Académique Documents
Professionnel Documents
Culture Documents
METERS
<RAJESH BANSAL>
<BSES, DELHI>
- 1-
Since the electronic meter has capability to log a vii. What is the number of times fuse has
large volume of data, it is worth visualizing an failed on the HT side of DT and how
electronic meter as essentially a ‘data logger’ that long has it taken to be restored?
also measures energy accurately. If one is able to
viii. What is the number of times the DT
look at an electronic meter from this perspective,
has been subjected to a jerk of
a whole range of applications come to view and
currents due to a downstream fault?
one is able to derive far greater benefits from an
electronic meter. ix. This fault has affected which phases
and what is the type of fault?
The user will surely desire different data logging
features for different applications because only x. And of course, what is the energy
through specialization one can obtain far greater sent out by the DT so that we find out
benefits. With this the meter is no longer ‘inter- the loss in the LV system, and loss in
changeable’ between different applications. That the HT system (between the 11 kV
is, the same meter cannot be used for both a DT feeders and groups of DTs
as well as for a consumer. A meter meant for a downstream.)
DT will have to be used only for DTs and a meter
Surely if we can find out the data logging needs to
meant for a consumer will have to be used only
obtain the above information, one can work out
for consumers. This is really not a restriction but a
the functional requirements for a DT meter. It may
specialization. This Special purpose
be seen from above that if at all the DT meter can
Customization fetches a greater benefit from
deliver the above management information; its
products.
utility is far beyond a simple energy meter.
The modern electronic meter, therefore is a
powerful data-logger that also measures energy. It 5. FUNCTIONAL FEATURES IN A DT
all depends how much of ‘power’ is punched into METER
this data-logger for different applications. With this
perspective, let us examine the need for a DT Let us work out the data logging requirements to
meter. obtain the above information:
5.1 Overloading of DT
4. NEED FOR DISTRIBUTION
TRANSFORMER METERING There are two parameters important to determine
the overloading effect on a DT. They are the peak
Let us first examine the general need for loading in kVA and duration for which the loading
monitoring performance of a DT and not merely has exceeded the nominal kVA rating (or any pre-
metering needs. Because, if we examine the decided percentage of its nominal rating). Hence,
needs for DT metering, all one can think of is logging the kVA for each ½ hour period is
simply measuring the kWh and may be kVARh but necessary for this purpose. This kVA can be
little else. obtained in case either kVA is logged, or in case
kW and kVAr (both) are logged. Logging kW and
If we imagine we are logging data for a DT
kVAr gives other benefits as well.
monitoring, we would surely be interested to find
out the following: Now, a DT may have different loading in its three
i. Is the DT overloaded, and if so, what
is the duration of overloading?
ii. What is the trend of overloading in the
DT so that upgradation can be
planned in time?
iii. Is the DT unbalanced, and if so what
is the measure of unbalance so that
the unbalance can be corrected?
iv. What is the neutral current on the
DT?
v. What is the minimum and maximum
reactive power drawn from the DT so phases. Hence, the information (i.e. kW & kVAr)
that fixed or switched capacitors can needs to be logged phase-wise. That is, kW R phase,
be planned? KW Y phase, kW B phase and kVArR phase , KVArY phase,
kVArB phase needs to be logged for each ½ hour
vi. What is the reliability of supply for the period.
DT in terms of hours of supply and
number of interruptions?
- 2-
Normally in load survey data of energy meters from the sample results in the very first month of
an average value is reported. That is, the kVAh monitoring of DT loads by BSES- Table 1.
for the ½ hour is logged and multiplied by 2 to
give the kVA load for the DT. This calculation can 5.2 Unbalance in DT
be misleading. What one is interested is to know Data logged by DT meters can provide an
the peak kVA of the DT that has occurred during indication of the degree of unbalance in the LV
the ½ hour interval. So, the phase-wise kW & loads connected to a DT. Conventional methods
kVAr logged by meter should correspond to the to balance the loads on a DT are to find out how
highest kVA occurring during the ½ hour interval. many consumers are connected to each phase,
measuring the phase wise currents during peak
By plotting the highest kVA for each ½ hour
load etc. None of these however can give
interval one obtains a kVA loading profile for the
information to balance the loads on a DT because
DT. Now, by rearranging the peak kVA values in
balancing the number of consumers may not lead
form of a load duration curve, one can know not
to balancing their loads, and unbalance during
only the highest kVA delivered by the DT but also
peak load may not be an indication of unbalance
the duration of overloading of DT, in steps of ½
for the entire day or month.
hour intervals. Had the ‘average kVA’ been logged
by the meter, it would not have been possible to
obtain information about the peak load on the DT.
Moreover, there are more advantages of logging
kW & kVAR at the peak kVA value (rather than
the average value) for each ½ hour interval, as we
shall presently see.
An easier option is to find out the base & peak But most faults in the downstream of a DT are of a
capacitor requirement for each DT from the kVAr temporary nature and are not that severe enough
data logged by the DT meter. This is by far easier to cause the fuse to blow. Now, since half hourly
and more reliable than theoretical computations. data is being logged for the peak kVA conditions,
The DT meter also provides this data. the faults in the LV system, even if they are of a
minor nature cause a surge in the DT load and
5.5 Reliability of supply for the DT this surge is captured and logged by the DT meter
because it will surely correspond to the peak kVA
Reliability of supply for a DT can be expressed as during a ½ hour interval. A unity PF surge will
no. of hours of supply and no. of interruptions of indicate a resistive fault (like tree touching) and a
supply to the DT. low PF surge will indicate a reactive fault like
flashovers and short circuits.
Whenever a fault happens, the voltage of the
concerned phase is reduced. Hence, if we were to
filter out the ½ hourly data for ½ hour intervals in
which voltage was normal and ½ hour intervals for
which voltage of any phase was less than (say)
160 Volts, one would obtain (a) the loading,
unbalance, neutral current, reactive demand etc.
for normal operating conditions and, (b) the
number of incidents during fault conditions. After
all, one expects the load on DT, neutral current
Figure 5 Supply reliability for a DT and phase unbalance to be temporarily high
during fault conditions and we do not want to mix
- 4-
up this information with the normal operating In general, we followed turnkey project approach.
information of the DT. We selected one vendor for meter supply,
installation quality check and Downloading,
5.8 Measurement of the energy drawn by Processing, Analyzing of DT meter data and
DT another vendor for DT meter installation and
maintenance of DT meters.
Needless to say, measurement of the energy
(kWh) by the meter is of course a requirement.
8. ISSUES DURING IMPLEMENTATION &
Hence kWh needs to be measured by the DT for
SOLUTIONS WORKED OUT
each ½ hour interval. This energy can be used for
assessing the loss in the LV system and the loss The issues faced during implementation were of a
in the HT system (between the feeder and groups very practical nature which may sound trivial on
of DTs). paper but can become a concern in a feild. These
were as follows:
6. FUNCTIONAL SPECIFICATIONS FOR
i. Location of DTs
DT METER
ii. Correctness of wiring and installation
The functional specifications for obtaining the best
related problems
benefits from a DT meter are as follows
iii. Shut Down.
i. Half hourly logging of kW, kVAr and
Voltage (phase-wise) for peak kVA
8.1 Location of DTs
conditions
Installation of meters on DTs is carried out by one
ii. Half hourly logging of kWh (a single 3
agency. It is necessary that information about the
phase value will suffice)
location and rating of each DT is accurately
iii. Duration of power availability or obtained and provided to the agency concerned.
power outage (in minutes) during This is not as easy a task as it perhaps sounds.
each ½ hour interval Every Division may accurately know where their
DTs are located but a reasonably accurate record
In addition to above event logging for power OFF
of the same can be difficult. This was one of the
and power ON events is useful, and history
difficulties initially faced by us because in the
registers for monthly energy (kWh). Now with
absence of a detailed description where a DT is
above half hourly data logging, a data logging
located, the concerned agency lost time in finding
period for 36 days (20% more than a month) or at
out the respective locations. To overcome this
most 39 days (30% more than a month), is
problem, the installation agency was advised to
sufficient.
work in close coordination, if required to have
business agreement, with O&M maintenance
7. DT METER PROJECT OF BSES, DELHI. contractors. Parallel GIS Maps with unique
Using these above concepts BSES DISCOM at transformer code were provided to help in
Delhi have initiated a DT metering project of identifying and monitoring of the progress. Further
installing meters on DTs in the areas covered by close coordination between DT team and O&M
BRPL and BYPL, to get DT metering MIS reports has resulted in installation of DT meter during
for preventive and corrective actions. During the planned shutdown (during load shedding or
initial study, we anticipated following challenges preventive maintenance of DT).
and prepared our self for the same:
i. Supply of Meters as per desired
functional specifications. 8.2 Correctness of wiring and installation
related problems
ii. To install the Meters correctly, within
planned time frame. A number of practical problems were faced in the
installation, which could be detected once the
iii. Inconvenience to consumer – meter was downloaded and analysed. The typical
problem of shut down. problems were:
iv. DT meter data base. i. CT Reversal
v. Timely Downloading, Processing and ii. CT Short/ by pass (TTB link remain
Analyzing of DT meter data. closed)
vi. Useful MIS reports with follow up for iii. PT Missing or Loose Connection
corrective action.
iv. Phase Association
vii. Maintenance of Meters.
- 5-
v. Communication failure – Due to break the transformer, reliability of supply, occurrences
in communication cable or Com port of faults and response of maintenance team for
Damage repairing/replacing fuses, and of course the
energy and loss for the DT and loss for the 11 kV
feeder (up to DTs). To realize these benefits one
These problems however came to light after the
needs to look at the DT meter as a ‘data logger’
first set of readings from these DT meters were
making full use of the potential of electronics,
analysed.
rather than look at it as a ‘simplistic energy meter’.
At BSES, DT meters are installed at a height and Once this is realized, then the DT meters serve as
enclosed in a box. A small downloading box is the ears and eyes of a distribution system,
connected to meter for data downloading. In provided they are specified appropriately. Deriving
absence of a feature to read them, it is very likely MIS from the data logged by a DT meter is not at
that no one will read them regularly. In addition to all an easy task. A single meter logs a large
above any form of remote reading, like Low Power volume of data, and services of any dedicated
Radio (LPR) or GSM is useful because it will team or third party or professional agency who
facilitate in reading the meters. can read all meters regularly, analyse the data
and provide timely MIS may perhaps be
9. PROGRESS OF THE PROJECT necessary.
The DT meter project of meter installation has
started in March ’06, and by July end, we did
more than 90% metering. In August ’06, few
monthly reports were prepared. The main thrust at
present is to identify and correct the installation
problems and identify the group of DTs connected
to each 11 kV feeder. The latter is a difficult task,
particularly in view of the frequent changes in
network operating configurations. The next phase
will be to assess the loss for each DT by finding
out the consumption of all consumers connected
to each DT. Initially DT reports related to
distribution system health are highly appreciated
by user department and corrective actions based
on reports have already started.
Feed back
Analysis Analysis
Report By User
By EA team
CONCLUSION
A meter on a distribution transformer can provide
a range of information on the loading conditions of
- 6-
- 7-