Académique Documents
Professionnel Documents
Culture Documents
0-5151-20 S-900-1670-501 1
FOR CONSTRUCTION
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 2 OF 62
ERECTION
CONTENTS
1 SCOPE ............................................................................................................................................. 3
2 DEFINITION...................................................................................................................................... 3
5 RESPONSIBILITIES ......................................................................................................................... 3
9 REPORT FORM................................................................................................................................ 5
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 3 OF 62
ERECTION
1 SCOPE
This specification describes the scope of test and inspection and the report format for static
equipment erection except for site fabricated tank and furnace of DSLNG Project at site.
In case Inspection and Test Plan (ITP) have been already issued by SUBCONTRACTOR, the
SUBCONTRACTOR’s ITP shall be superseded by this specification.
2 DEFINITION
The following terminologies are used in this specification.
3 REFERENCE DOCUMENT
Contractor Doc. No. Document Title
S-900-1161-001 Construction Execution Plan
4 ACCEPTANCE CRITERIA
Acceptance criteria shall be in accordance with the project specifications, drawing and instructions.
If the results of the inspection are unacceptable, changes or repairs shall be made and the
work/materials shall be re-inspected.
5 RESPONSIBILITIES
CONTRACTOR and SUBCONTRACTOR will perform quality control with CONTRACTOR’s ITP,
by means of check, tests and inspections, at scheduled or required stage of construction in
accordance with CONTRACTOR’s construction specifications, drawings and instructions.
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 4 OF 62
ERECTION
7 OTHER REQUIREMENTS
I : Execution of inspection
F : Full, ex, “FW” means “Full Witness”, “FI” means “Full Inspection”
S : Spot, ex, ”SW” means “Spot Witness”, “SI” means “Spot Inspection” including
100% review of inspection report
H : Hold point
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 5 OF 62
ERECTION
OR : Official Record
IR : Internal Record
9 REPORT FORM
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 6 OF 62
ERECTION
5000-313 : Inspection Report for Equipment Internal (Installation Checklist for Random
Packing)
5000-314 : Inspection Report for Equipment Internal (Distribution Levelness and Feed Hole
Direction)
5000-315 : Inspection Report for Equipment Internal (Installation Checklist for Structured
Packing)
5000-316 : Inspection Report for Equipment Internal (Levelness of Structured Packing
Support Rings)
5000-317 : Inspection Report for Equipment Internal (Orientation of Structured Packing)
5000-001 : Inspection Report for Equipment Nozzle Flange Face
5000-001B : Inspection Report for Equipment and Piping Flange Face, Gasket and Bolt / Nut
5000-511 : Inspection Report for Flange Bolt Tightening
5000-319 : Internal Installation Checklist for Mesh and Ceramic Ball
5000-320 : Inspection Report for Name Plate
5000-321 : Inspection Report for Anodes installation for Heat Exchanger
5000-322 : Inspection Report for PMI
5000-323 : Inspection Report for Davit installation
5000-324 : Inspection Report for Bed Support Installation
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 7 OF 62
WITNESS BY
CONTRACTOR
SUBCONT’R
OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
1.1 Padding
(1) Material A283, A36 or Material Certificate Check before 5000-102 FI/P SW IW
(Liners) equivalent erection
5000-104
5000-106
5000-302
5000-304
5000-402
(2) Interval Max. spacing 800 mm
(3) Loading Max. 30 kg/cm²
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 8 OF 62
WITNESS BY
CONTRACTOR
SUBCONT’R
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
OWNER
1.2 Verticality / Section 7.2 ±6mm/10m, not exceed 5000-101 FI/P FW FW
Horizontally 12mm/20m and over
5000-103
5000-105
5000-301
5000-303
5000-305
5000-307
5000-401
1.3 Position / Direction Section 7.1 Set to within ± 3mm of grid line After setting 5000-101 FI/P FW SW Nozzle Orientation
5000-103
5000-105
5000-301
5000-303
5000-305
5000-307
5000-401
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 9 OF 62
WITNESS BY
CONTRACTOR
SUBCONT’R
OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
1.4 Elevation Section 7.3 Within ± 1mm / 1m After setting 5000-101 FI/P FW SW
5000-103
5000-105
5000-301
5000-303
5000-305
5000-307
5000-401
1.5 Anchor Bolts ANSI A10.13 Snug tight, fully tightened by After setting 5000-102 FI/P FW SW
Section 9.6 using ordinary spud wrench
5000-104
5000-106
5000-302
5000-304
5000-306
5000-401
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 10 OF 62
WITNESS BY
’R
CONTRACT
SUBCONT
OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
OR
1.7 Platform and Ladders As per drawing 5000-999 FI/P FW FW
1.11 Field Hydrostatic Test If required Comply with requirements 5000-311 FI/P H H MIGAS Witness Required
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 11 OF 62
WITNESS BY
’R
CONTRACT
SUBCONT
OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
OR
1.13 Box Up
(2) Final closure inspection Manhole bolt, nut and gasket 5000-312
Equipment Nozzle Face check
/ MH Face Gasket, Bolt 5000-001 FI/P H FW
and Nut B
(3) Bolt Tightening Final Manhole bolt, nut and gasket 5000-312
closure inspection after check (Bolt tensioning work, if
final manway closure applicable) 5000-511 FI/P H H
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 12 OF 62
WITNESS BY
CONTRACTOR
SUBCONT’R
OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
2. INTERNAL Drawings
INSTALLATION
2.1 Distributor Pipe 5000-201
(1) Assembly As per drawing After setting FI/P FW FW
(2) Bolt Tightness After setting FI/P FW FW
(3) Gasket As per drawing After setting FI/P FW FW
2.2 Demister 5000-201
(1) Assembly After setting FI/P FW FW
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 13 OF 62
WITNESS BY
CONTRACTOR
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
SUBCONT’R
OWNER
(3) Tray Clamping As per drawing After setting 5000-202 FI/P FW SW
5000-202A
5000-203
5000-203A
5000-204
5000-204A
(4) Bolt Tightness After setting 5000-202 FI/P FW SW
5000-202A
5000-203
5000-204
(5) Tack welding of As per drawing After setting 5000-202 FI/P FW SW
nut
(6) Field welding ASME Sec IX WPS, PQR,WQT After setting 5000-205 FI/P FW FW
Final check for ASME Sec VIII
every tray
(7) Panel As per drawing After setting 5000-203 FI/P FW SW
Connection
(8) Level Check Manufacturer’s Tolerance = 1/500 After setting 5000-204 FI/P FW FW
specification (unless noted otherwise) 5000-204A
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 14 OF 62
WITNESS BY
SUBCONT’R
CONTRACTOR
OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
(9) Leak test Manufacturer’s As per drawing After setting 5000-206 FI/P FW FW
specification
(10) Check As per drawing After setting 5000-202 FI/P FW FW
thermowell
location
(11) PMI If required 5000-322 FI/P FW SW
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 15 OF 62
WITNESS BY
CONTRACTOR
SUBCONT’R
SITE INSPECITON ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
OWNER
3. AIR FIN COOLER
Structure Steel Work
refer to Steel structure
(1) Position As per drawing After setting 5000-307 FI/P FW FW
3.1 Fan Hood / Fan ring As per drawing After setting 5000-307 FI/P FW SW
(1)Verticality/Elevation
3.2 Fan & Drive Assembly 5000-308
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 16 OF 62
WITNESS BY
CONTRACTOR
SUBCONT’R
OWNER
SITE INSPECITON ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 17 OF 62
REPORT No.
INSPECTION REPORT
Job Code
VESSEL (VERTICAL ON GROUND)
Date
(2) VERTICALITY
DIRECTION BOTTOM REFERENCE POINT
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 18 OF 62
REPORT No.
INSPECTION REPORT
Job Code
VESSEL (VERTICAL ON GROUND)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 19 OF 62
REPORT No.
INSPECTION REPORT
Job Code
VESSEL (VERTICAL WITH LEGS)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 20 OF 62
REPORT No.
INSPECTION REPORT
Job Code
VESSEL (VERTICAL WITH LEGS)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 21 OF 62
REPORT No.
INSPECTION REPORT
Job Code
VESSEL (HORIZONTAL)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 22 OF 62
REPORT No.
INSPECTION REPORT
Job Code
VESSEL (HORIZONTAL)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 23 OF 62
REPORT No.
INSPECTION REPORT
Job Code
(HEAT EXCHANGER (HORIZONTAL)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 24 OF 62
REPORT No.
INSPECTION REPORT
Job Code
(HEAT EXCHANGER (HORIZONTAL)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 25 OF 62
REPORT No.
INSPECTION REPORT
Job Code
STACKED HEAT EXCHANGER
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 26 OF 62
REPORT No.
INSPECTION REPORT
Job Code
STACKED HEAT EXCHANGER
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 27 OF 62
REPORT No.
INSPECTION REPORT
Job Code
(HEAT EXCHANGER (VERTICAL)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 28 OF 62
REPORT No.
INSPECTION REPORT
Job Code
(HEAT EXCHANGER (VERTICAL)
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 29 OF 62
REPORT No.
INSPECTION REPORT
Job Code
AIR COOLED HEAT EXCHANGER
Date
(1) STRUCTURE LEVEL & VERTICALITY (2) FAN HOOD / RING LEVEL
SUBCONTRACTOR JGC OWNER SUBCONTRACTOR JGC OWNER
ACCEPTANCE (FI/P) (FW) (FW) REMARKS ACCEPTANCE (FI/P) (FW) (FW) REMARKS
Inspected by Witnessed by Witnessed by Inspected by Witnessed by Witnessed by
Reviewed by Reviewed by Reviewed by Reviewed by
Name Name
Signature Signature
Date Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 30 OF 62
REPORT No.
INSPECTION REPORT
Job Code
AIR COOLED HEAT EXCHANGER
Date
- - 2 Belt Tension
Set P = kg
- - 2 Tip Clearance (Set : mm) dept = cm
0º 45º 90º 135º 180º 225º 270º 315º
tension = kg
Result
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 31 OF 62
REPORT No.
INSPECTION REPORT
AIR COOLED HEAT EXCHANGER Job Code
Date Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 32 OF 62
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 33 OF 62
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT ERECTION SHEET 34 OF 62
Form 5000-402
REPORT No.
INSPECTION REPORT
Job Code
Skid and Others
Date
D R A
N
I 21-OCT 12
- 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 35 OF 62
ERECTION
FORM- 5000-201
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 36 OF 62
ERECTION
FORM-5000-202
INSPECTION REPORT
FOR
TRAY INSTALLATION
INSPECTION FOR : Confirmation of Tray Assembly Completion, Support Beam installed, Panel Connection, Bolt
Tightened, Clump Tightened, Cleaned and Ready for Man-way Closing, Tack Welding of Nut and
Thermowell Location
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 37 OF 62
ERECTION
FORM-5000-202A
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 38 OF 62
ERECTION
FORM-5000-203
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 39 OF 62
ERECTION
FORM-5000-203A
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 40 OF 62
ERECTION
FORM-5000-204
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 41 OF 62
ERECTION
Mea
b a sure b a b a
ment
d c
d c
d c f e
f e
h g
Two-pass Tray
c b Case 2 c
Case 1 d
b
b a d a b a e a
d c d c
f e f e
h g h e h g j f
i g
g f
h
Four-pass Tray (Support ring)
Case 1 Case 2
c a
b a d
d c e d
e g f
f
h g j h
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 42 OF 62
ERECTION
FORM-5000-204A
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
Column No.
Inner Diameter
Total No. of Trays
No. of Tray Passes
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 43 OF 62
ERECTION
One-pass Tray
Case 1 Case 2
Measurement Point
b a
b a
e d g c
• •
f e
d c
Two-pass Tray
Case 1 Case 2
b
•e a
b •e
b a b a a
d c d c
d g c d
• •g c
•j
g f g f
f e f e i h
i •j h
b a b a
d g c
d c
f e f e
h g i l h
i k j
j
b a
b a d e c
d g c
f e g f
i l h
i h k j
k n j
m l n q m
p o
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 44 OF 62
ERECTION
FORM-5000-205
INSPECTION REPORT
FOR
TRAY INSTALLATION
(INTERNAL WELDING INSPECTION)
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 45 OF 62
ERECTION
FORM-5000-206
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
(TRAY LEAK TEST)
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 46 OF 62
ERECTION
FORM-5000-311
INSPECTION REPORT
FOR
FIELD PROOF TEST
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 47 OF 62
ERECTION
FORM-5000-999
INSPECTION REPORT
FOR
PLATFORM AND LADDER
INSPECTION ACCEPTANCE
No. DETAIL INSPECTION DESCRIPTION
DATE SUB-CON
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 48 OF 62
ERECTION
FORM- 5000-312
Form No. :
DSLNG PROJECT Rev. :
PRE-COMMISSIONING & START-UP Owner :
H.O. Class :
EQUIPMENT CLOSURE CERTIFICATE Page : 1 of 1
Serial No. :
Unit Number System No Drawing No. Equipment No.
PART 1
MECHANICAL CHECK
NO. DESCRIPTION Y N N/A REMARKS
1. Equipment Vendor, Construction Drawing provided for inspection.
2. Equipment Data Sheet provided for inspection.
3. Insulation Completed.
4. Painting Completed.
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 49 OF 62
ERECTION
FORM-5000-313
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
ITEM NO.
Inner Diameter
Packing Type
Total No. of Beds
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 50 OF 62
ERECTION
FORM-5000-314
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
ITEM NO.
Inner Diameter
Packing Type
Total No. of Beds
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 51 OF 62
ERECTION
FORM-5000-315
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
ITEM NO.
Inner Diameter
Packing Type
Total No. of Beds
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 52 OF 62
ERECTION
FORM-5000-316
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
ITEM NO.
Inner Diameter
Packing Type
Total No. of Beds
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 53 OF 62
ERECTION
FORM-5000-317
INSPECTION REPORT
FOR
EQUIPMENT INTERNAL
ITEM NO.
Inner Diameter
Packing Type
Total No. of Beds
OWNER
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 54 OF 62
ERECTION
FORM-5000-001
INSPECTION REPORT
FOR
EQUIPMENT NOZZLE FLANGE FACE
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 55 OF 62
ERECTION
FORM-5000-001B
INSPECTION REPORT
FOR
EQUIPMENT AND PIPING FLANGE FACE, GASKET AND BOLT/NUT
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 56 OF 62
ERECTION
FORM-5000-511
INSPECTION REPORT
FOR
FLANGE BOLT TIGHTENING
MIN. BOLT
NOZZLE NO. TORQUE ACTUAL
OR BOLT SIZE VALUE SNUG TIGHT REMARKS
FLANGE NO.
Kgf – M / N.M Kgf – M / N.M
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 57 OF 62
ERECTION
FORM-5000-319
INTERNAL INSTALLATION CHECKCLIST
OF
MESH AND CERAMIC BALL
Description Vendor
Area Drawing No.
Subcontractor
SN. Check Items
Accepted Rejected
4. Inner Ball
1. Ceramic ball layer evenly
installed with proper depth. (Not
allow to mix with other size of
ball). Put ceramic balls first at
the circumference of the vessel
to maintain the mesh screens.
Top of ceramic ball layer shall be
higher than the top of the fine
mesh.
2. Ceramic ball layer evenly
installed with proper depth.
Check no ceramic balls shall fall
between the shell wall and the
fine mesh.
Molecular sieve (1.6 Ø) evenly
5. installed with proper depth. (Layer is
higher than top of fine mesh)
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 58 OF 62
ERECTION
FORM-5000-320
INSPECTION REPORT
FOR
NAME PLATE
INSPECTION ACCEPTANCE
No. DETAIL INSPECTION DESCRIPTION
DATE SUB-CON
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 59 OF 62
ERECTION
FORM-5000-321
INSPECTION REPORT
FOR
ANODES INSTALLATION FOR HEAT EXCHANGER
INSPECTION ACCEPTANCE
No. DETAIL INSPECTION DESCRIPTION
DATE SUB-CON
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 60 OF 62
ERECTION
FORM-5000-322
INSPECTION REPORT
FOR
PMI
INSPECTION ACCEPTANCE
No. DETAIL INSPECTION DESCRIPTION
DATE SUB-CON
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 61 OF 62
ERECTION
FORM-5000-323
INSPECTION REPORT
FOR
DAVIT INSTALLATION
INSPECTION ACCEPTANCE
No. DETAIL INSPECTION DESCRIPTION
DATE SUB-CON
REMARKS :
D R A
N
I 21-OC 12
T - 2 0
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-501 <Rev.1>
TEST AND INSPECTION PLAN FOR STATIC EQUIPMENT SHEET 62 OF 62
ERECTION
FORM-5000-324
INSPECTION REPORT
FOR
BED SUPPORT INSTALLATION
INSPECTION ACCEPTANCE
No. DETAIL INSPECTION DESCRIPTION
DATE SUB-CON
REMARKS :
D R A
N
I 21-OC 12
T - 2 0