DIVISI 1. UMUM
1.2 Mobilisasi Ls 231,750,000.00 1.00 231,750,000.00 3.74
1.8.(1) Manajemen dan Keselamatan Lalu Lint Ls 139,450,000.00 1.00 139,450,000.00 2.25
1.17 Pengamanan Lingkungan Hidup Ls 43,600,000.00 1.00 43,600,000.00 0.70
1.21 Manajemen Mutu Ls 126,500,000.00 1.00 126,500,000.00 2.04
541,300,000.00 8.73
DIVISI 9. PEKERJAAN HARIAN
9.1(1) Mandor Jam 27,500.00 80.00 2,200,000.00 0.04
9.1(2) Pekerja Biasa Jam 17,518.70 80.00 1,401,496.00 0.02
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 80.00 1,822,856.80 0.03
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 80.00 35,001,988.00 0.56
9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 80.00 64,315,943.20 1.04
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 80.00 52,687,109.60 0.85
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 80.00 60,132,744.00 0.97
217,562,137.60 3.51
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 489.39 45,810,990.41 0.74 44.79 4,192,402.60 -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 55.68 16,995,965.88 0.27 5.57 1,699,596.59 -
Skh-2.10.a.(2)* Timbunan Pilihan Untuk Lereng Tepi Sa M3 271,025.42 38.78 10,510,907.84
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 240.17 286,116,941.91 4.62 - - 38.15
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 1,279.71 1,136,247,828.91 18.33 562.63 499,556,240.07 -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 69.65 59,994,107.77 0.97 - - 69.65
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 778.78 2,901,832,157.07 46.82 - - 147.82
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 2,258.56 51,338,965.99 0.83 225.86 5,133,987.52 -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 8,031.59 139,189,186.31
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 187.67 4,062,466.22 0.07 - - 187.67
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 1,394,400.00 854,097,888.00 13.78 - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 7,000.00 82,182,520.00 1.33 - - -
5,438,679,832.16 87.76

A Jumlah Harga 6,197,541,969.76 100.00 660,282,320.93


B PPN = (10% X A) 619,754,196.98 66,028,232.09
C Jumlah Harga + PPN = (A + B) 6,817,296,166.73 726,310,553.02
D Pembulatan 6,817,296,000.00 726,310,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

1. ..............................................................................
PUJI EKO AGUS PRASETYO, ST : 5. HERY MULYANTO, ..............................................................................
ST :
Ketua Anggota

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota

3. KHANIF ASHAR, ST ..............................................................................


: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
N TAMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

S BTS NEGARA - SEI. ULAR DAN SEBATIK ( KOMULATIF SEBATIK )


PEKERJAAN KURANG (-) DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
JUMLAH HARGA BOBOT (%)
JUMLAH HARGA (Rp) KUANTITAS
(Rp) (%)

1.00 231,750,000.00 3.74 - TETAP


1.00 139,450,000.00 2.25 - TETAP
1.00 43,600,000.00 0.70 - TETAP
1.00 126,500,000.00 2.04 - TETAP
541,300,000.00

80.00 2,200,000.00 0.04 - TETAP


80.00 1,401,496.00 0.02 - TETAP
80.00 1,822,856.80 0.03 - TETAP
80.00 35,001,988.00 0.56 - TETAP
80.00 64,315,943.20 1.04 - TETAP
80.00 52,687,109.60 0.85 - TETAP
80.00 60,132,744.00 0.97 - TETAP
217,562,137.60

- 534.18 50,003,393.01 0.81 9.15 BERTAMBAH


- 61.25 18,695,562.46 0.30 10.00 BERTAMBAH
38.78 10,510,907.84 0.17 30.35 BERTAMBAH
45,448,479.55 202.02 240,668,462.36 3.88 15.88 BERKURANG
- 1,842.34 1,635,804,068.99 26.39 43.97 BERTAMBAH
59,994,107.77 - - - 100.00 BERKURANG
550,777,267.39 630.97 2,351,054,889.68 37.94 18.98 BERKURANG
- 2,484.42 56,472,953.51 0.91 10.00 BERTAMBAH
8,031.59 139,189,186.31 2.25 255.61 BERTAMBAH
4,062,466.22 - - - 100.00 BERKURANG
- 1,394,400.00 854,097,888.00 13.78 - TETAP
- 7,000.00 82,182,520.00 1.33 - TETAP
5,438,679,832.16

660,282,320.93 6,197,541,969.76 100.00


66,028,232.09 619,754,196.98
726,310,553.02 6,817,296,166.73
726,310,000.00 6,817,296,000.00

Mengetahui, Menyetujui,
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003
DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI KALIMANTAN UTARA
NAMA PAKET : DAFTAR PEKERJAAN TAMBAH/KURANG (BALANCE BUDGET)
NO. KONTRAK : 06-35/APBN/PJNAS.I-KALTARA/2018

NILAI KONTRAK : Rp8,618,978,000.00


TANGGAL KONTRAK : 27FEBRUARI 2018
SUMBER DANA : APBN - MURNI
PROVINSI : KALIMANTAN UTARA
RUAS JALAN : RUAS SEI ULAR

PRESERVASI RUTIN JALAN SP. 3 POS BTS NEGARA - SEI. ULAR DAN SEBATIK ( KOMULATIF SEI. ULAR )
KONTRAK AWAL PEKERJAAN TAMBAH (+) PEKERJAAN KURANG (-)
NO.ITEM.
URAIAN PEKERJAAN
PEMB HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA JUMLAH HARGA
SATUAN KUANTITAS KUANTITAS KUANTITAS
(Rp) (Rp) (%) (Rp) (Rp)
RUAS JALAN SP. 3 BTS NEGARA - SEI. ULAR
DIVISI 1. UMUM
1.2 Mobilisasi Ls 179,750,000.00 1.00 179,750,000.00 10.97
179,750,000.00 10.97
DIVISI 9. PEKERJAAN HARIAN
9.1(1) Mandor Jam 27,500.00 30.00 825,000.00 0.05
9.1(2) Pekerja Biasa Jam 17,518.70 30.00 525,561.00 0.03
9.1(3) Tukang Kayu,Tukang Batu,dsb Jam 22,785.71 30.00 683,571.30 0.04
9.1(4)a Dump Truk,Kapasitas 3-4 M3 Jam 437,524.85 30.00 13,125,745.50 0.80
9.1(8) Motor Gleder min.100 Pk Jam 803,949.29 30.00 24,118,478.70 1.47
9.1(9) Loder Roda Karet 1.0-1.6 M3 Jam 658,588.87 30.00 19,757,666.10 1.21
9.1(11) Alat Penggali (Excavator)80-140 Pk Jam 751,659.30 30.00 22,549,779.00 1.38
81,585,801.60 4.98
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
Skh-2.10.a.(1) Galian Tanah Untuk Saluran Air Dan Le M3 93,608.35 - - - - -
Skh-2.10.a.(2) Timbunan Pilihan Untuk Lereng Tepi Sa M3 305,243.64 - - - - - - -
Skh-2.10.a.(3) Pasangan Batu dengan Mortar M3 1,191,310.08 24.81 29,556,403.08 1.80 - 24.81 29,556,403.08
Skh-2.10.a.(4) Lapis Pondasi Agregat Kelas A M3 887,894.78 172.46 153,126,333.76 9.35 223.01 198,008,242.87 - -
Skh-2.10.a.(5) Lapis Pondasi Agregat Klas B M3 861,365.51 - - - - - - -
Skh-2.10.a.(10) Campuran Aspal Panas M3 3,726,125.68 155.65 579,971,462.09 35.41 - - 49.92 186,013,395.62
Skh-2.10.a.(13) Residu Bitumen Liter 22,730.84 957.97 21,775,462.79 1.33 95.80 2,177,614.47 - -
Skh-2.10.a.(13) Residu Bitumen* Liter 17,330.22 924.67 16,024,688.42
Skh-2.10.a.(17) Bahan Penutup (sealint) Kg 21,646.86 29.60 640,747.06 0.04 - - 29.60 640,747.06
Skh-2.10.a.(19) Pengendalian Tanaman M2 612.52 908,160.00 556,266,163.20 33.96 - - - -
Skh-2.10.a.(20) Pembersihan Drainase M1 11,740.36 3,000.00 35,221,080.00 2.15 - - - -
1,376,557,651.99 84.04 216,210,545.76 216,210,545.76

A Jumlah Harga 1,637,893,453.59 100.00 216,210,545.76 216,210,545.76


B PPN = (10% X A) 163,789,345.36 21,621,054.58 21,621,054.58
C Jumlah Harga + PPN = (A + B) 1,801,682,798.95 237,831,600.34 237,831,600.34
D Pembulatan 1,801,682,000.00 237,831,000.00 237,831,000.00

PANITIA PENELITI PELAKSANAAN KONTRAK

1. ..............................................................................
PUJI EKO AGUS PRASETYO, ST : ..............................................................................
5. HERY MULYANTO, ST : Mengetahui,
Ketua Anggota PT. BUMALINDO PRIMA A

2. YOHANSYAH ..............................................................................
: 6. AHMAD ZAIS, ST ..............................................................................
:
Sekertaris Anggota
SUHARTO, SE
DIREKTUR UTAMA
3. KHANIF ASHAR, ST ..............................................................................
: 7. TOMMY IRAWAN ..............................................................................
:
Anggota Anggota

4. Ir. ROSIHAN ANWAR ..............................................................................


:
Anggota
AMBAH/KURANG (BALANCE BUDGET)
KONTRAKTOR PELAKSANA : PT. BUMALINDO PRIMA ABADI
KONSULTAN SUPERVISI : PT. WAHANA MITRA AMERTA. JO

NEGARA - SEI. ULAR DAN SEBATIK ( KOMULATIF SEI. ULAR )


DRAFT ADDENDUM 01 SELISIH
BOBOT KETERANGAN
BOBOT (%)
KUANTITAS JUMLAH HARGA (Rp)
(%)

1.00 179,750,000.00 10.97 - TETAP


179,750,000.00 10.97

30.00 825,000.00 0.05 - TETAP


30.00 525,561.00 0.03 - TETAP
30.00 683,571.30 0.04 - TETAP
30.00 13,125,745.50 0.80 - TETAP
30.00 24,118,478.70 1.47 - TETAP
30.00 19,757,666.10 1.21 - TETAP
30.00 22,549,779.00 1.38 - TETAP
81,585,801.60 4.98

- - - 100.00 TETAP
- - - TETAP
- - - 100.00 BERKURANG
395.47 351,134,576.62 21.44 129.31 BERTAMBAH
- - - TETAP
105.73 393,958,066.47 24.05 32.07 BERKURANG
1,053.77 23,953,077.27 1.46 10.00 BERTAMBAH
924.67 16,024,688.42 0.98 3.48 BERTAMBAH
- - - 100.00 BERKURANG
908,160.00 556,266,163.20 33.96 - TETAP
3,000.00 35,221,080.00 2.15 - TETAP
1,376,557,651.99 84.04

1,637,893,453.59 100.00
163,789,345.36
1,801,682,798.95
1,801,682,000.00

Mengetahui, Menyetujui,
PT. BUMALINDO PRIMA ABADI PEJABAT PEMBUAT KOMITMEN ( PPK 1.4 )

SUHARTO, SE RIVANIZAR, ST
DIREKTUR UTAMA Nip. 19640811 200701 1 003